Modular Plant Unit Project: TAIF-NK HRCC Sulphur Production Unit

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Modular Plant Unit Date Issue : 25-Jun-14

Project: TAIF-NK HRCC Sulphur Production Unit Revision : 2

LIST OF MODULES & LOOSE PACKAGES


SRU 1A
DESCRIPTION TAG NO LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
3
meter (m) meter (m) meter (m) m pcs metric ton (MT)
SRU-1A-G1 21.000 5.330 6.500 727.55 1 SKID 52.16 3 JULY 2015
SRU-1A-G2 15.650 6.000 3.740 351.19 1 SKID 18.59 3 JULY 2015
SRU-1A-1st-1 21.000 5.330 3.240 362.65 1 SKID 22.16 3 JULY 2015
SRU-1A-1st-2 15.650 6.000 6.000 563.40 1 SKID 57.45 3 JULY 2015
SRU-1A-2nd-1 21.000 5.330 6.200 693.97 1 SKID 69.31 3 JULY 2015
SRU-1A-2nd-2 15.650 6.000 3.740 351.19 1 SKID 53.12 3 JULY 2015
3,049.94 6 272.79 3 JULY 2015

SRU 2A
DESCRIPTION LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
SRU-2A-G1 21.000 5.330 6.500 727.55 1 SKID 52.16 3 JULY 2015
SRU-2A-G2 15.650 6.000 3.740 351.19 1 SKID 18.59 3 JULY 2015
SRU-2A-1st-1 21.000 5.330 3.240 362.65 1 SKID 22.16 3 JULY 2015
SRU-2A-1st-2 15.650 6.000 6.000 563.40 1 SKID 57.45 3 JULY 2015
SRU-2A-2nd-1 21.000 5.330 6.200 693.97 1 SKID 69.31 3 JULY 2015
SRU-2A-2nd-2 15.650 6.000 3.740 351.19 1 SKID 53.12 3 JULY 2015
3,049.94 6 272.79

SRU 1B
DESCRIPTION LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
SRU-1B-G1 30.490 7.500 6.500 1,486.39 1 SKID 45.28 3 JULY 2015
SRU-1B-1st 30.490 7.500 6.500 1,486.39 1 SKID 45.28 3 JULY 2015

2,972.78 2 90.56

SRU 2B
DESCRIPTION LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
SRU-2B-G1 30.490 7.500 6.500 1,486.39 1 SKID 45.28 3 JULY 2015
SRU-2B-1st 30.490 7.500 6.500 1,486.39 1 SKID 45.28 3 JULY 2015

2,972.78 2 90.56

ARU
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
ARU-G1 15.800 7.000 6.500 718.90 1 SKID 27.41 3 JULY 2015
ARU-G2 15.800 7.000 6.500 718.90 1 SKID 48.55 3 JULY 2015
ARU-G3 16.825 5.250 6.500 574.15 1 SKID 22.20 3 JULY 2015
ARU-G4 16.825 5.000 6.500 546.81 1 SKID 16.66 3 JULY 2015
ARU-G5 16.825 5.650 6.500 617.90 1 SKID 39.04 3 JULY 2015
ARU-1st-1 15.800 6.274 6.500 644.34 1 SKID 19.63 3 JULY 2015
ARU-1st-2 15.800 6.000 6.500 616.20 1 SKID 22.27 3 JULY 2015
ARU-1st-3 15.800 6.300 6.500 647.01 1 SKID 42.52 3 JULY 2015
ARU-1st-4 15.800 6.000 6.500 616.20 1 SKID 59.74 3 JULY 2015
ARU-1st-5 15.800 6.239 6.500 640.75 1 SKID 22.39 3 JULY 2015
ARU-2nd-1 15.848 6.574 6.500 677.20 1 SKID 20.63 3 JULY 2015
ARU-2nd-2 15.848 6.000 6.500 618.07 1 SKID 105.83 3 JULY 2015
7,636.43 12 446.86

UTILITIES A
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
3
meter (m) meter (m) meter (m) m pcs metric ton (MT)
UTL-A-1 14.800 7.007 6.500 674.07 1 SKID 21.58 3 JULY 2015
UTL-A-2 14.800 7.450 6.500 716.69 1 SKID 24.37 3 JULY 2015
UTL-A-3 14.800 7.450 6.500 716.69 1 SKID 21.83 3 JULY 2015
UTL-A-4 14.800 7.000 6.500 673.40 1 SKID 20.51 3 JULY 2015
UTL-A-5 14.800 7.000 6.500 673.40 1 SKID 20.51 3 JULY 2015
UTL-A-6 14.800 7.000 6.500 673.40 1 SKID 20.51 3 JULY 2015
UTL-A-7 14.800 7.000 6.500 673.40 1 SKID 20.51 3 JULY 2015
UTL-A-8 14.800 7.007 6.500 674.07 1 SKID 20.53 3 JULY 2015
4,801.05 8 149.84

UTILITIES B
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
UTL-B-G1 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-G2 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-G3 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-G4 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-1st-1 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-1st-2 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-1st-3 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
UTL-B-1st-4 28.450 7.400 6.500 1,368.45 1 SKID 41.68 3 JULY 2015
10,947.56 8 291.79

Page 1
TGTU-A
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
3
meter (m) meter (m) meter (m) m pcs metric ton (MT)
TGTU A-1st-1 9.200 5.101 6.500 305.04 1 SKID 11.39 3 JULY 2015
TGTU A-1st-2 9.200 5.101 6.500 305.04 1 SKID 9.29 3 JULY 2015
TGTU A-1st-3 15.000 7.400 6.500 721.50 1 SKID 48.11 3 JULY 2015
TGTU A-1st-4 15.000 5.000 6.500 487.50 1 SKID 16.83 3 JULY 2015
TGTU A-1st-5 15.000 5.000 6.500 487.50 1 SKID 14.85 3 JULY 2015
TGTU A-1st-6 15.000 5.000 6.500 487.50 1 SKID 16.83 3 JULY 2015
TGTU A-2nd-1 10.200 7.158 6.500 474.58 1 SKID 28.89 3 JULY 2015
TGTU A-2nd-2 15.000 7.400 6.500 721.50 1 SKID 44.79 3 JULY 2015
TGTU A-2nd-3 15.000 6.250 6.500 609.38 1 SKID 18.56 3 JULY 2015
TGTU A-2nd-4 15.000 6.250 6.500 609.38 1 SKID 18.56 3 JULY 2015
TGTU A-3nd-1 10.200 7.158 6.500 474.58 1 SKID 12.05 3 JULY 2015
TGTU A-3nd-2 15.000 7.400 6.500 721.50 1 SKID 18.32 3 JULY 2015
TGTU A-4th 15.000 7.400 6.500 721.50 1 SKID 18.32 3 JULY 2015
7,126.48 13 276.79

TGTU-B
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
TGTU B-1st-1 9.200 5.101 6.500 305.04 1 SKID 11.39 3 JULY 2015
TGTU B-1st-2 9.200 5.101 6.500 305.04 1 SKID 9.29 3 JULY 2015
TGTU B-1st-3 15.000 7.400 6.500 721.50 1 SKID 48.11 3 JULY 2015
TGTU B-1st-4 15.000 5.000 6.500 487.50 1 SKID 16.83 3 JULY 2015
TGTU B-1st-5 15.000 5.000 6.500 487.50 1 SKID 14.85 3 JULY 2015
TGTU B-1st-6 15.000 5.000 6.500 487.50 1 SKID 16.83 3 JULY 2015
TGTU B-2nd-1 10.200 7.158 6.500 474.58 1 SKID 28.89 3 JULY 2015
TGTU B-2nd-2 15.000 7.400 6.500 721.50 1 SKID 44.79 3 JULY 2015
TGTU B-2nd-3 15.000 6.250 6.500 609.38 1 SKID 18.56 3 JULY 2015
TGTU B-2nd-4 15.000 6.250 6.500 609.38 1 SKID 18.56 3 JULY 2015
TGTU B-3nd-1 10.200 7.158 6.500 474.58 1 SKID 12.05 3 JULY 2015
TGTU B-3nd-2 15.000 7.400 6.500 721.50 1 SKID 18.32 3 JULY 2015
TGTU B-4th 15.000 7.400 6.500 721.50 1 SKID 18.32 3 JULY 2015
7,126.48 13 276.79

SWS
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
SWS-G1 15.900 7.000 6.500 723.45 1 SKID 22.04 3 JULY 2015
SWS-G2 15.900 6.500 6.500 671.78 1 SKID 28.93 3 JULY 2015
SWS-G3 15.900 5.372 6.500 555.20 1 SKID 21.81 3 JULY 2015
SWS-G4 15.900 6.000 6.500 620.10 1 SKID 22.95 3 JULY 2015
SWS-G5 12.400 6.000 6.500 483.60 1 SKID 20.53 3 JULY 2015
SWS-1st-1 15.900 7.000 6.500 723.45 1 SKID 28.83 3 JULY 2015
SWS-1st-2 23.813 5.574 6.500 862.77 1 SKID 26.28 3 JULY 2015
SWS-1st-3 23.813 5.000 6.500 773.92 1 SKID 23.57 3 JULY 2015
SWS-1st-4 23.813 5.274 6.500 816.33 1 SKID 24.87 3 JULY 2015
SWS-2nd 15.728 6.450 6.500 659.40 1 SKID 42.91 3 JULY 2015
6,889.99 10 262.73

LOOSE STRUCTURE
PIPERACK 1
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
MODULE 1 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 2 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 3 10.48 7.76 5.18 421.26 1 MODULE 16.40 28 FEBRUARY 2015
MODULE 4 10.48 7.76 3.85 313.10 1 MODULE 8.90 28 FEBRUARY 2015
MODULE 5 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 6 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 7 11.73 7.76 5.18 471.43 1 MODULE 19.71 28 FEBRUARY 2015
MODULE 8 11.73 7.76 3.85 350.39 1 MODULE 11.00 28 FEBRUARY 2015
MODULE 9 11.55 7.78 5.16 463.67 1 MODULE 22.20 28 FEBRUARY 2015
MODULE 10 11.55 7.78 4.00 359.44 1 MODULE 12.20 28 FEBRUARY 2015
MODULE 11 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 12 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 13 6.73 7.76 5.18 270.44 1 MODULE 11.73 28 FEBRUARY 2015
MODULE 14 6.73 7.76 3.85 201.01 1 MODULE 6.40 28 FEBRUARY 2015
MODULE 15 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 16 12.42 7.78 4.00 386.51 1 MODULE 8.23 28 FEBRUARY 2015
MODULE 17 10.65 7.78 5.16 427.54 1 MODULE 19.11 28 FEBRUARY 2015
MODULE 18 10.65 7.78 4.00 331.43 1 MODULE 10.51 28 FEBRUARY 2015
MODULE 19 9.51 7.76 5.18 382.19 1 MODULE 15.90 28 FEBRUARY 2015
MODULE 20 9.51 7.76 3.85 284.06 1 MODULE 8.60 28 FEBRUARY 2015
MODULE 21 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 22 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 23 11.73 7.76 5.18 471.43 1 MODULE 19.71 28 FEBRUARY 2015
MODULE 24 11.73 7.76 3.85 350.39 1 MODULE 10.70 28 FEBRUARY 2015
MODULE 25 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 26 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 27 11.73 7.76 5.18 471.43 1 MODULE 19.70 28 FEBRUARY 2015
MODULE 28 11.73 7.76 3.85 350.39 1 MODULE 10.69 28 FEBRUARY 2015
MODULE 29 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 30 12.42 7.78 4.00 386.51 1 MODULE 8.22 28 FEBRUARY 2015
MODULE 31 11.05 7.76 5.18 444.09 1 MODULE 22.00 28 FEBRUARY 2015
MODULE 32 11.05 7.76 3.85 330.07 1 MODULE 12.00 28 FEBRUARY 2015
MODULE 33 12.42 7.78 5.16 498.60 1 MODULE 15.10 28 FEBRUARY 2015
MODULE 34 12.42 7.78 4.00 386.51 1 MODULE 8.23 28 FEBRUARY 2015
13,774.62 34 532.85

Page 2
PIPERACK 2
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
3
meter (m) meter (m) meter (m) m pcs metric ton (MT)
MODULE 1 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
MODULE 2 12.120 6.230 1.040 78.53 1 MODULE 9.50 28 FEBRUARY 2015
MODULE 3 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
MODULE 4 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
MODULE 5 12.120 6.230 1.040 78.53 1 MODULE 9.50 28 FEBRUARY 2015
MODULE 6 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
471.17 6 66.96

PIPERACK 3
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
MODULE 1 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
MODULE 2 12.120 6.230 1.040 78.53 1 MODULE 8.50 28 FEBRUARY 2015
MODULE 3 12.120 6.230 1.040 78.53 1 MODULE 8.50 28 FEBRUARY 2015
MODULE 4 12.120 6.230 1.040 78.53 1 MODULE 9.20 28 FEBRUARY 2015
314.11 4 42.48

PIPERACK 4
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
MODULE 1 12.120 6.230 0.900 67.96 1 MODULE 8.60 28 FEBRUARY 2015
MODULE 2 12.120 6.230 0.900 67.96 1 MODULE 8.70 28 FEBRUARY 2015
MODULE 3 12.120 6.230 0.900 67.96 1 MODULE 8.10 28 FEBRUARY 2015
MODULE 4 12.120 6.230 0.900 67.96 1 MODULE 8.30 28 FEBRUARY 2015
MODULE 5 12.120 6.230 0.900 67.96 1 MODULE 9.10 28 FEBRUARY 2015
MODULE 6 12.120 6.230 0.900 67.96 1 MODULE 10.10 28 FEBRUARY 2015
407.74 6 63.48

PIPERACK 5
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
3
meter (m) meter (m) meter (m) m pcs metric ton (MT)
MODULE 1 12.120 4.236 3.060 157.10 1 MODULE 5.00 28 FEBRUARY 2015
MODULE 2 8.000 5.230 1.460 61.09 1 MODULE 4.00 28 FEBRUARY 2015
MODULE 3 8.000 5.130 1.460 59.92 1 MODULE 4.00 28 FEBRUARY 2015
MODULE 4 12.120 4.230 3.060 156.88 1 MODULE 5.00 28 FEBRUARY 2015
MODULE 5 7.000 6.230 0.760 33.14 1 MODULE 4.90 28 FEBRUARY 2015
MODULE 6 12.120 6.230 6.560 495.33 1 MODULE 12.30 28 FEBRUARY 2015
MODULE 7 12.120 6.230 6.560 495.33 1 MODULE 12.20 28 FEBRUARY 2015
MODULE 8 12.120 6.230 6.560 495.33 1 MODULE 11.70 28 FEBRUARY 2015
MODULE 9 11.130 6.230 6.560 454.87 1 MODULE 12.00 28 FEBRUARY 2015
2,408.99 9 85.32

STAND ALONE EQUIPMENT


LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
Incinerator HT432/442 40.000 1.200 1.200 57.60 2 CRADLE 25.00 28 FEBRUARY 2015
Quench Tower K-431 3.500 3.500 23.000 281.75 1 CRADLE 50 28 FEBRUARY 2015
Quench Tower K-441 3.500 3.500 23.000 281.75 1 CRADLE 50 28 FEBRUARY 2015
Amine Absorber K-432 3.400 3.400 23.000 265.88 1 CRADLE 50 28 FEBRUARY 2015
Amine Absorber K-442 3.400 3.400 23.000 265.88 1 CRADLE 50 28 FEBRUARY 2015
Sour Water Stripper K-421 4.600 4.600 48.000 1015.68 1 CRADLE 151.2 28 FEBRUARY 2015
Sour Water Blowdown Drum E-422 5.400 3.800 13.000 266.76 1 CRADLE 35 28 FEBRUARY 2015
Amine Regenerator K-412 4.600 4.600 39.100 827.36 1 CRADLE 101.4 28 FEBRUARY 2015
Amine Sump Drum E-413 5.100 3.100 14.800 233.99 1 CRADLE 26.8 28 FEBRUARY 2015
Slope Oil Drain Drum E-466 5.100 3.100 12.000 189.72 1 CRADLE 20.2 28 FEBRUARY 2015
SWS Reboiler Condensate Drum E-423 8.385 1.725 2.482 35.90 1 CRADLE 4.4 28 FEBRUARY 2015
Atm Condensate Drum E-463 A/B 6.460 2.652 3.374 115.61 2 CRADLE 13.2 3 JULY 2015
Incinerator Burner GO-432 3.600 13.500 1.100 53.46 1 CRADLE 1.2 28 FEBRUARY 2015
Incinerator Burner GO-442 3.100 13.500 1.100 46.04 1 CRADLE 1.1 28 FEBRUARY 2015
Sour Water Stripper Reboiler T-422 8.800 2.700 2.700 64.15 1 CRADLE 25.68 28 FEBRUARY 2015
Acid Gas Flare KO drum E-465 A/B 17.500 4.000 5.000 700.00 2 CRADLE 80 28 FEBRUARY 2015
Stack Section 1 29.00 4.800 4.800 668.16 1 CRADLE 43.5 28 FEBRUARY 2015
Stack Section 2 30.500 2.900 2.900 256.51 1 CRADLE 22.5 28 FEBRUARY 2015
5,626.18 21 751.18

SHIP LOOSE
LENGTH WIDTH HEIGHT VOLUME QTY TYPE WEIGHT DELIVERY DATE FROM KPS
meter (m) meter (m) meter (m) m3 pcs metric ton (MT)
SWS Blowdown Pump H-424 3.000 1.000 1.000 3.000 1 CONTAINER 1.15 3 JULY 2015
Amine Sump Pump H-414 4.000 1.000 1.000 4.000 1 CONTAINER 1.44 3 JULY 2015
Condensate Transfer Pumps H-461 A/B 2.500 1.000 0.850 4.250 2 CONTAINER 3.53 3 JULY 2015
HP Boiler FW Pumps H-462 A/B/C TBC 3 JULY 2015
LP Boiler FW Pumps H-463 A/B/C 2.500 1.000 0.800 6.000 3 CONTAINER 4.72 3 JULY 2015
Slope Oil Pump H-466 3.000 1.000 1.000 3.000 1 CONTAINER 1.09 3 JULY 2015
Sulfer Seal legs ME-431/441 8.500 0.700 1.000 11.900 2 CONTAINER 2.78 3 JULY 2015
Sulfer Seal legs (Filter) ME-431/441 1.500 1.200 0.600 2.160 2 CONTAINER 0.49 3 JULY 2015
Sulfer Seal legs (Lock Pot) ME-431/441 1.225 0.660 1.000 1.617 2 CONTAINER 0.46 3 JULY 2015
Sulfer Seal legs ME-432/442 8.500 0.700 1.000 11.900 2 CONTAINER 2.78 3 JULY 2015
Sulfer Seal legs (Filter) ME-432/442 1.500 1.200 0.600 2.160 2 CONTAINER 0.53 3 JULY 2015
Sulfer Seal legs (Lock Pot) ME-432/442 1.225 0.660 1.000 1.617 2 CONTAINER 0.63 3 JULY 2015
Sulfer Seal legs ME-433/443 8.500 0.700 1.000 11.900 2 CONTAINER 4.35 3 JULY 2015
Sulfer Seal legs (Filter) ME-433/443 1.500 1.200 0.600 2.160 2 CONTAINER 0.49 3 JULY 2015
Sulfer Seal legs (Lock Pot) ME-433/443 1.225 0.660 1.000 1.617 2 CONTAINER 0.63 3 JULY 2015
Sulfer Seal legs ME-434/444 8.500 0.700 1.000 11.900 2 CONTAINER 2.37 3 JULY 2015
Sulfer Seal legs (Filter) ME-434/444 1.500 1.200 0.600 2.160 2 CONTAINER 0.47 3 JULY 2015
Sulfer Seal legs (Lock Pot) ME-434/444 1.225 0.660 1.000 1.617 2 CONTAINER 0.49 3 JULY 2015
40FT. CONTAINER VAN 12.000 2.500 2.200 1,320 20 582.00 3 JULY 2015
STEEL CRADLES 12.000 3.000 2.400 1,728 20 608.00 3 JULY 2015
3,130.96 72 1,218.39

TOTAL VOLUME 82,624.23 232 5,192.14


As per plot plan Rev : 5