CE 5015 Foundation Engg
CE 5015 Foundation Engg
CE 5015 Foundation Engg
CE - 5015
FOUNDATION ENGINEERING
SEMESTER – II
B.E
CIVIL ENGINEERING
No.1 A fully embedded precast concrete pile 50 ft long is driven into a homogeneous sand
layer (c=0).The pile is square in cross section with sides measuring 12 in. The dry unit weight
of sand, γd , is 110 lb/ ft3 , the average soil friction angle is 35 degree , and the standard
penetration resistance near the vicinity of the pile tip is 16.Calculate the ultimate point load
on the pile by
a. Meyerhof ’s method using Eqs. (8.12) and (8.13)
b. Meyerhof’s method using Eqs.(8.16b)
c. Vesic’s method using Eq. (8.19) and Ir = Irr =90
Solution:
Part(a):Meyerfof’s method using Eqs. (8.12) and (8.13)
This soil is homogeneous,
Lb = L , For φ = 35° , Nq∗ ≈ 120.Thus q/= γd L=(110)(50)=5500 lb/ft2
Qp=Ap q/ Nq∗=[ (12)(12)/144](5500)(120)=66 ×104lb=330ton
From eq (8.15)
q1=100 Nq∗tanφ =(1000)(120)(tan35°)=84025lb/ft2=42ton/ft2
Qp=Apq1=[(12)(12)/144](42)=42 ton
So
Qp=42 ton
Part(b):Meyerhof’s method using Eqs. (8.16b)
Qp(lb/ft2)=800N(L/D) ≤8000N
L/D=50ft/1ft=50
As L/D > 10,
qp=8000N=(8000)(16)=128000lb/ft2
Qp=Apqp=[(12)(12)/144](128000)=128000lb=64 ton
Part(c):Vesic’s Method
Irr ≈for 90. φ =35 °, Table 8.8gives N σ∗≈79.5 From Eq (8.19)
Qp=Ap σo´ N σ∗
(1 + 2k 0 ) /
σo´= q
3
K0=1-sin φ =1-sin 35° =0.43
σ0´=[{1+(2)(0.43)}/3](5500)=3410lb/ft2
Qp=[(12)(12)/144](3410)(79.5)=271095lb≈135.5ton
Partd:Coyle and Castello’s method
For L/D =50 and φ =35° , figure 8.21 gives Nq∗=33.
Qp=q´ Nq∗Ap=(5500)(33)[(12)(12)/144]=181500lb≈ 91ton
Qp=[(42+64)/2] ≈53ton
No.2 Consider a precast concrete pile 12 m long in a homogeneous soil layer .The pile cross
section = 305mm ×305mm, the unit weight of sand γd =16.8 KN/ m3 ,and the soil friction
angle , φ =35degree .Determine the total frictional resistance .
a. Use eqs. (8.32), (8.33) and (8.36) . Also use K=1.4 and δ =0.6 φ.
b. Use Coyle and Castello’s method
Solution
By eq. 8.33
f= K σv´tan δ
76.86 KN/m2
Vertical effective stress, σv´
15D
Depth
Qs = pL/fav
=[(4)(0.305)][15D][{(1.4)(76.86)tan(0.6×35)}/2]
= (1.22)(4.575)(20.65)=115.26KN
The frictional resistance from from z = 15D to 12m
Qs = p(L-L/)fz=15D
=[(4)(0.305)][12-4.575][(1.4)(76.86)tan(0.6×35)]
=(1.22)(7.425)(41.3)=374.1KN
Qs = 115.26 + 374.1 = 489.35KN≈ 490KN
Part (b):Coyle and Castello’s method
fav =K σ-/ v ≈ tan δ
δ = 0.8 φ
Qs = favpL=[ K σ-/vtan (0.8φ) ] pL
For this pile , L/D = 39.34
And φ =35 ° , K≈ 0.7(from fig 8.22)
σ-1 v = γ L/2 = [(16.8) (12)]/2 = 100.8 KN/m2
Qs = [ (0.7)(100.8)tan(0.8 × 35)](4 × 0.305)(12)=549.3KN ≈ 550KN
No.3. A concrete pile embedded in sand has a cross section of 0.305m×0.305m .The length
of embedment of the pile is 15m, the relative density of sand is 50 percent , and the
unit weight of sand is 17 KN/m3. Use Eqs (8.32),(8.33),(8.34),and (8.36) to
determine the frictional resistance of the pile .
Solution:
From eq. 8.33 ,
f=K σv´ tan δ
from eq. 8.36
L′ = 15D = (15)(0.305)=4.575 m
From eq. 8.34
Ktanδ = 0.18 + 0.0065Dr = 0.18 + (0.0065)(50)=0.505
Qs = p L′ fav (z=0 to 4.575m)+p(L- L′ ) f z=4.575m
= (4 × 0.305) (4.575) [{0+(0.505) (17 ×4.575) }/2]
+ (4 × 0.305) (15-4.575) [(0.505)(17 ×4.575) ]
=109.6+499.5 ≈ 609KN
No.4. An HP 310× 1.079 steel pile is driven into sand , as shown in figure:
a. Calculate the ultimate point load (1) by Meyerhof’s procedure , (2) by Vesic’s
procedure (Ir=150=Irr) , and (3) by using standard penetration resistance equations
.(The average value of N in the vicinity of the pile point is 45).
b. Estimate the value of the ultimate point load from the calculations in part (a)
c. Calculate the ultimate frictional resistance Qs .Use eqs (8.32) , (8.33) , and (8.36) ,
K=1.4 and δ =0.6φ
d. Calculate the allowable pile load .Use FS = 4.
Also check the allowable load bearing capacity of the steel section of the pile.
Use fs = 62000KN/m2 for steel.
γ=15.7 kN/m2
5m Φ1=30°
c1=0
18 m
Ground water table
Loose sand γsat=18.1 kN/m2
Φ1=30°
c1=0
γsat=19.4 kN/m2
4m Dense sand Φ2=40°
c1=0
Solution
Qp=(0.0955)(128.34)(163.8)=2008KN
Standard penetration resistance equations (N=45)
qp=40 N L/D ≤ 400 N
qp=40(45)(22/0.308)=128,571KN/m2
qp=(400)(N)=(400)(45)=18,000KN/m2 (control)
Qp=Apqp=(0.0955)(18,000)=1719KN
N0.5. A concrete pile 18 in× 18 in cross section is embedded in a saturated clay . The length
of embedment is 55 ft .The undrained cohesion , Cu , of clay is 1250 lb/ft2 , and the unit
weight of clay is 118 lb/ft3.Use a factor of safety of 5 to determine the allowable load the pile
can carry .
a. Use the α method
b. Use the λ method
Solution
a. The α method
From eq 8.18,
Qp = Apqp=ApCuNc∗=[{(18)(18)/144}{1250×9}]/1000=23.5kip
Qs= α Cu ρL
From fig (8.19) for Cu=1250lb/ft2,α ≈ 0.77
Qs=[{0.77× 1250}{4 ×18/12}{55}]/1000
=317.6 kip
Q all =[ Qp +Qs] / Fs=(25.3+317.6)/5 ≈68.6 kip
b. The λ method
From eq (8.40)
fav=λ(σ-1v´+2cu)
Convert L=55ft to L=16.77 m .From fig 8.17 for L=16.77m , λ≈0.2
fav=0.2[{(118 × 55)/2}{1/1000}+2{1250/1000}]=1.149 kip/ft2
Qs= ρLfav={4 ×18/12}(55)(1.149)=379.2 kip
Qall=(Qp+Qs)/Fs=(25.3+379.2)/5=80.9 kip
N0.6.A driven pipe pile in clay is shown in fig . The pipe has an outside diameter 406 mm
and a wall thickness of 6.35 mm .
a.Calculate the net point bearing capacity .Use eq 8.18.
b.Calculate the skin resistance (1) by using eq 8.42 and eq 8.43 (α method)
(2)by using eq 8.40 (λ method) ,and
(3)by using eq 8.44 (β method ).
For all clay layers , φ R=30 .The top 10m of clay is normally consolidated .The bottom clay
layer has an OCR of 2.
c.Estimate the net allowable pile capacity .Use FS=4.
Solution
σv´ =kN/m2
30 326.75
Solution
Qp(all)=[{qu tan 2(Nφ +1)}Ap]/FS
{[qu(lab)/5][tan 2 (45+φ /2)+1]}Ap
= FS
=[{[(76× 103KN/m2)/5][tan2(45+28/2)+1]}(15.9×10-3m2)]/5
=182KN
N0.8.A 40 ft long precast concrete pile is fully embedded in sand .The cross section of the
pile measures 12 in ×12 in .The allowable working load for the pile is 80 kip ,of which 54 kip
is contributed by skin friction .Determine the elastic settlement of the pile for Ep=3 106 lb /
in2 , Es = 4500 lb/in2 and μs = 0.3.(ξ = 0.6,Iwp=0.82)
Solution
From eq 8.61
s1= [(Qwp+ξQws) L ] / (Ap Ep)
Let ξ =0.6 , Εp = 3 ×106 lb/in2 = 3× 103kip/in2 ,Qws = 54kip ,
Qwp = 26kip and Ap = 12 ×12 = 144 in2
s1= [ [26+(0.6)(54)](40 12)] / [ (144)(3 x103) ]=0.065 in
From eq 8.62
s2= [ qwpD / Es ](1-μ2s)Iwp
From fig 3.27 , Ipw = 0.82 .
qwp = Qwp / Ap = 26/144=0.18 kip / in2
s2 = [(0.18 × 12) / (4500 / 1000) ](1-0.32)(0.82)= 0.358 in
Again , from eq 8.64 ,
s3 = ( Qws / ρL )(D /Es )(1-μ2s)Iws
L 40
Iws = 2+0.35 = 2+0.35 = 4.21
D 1.0
s3 = [ 54/(4× 12 ×40) ][12/(4500/1000) ](1-0.32)(4.21) = 0.287 in
s= 0.065+0.358+0.287 = 0.71in
N0.9.A driven pipe pile in clay is shown in fig . The pipe has an outside diameter 406 mm
and a wall thickness of 6.35 mm Determine the net ultimate uplift capacity.
σv´ =kN/m2
30 326.75
Solution
cu > 27 KN/m2 , α´= 0.2
From eq 8.69
Tun = ρα′∑cu ΔL = π(0.406)(0.2)[(30)(10)+(100)(20)] = 586.7 KN
N0.10.A fully embedded precast concrete pile 50ft long is driven into a homogeneous sand
layer (c=0).The pile is square in cross section with sides measuring 12 in .The dry unit weight
of sand , γd , is 110 lb/ft3 , the average soil friction angle is 35 degree , and the standard
penetration resistance near the vicinity of the pile tip is 16.For the concrete pile , determine
the net ultimate pull out capacity . Assume the relative density of soil to be 60% .
Solution
N0.11.Consider a steel H-pile (HP 250× 0.834) 25m long embedded fully in a granular soil .
Assume that nh = 12000 KN/m3.The allowable displacement at the top of the pile is 8 mm
.Determine the allowable lateral load , Qg .Assume that Mg = 0.
Solution
From table 8.1(b) for an HP 250 ×0.834 pile ,
Ip= 123 ×10-6 m4(about the strong axis )
Ep = 207× 106 KN/m2
From eq 8.90 ,
Solution
Part a ,
Use of eq (8.100):
EHE
Qu =
S +C
E = 0.8 , HE = 26 kip-ft
S = 1 / 5 = 0.2 in
(0.8)(26)(12)
Qu = = 832 kip
0.2+0.1
Qall = Qu / FS = 832 / 6 = 138.7 kip
Part b ,
Eq 8.101,
EWRh WR+n2WP
Qu =
S + C WR + W p
Weight of piles = LAp γc = (65ft)(1ft ×1ft)(150 lb/ft3)
= 9750lb = 9.75 kip
Wp = weight of pile + weight of cap
= 9.75 + 0.72 = 10.47 kip
So
(0.8)(8)(1) 8+(0.45)2(10.47)
Qu = ×
0.2 + 0.1 8 + 10.47
= 11.687 kip
Qall = Qu / FS = 11.687 / 4
Part c ,
Eq 8.103 ,
EHE
Qu =
EHEL
S+
2ApEp
2
Ep = 3 106 lb /in ,
(0.8)(26)(12)
Qu = = 369.8 kip
0.2 + 0.475
Qall = Qu / FS = 369.8 / 3 = 123.3 kip
N0.13.Show in fig which shows the plan of a pile group . Each pile has square cross section
measuring 12 in ×12 in . The center – to – center spacing of the piles is 30 in .
30 in
Solution
Part a : Eq 8.112
2(n1+n2-2)d+4D
η=
pn1n2
For n1 = 4 , n2 = 3 , D = 12 in , and = 4D = 48 in
2(4+3-2)(30)+48
η= = 0.604 = 60.4 %
(48)(4)(3)
Part b , Eq 8.114 ,
(n1-1)n2+(n2-1)n1
η=1- tan -1(D/d)
90n1n2
(3)(3) + (2)(4)
η = 1- (21.8°) = 0.657 = 65.7 %
(90)(3)(4)
d d
d d
Bg
Lg d
Solution
From Eq 8.116 ,
∑Qu = n1n2 [9Ap cu(p)+∑αp cu ΔL ]
Ap = (0.305) (0.305) = 0.093 m2
p = (4)(0.305) = 1.22 m
From fig 8.19 , cu = 70KN/m2 , α = 0.63
∑Qu = (4)(3)[ (9)(0.093)(70) + (0.63)(1.22)(70)(15) ]
= 12(58.59+807.03) 10,387 KN
∑Qu = LgBgcu(p)Nc + ∑2(Lg+Bg)cuΔ L
Lg = (n1-1)d + 2(D/2) = ( 4-1 )( 1.22 ) + 0.305 = 3.965 m
Bg = (n2-1)d + 2 (D/2) = (3-1) ( 1.22 ) + 0.305 = 2.745 m
L/Bg = 15/2.745 = 5.46
Lg / Bg = 3.965/2.745 = 1.44
From fig 7.16 , Nc∗ ≈ 8.6
Block capacity = (3.965)(2.745)(70) (8.6)+2(3.965+2.745)(70)(15)
= 6552 + 14091 = 20643 KN
Qg(u) = 10387 KN < 20643 KN
Qg(all) = Qg(u)/FS = 10387 / 4 ≈ 2597 KN
N0.15.A group pile in clay is shown in fig .Determine the consolidation settlement of the pile
groups. All clays are normally consolidated..
Qg=500kip
Sand
γ= 105lb/ft3 6ft
30 ft
45 ft 27 ft
clay γsat=115lb/ft3
48 ft e0 = 0.82
Cc =0.3
21ft
z
2V:1H
2V: 1H P 0 (1)
ΔP(1)
γsat=120lb/ft3
clay P 0 (2) e0 = 0.7
ΔP(2) 12 ft
Cc =0.2
clay P 0(3) γsat=122lb/ft3
ΔP(3) 6ft e0 = 0.75
Cc =0.25
Rock
pile group: Lg=9 ft,Bg=6 ft
Solution
The stress distribution pattern is shown in fig
Qg (500)(1000)
Δp(1) = =
(Lg + z1)(Bg + z1) [9+(21/2) ] [6 + (21/2)]
= 1554 lb/ft2
(500)(1000)
Δp(2) = = 421 lb/ft2
(9+27)(6+27)
500 x1000
Δp(3)= = 265lb / ft 2
(9 + 36)(6 + 36)
Cc(1)H1 po(1)+ Δp(1)
Δs1 = log
1 + e0(1) p0(1)
Po1 = (6)(105) + [27 + (21/2) ](115-62.4) = 2603 lb/ft2
0.3)(21) 2603 + 1554
Δs1 = log = 0.7 ft = 8.45 in
1 + e0 (2) p0 (2)
N0.16.Show in fig : Hf = 2 m . The pile is circular in cross section with a diameter of 0.305
m .For the fill that is above the water table , γf = 16 KN/m3 and φ = 32 . Determine the total
drag force.
clay fill
Hf
L sand
Solution
From eq 8.129 ,
p K´γ2f tan δ
Qn =
2
p = (0.305) = 0.958 m
K´ = 1- sin φ = 1- sin 32° = 0.47
δ = (0.6)(32) = 19.2 °
Qn = (0.958)(0.47)(16)(2)2 tan 19.2 °
2
= 5.02KN
Sand fill
H f=2m
L=20m
L1= 11.75m
Neutral plane
z clay
Solution
L-Hf L- Hf γf Hf 2γ´fHf
L1 = + -
L1 2 γ´ γ´
γ´f has been by f because the fill is above the water table .
N0.18.Fig shows a cantilever sheet pile wall penetrating a granular soil .Here , L1 = 10 ft , L2
= 20 ft , γ= 120 lb/ft3 , γsat = 129.4 lb/ft3 , and φ= 40˚ .
a.What is the theoretical depth of embedment , D ?
b.For a 30% increase in D , what should be the total length of the sheet piles ?
c.What should be the minimum section modulus of the sheet piles?
L1 sand
γ
c=0
Water table
φ
sand
L2 γ sat
c=0
φ
Dredge line
sand
D γ sat
c=0
φ
Solution
Step 1
Ka = tan 2 [45-( φ/2)] = tan 2 [45-(40/2)] = 0.217
Kp = tan 2 [45+( φ/2)] = 4.599
Step 2
ρ1 =γL1Ka = (0.12)(10)(0.217) = 0.26 kip / ft2
ρ2 = (γL1+γ´L2)Ka = [(0.12)(10)+(0.1294-0.0624)(20)]0.217
= 0.551 kip /ft2
Step 3
Ρ2 0.551
L3 = =
γ´ (Kp-Ka) (0.1294-0.0624)(4.599-0.217)
=1.88ft
Step 4
P = (1/2)ρ1L1 + ρ1L2 + (1/2)(ρ2-1)L2 + (1/2)ρ2L3
= (1/2)(0.26)(10) + (0.26)(20) + (1/2)(0.551-0.26)(20)
+ (1/2)(0.551)(1.88)
= 1.3 + 5.2 + 2.91 + 0.518 = 9.928 kip/ft
Step 5
Taking the moment about E(fig 6.7) yields
z = [(1.3){(10/3)+20+1.88}+(5.2){1.88+(20/2)}+(2.91){1.88+
(20/3)}+(0.518)(2/3)(1.88)] / 9.928 = 12.1 ft
Step 6
ρs = (γL1+γ´L2)Kp + γ´L2(Kp-Ka)
= [(0.12)(10)+(0.1294-0.0624)(20)] 4.599
+ (0.0624)(1.88)(4.599-0.217)
= 12.233 kip /ft2
Step 7
ρs 12.233
A1 = = = 41.7
γ´ (Kp-Ka) (0.1294-0.0624)(4.382)
8P (8)(9.928)
A2 = = = 270.7
γ´ (Kp-Ka) (0.1294-0.0624)(4.382)
6P[2 z γ´ (Kp-Ka)+ρs]
A3 =
γ´2(Kp-Ka)2
(6)(9.928)[(2)(12.1)(0.067)(4.382)+12.233]
= = 13.37
(0.067)2(4.382)2
P(6z ρs + 4P)
A4 =
γ´2(Kp-Ka)2
(9.928)[(6)(12.1)(12.233)+(4)(9.928)]
= = 106.95
(0.067)2(4.382)2
Step 8
L44 + 41.7 L34 – 270.7 L24 – 13.37 L4 -106.95 = 0
By trial and error , L4 ≈ 5.81 ft
D = 1.88 + 5.81≈ 7.69 ft
Part b
Total length of the sheet piles = 10+20+(1.3)(7.69) =40 ft
Part c
2P (2)(9.928)
z´ = = = 8.23 ft
γ´(Kp-Ka) (0.067)(4.382)
N0.19.Shown in fig , for L = 15 ft,γ = 110 lb/ft3 , φ= 30 , and P = 2000 lb/ft , determine :
a.The theoretical depth of penetration , D
b.The maximum moment , M max (lb-ft / ft)
P
L=15ft
Sand
D γ=110lb/ft3
φ=30
c =0
L5
P3=γD(Kp-Ka) P4=γD(Kp-Ka)
Solution
Kp = tan2[45+(φ/2)] = tan2[45+(30/2)] = 3
Ka = tan2[45-(φ/2)] = tan2 [45-(30/2)] = 1/3
Kp-Ka = 3-0.333 = 2.667
Part a ,
2
8P 12PL 2P
D4 - D2 - D - = 0
γ(Kp-Ka) γ (Kp-Ka) γ (Kp-Ka)
8P (8)(2000)
= = 54.54
γ (Kp-Ka) (110)(2.667)
12PL (12)(2000)(15)
= = 1227.1
γ (Kp-Ka) (110)(2.667)
2P (2)(2000)
= = 13.63
γ (Kp-Ka) (110)(2.667)
D4-54.54D2-1227.1D-(13.63)2 = 0
From the preceding equation , D ≈13 ft
Part b,
2P (2)(2000)
z´= = = 3.69 ft
γ(Kp-Ka) (110)(2.667)
L1 =2m sand
γ=15.9kN/m3
c=0
Water table
φ=32
L2 =3m sand
γ sat =19.33kN/m3
c=0
φ=32
clay
D
c=47kN/m2
φ=0
Solution
Part a ,
Step 1,
Ka = tan2[45 – (φ/2)] = tan2[45 – (32/2)] = 0.307
Step 2,
ρ 1 = γL1Ka = (15.9)(2)(0.307) = 9.763KN/m2
ρ2 = (γL1 + γ´L2)Ka = [(15.9)(2)+(19.33-9.81)(3)](0.307)
= 18.53 KN/m2
Step 3 ,
In fig,
P1=(1/2)ρ1L1+ρ1L2+(1/2)(ρ2-ρ1)L2
= 9.763+29.289+13.153 =52.2 KN/m
z1=(1/52.2)[9.763{3+(2/3)}+29.289(3/2)+13.151(3/3)]
= 1.78 m
Step 4 ,
From eq 6.48 ,
D2[4c – (γL1+γ´L2)] – 2DP1 – [P1(P1+12 c z 1 ) ] /[(γL1+γ´L2)+2c]
= 0
D2{(4)(47) – [(2)(15.9) + (19.33 – 9.81)3 ]} – 2D(52.2)
52.2[52.2+(12)(47)(1.78)]
- = 0
[(15.9)(2)+(19.33 - 9.81)3]+(2)(47)
z
L2
P
Sand
γ sat =19.33kN/m3
Dredge line Z φ = 32
p2 D
1 Sand
L3 γ sat =19.33kN/m3
D E
γ´ ( Kp-Ka) φ = 32
L4
F B
P3
Solution
Hence L4 ≈1.4m
Dtheoretical = L3+L4 =0.66+1.4 = 2.06 m
Dactual ≈ 1.4Dtheory = (1.4)(2.06) = 2.88 m(rounded to 2.9 m)
Part b: Anchor force
F = P – (1/2)[γ´(Kp - Ka)]L24
= 58.32 – (1/2)[9.52(3.25 – 0.307)](1.4)2 = 30.86KN/m
Part c : Maximum moment (Mmax)
From eq 6.69 for zero shear ,
(1/2) ρ1L1 – F+ρ1(z-L1)+(1/2)Kaγ´(z-L1)2 = 0
(1/2)(9.763)(2) – 30.86+(9.763)(z-2)+(1/2)(0.307)(9.52)(z - 2)2=0
Let z-2 = x
9.763 – 30.86+9.763x+1.461x2 = 0
x2+6.682x – 14.44 = 0
x = 1.72 m
z = x+2 = 1.72+2 = 3.72 m (L1+L2 < z <L1 ----------checks )
Taking the moment about the point of zero shear force (z= 3.72 m or x = 1.72 m)
Mmax = - [(1/2)ρ1L1][x+(1/3)(2)]+F(x+1) – (ρ1x)(x/2) - (1/2)Kaγ´(x2)(x/3)
9.763(1.72)2
Mmax = - (9.763)(2.387)+(30.86)(2.72) –
2
(0.307)(9.52)(1.72)3
-
6
= - 23.3 + 83.94 – 14.44 – 2.48 = 43.72 KN-m / m
N0.22.Shown in fig , which shows that L1 = 10.8 ft , L2 = 21.6ft , and l1 = 5.4ft .Also γ=
108lb/ft3 ,γsat = 127.2 lb/ft3 , φ = 35° , and
c = 850lb/ft2.
a.Determine the theoretical depth of embedment.
b.Calculate the anchor force per unit length of the sheet pile wall.
A
Sand
L1 l1 γ=108lb/ft3
O´ F
Water table l2 φ = 35
p1 C
z
L2
P1
Sand
γ sat =127.2lb/ft3
Dredge line Z=1 φ = 35
E p2 D
clay
D
F p6 B
Solution
Part a
For φ= 35° ,
Ka= tan 2[45 – (φ/2)] = tan2[45 – (35/2)] = 0.271
Kp = tan 2[45 + (φ/2)] = 3.69
The pressure diagram shown in fig
ρ1 = γL1Ka = (0.108)(10.8)(0.271) = 0.316 kip / ft2
ρ2 = (γL1+γ´L2)Ka
= [(10.8)(0.108)+(0.0648)(21.6)](0.271)
= (1.1664+1.4)(0.271) = 0.695 kip / ft2
P1 = areas of 1+2+3 = 1.706 + 6.826 +4.093 = 12.625 kip/ft
(1.706)[{21.6+(10.8/3)}]+(6.826)(10.8)+(4.093)(21.6/3)
z1 =
12.625
= [42.99+73.72+29.47] / 12.625 = 11.58 ft
From eq 6.75 ,
ρ6D2+2ρ6D(L1+L2-l1) – 2P1(L1+L2 – l1– z1 ) = 0
ρ6 = 4c – (γL1+γ´L2)
= 4(0.850) – (1.1664+1.4) ≈ 0.834 kip /ft2
0.834D2+(2)(0.834)(D)(27) – (2)(12.625)(15.42) = 0
D2+54D – 466.85 = 0
D = 7.6ft
l1=5.4ft
L1=10.8ft F
1 l2=5.4ft
p1=0.316kip/ft2
L2=21.6ft
2 3
0.834kip/ft2 p2 =0.695kip/ft2
D=7.6 ft
Part b ,
From eq 6.74 ,
F = P1 – ρ6D = 12.625 – (0.834)(7.6) = 6.29 kip/ft
N0.23.For the anchored sheet pile wall shown in fig , determine (a)D, (b)F , and (c)Mmax.Use
the CPD method ; assume that C = 0.68 and R = 0.6 .
D sand
3
γ sat =122.4lb/ft
c=0
φ=35
Solution
Part a ,
γ´= γsat – γw = 122.4 – 62.4 = 60 lb/ft3
From eq 6.82
γav = [γL1+γ´L2] / [L1+L2] = [(110)(10)+(60)(20)] / [10+20] = 76.67 lb/ft3
Ka= tan 2[45 – (φ/2)] = tan2[45 – (35/2)] = 0.271
ρa = CKa γavL = (0.68)(0.271)(76.67)(30) = 423.9 lb/ft2
ρp= Rρa = (0.6)(423.9) = 254.3 lb/ft2
D2+2DL[1-(l1/L)] – (L2/R)[1 – 2(l1/L)] = 0
D2+2(D)(30)[1 – (5/30)] – (302/0.6)[1 – 2(5/30)]
= D2+50D – 1000 = 0
D ≈ 15.3ft
Check
L(L – 2l1) 30[30 – (2)(5)]
R= = ≅ 0.6----- OK
D(2L+D-2l1) 15.3[(2)(30)+15.3-(2)(5)]
Part b ,
F = ρa(L-RD) = 423.9[30-(0.6)(15.3)] = 8825 lb/ft
Part c ,
Mmax = 0.5 ρa L2[{1-(RD/L)}2-{2l1/L}{1-(RD/L)}]
1 – (RD/L) = 1 – [(0.6)(15.3)] / 30 = 0.694
Mmax = (0.5)(423.9)(30)2[(0.694)2 – {(2)(5)(0.694)} / 30]
= 88248 lb-ft/ft
N0.24.A row of vertical anchors embedded in sand is shown in fig.The anchor plates are
made of 6 in thick concrete .The design parameters are B = h = 15 in , S´ = 48 in , H = 37.5 in
γ= 105 lb/ft3 , φ = 35°, and the unit weight of concrete = 150 lb/ft3.
Sand
H=37.5 γ =105lb/ft3
B=15in
φ =35
S´=48 in S´=48 in
h=15in
Determine the
a.Ultimate resistance of each anchor plate .
b.Anchor resistance for a maximum horizontal displacement of
1.5 in.
Solution
Part a ,
From fig 6.37 a for φ= 35° , (Ka = 0.26)
W = Htγconcrete = (37.5/12)(6/12)(150 ) = 234.4 lb/ft
Eq 6.93
W +(1/2)H2Ka sin φ
Kp sin =
(1/2)γH2
234.4 + (1/2)(105)(37.5/12)2(0.26)(sin 35)
= = 0.606
(1/2)(105)(37.5/12)2
From fig 6.37 b , φ= 35 , Kp sin δ= 0.606 , Kp cos δ= 4.5
Eq 6.92
Pu = ½ H2(Kp cos δ – Ka cos φ)
= (1/2)(105)(37.5/12)2[4.5 – (0.26)(cos 35)] = 2198 lb/ft
To calculate P´us , Cov = 14(loose sand)
Cov +1 14+1
P´us = Pu = (2198)
Cov + (H/h) 14+(37.5/15)
= 1998 lb/ft
[(S´– B) / (H+h)] = [(48- 15)/(37.5+15)] = 0.61
For (S´– B) / (H+h) = 0.61 , fig 6.39 b (loose sand )
[(Be - B)/(H -h)] = 0.227
(0.227)(37.5+15)+15
Be = (0.227)(H+h)+B = = 2.24ft
12
Eq 6.95
Pu = P´usBe = (1998)(2.24) = 4476 lb
Part b,
From fig 6.40 , H / h = 2.5 and B / h = 1 ,Δu / h = 0.24
Δu = 0.24h = 0.24 ×15 = 3.6 in
IfΔ= 1.5 in , Δ = Δ/Δu= 1.5/3.6 = 0.417
Eq 6.96
P = Δ / [0.15+0.85Δ ]
= [(0.417)/{(0.15)+(0.85)(0.417)}] = 0.827
PatΔ = 1.5 in = 0.827 Pu = (0.827)(4476) = 3702 lb
Solution
Eq 6.99
(H/h)cr – S = 4.7 + 2.9 10-3c
= 4.7 + (2.910-3)(500) = 6.15
Eq 6.100
(H/h)cr – R = (H/h)cr - S[0.9+0.1(B/h)]
= (6.15)[0.9+0.1(5/2)] = 7.07
As H/h = 6/2 = 3 < (H/h)cr
Eq 6.104 To obtain Pu ,
(3/7.07)
= 0.41+(0.59)(3/7.07)
[(Pu/cBh)/{( 7.425)+(1.575)(2/5)}]
Or
(0.424) / [(Pu/cBh)/(8.055)] = 0.66
So
Pu / cBh = (0.424/0.66)(8.055) = 5.17
Pu = (5.17)cBh = (5.17)(500)(5)(2) = 25850lb
N0.26.Fig shows the cross section of a long braced cut .
a.Draw the pressure envelope .
b.Determine the strut loads at levels A,B and C.
c.Determine the section modulus of the sheet pile required .
d.Determine the section modulus for the wales at level B.
The struts are placed 10ft centre to centre .
20ft
3ft
A
5.5ft
8ft
Sheet pile
B
11ft
Clay
759lb/ft2 γ =115lb/ft3
C=750lb/ft2
φ=0
8ft
5.5ft
3ft
Solution
Part a ,
γH/c = [{115}{22}] / (750) = 3.37 < 4
ρa = 0.3γ H = (0.3)(115)(22) = 759 lb/ft2
5.5ft
Pa=759lb/ft2
11ft
5.5ft
Pressure envelope
Part b
To determine the struts loads , fig ( a )
Taking the moment about B1 ,∑MB1 = 0
A (8 ) – (1/2)(759)(5.5){5.5+(5.5/3)} – (5.5)(759)(5.5/2) = 0
8A – 15306.5 – 11479.9 = 0
A = 3348.3 lb
∑Vertical forces = 0
B1 = (1/2)(5.5)(759) + (759)(5.5) – A = 2913.5 lb
B2 = 2913.5lb
C = 3348.3lb
759lb/ft2
759lb/ft2
414lb/ft2
2727.3lb 2727.3 lb
X =3.84ft
B2 F C
A E B1
621lb 621lb
2913.5lb 2913.5lb
16 ft
6 ft
9 ft 3
γ =112lb/ft
φ =32
B c=0
9 ft
3 ft
Solution
For this case , the earth pressure envelope shown in fig
H=
27ft Pa=603.
44
Calculate B1,
603.44 ft
6 ft 9ft
A B1
∑MB1 = 0
A = [(603.44)(15)(15/2)] / (9) = 7543lb/ft
B1 = (603.44)(15) – 7543 = 1508.6 lb/ft
Calculate B2
603.44
9ft 3ft
B2 C
∑MB2 = 0
C = [(603.44)(12)(12/2)]/(9) = 4827.5 lb/ft
B2 = (603.44)(12) – 4827.5 = 2413.7 lb/ft
N0.28. The braced cut shown in fig , for which γ= 112 lb/ft3 ,
φ = 32°and c = 0.The struts are located 12ft on center in the plane.Determine
(a) the sheet pile section
(b) the required section modulus of the wales at level A, assume that all = 24 kip /in2
16 ft
6 ft
9 ft 3
γ =112lb/ft
φ =32
B c=0
9 ft
3 ft
Solution
Part a,
Determine x1 and x2:
x1 = 3.923 / 0.603 = 6.5 ft
x2 = 3.017 / 0.603 = 5 ft
Ka = tan2[45 – (φ/2)] = tan2[45-(32/2)]
A 6ft = 0.307
9ft
B
9ft pa = 0.65γHKa
C = (0.65)(112)(27)(0.307)
3ft = 603.44 lb/ft2
603.44 603.44
lb/ft2 lb/ft2
A B1 B2 C
6ft 9ft
3.923kip
A B´ B1
x1
1.509 kip
3.62 kip
3.017 kip
B2 B´´ C
x2
1.81 kip
Part b ,
For the wale at level A ,
Mmax = [A(s)2]/8
A = [(603.44)(15)(15/2)] / (9) = 7543lb/ft
Mmax = [(7.543)(12)2]/8 = 135.77 kip-ft
Sx = Mmax/σall = [(135.77)(24)] = 67.9 in3 /ft of wall
5.7 c 5.7 42
FS = (1/H) = (1/8) = 7.74
. γ - c/(0.7B) 17.2 – 42 / (0.7 4.5)
Part b ,
FS = [cNc] / [γH]
From fig 7.16 for H / B = 8 / 4.5 = 1.78 and B / L ≈ 0 ,
The magnitude of Nc ≈ 7
FS = [(42)(7)] / [(17.2)(8)] = 2.14