Noida Metro Rail Project Cec-Sam-Jv.: Presentation On U-Girder Casting by L.K.Prasad

Download as pdf or txt
Download as pdf or txt
You are on page 1of 116

Presentation on U-Girder casting

By
L.K.Prasad

Noida Metro Rail Project


CEC-SAM-JV.
Project Route Map
Casting Yard
Scope U-girder

Scope of Work

27 m standard
Sl no Package Nos of Girder span Non standard span Concrete Qty Steel Qty.

1 NC-01 656 460 196 38376 6667.58

2 NC-02 704 532 172 41184 7155.46

Total 1360 992 368 79560 13823


U-GIRDER MIX DESIGN

U-GIRDER MIX DESIGN

Grade of Concrete:M55

Ingredients Sourcr/Brand Qty/M3

Cement(Kg) Ultratech OPC-53 450

Microsilica(Kg) Elkem/Comiche 25

20mm Aggregate(Kg) Kotputli 577

10mm Aggregate(Kg) Kotputli 532

Fine aggregate(Sand)(Kg) Bajpur 765

Free Water(Kg) Batching plant 141.66

Admixture(Kg) Don super flow PC-250 4.037

Slump after 2 hours retension(mm) 140

7days strength(Mpa) 61.55

28 days strength(Mpa) 74.61

W/C Ratio 0.31


CASTING YARD INFRASTRUCTURE

1. Total No of BAY-4.

2.U-girder bay-03 nos

3.Pier cap Bay-1

4. No of U-girder bed 36 (6 bed in each row).

5. Pier cap mould-16.

6. 100 MT capacity gantry 02 nos in each u-girder bay.

7. T ime cycle is 10 days FOR U-girder casting.

8. Peak Max production 6*6*3=108 nos u-girder per month


STACKING CAPACITY

1. Bay-1 28*2= 56

2.Bay-2 28*2 56

3.Bay-3 23*2 46

Total 158
Casting Bed Preparation

PCC for casting bed


Casting Bed preparation

Rebar fixing
C/Bed Wall
Casting Bed Wall

RCC Wall 1100*300 mm

Longitudional Wall
300*1100

2800mm
Shutter Making

5050mm

Outer
Shutter Outer
Shutter
3800mm

1850 mm Lifting hole


Bottom Lifting hole
Shutter
Inner Shutter

Inner shutter

Lifting hole

Lifting hole
Outer Shutter

Outer shutter
support
Outer shutter

Outer form

Bottom shutter
Buffing of Shutter

Buffing/cleaning
of shutter
Girder Mould

Applying shuttering
oil(Reebol)
Automatic bar cutting & Bending M/c
Automatic bar cutting & Bending M/c

Capacity 100 MT/Day


Automatic bar cutting & Bending M/c

Format Line 12

12mm dia rebar coil


Format line 16
Bending upto 32mm
Bending upto 32mm
Re-bar zig

Rebar zig
Re bar cage placing

Rebar cage

Rebar zig.
Pre Fab Rebar

Pre Fab Rebar

Rebar zig.
Cage Lifting

Cage lifter
Wt. of cage 10.2
MT
Cage Placing
Cage Placing
Cage Lifter

Cage Lifter
Cage Lifting

U-girder cage 27
mts long
wt.10.12 MT
Cage lifting from zig.
Outer Shutter

2500mm c/c

Turn buckle
Shutter vibrator

Shutter vibrator
Shutter vibrator

Shutter vibrator
Rebar cage Placing

Rebar cage

Shear Key Box

Bulk Head
Cage Placing

Re bar is coated with inhibitor


solution for corrosion protection
HT Coil despenser

HT Coil despenser

HT coil
HTS CABLE
Cable Threading

Bulk head

HT Cable
Cable Threading

15.2mm dia . 7 ply


Bulk head LRPC Class-2

Floating Beam
Stressing end

Wedge & Barrel

75mm dia Macalloy bar


Grip for cable

Barrel

15.2 mm
cable grip
wedge 3
segmental

15.2mm dia HT cable


Prestressing

300MT Capacity hyd. Jack


600mm stroke
Prestressing

1. HT cable 15.2mm
dia
2. Load in each
cable 195.5
KN/19.92 MT
3. Total load
1434.24 MT
4. Ram area of jack
529.2 sq.cm
5. Required
pressure 460.55
kg/cm2
6. Modified
elongation
1179mm

Hydraulic hose
700 bar.
Stressing operation

700 bar cap. Hyd


.hose
Power pack 10 HP motor

Return line

Stressing line
Stressing Mechanism

75mm dia Macalloy


Stressing jack bar

Washer plate

75mm dia Nut


macalloy nut

300MT cap. 600mm stroke

Hollow device
Washer plate
Prestressing

Stressing line

Washer Return Line

Piston

Nut
Dead End

Reaction wall
6500*1450*1200 mm Cable grip
Cable Threading

Debonding
tube

Drainage
spout
Debonded tube

Debonded length 2175 mm both side

Debonding
tube 20 mm id
HDPE pipe
Stressing End

Bulk head

Floating
Beam
Anchorage/Grip

HT strand
Stressing End

Washer plate & Nut. 75mm dia.


Macalloy bar.
Concrete placing

Boom Placer

Concreteing by Boom placer


Grade of conc. M55 with micro silica
Cement content 450 kg.
W/c Ratio 0.31
Admixture Don super flow PC-250
4.037 Kg/m3.
Conc. Qty per girder 60m3
Concreting

Boom Placer
Concreting

Transit Mixture
Load Transfer
Load Transfer criteria

After 3 days of
concreting with a
minimum
compresshive
strength of conc.
35 Mpa.
Load Transfer To Concrete
Pre cast pier cap cage
Precast pier cap cae
Pier cap

Anchor cone
Cross Arm
Anchor cone

Anchor cone
Stressing

Multipull stressing jack


Girder Lifting

Girder lifting &


shifting
Girder Lifting From Bed

Lifter 02 nos
40 mm dia
Macalloy bar 4
nos
Girder Lifting

Lifting hole
Girder Lifting

40 mm dia Macalloy
nut

Washer plate
Girder Lifter

40mm Dia. Macalloy Bar


Girder Lifter
Girder Lifting from Bed
Double layer Stacking
Stacking
Girder Stacking

Girder stacking
Girder Lifting

100 MT
Capacity EOT

Girder wt 150 MT
Cable cutting

Cable cutting by Mechanical cutter


Recess Filling with
conbextra GP-2.
Recess Filling with conbextra
GP-2

Recess Filling
Double layer stacking

Stacking stool
Curing

Curing period 21 days from


DOC
Girder Lifting & Stacking

Girder stacking
Time cycle U-girder

TIME CYCLE FOR U-GIRDER

Sl no Activity Day Duration in Total Hours Remarks


hours
1 Cleaning of bed and shuttering oil applying 12 12
2 Fixing of outer shutter 1 10 22
3 Fixing of bulkhead & cage placing. 2 12 34
4 Threading of HT strand. 24 58
5 Initial prestressing 3 6 64
6 Final Prestressing 6 70
7 Sealing of debonding tubes 3 73
8 Inner shutter placing 5 78
4
9 Inner shutter Alignment 9 87
10 Inspection by Client. 4 91
11 Pouring of concrete 5 48 139
12 Curing 6,7,&8 72 211
13 Load transfer 9 6 217
14 Lifting of girder for stacking. 10 24 241
10.04167
Note: Time cycle for 6 U-girder casting 10 Days.
Loading for Launching
200 MT Capacity Trailor
Loading For Launching

Loading for launching


Loading For Launching
Ready for Despatch

Tieing with 04 nos Belt


Positioning gor lifting
Lifting From Trailor
Lifting for launching
Neoprene Bearing.
Denka chloroprene

Denka chloroprene
section of Neoprene Bearing.

Steel Neoprene
Wedge plate

Steel wedge plate


400 MT Capacity
crane

350 MT Capacity tyre


mounted crane.
Position of crane during
lifting

Beside pier cap

Behing pier cap


Lifting for launching

Straight lifting above pier cap


Lifting for launching

350 MT cap. 400 MT Capacity


crane crane
Swing for proper position
Lowering on bearing
pedestal
Lowering on bearing
pedestal
Lowering on pedestal
Position of crane during
final lowering
Final position
Launching view
Launching

400 MT Capacity crane


02 nos
Thank you