Error Assessment of Solar Irradiance Forecasts and AC Power From Energy Conversion Model in Grid-Connected Photovoltaic Systems
Error Assessment of Solar Irradiance Forecasts and AC Power From Energy Conversion Model in Grid-Connected Photovoltaic Systems
Error Assessment of Solar Irradiance Forecasts and AC Power From Energy Conversion Model in Grid-Connected Photovoltaic Systems
1. Introduction
Photovoltaic (PV) generation strongly depends on weather conditions, in particular on solar
irradiance and temperature. As such, availability of accurate weather forecast data is very important
for PV system planning and operation. For grid-connected PV systems, the power injected into the
grid is concentrated during sunlight hours, in which typically the maximum peak load occurs.
In the power system, the task of the Transmission System Operator (TSO) is to ensure a
constant balance between supply and consumption within the grid. Actually, the presence of strong
fluctuations of the irradiance increases the uncertainty on the PV generation and requires additional
regulatory actions for the procurement of reserve services. This may cause an increase in the costs
for ancillary services. The irradiance forecast is then useful for grid management, to obtain more
accurate information on the expected weather conditions. This information may assist the operators
in undertaking decisions concerning the energy market and to reduce the costs of energy imbalance.
The first research on solar irradiance forecasting was conducted more than twenty years ago [1],
using the Model Output Statistics (MOS) technique [2]. This technique allows the prediction of
a daily average value one or two days ahead. Concerning the forecasting on a short-time scale
(a few hours), the effectiveness of a statistical approach based on the prediction of the motion of the
clouds through images provided by satellites of the Meteosat constellation has been demonstrated
in [3]. However, this method requires a huge computational effort. A multi-resolution decomposition
technique applied to satellite images has been studied in [4], in order to obtain information on the
local mean value and on the gradient of solar irradiance at different spatial scales. Other studies on
short and very short time scales are available in the literature, taking into account the information
provided by satellites. Currently, the weather forecasting tools are based on numerical techniques,
which provide good results when applied to extended spatial scales. However, these tools are not
able to address local variability of the weather conditions.
The forecasting field is rapidly evolving according to the growth of the PV market. A model to
predict the power P produced by a PV plant can be written in the general form P “ f pX1 , X2 , ..., Xn q
where Xi (i = 1, 2, . . . , n) are n different physical quantities of influence. These quantities, including
the solar irradiance, the PV module’s temperature, the air temperature, the wind speed, the relative
humidity, etc., have to be provided by forecasting tools. The input of many models is the solar
irradiance [5], while different methods are based on the irradiance and on the temperature of the air
or of the PV module [6]. In general, as shown in [7] the models based on irradiance and temperature
perform better than the ones where only the irradiance is considered. Conversely, the adoption of the
models based on other working conditions does not necessarily improve the prediction accuracy.
Different techniques showing accurate results have been used to predict the power produced by
a PV plant. Some examples are Artificial Neural Networks (ANN)-based techniques [7–9], regression
model-based techniques [10], support vector machine [11], hybrid models [12] and PV system
models [13]. The prediction methods may change depending on the availability of local data coming
from a weather station specifically designed and installed to measure the operating conditions of the
PV system under study. Most residential PV plants (as well as many of the commercial/industrial
ones) are not equipped with any sensor of climate conditions. In this case, the usage of commercial
weather data allows the implementation of simpler models for the estimation of the power produced
by the PV plants [14].
Recently, a growing interest in using spatio-temporal forecasting methods has emerged, due to
the availability of time series data over a large number of meteorological stations. Interesting results
incorporating spatial-temporal forecasting method based on the vector autoregression framework
have been presented in [15]. This framework combines observations collected by smart meters
and distribution transformer controllers, to obtain 6 h-ahead forecasts at the residential PV and
medium-voltage/low-voltage substation levels. Spatio-temporal information from satellite images
has been used in [16] through an autoregressive approach to forecast the global horizontal irradiance
at ground level.
This paper presents a procedure to assess the errors occurring in the 1 day-ahead solar irradiance
estimation and in the model-based estimation of the Alternating Current (AC) power delivered to the
grid by the PV system. This procedure is based on:
(1) The use of solar irradiance weather forecasts updated every a few hours from a provider. These
data are interpolated with polynomial splines to obtain a higher number of estimated values
during the day. The results are compared with the measurements gathered at 1-min intervals
during a period of one year in order to calculate the estimation error.
(2) The application of a PV conversion model from solar irradiance to AC power, determining 1-min
AC power estimates. From these values, 15-min averaged data are calculated and compared
with the energy meter readings at 15-min intervals in order to calculate the error on AC
power estimates.
Energies 2016, 9, 8 3 of 27
(a) The procedure presented can be used to select the best forecasting model or the best
provider of weather forecasts in the location of interest.
(b) The irradiance error estimation is particularly accurate, because the meteorological stations
are equipped with pyranometers (secondary standards used as reference instruments)
installed in the same sites of two operating PV plants. Moreover, the AC power error
estimation is relevant because (i) the PV plants analyzed are located in the Italian region
(Puglia) with the highest PV power density; and (ii) the measurements referring to the PV
plants are taken from calibrated energy meters.
The results of the proposed procedure are presented in the form of duration curves of the
positive and negative errors between estimated and measured values, determined during a period of
one year. The evaluation of the estimation errors is helpful for the grid operator to estimate to what
extent the estimation of the PV contribution as grid-connected local generation, calculated starting
from 1 day-ahead forecast data, can be trustable. The occurrence of irradiance spikes due to the
phenomenon of “broken clouds” is also presented and discussed as a source of possible irradiance
peaks, in some cases exceeding the rated value of the AC power injected into the grid.
The next sections of this paper are organized as follows: the second section presents an overview
of solar irradiance models and the PV conversion model. The third section introduces the proposed
model for hourly classification in clear, variable and cloudy sky conditions, according to the clearness
index values. Section 4 discusses the error calculation of the estimated irradiance with respect to
the measured irradiance. The fifth section addresses the errors between the AC power estimates
and the AC power values measured on two PV systems in operation. The last section contains
the conclusions.
‚ latitude ξ, in radians or degrees, with respect to the equator (>0 toward North);
‚ longitude ζ, in radians or degrees, referred to the Greenwich line (>0 toward East);
‚ solar declination δ, the angle between the Sun-Earth line and the equator plane (>0 North);
‚ hour angle ψ, between the meridian plane passing through the observer and the meridian plane
passing through the Sun (>0 West);
‚ azimuth angle φ between the projection of the Sun-Earth line and the plane at the horizon with
South direction (>0 West);
‚ zenith angle z between the Sun-Earth line and the zenith direction;
‚ solar height α, that is, the angle between the Sun-Earth line and the horizon plane.
The latitude ξ and the longitude ζ are the only parameters that do not require calculations,
because they are known as the geographical coordinates of the place of observation.
Energies 2016, 9, 8 4 of 27
The hour angle ψ of the Sun is a more complex parameter, because it depends on the position of
the observer (longitude effect) and on the measurement of the local time. During the year, the time
indicated from a meridian deviates periodically a few minutes with respect to the time indicated by a
clock, which in Italy is normally referred to the Central European Time (CET). This difference is called
“equation of time” τ, defined as the East or West component of the analemma, a curve representing
the angular offset of the Sun from its mean position on the celestial sphere as viewed from the Earth.
At any point in time, the solar irradiance incident on a horizontal plane outside the atmosphere is the
normal solar irradiance G0 , given by ([18], pp. 37–41):
ˆ ˙
360d
G0 “ Gsc 1 ` 0.033cos cosz (1)
365
where Gsc is the solar constant, d is the day of the year, and cosz “ cosξ cosδ cosψ ` sinξ sinδ.
By integrating this equation for an interval between the hour angles ψ1 and ψ2 , which define an
hour (where ψ2 is the larger), the irradiation H0 (in MJ/m2 ) is obtained as:
ˆ ˙
12 ˆ 3600 360d
H0 “ Gsc 1 ` 0.033cos rcosξ cosδ psinψ2 ´ sinψ1 q ` pψ2 ´ ψ1 q sinξ sinδs (2)
π 365
The solar irradiance, in the path through the atmosphere towards the Earth surface, is subject to
scatter, absorption, reflection, diffusion, meteorological conditions and air mass [19]. It is useful to
define a standard “clear” sky and calculate the hourly and daily irradiance that would be received on
a horizontal surface under these standard conditions ([18], pp. 85–95). In order to calculate the clear
sky irradiance, several methods have been developed [20]. Among these methods, the Moon-Spencer
model [21] provides the theoretical instantaneous values of the irradiance at clear sky on a surface
orientated in any direction. The irradiance values obtained from the Moon-Spencer model refer to
free view with respect to the horizon. The results may differ in case of obstacles hiding the visual
landscape, for some parts of the day, in the directions in which the Sun should impact on the surface
(e.g., presence of mountains or adjacent buildings). In these cases, the results of the Moon-Spencer
model have to be adjusted to take into account the actual skyline seen from the surface.
The Moon-Spencer model was developed for the atmospheric conditions in the United States,
but sometimes it over-estimates or under-estimates the global irradiance in case of geographical
locations different from the United States. Therefore, this clear sky model cannot be considered as
an ideal profile with minimum turbidity of the sky, but it represents an indicative daily evolution for
the comparison with the weather forecasts. In order to take into account the information provided
by the clear-sky model, a dedicated variable space has been created in [22], in which the time axis
is normalized in such a way to map the time interval between the sunrise and the sunset in the
(0, 1) interval; the irradiance values are normalized so that the unity value corresponds to the peak
conditions at clear-sky from the Moon-Spencer model.
Another clear-sky model has been implemented in the online software PVGIS [23]. In [24] a
comparison between the irradiance measured by the pyranometer and the simulated PVGIS clear-sky
irradiance has been discussed for a particular day of July. Examining other days during the whole
year, owing to higher air turbidity the measured values are, many times, lower than the ones obtained
from the clear-sky model.
In this paper, the data are elaborated in order to create a partitioning into three types of sky
conditions: variable, clear, and cloudy. Classifications with more types of sky conditions have been
used in various references for different purposes [25,26].
(Puglia region, Figure 1). The distance between the two meteorological stations is 61 km. As discussed
in [27], each meteorological station is provided with:
‚ A 2016,
Energies pyranometer
9, page–page(Secondary Standard according to ISO 9060 [28]) for measuring the horizontal
global irradiance G pyr ;
‚ Two reference
reference solar
solar cells in polycrystalline silicon (p-Si) with South orientation for measuring
the 30˝
30° tilted global irradiance Gtcell ;;
tcell
‚ One thermo-hygrometer for measuring
measuring the
the ambient
ambient temperature
temperature TTamb
amb, relative humidity and
Figure 1. Location of the two grid-connected PV systems and satellite photo of the “Gi” site.
Figure 1. Location of the two grid-connected PV systems and satellite photo of the “Gi” site.
To obtain a correctly integrated value for the solar irradiance over the day, small time steps are
To
recommendedobtain for a correctly
data sampling. integrated value for
However, duetheto solar irradiance
the response time over thepyranometer,
of the day, small time the steps
time
are recommended for data sampling. However, due to the
step cannot be lower than 5 s. The sampling time steps may be chosen depending on the data response time of the pyranometer, the
time step cannot be lower than 5 s. The sampling time steps may
collection system and on the calculation and update speed of the algorithms used. In our case, the be chosen depending on the data
collection
pyranometer system and on the
is connected to calculation
the meteorologicaland update speed
station. of the algorithms
Therefore, a time step used.
of 10In sourandcase,
an
the pyranometer is connected to the meteorological station.
averaging time for the integrated values of 1 min are used. This averaging time is suitable for Therefore, a time step of 10 s and an
averaging
obtaining atime for thenumber
sufficient integrated of data values
to beoffurther
1 min averaged
are used. within
This averaging
longer timetime is suitable
steps, such as the for
obtaining a sufficient number of data to be further averaged within
ones used in the electricity markets (e.g., 10, 15 min, 30 min, or 1 h). The global irradiance data longer time steps, such as the ones
used
from in the electricity
solar cells on the markets
tilted (e.g.,
plane10, are15validated
min, 30 min, or 1 h).
through theThe global irradiance
comparison with the data from solar
pyranometer
cells on the tilted
uncertainty [24],plane showing are validated
the possiblethrough the comparison
effect with the pyranometer
of the measurement accuracy. uncertainty
The expanded [24],
showing the possible effect of the measurement accuracy. The expanded
uncertainty of a pyranometer having the same characteristics of the pyranometers used in the two uncertainty of a pyranometer
having the same characteristics of the level
pyranometers used factor
in thektwo 2 with
sites is about 30 W/m 2 with confidence 95% (coverage = 2) sites is about
[29]. This value30isW/m
valid when
confidence
the irradiance level 95% (coverage
reaches its peaksfactor up to k1200= 2) W/m
[29]. 2This value is valid
. A confidence level when
99.7% the(coverage
irradiancefactor
reachesk = its
3)
peaks up to 1200 W/m 2 . A confidence level 99.7% (coverage factor k = 3) corresponds to an expanded
corresponds to an expanded uncertainty of about 45 W/m2. At mid-level of irradiance (e.g., around
uncertainty of expanded
about 45 W/m 2 . At mid-level of irradiance (e.g., around 500 W/m2 ) the expanded
500 W/m2) the uncertainty for k = 2 is about 15 W/m2.
uncertainty for k = 2 is about 15 W/m 2.
The real grid-connected PV system has a power rating Ppeak = 993.6 kWp for the site “Gi” and
Ppeak The real kW
= 997.3 grid-connected PV system has a power rating P peak =(STC)
p for the site “Ma” at Standard Test Conditions
993.6 with
kWp global
for theirradiance
site “Gi”
GSTC P
and = peak = 997.3
1 kW/m 2, cellkW p for the site
temperature “Ma”
TSTC = 25at°CStandard
and standardTest Conditions
spectrum AM (STC)
1.5.with
The global
PV systemirradiance
in the
G = 1 kW/m 2 , cell temperature T = 25 ˝ C and standard spectrum AM 1.5. The PV system
STC“Gi” is equipped with polycrystalline
site STC silicon modules of 230 Wp each, tilted at 30° with South
in the site “Gi”
orientation. On isthe equipped
contrary,with the polycrystalline
PV system in silicon the sitemodules
“Ma” isofequipped
230 Wp each,
with tilted at 30˝ with
mono-crystalline
South
siliconorientation.
modules ofOn 230the Wpcontrary,
, 235 Wp the andPV 240system
Wp and in the
withsite “Ma” is equipped
polycrystalline siliconwith mono-crystalline
modules of 230 Wp,
silicon modules of
235 Wp and 240 Wp, tilted 230 W , 235 W and 240 W and with polycrystalline
p at 30°pwith South porientation. The PV arrays of each site, placed silicon modules of 230on Wpa,
235 Wp and 240 Wthat ˝
metallic structure p , tilted
permits at 30thewithnaturalSouth air orientation.
circulation, feed The two
PV arrays of each
centralized site, placed
inverters on a
with high
metallic structure that permits the natural air circulation, feed
efficiency (transformerless option). These power conditioning units are slightly undersized, giventwo centralized inverters with high
efficiency (transformerless
that the 500-kVA inverter isoption).suppliedThese power
by a 552.0 kW conditioning units are slightly undersized, given
p array for the site “Gi” and by a 542.0 kWp array
that thesite
for the 500-kVA
“Ma”;inverter
the 400-kVA is supplied
inverterby ais552.0 kWp by
supplied array for the
a 441.6 kWsite “Gi” and by a 542.0 kWp array
p array for the site “Gi” and by a
for the site “Ma”; the
455.3 kWp array for the site “Ma”. 400-kVA inverter is supplied by a 441.6 kW p array for the site “Gi” and by a
455.3 kWp array for the site “Ma”.
2.3. Definition of the PV Conversion Model
In the definition of the PV conversion model, it is important to take into account the efficiencies
referring to the main loss factors affecting the PV system behavior. As mentioned in [30], the main
loss factors are summarized in the efficiencies defined as follows:
Energies 2016, 9, 8 6 of 27
pHa_rain ´ Hb_rain q
ηdirt “ 100 (3)
Ha_rain
where Ha_rain and Hb_rain are the values of the daily irradiation in two clear-sky days, one after
rain (12th day) and the other before rain (10th day), respectively. The corresponding value of
ηdirt is generally in the range 0.97–0.98.
‚ Efficiency ηre f l , due to reflection of the PV module glass; the value used is 0.971, taken from the
PVGIS website [23].
‚ Efficiency ηth , due to the thermal losses lth with respect to the STC, calculated as:
where γth is the thermal coefficient of maximum power of the PV modules, depending on the PV
technology (for crystalline silicon γth = 0.5%/˝ C); TC is the cell temperature (mean temperature
in outdoor operation at G NOCT = 800 W/m2 and Tamb,NOCT = 20 ˝ C), which can be calculated as
a function of the ambient temperature Tamb , the cell irradiance on the tilted plane Gtcell and the
Normal Operating Cell Temperature (NOCT) of 42–50 ˝ C [31,32]:
` ˘ Gtcell
TC “ Tamb ` NOCT ´ Tamb,NOCT (5)
GNOCT
‚ Efficiency ηmism , taking into account the current-voltage (I-V) mismatch losses, assuming that
the bottleneck effect globally leads to 97% of the power rating declared by the manufacturer for
all the modules in the PV array. This loss is a consequence of the weakest modules in the series
connection inside the strings, and of the weakest strings in the parallel connection inside the PV
array [33].
‚ Efficiency ηcable , including the DC cable losses, with the value 0.99 considered according to good
design criteria [34].
Considering these efficiencies, the available power at the maximum power point is expressed as:
Pmpp “ Prated pGtcell ´ Glim q ηdirt ηre f l ηth ηmism ηcable (6)
where Glim = 17.7 W/m2 is the irradiance limit below which the output is vanishing, calculated
by linear interpolation of the irradiance and power values declared by the manufacturer of the
silicon modules installed in the PV array.
Finally, considering the efficiency η MPPT of the maximum power point tracker, and thanks to
the model of the power conditioning unit for grid connection, the AC power injected into the grid is
calculated by solving the second-order equation [35]:
Energies 2016, 9, 8 7 of 27
2
cQ PAC ` p1 ` c L q PAC ` P0 ´ PDC “ 0 (7)
with:
PDC “ η MPPT Pmpp (8)
where P0 is the no-load power losses along the operation, while c L and cQ are the linear and quadratic
loss coefficients, respectively.
Therefore, if the reference-cell data Gtcell , averaged on 15-min basis, are used as inputs of the
above-described model, the power P AC delivered to the grid can be compared with the power Pmeas
indicated by the energy meter of the PV plant.
For the error calculation of the AC power profiles compared to the experimental results of each PV
plant in the two sites, the estimation error ∆P is defined as the difference between the estimated power
to be delivered to the grid P AC and the AC power Pmeas measured by the energy meter of each PV plant:
The above-mentioned correlations permit the hourly classification of the sky conditions.
In particular:
‚ for kt ď 0.21 a total cloudy sky condition occurs, and a linear expression of kd is assumed;
‚ in the range 0.21 < kt ď 0.76, a variable (i.e., partially cloudy) sky condition occurs, in which
the Sun is partially obscured by clouds, and the correlation is represented by a cubic
polynomial expression;
‚ for kt > 0.76 a clear-sky condition occurs, in which that the sunlight is not reduced by clouds,
and the fraction of diffuse irradiance is assumed to be 18% of the global one.
The weather forecasts considered in this paper are provided by the meteorological service of
Catalonia [42]. The available data are based on the Weather Research and Forecasting (WRF) [43]
Energies 2016, 9, 8 8 of 27
model: a next-generation mesoscale numerical weather forecast system designed to serve both
atmospheric research and operational forecasting needs. It features two dynamical cores, a data
assimilation system, and a software architecture allowing for parallel computation and system
extensibility. The model serves a wide range of meteorological applications across scales ranging
from meters to thousands of kilometers. As shown in Table 1, the coordinates of the points of the
WRF model (WRF latitude and WRF longitude) are close to the real points (real latitude and real
longitude) for the two sites under analysis.
Table 1. Real and WRF coordinates for the two sites (degrees).
The data set taken from the meteorological provider consists of solar irradiance forecasts for the
two meteorological stations during the whole year 2012 [44]. The forecast values are given in W/m2 at
four points in time (hours 7 a.m., 10 a.m., 1 p.m. and 4 p.m.). There is no indication on the uncertainty
of these data. The maximum timespan is 72 h. The forecast data have been first interpolated by using
polynomial splines [45], obtaining an estimated irradiance pattern that can be represented with a
number of points per day higher than the four points available from the forecast data.
On the basis of the hourly correlations from Equation (10), each hour of a day has been classified
belonging to clear, cloudy or variable sky conditions for both the estimated and measured data [44].
In particular, the value of the hourly clearness index of pyranometer ktp has been calculated as the
ratio of the solar irradiance from the pyranometer to the extra-atmospheric total irradiance G0 . Then,
the hourly clearness index of forecasts kt f has been calculated as the ratio between the 1 day-ahead
forecast data (considered to be more accurate than the 2 and 3 days-ahead forecasts, as confirmed by
the results indicated in Section 4) and the abovementioned G0 .
clear-sky,
working with because of the shield
smoothed of the direct
data would makeirradiance by theamong
the distinction clouds.different
This phenomenon may cause
sky conditions more
fast
challenging. In this respect, the ISBC effect is useful to provide highly variable realbydata
positive and negative variations with the mentioned abnormal peak, which are revealed the
pyranometer
characterizingon 1 min or
variable scale. In sky
cloudy order to identifyimpacting
conditions, this effectoninthe
a synthetic
increase way,
of theletforecasting
us introduce the
errors.
acronym ISBC (Irradiance Spikes caused by Broken Clouds; no specific acronym
Hence, the polynomial splines obtained from the forecasted values are represented at 1-min time has been found in
the literature to identify this phenomenon. Thereby,
step as well in order to be compared with the measured values. the new acronym ISBC is introduced here to
represent synthetically
A specific aspect canthebe occurrence
observedof infast positive
Figure and negative
2b, where irradiance
the measured data variations
indicate a in “broken
systematic
clouds” conditions).
irradiance reduction at the “Ma” site in the early morning. This is due to the location of the
Averaging
irradiance sensor theinirradiance data over station
the meteorological a time building.
period longer thansensor,
For this 1 minthe (to direct
obtainirradiance
a smoother is
irradiance pattern) can reduce the relevance of the ISBC effect on the measured
shadowed in the early morning in the summer period, causing a bias in the error calculations. This values. However,
working
systematicwith smoothed
error varies withdata the
would
day.make the distinction
Its impact among different
on the free-view curve can skybeconditions
determined more
by
challenging.
knowing theIn this sky
clear respect,
model theof
ISBC
the effect
days is useful
and to provide
the exact highly
location variable
of the real data
shadowing characterizing
obstacles. When
variable
the sensor cloudy sky conditions,
or shadowing impacting
occurs, the total on the
irradiance increase to
is reduced of the
the diffuse
forecasting errors.InHence,
irradiance. the
the model
polynomial splines obtained from the forecasted values are represented at
used in this paper, for the periods in which the systematic error occurs, the maximum spline values1-min time step as well
in
canorder to be compared
be reduced withof
to the values the measured
the values. calculated from the clear sky model.
diffuse irradiance
Figure 2. Cont.
9
Energies 2016, 9, 8 10 of 27
Energies 2016, 9, page–page
(a) (b)
Figure2.2. Solar
Solar irradiance
irradiancevalues
valuesfrom: thethe
from: Moon-Spencer model
Moon-Spencer (Gth),(G
model pyranometer measurements (Gpyr),
Figure th ), pyranometer measurements
(G pyr ), the 3-hour forecasts (dots) and the spline-approximated estimations for days
the 3-hour forecasts (dots) and the spline-approximated estimations for seven sevenofdays
Julyof2012.
July
(a) Site “Gi”; (b) Site “Ma”.
2012. (a) Site “Gi”; (b) Site “Ma”.
10
Energies 2016, 9, 8 11 of 27
Comparing the number of passes with the number of fails, it is interesting to point out that in
both sites only in two months (February and July) the number of passes is lower than the number
of fails. In particular, in July the classification of the cloudy conditions in these sites is particularly
challenging, especially when a cloudy day appears after a number of successive clear days.
3.4. Identification of the Irradiance Spikes caused by Broken Clouds (ISBC) Conditions
In order to estimate the number of occurrences of the ISBC effect in a day, an additional control
has been performed. In general, the ISBC effect may happen at each time (minute, hour . . . ) of the
day, when the irradiance spikes exceed the irradiance indicated by the reference model at clear sky.
The maximum value of clear-sky irradiance changes in each day; the monthly values are shown in
Table 4. The reference model considers a fixed plane (i.e., with the same 30˝ tilt angle of the modules
in the PV plant).
Table 4. Maximum clear-sky solar irradiance values with tilted angle of 30˝ for each month of 2012.
In this paper, a spike is defined by the occurrence of an increase in the global irradiance Gtcell on
the tilted solar cells, from one minute to the successive minute, higher than a threshold value. The
threshold is set to 45 W/m2 , that is, the maximum expanded uncertainty of the pyranometer with
99.7% confidence indicated in Section 2.2. The occurrence of the ISBC effect has been determined by
showing two different outcomes:
(i) the number of irradiance spikes for which the measured irradiance exceeds the irradiance of the
reference model at the same minute;
(ii) the number of irradiance spikes for which the measured irradiance is so high to exceed
the maximum irradiance Gmax indicated by the reference model of the corresponding day.
The rationale of this choice is that for irradiance values higher than the maximum value
established at clear-sky conditions the PV system may inject in the electrical network a power
that could be even higher than the rated power of the PV plant.
For the two sites, the global irradiance Gtcell is gathered with a resolution of 1 min. For the
“Gi” site, in the year 2012 the ISBC effect occurs for a number of minutes corresponding to about
2 days and 17 h. The details by month are shown in Table 5a. The occurrence of the ISBC effect in
2012 at the “Ma” site is similar to what happens at the “Gi” site, with a number of minutes in which
the ISBC effect occurs corresponding to 2 days and 16 h. The details by month are shown in Table 5b.
The months with a higher occurrence of the ISBC effect are in spring (April–May) and in autumn
(September).
Energies 2016, 9, 8 14 of 27
Table 5. Number of ISBC events for each month, considering Gtcell with time step of 1 min, exceeding
the minute-by-minute points and the daily peak of the clear sky model.
4.1. Error Indices to Compare the Irradiance Estimates with the Measurements
In order to compare the estimated quantities with the measured ones, the estimation error εG is
the difference between the estimated irradiance Gest and the measured irradiance Gmeas [52]:
Different statistical parameters [53] have been calculated on a daily basis, by considering a
generic error ε:
‚ the mean bias error (MBE), representing the systematic part (bias) of the error [54]:
N
1ÿ
MBE “ ε “ εi (13)
N
i “1
The estimation error is calculated by using Equation (11) with Gest given by the estimated data
interpolated from the 1, 2 and 3 days-ahead irradiance forecasts, and Gmeas equal to the irradiance
G pyr measured from the pyranometer. Figures 3–5 show the RMSE, the MBE and the MAE calculated
errors, respectively, expressed in kW/m2 for the days of July 2012 in the sites “Gi” and “Ma”.
For example, it can be observed that on 23 July there is a significant increase of the three errors with
Energies 2016, 9, 8 15 of 27
respect
Energiesto2016,
the9,preceding
page–page days, at both sites. This situation can be explained by looking at the last
graphs of Figure 2, in which the sky on 23 July becomes variable after a sequence of clearer days.
graphs situation
A similar of Figure occurs
2, in which
on 24theJulyskyat on 23 sites
both July and
becomes
on 25variable aftersite
July at the a sequence
“Gi”. of clearer days.
A similar situation occurs on 24 July at both sites and on 25 July at the site
On the average, the 1-day ahead estimate is the most accurate, with lower errors compared “Gi”.
On the average, the 1-day ahead estimate is the most accurate, with lower errors compared to
to the 2-days and 3-days ahead estimates. In particular, considering the RMSE errors in Figure 3,
the 2-days and 3-days ahead estimates. In particular, considering the RMSE errors 2 for in Figure 3, the
the average value of the 1-day ahead estimates give figures around 119 W/m the site “Gi” and
average value of the 1-day ahead estimates give figures around 119 W/m for the site2 “Gi” and 2
around 107 W/m2 2for the site “Ma”; whereas the maximum value is around 266 W/m for the site
around 107 W/m for the 2site “Ma”; whereas the maximum value is around 266 W/m2 for the site 2
“Gi” and around 280 W/m 2for the site “Ma”. Furthermore, the minimum value is around 81 W/m
“Gi” and around 280 W/m for the site “Ma”. Furthermore, the minimum value is around 81 W/m2
for the site “Gi” and around 82 W/m2 2 for the site “Ma”. From Figure 4, it can be pointed out that
for the site “Gi” and around 82 W/m for the site “Ma”. From Figure 4, it can be pointed out that the
the1-day
1-dayahead
aheadestimates
estimates give MBE figures around 2 for the site “Gi” and around 40 W/m2
give MBE figures around 50 50
W/mW/m
2 for the site “Gi” and around 40 W/m2 for
forthe
thesite
site“Ma”.
“Ma”.In In 2
the best results the MBE index decreases down to 20to
the best results the MBE index decreases down 20 2W/m
W/m for theforsitethe siteand
“Gi” “Gi”
and 2 2
down to 10 W/m for the site “Ma”, and in the worst results the MBE raises up to 140 W/m for thefor
down to 10 W/m2 for the site “Ma”, and in the worst results the MBE raises up to 140 W/m
2
thesite
site“Gi”
“Gi” and 2 for the site “Ma”. The presence of a positive bias (with estimates
and upup to 160
to 160 W/m W/m
2 for the site “Ma”. The presence of a positive bias (with estimates higher
higher
than than the measured
the measured values)values)
may be may be associated
associated with
with air air pollution.
pollution. From Figure
From Figure 5, the 5,MAEthe for
MAE thefor
the1-day
1-dayahead
ahead estimates
estimates is 90
is 90 W/mW/m2 for2 the
forsite
the“Gi”
site “Gi”
and 80and
W/m80 2W/m 2 for the site “Ma”, the minimum
for the site “Ma”, the minimum value
value is about 60 2W/m 2 for both sites and the maximum value 2is 180 W/m2 for the site “Gi” and
is about 60 W/m for both sites and the maximum value is 180 W/m for the site “Gi” and 190 W/m2 for
190the
W/m 2
site “Ma”.
for the site “Ma”.
0.6
0.5
0.4
[kW/m2]
0.3
0.2
0.1
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
days
(a)
RMSE 1-day RMSE 2-days RMSE 3-days
0.6
0.5
0.4
[kW/m2]
0.3
0.2
0.1
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
days
(b)
Figure 3. The RMSE in kW/m2 in July. (a) Site “Gi”; (b) Site “Ma”.
Figure 3. The RMSE in kW/m2 in July. (a) Site “Gi”; (b) Site “Ma”.
15
Energies 2016, 9, page–page
Energies 2016, 9, 8 16 of 27
Energies 2016, 9, page–page
MBE 1-day MBE 2-days MBE 3-days
0,4
0,4
[kW/m2]
0,3
[kW/m2]
0,3
0,2
0,2
0,1
0,1
0,0
0,0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
days
days
(a)
(a)
MBE 1-day
MBE 1-day
MBE 2-days
MBE 2-days
MBE 3-days
MBE 3-days
0,60,6
0,50,5
0,40,4
[kW/m2]
[kW/m2]
0,30,3
0,20,2
0,1
0,1
0,0
0,0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15days
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
days
(b)
(b)
Figure 4. The MBE in kW/m2 in
TheMBE
MBEininkW/m
kW/m 2 July. (a)(a)
Site “Gi”; (b) Site “Ma”.
Figure4.4.The
Figure 2 in in July.
July. Site“Gi”;
(a) Site “Gi”;(b)
(b) Site
Site “Ma”.
“Ma”.
MAE 1-days MAE 2-days MAE 3-days
0,7 MAE 1-days MAE 2-days MAE 3-days
0,7
0,6
0,6
0,5
0,5
0,4
[kW/m2]
0,4
[kW/m2]
0,3
0,3
0,2
0,2
0,1
0,1
0,0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
0,0 days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
(a)
days
Figure(a)
5. Cont.
Figure
Figure 5.
5. Cont.
Cont.
16
16
Energies 2016, 9, 8 17 of 27
Energies 2016, 9, page–page
Energies 2016, 9, page–page
MAE 1-days MAE 2-days MAE 3-days
0,7 MAE 1-days MAE 2-days MAE 3-days
0,7
0,6
0,6
0,5
0,5
0,4
2] 2
]
0,4
[kW/m
[kW/m
0,3
0,3
0,2
0,2
0,1
0,1
0,0
0,0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15days
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
days
(b)
(b)
Figure
Figure5.5.The
TheMAE
MAEininkW/m
kW/min
2 July.
2 in (a)(a)Site
July. Site“Gi”;
“Gi”;(b)
(b) Site “Ma”.
Site “Ma”.
Figure 5. The MAE in kW/m2 in July. (a) Site “Gi”; (b) Site “Ma”.
In order to provide an overall view of the estimation errors during the year 2012, Figure 6
showsInthe
order to provide
monthly average anvalues
overall
of view of the
the daily estimation
RMSE, MAE anderrors
MBEduring thefrom
obtained yearthe
2012, Figure 6
1 day-ahead
shows the monthly average values of the daily RMSE, MAE and MBE obtained from the 1 day-ahead
estimates. At both sites, relatively high average errors occur in April and May, while generally the
estimates.
months withAt
Atboth
bothsites,
lower
sites,relatively
errors are from high
relatively average
high average
October errors
to occur
errors in April
occur
January. These andand
in April
results May, while
May, generally
while
are consistent with the
generally
the
months with
the months lower
with lowererrors are
errors from
are fromOctober
OctobertotoJanuary.
January.These
Theseresults
resultsare
occurrence of the most relevant ISBC effects in April and May, as shown in Table 5.
are consistent
consistent with
with the
occurrence
occurrence of
of the
the most
most relevant ISBC effects
relevant ISBC effects in
in April
April and
and May,
May, as
as shown
shownin inTable
Table5.5.
0.20
0.18 RMSE
MAE
0.16
MBE
0.14
average error [kW/m2]
0.12
0.10
0.08
0.06
0.04
0.02
0.00
1 2 3 4 5 6 7 8 9 10 11 12
month number
(a)
(a)
Figure 6. Cont.
Figure 6. Cont.
Figure 6. Cont.
17
17
Energies 2016, 9, 8 18 of 27
Energies 2016, 9, page–page
(b)
Figure 6. Monthly average values of the daily RMSE, MAE and MBE obtained from the 1-day ahead
Figure 6. Monthly average values of the daily RMSE, MAE and MBE obtained from the 1-day ahead
estimates at
estimates at the
the two
two sites. (a) Site
sites. (a) Site“Gi”;
“Gi”;(b)
(b) Site
Site “Ma”.
“Ma”.
18
Energies 2016, 9, 8 19 of 27
Energies
Energies 2016,
2016, 9, page–page
9, page–page
1 1
1 1
0.8 0.8
0.8 0.8
positive bias positive bias
positive bias positive bias
0.6 negative bias 0.6 negative bias
0.6 negative bias 0.6 negative bias
0.4 0.4
0.4 0.4
0.2 0.2
0.2 0.2
Bias
Bias
0 0
Bias
Bias
0 0
-0.2 -0.2
-0.2 -0.2
-0.4 -0.4
-0.4 -0.4
-0.6 -0.6
-0.6 -0.6
-0.8 -0.8
-0.8 -0.8
-1 -1
0 2000 4000 6000 8000 10000 12000 14000 0
16000 2000 20000
18000 4000 6000 8000 10000 12000 14000 16000 18000 20000
-1 -1
number of 15-min number of 15-min
0 2000 4000 6000 8000 10000 12000 0 2000 4000
14000 16000 18000 20000 6000 8000 10000 12000 14000 16000 18000 20000
(a)
number of 15-min
(b) number of 15-min
Figure 7. Duration(a)
curve of positive and negative bias for the solar irradiance(b)
estimated data with
Duration
Figure 7. respect curve of positive
to measurements and
for the year negative
2012. bias (b)
(a) Site “Gi”; forSite
the“Ma”.
solar irradiance estimated data with
Figure 7. Duration curve of positive and negative bias for the solar irradiance estimated data with
respect to measurements for the year 2012.MBE+ (GI)
(a) Site MBE+ (MA)
“Gi”; (b) Site “Ma”.
respect to measurements
0.8 for the year 2012. (a) Site “Gi”; (b) Site “Ma”.
MBE+ (GI) MBE+ (MA)site “Gi”
site “Ma”
0.80.7
site “Gi”
site “Ma”
0.70.6
Bias Error
0.60.5
Bias Error
MeanBias
0.50.4
Positive
MeanBias
Positive
5 % of the data 95 %
0.1
0.2 5 % of the data 95 %
0
0.1 0 80 160 240 320 400 480 560 640 720 800
number of 15-min
n° of 15-min
0
Figure 8. Zoom
0 of the
80 duration
160 curves
240 of positive
320 bias
400 for 480
the solar
560irradiance
640 estimated
720 data with
800
number
respect to measurements for the year 2012 at then° of“Gi”
15-min
of 15-min
sites and “Ma”.
Figure 8. Zoom of the duration curves of positive bias for the solar irradiance estimated data with
Figure 8. Zoom of the duration curves of positive bias for the solar irradiance estimated data with
respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
Energies 2016, 9, page–page
number
n° of 15-min
of 15-min
0 60 120 180 240 300 360 420 480 540 600
0
5 %of the data 95 %
-0.1
BiasBias Error
5 % of the data 95 %
-0.2
Mean
Negative
-0.3
Negative
19
site “Gi”
-0.4 site “Ma”
19
-0.5 MBE- (GI) MBE- (MA)
-0.6
Figure 9. Zoom of the duration curves of negative bias for the solar irradiance estimated data with
Figure 9. Zoom of the duration curves of negative bias for the solar irradiance estimated data with
respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
1
0.9
0.8
0.7
site "Gi"
e Error
Figure
Energies 2016, 9.
9, 8Zoom
-0.6 of the duration curves of negative bias for the solar irradiance estimated data with
20 of 27
respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
Figure 9. Zoom of the duration curves of negative bias for the solar irradiance estimated data with
respect to measurements
1
for the year 2012 at the sites “Gi” and “Ma”.
0.91
0.8
0.9
0.7
0.8
site "Gi"
Error Error
0.6
0.7 site "Ma"
site "Gi"
Absolute
0.5
0.6 site "Ma"
Absolute
0.4
0.5
0.3
0.4
0.2
0.3
0.1
0.2
0
0.1
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
0 number of 15-min
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
Figure 10. Duration curve of the absolute errors forof the
number solar irradiance estimated data with respect
Figure 10. Duration curve of the absolute errors
MAE (GI)
for 15-min
the solar irradiance estimated data with respect
MAE (MA)
to measurements for the year 2012.
to measurements
Figure 0.8
for
10. Duration the
curveyear
of 2012.
the absolute errors for the solar irradiance estimated data with respect
MAE (GI) MAE (MA)
to measurements for the year 2012. site “Gi”
0.8
0.7 site “Ma”
site “Gi”
0.7 site “Ma”
0.6
ErrorError
0.6
0.5
Absolute
Error
0.5
0.4
Absolute
Error
MeanAbsolute
ean
0.4 95 %
0.3 5 %of the data
M
Absolute
0.3
0.2 5 %of the data 95 %
5 %of the data 95 %
0.2
0.1 95 %
5 %of the data
0.1
0
0 100 200 300 400 500 600 700 800 900 1000
0 n° ofof15-m
number in
15-min
0 100 200 300 400 500 600 700 800 900 1000
Figure 11. Zoom of the duration curves of the
estimated data n° ofof15-m
absolute
number in
error for the solar irradiance
15-min
with respect to measurements for the year 2012 at the sites “Gi” and “Ma”.
Figure
Figure 11.
11. Zoom
Zoom of
of the
the duration
duration curves
curves of
of the
the absolute
absolute error
error for
for the
the solar
solar irradiance
irradiance estimated
estimated data
data
with respect to measurements for the year 2012 at the sites “Gi” and
with respect to measurements for the year 2012 at the sites “Gi” and “Ma”. “Ma”.
20
20
5. AC Power Estimations Compared with Experimental Results
Figure 12 shows the application of the PV conversion model to the reference-cell irradiance data
for seven consecutive days of July 2012 in the sites “Gi” and “Ma”. For example, low deviations occur
on 23 July (an extremely variable day), meaning that the model is able to follow also huge irradiance
variations. Moreover, thanks to the days with clear sky, since the deviations are proportional to the
solar irradiance, it is possible to detect the failure of a portion of the PV arrays, becoming evident by
the occurrence of large and regular deviations between the measured values and the outputs of the
model, as reported in [20]. Thereby, a salient characteristic of the model is that it can be useful for
fault diagnosis.
irradiance variations. Moreover, thanks to the days with clear sky, since the deviations are
proportional to the solar irradiance, it is possible to detect the failure of a portion of the PV arrays,
becoming evident by the occurrence of large and regular deviations between the measured values
and the outputs of the model, as reported in [20]. Thereby, a salient characteristic of the model
Energies 2016, 9, 8
is that
21 of 27
it can be useful for fault diagnosis.
(a) (b)
Figure 12. 12.
Figure Comparison
Comparisonbetween
between PVPVpower
powermeasurements
measurements and simulations
and simulations forconsecutive
for seven seven consecutive
days
daysofofJuly
July2012.
2012. (a) Site “Gi”; (b) Site
(a) Site “Gi”; (b) Site “Ma”. “Ma”.
21
The differences appearing in Figure 12 may be also attributed to the fact that average values
have been used in the representation of the sources of losses and efficiencies, with the scope of
Energies 2016, 9, page–page
Energies 2016, 9, 8 22 of 27
The differences appearing in Figure 12 may be also attributed to the fact that average values
have been used in the representation of the sources of losses and efficiencies, with the scope of
estimating both clear sky and and variable
variable conditions
conditions without
without varying
varying the
the efficiencies
efficiencies in function of thethe
sky conditions.
the calculation
For the calculationofofthe
thepower
powerPAC P AC to used
to be be used in Equation
in Equation (9),reference-cell
(9), the the reference-cell irradiance
irradiance data
data gathered
gathered on theon tilted
the tilted
plane GtcellG, tcell
plane , averaged
averaged on on 15-min
15-min basis,
basis, areare usedasasinputs
used inputsofof the
the model
model
previously described.
described. The Theresults
resultsofoferror
errorcalculation
calculationfor for the
the estimated
estimated power
power profiles
profiles areare reported
reported in
in the
the following
following figures.
figures. TheThe error
error durationcurves
duration curvescalculated
calculatedforforP∆Pare
arerepresented
represented with
with averaging
time step of 15 min and on an annual basis. Figure Figure 1313 shows
shows the
the duration
duration curves
curves ofof positive
positive and
and
negative P∆P errors. At At both
both sites,
sites, the number of negative errors errors ∆P
P isis higher
´
− higher than
than the
the number
number of
∆P+`, ,but
positive errors P butthe
thepositive
positiveerrors
errorsmay maybe bequantitatively
quantitativelyhigher.
higher. This
This aspect
aspect is
is confirmed
confirmed by
comparing the results shown in the zoom of of Figure
Figure 14 (for
(for positive
positive estimation
estimation errors)
errors) and Figure 15
(for negative estimation errors). The The corresponding
corresponding errors exceeded by 5% of the number of quarters
of hour in one year are of about 120–130 kW for the positive errors at the two sites, and of about about
kW and kW for the negative errors at the sites “Gi” and
−60 kW and −100 kW for the negative errors at the sites “Gi” and “Ma”, respectively.
´60 ´100 “Ma”, respectively.
(a)
(b)
Figure
Figure 13.
13. Duration
Duration curve
curve of
of positive
positive and
and negative
negative estimation
estimation errors
errors of
of the
the AC
AC power
power profiles
profiles with
with
respect to experimental results for the year 2012. (a) Site “Gi”; (b) Site “Ma”.
respect to experimental results for the year 2012. (a) Site “Gi”; (b) Site “Ma”.
22
Energies 2016, 9, 8 23 of 27
Energies 2016, 9, page–page
Figure 14. Zoom of the duration curves of positive estimation errors of the AC power profiles with
Figure 14. Zoom of the duration curves of positive estimation errors of the AC power profiles with
respect to experimental results for the year 2012 at the sites “Gi” and “Ma”.
Figure
respect 14. Zoom of the results
to experimental durationforcurves of 2012
the year positive estimation
at the sites “Gi”errors of the AC power profiles with
and “Ma”.
respect to experimental results for the year 2012 at the sites “Gi” and “Ma”.
Figure 15. Zoom of the duration curves of negative estimation errors of the AC power profiles with
respect to experimental results for the year 2012 at the sites “Gi” and “Ma”.
Figure 15. Zoom of the duration curves of negative estimation errors of the AC power profiles with
Figure 15. Zoom of the duration curves of negative estimation errors of the AC power profiles with
respect to experimental results for the year 2012 at the sites “Gi” and “Ma”.
6. Conclusions
respect to experimental results for the year 2012 at the sites “Gi” and “Ma”.
This paper has presented the comparison of irradiance and AC power estimates with respect to
6. Conclusions
6. Conclusions
the experimental results gathered from meteorological stations and energy meters in grid-connected
This paper has presented the comparison of irradiance and AC power estimates with respect to
PV systems.
This paper Thehasdata used refer
presented to two PV of
the comparison sites located and
irradiance in Southern
AC power Italy. The solar
estimates with irradiance
respect to
the experimental results gathered from meteorological stations and energy meters in grid-connected
forecasts
the up to 3 days
experimental ahead
results on the
gathered horizontal
from plane, available
meteorological from
stations and a weather
energy forecast
meters provider at
in grid-connected
PV systems. The data used refer to two PV sites located in Southern Italy. The solar irradiance
geographic
PV systems.coordinates
The data usedclose refer
to the
toPV
twoplants, have
PV sites been used
located to obtain
in Southern estimated
Italy. The solardatairradiance
patterns.
forecasts up to 3 days ahead on the horizontal plane, available from a weather forecast provider at
It has been
forecasts upestablished to what
to 3 days ahead on extent the estimated
the horizontal plane, data referring
available fromtoa the 1 day-ahead
weather forecast forecast
providerare
at
geographic coordinates close to the PV plants, have been used to obtain estimated data patterns.
better than coordinates
geographic the estimated datatodetermined
close the PV plants,fromhave
the been
2 andused
3 days-ahead forecasts, by
to obtain estimated calculating
data patterns.
It has been established to what extent the estimated data referring to the 1 day-ahead forecast are
some
It has classical average to
been established errors.
whatAextent
methodthe to classify each
estimated hour of atoday
data referring theby using threeforecast
1 day-ahead categories
are
better than the estimated data determined from the 2 and 3 days-ahead forecasts, by calculating
(variable,
better thancloudy, or clear) has
the estimated databeen implemented.
determined from the Examining the resultsforecasts,
2 and 3 days-ahead month byby month, it hassome
calculating been
some classical average errors. A method to classify each hour of a day by using three categories
possible average
classical to determine
errors.the number to
A method ofclassify
successfuleachand
hourunsuccessful
of a day by classifications provided(variable,
using three categories by the
(variable, cloudy, or clear) has been implemented. Examining the results month by month, it has been
1 day-ahead
cloudy, or clear)estimated
has beendata with respect
implemented. to the pyranometer
Examining measurements.
the results month by month, The low
it has number
been of
possible
possible to determine the number of successful and unsuccessful classifications provided by the
clear-sky
to determinedays,theespecially
number of insuccessful
spring and andsummer, can beclassifications
unsuccessful explained by provided
the air turbidity,
by the 1e.g., due to
day-ahead
1 day-ahead estimated data with respect to the pyranometer measurements. The low number of
pollution deriving
estimated data withfrom human
respect activities.
to the Deep measurements.
pyranometer cloudy weather The caseslow
cannumber
be reproduced when
of clear-sky the
days,
clear-sky days, especially in spring and summer, can be explained by the air turbidity, e.g., due to
WRF forecasts indicate low irradiance values and the polynomial spline connecting these points
pollution deriving from human activities. Deep cloudy weather cases can be reproduced when the
remains well below the clear sky conditions.
WRF forecasts indicate low irradiance values and the polynomial spline connecting these points
remains well below the clear sky conditions. 23
23
Energies 2016, 9, 8 24 of 27
especially in spring and summer, can be explained by the air turbidity, e.g., due to pollution deriving
from human activities. Deep cloudy weather cases can be reproduced when the WRF forecasts
indicate low irradiance values and the polynomial spline connecting these points remains well below
the clear sky conditions.
The results obtained for the ISBC effect have shown that this particular effect contributes to
determine variable sky conditions. Assessing the ISBC effect is useful to explain the presence of
power production peaks even higher than the rated power specified at STC of irradiance and cell
temperature. The ISBC effect, even if noticeable on 1-min scale, is smoothed on the 15-min scale and
considering the aggregation of more locations.
For the comparison between estimated and measured data, the statistical indicators RMSE,
MAE and MBE have been calculated. Considering positive and negative MBE, the error duration
curves have been obtained for 15-min averaged irradiance values on an annual basis. Finally,
the combination of irradiance estimation and PV conversion model provides interesting results to
boost the PV penetration into the grid. Considering the error of the AC power calculated from the
PV model with respect to the AC power measured by the meters on the real grid-connected PV
system, the error duration curve allows us determine which positive or negative errors occur for
an established percentage of the data analyzed.
The categorization of the types of sky for each period of the day, associated with the short-term
estimation of the weather conditions, is a specific information that can be used to quantify the
additional reserve necessary to balance the fluctuations of the PV generation in periods in which
high fluctuations are expected, without requiring such reserve to be continuously available [55,56].
The connection of PV power to the grid, like in the case of wind power, requires additional reserve
with respect to the normal reserve required for the balance control of the grid [57]. For this purpose,
the information on the PV forecasting uncertainty can be handled to assist the assessment of the
amount of reserves needed to integrate the uncertain PV generation into the electrical system. For this
purpose, persistence models, Markov chains and neural networks can be applied [56–58]. These
results are also useful to estimate the contribution of PV in the definition of capacity value and
capacity credit of renewable energy sources [59–61].
Acknowledgments: Part of the research leading to these results has received funding from the European
Union Seventh Framework Programme FP7 under grant agreement No. 309048, project SiNGULAR (Smart and
Sustainable Insular Electricity Grids Under Large-Scale Renewable Integration).
Author Contributions: The authors contributed equally to the work.
Conflicts of Interest: The authors declare no conflict of interest.
References
1. Jensenius, J.S. Solar Resources. In Insolation Forecasting; Massachusetts Institute of Technology (MIT) Press:
Cambridge, MA, USA, 1989; pp. 335–349.
2. Glahn, H.R.; Lowry, D.A. The use of model output statistics (MOS) in objective weather forecasting.
Appl. Meteorol. 1972, 11, 1203–1211. [CrossRef]
3. Kaifel, A.K.; Jesemann, P. An adaptive filtering algorithm for very short-range forecast of cloudiness
applied to meteosat data. In Proceedings of the 9th Meteosat Scientific Users Meeting, Locarno,
Switzerland, 15–18 September 1992.
4. Beyer, H.G.; Costanzo, C.; Heinemann, D.; Reise, C. Short range forecast of PV energy production using
satellite image analysis. In Proceedings of the 12th European Photovoltaic Solar Energy Conference,
Amsterdam, The Netherlands, 11–15 April 1994; pp. 1718–1721.
5. Kang, B.O.; Tam, K. New and improved methods to estimate day-ahead quantity and quality of solar
irradiance. Appl. Energy 2015, 137, 240–249. [CrossRef]
6. Huld, T.; Amillo, A. Estimating PV module performance over large geographical regions: The role of
irradiance, air temperature, wind speed and solar spectrum. Energies 2015, 8, 5159–5181. [CrossRef]
Energies 2016, 9, 8 25 of 27
7. Mellit, A.; Massi Pavan, A. Performance prediction of 20 kWp grid-connected photovoltaic plant at Trieste
(Italy) using artificial neural network. Energy Convers. Manag. 2010, 51, 2431–2441. [CrossRef]
8. Mellit, A.; Massi Pavan, A. A 24-h forecast of solar irradiance using artificial neural network: Application
for performance prediction of a grid-connected PV plant at Trieste, Italy. Sol. Energy 2010, 84, 807–821.
[CrossRef]
9. Izgi, E.; Oztopal, A.; Yerli, B.; Kaymak, M.K.; Sahin, A.D. Short-mid-term solar power prediction by using
artificial neural networks. Sol. Energy 2012, 86, 725–733. [CrossRef]
10. Da Silva Fonseca, J.G., Jr.; Oozeki, T.; Takashima, T.; Koshimizu, G.; Uchida, Y.; Ogimoto, K. Use of support
vector regression and numerically predicted cloudiness to forecast power output of a photovoltaic power
plant in Kitakyushu, Japan. Progress Photovolt. Res. Appl. 2011, 20, 874–882. [CrossRef]
11. Shi, J.; Lee, W.; Liu, Y.; Yang, Y.; Wang, P. Forecasting power output of photovoltaic systems based on
weather classification and support vector machines. IEEE Trans. Ind. Appl. 2012, 48, 1064–1069. [CrossRef]
12. Bouzerdoum, M.; Mellit, A.; Massi Pavan, A. A hybrid model (SARIMA–SVM) for short-term power
forecasting of a small-scale grid-connected photovoltaic plant. Sol. Energy 2013, 98, 226–235. [CrossRef]
13. Pelland, S.; Galanis, G.; Kallos, G. Solar and photovoltaic forecasting through post-processing of the global
environmental multiscale numerical weather prediction model. Progress Photovolt. Res. Appl. 2011, 21,
284–296. [CrossRef]
14. Cai, T.; Duan, S.; Chen, C. Forecasting power output for grid-connected photovoltaic power system without
using solar radiation measurement. In Proceedings of the 2nd IEEE International Symposium on Power
Electronics for Distributed Generation Systems (PEDG), Hefei, China, 16–18 June 2010.
15. Bessa, R.J.; Trindade, A.; Miranda, V. Spatial-temporal solar power forecasting for smart grids. IEEE Trans.
Ind. Inform. 2015, 11, 232–241. [CrossRef]
16. Dambreville, R.; Blanc, P.; Chanussot, J.; Boldo, D. Very short term forecasting of the global horizontal
irradiance using a spatio-temporal autoregressive model. Renew. Energy 2014, 72, 291–300. [CrossRef]
17. Iqbal, M. An introduction to solar radiation; Academic Press: Toronto, ON, Canada, 1983.
18. Duffie, J.A.; Beckman, W.A. Solar Engineering of Thermal Processes, 2nd ed.; Wiley Interscience: New York,
NY, USA, 1991.
19. Şen, Z. Solar Energy Fundamentals and Modeling Techniques; Springer: Berlin, Germany, 2008; pp. 70–71.
20. The American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE). Handbook of
Fundamentals, American Society of Heating, Refrigeration and Air-Conditioning Engineers; ASHRAE: Atlanta,
GA, USA, 1993.
21. Moon, P.; Spencer, D.E. Illumination from a non uniform sky. Illum. Eng. 1942, 37, 707–726.
22. Chicco, G.; Cocina, V.; Spertino, F. Characterization of solar irradiance profiles for photovoltaic system
studies through data rescaling in time and amplitude. In Proceedings of the 49th International Universities’
Power Engineering Conference (UPEC 2014), Cluj-Napoca, Romania, 2–5 September 2014.
23. Joint Research Centre of the European Commission, Photovoltaic Geographical Information System (PVGIS).
Available online: http://re.jrc.ec.europa.eu/pvgis/apps4/pvest.php (accessed on 16 December 2015).
24. Spertino, F.; di Leo, P.; Cocina, V. Accurate measurements of solar irradiance for evaluation of photovoltaic
power profiles. In Proceedings of the IEEE Conference Powertech, Grenoble, France, 16–20 June 2013;
pp. 1–5.
25. Czekalski, D.; Chochowski, A.; Obstawski, P. Parameterization of daily solar irradiance variability.
Renew. Sustain. Energy Rev. 2012, 16, 2461–2467. [CrossRef]
26. Badosa, J.; Haeffelin, M.; Chepfer, H. Scales of spatial and temporal variation of solar irradiance on Reunion
tropical island. Sol. Energy 2013, 88, 42–56. [CrossRef]
27. Chicco, G.; Cocina, V.; di Leo, P.; Spertino, F. Weather forecast-based power predictions and experimental
results from photovoltaic systems. In Proceedings of the IEEE Conference Speedam, Ischia, Italy,
18–20 June 2014.
28. International Organization for Standardization (ISO). Solar Energy—Specification and Classification of
Instruments for Measuring Hemispherical Solar and Direct Solar Radiation; ISO 9060:1990; ISO: Geneva,
Switzerland, 1990.
29. Carullo, A.; Ferraris, F.; Vallan, A.; Spertino, F.; Attivissimo, F. Uncertainty analysis of degradation
parameters estimated in long-term monitoring of photovoltaic plants. Measurement 2014, 55, 641–649.
[CrossRef]
Energies 2016, 9, 8 26 of 27
30. Reinders, A.H.M.E.; van Dijk, V.A.P.; Wiemken, E.; Turkenburg, W.C. Technical and economic analysis of
grid-connected PV systems by means of simulation. Progress Photovolt. Res. Appl. 1999, 7, 71–82. [CrossRef]
31. Markvart, T. Solar Electricity, 2nd ed.; John Wiley & Sons: Hoboken, NJ, USA, 2000.
32. International Electrotechnical Commission (IEC). Crystalline Silicon Photovoltaic (PV) Array. On-Site
Measurement of I-V Characteristics; IEC 61829; British Standards Institution: Geneva, Switzerland, 1998.
33. Spertino, F.; Sumaili Akilimali, J. Are manufacturing I-V mismatch and reverse currents key factors in large
photovoltaic arrays? IEEE Trans. Ind. Electron. 2009, 56, 4520–4531. [CrossRef]
34. Spertino, F.; Corona, F. Monitoring and checking of performance in photovoltaic plants: A tool for design,
installation and maintenance of grid-connected systems. Renew. Energy 2013, 60, 722–732. [CrossRef]
35. Spertino, F.; Corona, F.; di Leo, P. Limits of advisability for master-slave configuration of DC-AC converters
in photovoltaic systems. IEEE J. Photovolt. 2012, 2, 547–554. [CrossRef]
36. Tapakis, R.; Charalambides, A.G. Equipment and methodologies for cloud detection and classification:
A review. Sol. Energy 2013, 95, 392–430. [CrossRef]
37. De Miguel, A.; Bilbao, J.; Aguiar, R.; Kambezidis, H.; Negro, E. Diffuse solar irradiation model evaluation
in the North Mediterranean Belt area. Sol. Energy 2001, 70, 143–153. [CrossRef]
38. Erbs, D.G.; Kein, S.A.; Duffie, J.A. Estimation of the diffuse radiation fraction for hourly, daily and
monthly-average global radiation. Sol. Energy 1982, 28, 293–302. [CrossRef]
39. Orgill, J.F.; Hollands, K.G.T. Correlation equation for hourly diffuse radiation on a horizontal surface.
Sol. Energy 1977, 19, 357–359. [CrossRef]
40. Iqbal, M. Prediction of hourly diffuse solar radiation from measured hourly global radiation on a horizontal
surface. Sol. Energy 1980, 24, 491–503. [CrossRef]
41. Lorenz, E.; Heinemann, D. Prediction of solar irradiance and photovoltaic power. Compr. Renew. Energy
2012, 1, 239–292.
42. Meteorological Service of Catalonia, Meteo.Cat. Available online: http://www.meteo.cat (accessed on
16 December 2015).
43. The Weather Research & Forecasting Model. Available online: http://www.wrf-model.org (accessed on
16 December 2015).
44. Cocina, V. Economy of Grid-Connected Photovoltaic Systems and Comparison of Irradiance/Electric
Power Predictions vs. Experimental Results. Ph.D. Thesis, Politecnico di Torino, Torino, Italy, 2014.
45. Sluiter, R. Interpolation methods for climate data. Literature review. KNMI (Koninklijk Nederlands
Meteorologisch Instituut) intern rapport IR 2009-04. De Bilt, The Netherlands, 19 November 2008.
46. Estupiñán, J.G.; Raman, S.; Crescenti, G.H.; Streicher, J.J.; Barnard, W.F. Effects of clouds and haze on UV-B
radiation. J. Geophys. Res. 1996, 101, 16807–16816. [CrossRef]
47. Craig, F.; Bohren, C.F.; Clothiaux, E.E. Fundamentals of Atmospheric Radiation; Wiley-VCH: Weinheim,
Germany, 2006.
48. Morf, H. A stochastic solar irradiance model adjusted on the Ångström-Prescott regression. Sol. Energy
2013, 87, 1–21. [CrossRef]
49. Luoma, J.; Kleissl, J.; Murray, K. Optimal inverter sizing considering cloud enhancement. Sol. Energy 2012,
86, 421–429. [CrossRef]
50. Wirth, G.; Lorenz, E.; Spring, A.; Becker, G.; Pardatscher, R.; Witzmann, R. Modeling the maximum power
output of a distributed PV fleet. Progress Photovolt. Res. Appl. 2015, 23, 1164–1181. [CrossRef]
51. Yordanov, G.H.; Midtgård, O.-M.; Saetre, T.O.; Nielsen, H.K.; Norum, L.E. Overirradiance (Cloud
Enhancement) events at high latitudes. IEEE J. Photovolt. 2013, 3, 271–277. [CrossRef]
52. Lorenz, E.; Hurka, J.; Heinemann, D.; Beyer, H.G. Irradiance forecasting for the power prediction of
grid-connected photovoltaic systems. IEEE J. Sel. Top. Appl. Earth Obs. Remote Sens. 2009, 2, 2–10.
[CrossRef]
53. IEA (International Energy Agency). Photovoltaic and solar forecasting: State of the art. In Report IEA
Photovoltaic Power Systems Programme (PVPS) T14; IEA: St. Ursen, Switzerland, 2013; Volume 1, pp. 1–36.
54. Diagne, M.; David, M.; Lauret, P.; Boland, J.; Schmutz, N. Review of solar irradiance forecasting methods
and a proposition for small-scale insular grids. Renew. Sustain. Energy Rev. 2013, 27, 65–76. [CrossRef]
55. Nijhuis, M.; Rawn, B.; Gibescu, M. Prediction of power fluctuation classes for photovoltaic installations and
potential benefits of dynamic reserve allocation. IET Renew. Power Gener. 2014, 8, 314–323. [CrossRef]
Energies 2016, 9, 8 27 of 27
56. Yan, X.; Francois, B.; Abbes, D. Operating power reserve quantification through PV generation uncertainty
analysis of a microgrid. In Proceedings of the IEEE PowerTech, Eindhoven, The Netherlands,
29 June–2 July 2015.
57. Brouwer, A.S.; van den Broek, M.; Seebregts, A.; Faaij, A. Impacts of large-scale intermittent renewable
energy sources on electricity systems, and how these can be modeled. Renew. Sustain. Energy Rev. 2014, 33,
443–466. [CrossRef]
58. Tabone, M.D.; Callaway, D.S. Modeling variability and uncertainty of photovoltaic generation: A hidden
state spatial statistical approach. IEEE Trans. Power Syst. 2015, 30, 2965–2973. [CrossRef]
59. Perez, R.; Taylor, M.; Hoff, T.; Ross, J.P. Reaching consensus in the definition of photovoltaics capacity credit
in the USA: A practical application of satellite-derived solar resource data. IEEE J. Sel. Top. Appl. Earth Obs.
Remote Sens. 2008, 1, 28–33. [CrossRef]
60. Simoglou, C.K.; Biskas, P.N.; Bakirtzis, E.A.; Matenli, A.N.; Petridis, A.I.; Bakirtzis, A.G. Evaluation of the
capacity credit of RES: The Greek case. In Proceedings of the IEEE PowerTech, Grenoble, France, 16–20 June
2013.
61. Munoz, F.D.; Mills, A.D. Endogenous assessment of the capacity value of solar PV in generation investment
planning studies. IEEE Trans. Sustain. Energy 2015, 6, 1574–1585. [CrossRef]
© 2015 by the authors; licensee MDPI, Basel, Switzerland. This article is an open
access article distributed under the terms and conditions of the Creative Commons by
Attribution (CC-BY) license (http://creativecommons.org/licenses/by/4.0/).