Bill of Quantities
Bill of Quantities
Bill of Quantities
ITEM NO. ITEM DESCRIPTION QTY UNIT UNIT COST MATERIAL COST LABOR COST COST
I GENERAL REQUIREMENTS
Mobilization and demobilization 1 lot 75,000.00 - - 84,000.00
Permits- Building permit, mayor's permit,barangay clearance 1 lot 70,000.00 78,400.00
Safety Requirements 1 lot 20,000.00 - - 22,400.00
Relocation Survey 1 lot 16,000.00 17,920.00
Temporary Facility 1 lot 40,000.00 44,800.00
Electric and Water Consumption 1 lot 60,000.00 67,200.00
Construction Bond 1 lot 30,000.00 33,600.00
Gate pass fee/deliveries materials 1 lot 10,000.00 11,200.00
SUB-TOTAL = 359,520.00
II CIVIL AND STRUCTURAL WORKS
2.0 EARTHWORKS
Excavation - footing 34 cu.m 620.00 23,609.60
Disposal of excavated materials 25 cu.m 620.00 17,360.00
Soil poisoning 1 lot 11,000.00 12,320.00
2.1 CONCRETE WORKS (GROUND FLOOR) - - -
2.1.1 Concrete 3000psi - ( column footing, Column,wall footing,path walk,ramp,stairs) 44.60 cu.m 4,600.00 205,160.00 82,064.00 321,690.88
a. 16mm rebars 1,866 kg 45.00 83,984.95 33,593.98 131,688.40
b. 12mm rebars 279 kg 45.00 12,571.42 5,028.57 19,711.98
c. 10 mm rebars ( stirrups) 354 kg 45.00 15,912.12 6,364.85 24,950.21
d. Crushed Gravel Bedding 3 cu.m 3,600.00 10,800.00 4,320.00 16,934.40
e. Ga. 16 tie wires 5 roll 1,680.00 8,400.00 3,360.00 13,171.20
2.2 CONCRETE WORKS (SECOND FLOOR) -
2.2.1 Concrete 3000psi - (Column,Roof beam,Girders, slab) 39.93 cu.m 4,600.00 183,657.76 73,463.10 287,975.37
a. 16mm rebars 2,878 kg 45.00 129,522.24 51,808.90 203,090.87
b. 12mm rebars 813 kg 45.00 36,571.39 14,628.56 57,343.94
c. 10 mm rebars 565 kg 45.00 25,410.53 10,164.21 39,843.71
d. Ga. 16 tie wires 5 roll 1,680.00 8,400.00 3,360.00 13,171.20
Four million two hundred eleven thousand one hundred ninety eight and 8/100 pesos only