Construction Method Statement: Loyal Building Contracting LLC
Construction Method Statement: Loyal Building Contracting LLC
Construction Method Statement: Loyal Building Contracting LLC
PROJECT:
PROPOSED G+M OFFICE, WAREHOUSE AND ALLIED SERVICES
ON PLOT NO: 5320248 DUBAI INDUSTRIAL CITY, DUBAI – UAE.
Project Manager
Name: Date:
Signature:
Project Manager
Name: Date:
Signature:
LOYAL BUILDING CONTRACTING LLC
“This method statement sets out to demonstrate our ability to carry out the works
in the optimum time, in the most viable and safe manner to achieve a completed
project to the satisfaction of all parties involved.”
LOYAL BUILDING CONTRACTING LLC
Contents
General
Pre-Construction
Planning and Programming
Site Management
Security and Site establishment
Personnel
Site Access and Deliveries
Signage
Movement and Hoisting of Materials
Storage and Handling
Waste Management
Scaffolding
Temporary Services
Dust and Debris
Safety
Noise control
Construction Method
MOBILIZATION.
MATERIAL STORAGE.
EXCAVATION.
REINFORCEMENT WORK.
PCC AND FOUNDATIONS.
CONCRETE WORK.
BACKFILLING
COMPACTION
FLOOR SLABS
ERECTION OF STEEL STRUCTURE & ROOFING SHEETS
BLOCK WORK.
PLASTERING WORKS.
ELECTRICAL WORKS.
GYPSUM WALL/ CEILING WORKS
PLUMBING WORKS
PAINTING WORKS
DEMOLITION WORKS
RUBBISH AND CONSTRUCTION ARISING.
DUST CONTROL.
HEALTH AND SAFETY MANAGEMENT PROVISIONS.
RESPONSIBILITIES.
MANPOWER ON SITE.
EQUIPMENTS OF SITE.
SUPERVISION.
DOCUMENTS RECORDING.
COMMUNICATION OF METHOD STATEMENTS.
Handover documentation and Client Training
Protection of Completed Works
Conclusion
LOYAL BUILDING CONTRACTING LLC
General
This method statement has been prepared on the basis of the
new project information as issued and gives an indication of our
general approach to the construction and management of the
project.
Pre-start Investigations
Site Logistics Site Logistics Site Management Site Management
Prior to commencement of site works, an external survey will
be carried out to confirm the existing site levels, extent of any
existing services and the condition of the existing environs.
The site team will be supported and assisted by our head office
based staff including environmental, planning, temporary works,
health and safety managers.
Personnel
All personnel will be inducted prior to gaining access to the
site. They will be informed of the specific site rules required in the
preliminaries relating to this project as well as LBC’s site rules and
their own companies method statements.
Signage
Adequate signage will be installed such that vehicle deliveries
and access to the site are clearly defined within the general site
geographical area.
Waste Management
A waste removal strategy will be developed during the pre-
commencement period. This strategy will be incorporated within all
trade contractor orders
Scaffolding
LOYAL BUILDING CONTRACTING LLC
Temporary Services
Power supply will be provided by a generator until the new electric
main and substation
have been commissioned.
110/220v power will be utilized throughout the building.
Water will be provided direct from the mains system for use in the
welfare facilities.
Temporary drainage will be connected to an underground storage
tank until the new
Pumped foul main has been installed and commissioned.
Safety
All trade contractors are obliged to provide safety policies,
plans and method statements and will be interviewed prior to order
placement on all aspects of safety, health and welfare.
LOYAL BUILDING CONTRACTING LLC
Noise Control
Management of noise pollution and vibration control will be
given a high priority. Where the works are in close proximity of
occupied buildings WD will ensure that acceptable levels of noise are
adhered to as well as statutory levels imposed by the Environmental
Health Officers.
Construction Method
Mobilization
Material storage
Excavation
Loyal Engineer shall ensure that prior to commencing
work the position of services obstructing the work area
are established, marked, agreed, and recorded. The
position if cables shall be provided by carefully hand
digging.
Reinforcement works
This method of statements details the procedure for the Form and
reinforcement works.
Concrete Casting
Backfilling
Compaction
Floor slabs
STORAGE;
SHEETS STORAGE
ERECTION;
The columns for the braced bay base plate shall be set,
base plates shall be shimmed and anchor bolts & nuts
LOYAL BUILDING CONTRACTING LLC
SHEETING;
At the end of each working day clean the roof with a soft
brush, sweep off old drill bits, pop reverts, sward from
drill or cutting. These items can cause rusting if they are
not removed
Final Check
Check that roof and gutter are clear or debris and ferrous
metals
Block works
All the block work below ground level will be solid block
work made with SR cement.
Plastering Works
Materials
Pre installation
Preparation
Wire pulling
Make sure that all conduits and boxes in both ends are
free from damages and blockages etc. and installation is
approved.
Blockage shall be checked by inserting the draw wire and
checking that it reaches to the other end without any
disturbance.
Once the conduit is not blocked the wires shall be pulled
using the draw wires while ensuring no damage occurs
while pulling.
Pulling compound or lubricant shall be used for pulling
the wires where required.
LOYAL BUILDING CONTRACTING LLC
Set the Meggar meter to 1000 volts DC for cables and 500
volts DC for wires. Take reading between phase, phase
and neutral, phase and earth neutral and earth. Note that
resistance reading must not exceed 2 mega-ohms
(MΩ). Check and record the resistance readings as per
specification on the approved insulation resistance test
forms.
Cables Identifications
foreman.
The site foreman will check the materials as per the delivery note
and will verify against approved material submittal and MIR will
be raised.
Make sure that all materials are free from damages and defects :
Mark the level of ceiling on the walls with the help of chalk line
Fix the L angle/ Shadow line stopping Angle on the marks with the
Cut the “L-Angle for the vertical suspension” 100mm more than
from one end and bend it to form a L. Secure the bend part by
screwing the overlapping metals with drill point M4.2 wafer head
screw. Drill the upper slab with suitable drill @ specified center’s
along the line of the main channel offset by 50mm. through the
After suspending the Hanger, fix the main channels (1200mm max
centers) to the rigid hanger with the help of wafer head screw.
When Main channel are spliced, the ends shall be overlapped not
less than 300mm and securely fastened with wafer head screws.
clips.
all members.
LOYAL BUILDING CONTRACTING LLC
over the gypsum board joint duly filling the voids between
compound.
Plumbing Works
Trench Preparation for the underground pipes
The contractor shall carry out the excavation for the trench
lying.
LOYAL BUILDING CONTRACTING LLC
studied
Anchor bolts/ raw bolts are fixed and threaded rod of suitable
length is fixed
Straight pipes, cleaned from the inside, with fittings are inserted
Pipeline thus erected are plugged from both ends at the end of
Mark the drainage pipe route with the lime powder for excavation
the invert level of the pipe line as per the approved drawings.
Provide concrete base with required gradient for a firm base for
pipe installation.
Install the pipe between the manholes as per the specification and
approved drawings.
be only 25 to 30mtrs.
level.
After checking the level of the installed pipes arrange for testing.
Painting works
Surface Preparation
LOYAL BUILDING CONTRACTING LLC
primer coat.
commencement of painting.
painting.
Paint Preparation
first coat.
of plaster.
applied.
LOYAL BUILDING CONTRACTING LLC
supervisor or Consultant.
Demolition works
The scope of works involved in the demolition of the existing
structures is as follows:
d) Disconnection of services
k) Demolition of flooring
l) Demolition of foundations
LOYAL BUILDING CONTRACTING LLC
yard
METHODOLOGY
d) . Disconnection of Services:
8. Soft Stripping:
Now that roof sheet and wall sheet is removed, proceed with
the dismantling of steel structure.
Start with the end wall and proceed bay by bay pattern.
In the first bay, remove the roof flange brace, cross bracing,
sag rods and then purling by soft stripping.
Once secondary members are removed, proceed with the
primary members.
Mobile crane of 25 ton to be used for all the primary
members dismantling.
LOYAL BUILDING CONTRACTING LLC
Dust Control
Pre use checklist will be used for all plant and equipment.
Responsibilities.
Project Engineer:
Site Foreman:
Manpower on site
Project Manager
Project Engineer
Safety Officer
Site Supervisor
Operator as required
Equipment’s on site
General Tools
Supervision
LOYAL BUILDING CONTRACTING LLC
Document Recording.
1. Work Permit
3. Safety induction
4. Risk assessments
LOYAL BUILDING CONTRACTING LLC
adhered.
CONCLUSION
The above method statement has been developed specifically
to demonstrate our understanding of the project requirements and
the detailed methodology required to carry out a project of this
nature.