Methodology For Installation of Fire Pro
Methodology For Installation of Fire Pro
Methodology For Installation of Fire Pro
SYSTEM
QAP APPROVAL.
DESIGN APPROVAL.
RECEIPT RAW MATERIAL INSPECTION.
EQUIPMENT INSPECTION.
WPS, PQR AND WELDERS QUALIFICATION TEST.
WELDING CONSUMABLES AS PER WPS & PQR.WITH BATCH
CERTIFICATES. APPROVED MAKE—ESAB, D&H, OVERLINKOLN,
ADHOR, ADVANI, GEE (GEECON PINK, GREECON GREEN).
Page 1 of 4
FINAL RUN WITH E 6013 – 3.15MM ROD.
CHIPPING AND CLEANING OF FINAL RUN.
ERECTED PIPES IF THE SAME ROUTE MINIMUM DISTANCE SHOULD
BE 800MM. BETWEEN TWO PIPES.
Page 2 of 4
EXCAVATION OF TRENCHES WILL BE MANUAL OR WITH JCB OF
WIDTH OF MINIMUM 800M.M TO 1000M.M AND DEPTH OF MINIMUM
1000M.M FROM THE TOP OF THE PIPE AS APPROVED DRAWING.
ALL ABOVE GROUND PIPES SHALL BE BLASTED AND PAINTED AS
THE PAINTING PROCEDURE
ALL UNDER GROUND PIPES WRAPPING SHALL BE DONE AS PER THE
PROCEDURE.
THE EXCAVATED SOIL SHALL BE BACKFILLED AFTER REMOVING OF
HARD MATERIALS LIKE ROCKS ETC. TO AVOID THE DAMGE OF
COATING &WRAPPING OF THE PIPES.
AFTER INSTALLATION OF THE PIPES, THE UNDERGROUND PIPING
WILL BE HYDRAULICALLY TESTED TO APRESSURE OF 1.5 TIMES
FROM WORKING PRESSURE AND HOLDING TIME MINIMUM 3HRS.
THE COATED PIPES WILL BE LOWERED IN TO THE TRENCHES WITH
OUT GETTING DAMAGE OF COATING. IN ANY CASE TWO PARALLEL
PIPES DISTANCE SHALL BE MAITAINED 800M.M.
ALL EQUIPMENTS WILL BE ERECTED AND COMMISSIONED
AS PER DRAWING.