Metoda Precast Segment

Download as pdf or txt
Download as pdf or txt
You are on page 1of 51

PT. WIJAYA KARYA PT.

WASKITA KARYA COMBINED GROUP

PASTEUR – CIKAPAYANG – SURAPATI


ELEVATED ROAD AND BRIDGE PROJECT
BANDUNG

PRECAST BALANCE CANTILEVER METHOD

Presented by : Samsul Purba


PRECASTING METHOD
• SHORTLINE
• Formwork is at a
fixed location,
already cast
segments are
moved

• LONGLINE
Already cast
segments are
stationary, forms is
moved longitudinally
BALANCE CANTILEVER ERECTION

This is an erection method where segments are


erected alternatively on either side of pier in
cantilever up to the point where a cast−in−place
closure is made with the previous cantilever or
existing side span structure
Geometry Control

The bridge should be built as planned by


highway engineers.

This means achieving the


- global X,Y,Z coordinates along Setting Out Line
(gradient and offset)
- crossfall during the life span of the bridge.
Management of bridge geometry

1. Theoretical alignment (road planning)

2. Precamber (structural analysis)

3. At casting yard (handling casting errors)

4. In the field (setting out)


Geometry Software : FORMSET

DO BO D B Web

Control Points
3000mm

Group 1: A, B, C, D
FO EO F E Center line Level Control Point
3000mm Group 2: E, F
Cast New
Offset Control Point

CO AO C A Web

Plan view of segment showing


control points
FOTOGRAPH OF PRODUCTION SEGMENT
GENERAL VIEW OF CASTING
YARD
CASTING MOULD
CASTING MOULD
CASTING MOULD
GEOMETRY CHART
REBAR JIG AND GANTRY CRANE CAP.
2X5T
PREFAB REBAR AT REBAR
JIG
LIFTING REBAR CAGE TO THE CASTING
MOULD
FINAL SETTING REBAR AT CASTING MOULD
CONTROL POINT
POURING CONCRETE
FLOWABLE
CONCRETE
EXTERNAL VIBRATOR
RELEASE WING
FORMS
SETTING MATCH
CAST
APPLY BOND
BREAKER
MOVE SEGMENT TO STOCK YARD
LIFTING SEGMENT BY GANTRY 150 TONS
FOTOGRAPH OF ERECTION SEGMENT
LOW BED TRAILER UNDERNEATH OF ERECTED
SEGEMNT
INSTALLATION OF SPREADER BEAM
LIFTING SEGMENT
TRIAL JOINT
INSTALL TEMPORARY STRESSBAR
MIXING OF EPOXY
APLLY EPOXY
STRESSING STRESSBAR
INSTALL POST TENSIONING STRAND
INSTALL POST TENSIONING JACK
STRESSING PT STRAND
Detail of Equipment for Setting
Segment at Temporary Support
Detail of Equipment for Joining
Between Segment
Stiching and Closure Pour
STRESSING STRESSBAR AT STITCHING BEAM
INSTALL REBAR FOR CLOSURE POUR
INSTALL OUTER FORMS FOR CLOSURE POUR
INSTALL INNER FORMS FOR CLOSURE POUR
POURING CLOSURE POUR
POURING CLOSURE POUR
STRESSING CONTINUITY TENDON
FINISH ONE SPAN