Keepers Area
Keepers Area
Keepers Area
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
F PLASTERING 109,115.76
G PAINTING 53,265.60
H PAVING 36,320.00
M MISCELLANEOUS 534,124.00
1
ASIAN ZONE - SAFARI PARK-RIDIYAGAMA
SUMMARY
AMOUNT
ITEM NO DESCRIPTION QUANTITY (NRS) RATE
Rs. Cts.
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
A.2 Excavation for foundation in any material except m3 12.16 920.00 11,187.66 Analysis 2
rock requiring blasting, up to a depth of 1.5m from
existing levels
A.3 Filling under floors with approved imported earth m3 4.80 1,580.00 7,584.00 Analysis 3
in layers not exceeding 150mm including watering
and ramming up to a depth not exceeding 1.5m .
A.4 Excavation site for necessary levels in holding areas m3 1,200.00 717.00 860,400.00 Analysis 87
not exceeding 1.5m depth in any material except
rock requiring blasting and return filling.
A.5 Filling Excavated area with approved available m3 500.00 540.65 270,325.09 Analysis 88
earth in layers not exceeding 150mm including
watering and ramming up to a depth not exceeding
1.5m .
A.6 Anti-termite treatment to building area according m2 65.60 178.00 11,676.80 Analysis 4
to a approved specialist contractor's specification
and technical literature (Rate shall be included for
5 years warranty).
B CONCRETE WORK
Up to DPC level
B.1 50mm thick Grade 15 lean concrete under wall & m2 15.33 534.00 8,186.22 Analysis 5
column foundation
B.2 Grade 25 reinforced concrete in Column footing m3 0.91 17,500.00 15,946.88 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
B.3 Grade 25 reinforced concrete in plinth beams m3 1.42 17,500.00 24,885.00 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
B.5 Grade 25 reinforced concrete in Column shaft m3 1.01 17,500.00 17,640.00 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately.
B.6 225x150mm Copping Beam in Grade 25 concrete m3 0.38 17,500.00 6,667.50 Analysis 7
including necessary reinforcement and form work
finishes measured separately.
-
Form work
Rate of form work is included for all necessary
boarding, supports, erecting, framing, cutting
angles, cleaning, wetting and any surface treatment
before and after placing of concrete.
Up to DPC level
B.7 for Column footing m2 5.40 1,099.00 5,934.60 Analysis 8
B.8 for Plinth Beam m2 8.88 1,099.00 9,759.12 Analysis 8
-
DPC level to Roof level
B.9 for Copping Beam m2 1.91 1,099.00 2,093.60 Analysis 8
2
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
Reinforcement
Up to DPC level
B.11 for Column footing t 0.09 197,000.00 17,951.63 Analysis 9
-
DPC level to Roof level
Up to DPC level
Random rubble masonry
C.1 Random rubble masonry in cement and sand( 1:5 ) m3 5.34 10,471.00 55,930.85 Analysis 10
mortar in foundations.
3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
C.3 Prepare 150mmx150mm Ventilation Openings in to nrs 32.00 550.00 17,600.00 Analysis 95
30 angle, in block walls according to the detail
drawings.
4
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
D.2 Horizontal damp proof membrane DPM girth > m2 50.84 122.00 6,202.48 Analysis 13
300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The
rate shall included for laps & wastage
E.1 Supplying & fixing of Zn/Al roofing sheets on steel m2 56.00 4,633.00 259,448.00 Analysis 14
frame work for Roof as per detail drawing (rate
including with Steel frame work .)
E.2 Supplying & fixing of 6000 x 1200mm Reinforced m3 1.32 50,014.00 66,018.48 Analysis 16
Concrete Roof Canopy in 100mm thk as per detail
drawing
E.3 Supply & fixing of Zn Aluminum square gutter m 8.00 1,897.00 15,176.00 Analysis 15
approved by Engineer with all type of necessary
fittings.
E.4 Straight 100x100mm square type Zn/Al coated m 6.20 927.00 5,747.40 Analysis 17
approved colour bonded plain steel sheet down
pipe fixed to wall with and including standard down
pipe brackets (clips)at 600mm centers.
5
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
F PLASTERING
F.1 15mm thick cement & sand (1:5) plaster finished m2 157.82 450.00 71,020.80 Analysis 91
semi rough with wood float on internal and
external faces on block / concrete surfaces.
F.2 15mm thick cement & sand (1:5) plaster finished m 56.00 210.00 11,760.00 Analysis 92
semi rough with wood float on internal and
external reveals.
F.3 Smooth cement finish plastering with 20mm thick m2 37.44 557.00 20,854.08 Analysis 18
1:3 cement sand plaster to Internal surfaces of
walls up to 1.8m hight as directed.
F.4 Plinth plastering with 20mm thick 1:3 cement sand m2 9.84 557.00 5,480.88 Analysis 18
plaster finished smooth with colour cement
floating.
G PAINTING
G.1 Prepare surface and apply one coat of water m2 78.91 377.00 29,749.82 Analysis 93
proofing primer and two coats of approved type
weathershield paint to external plastered surfaces
of walls as directed.
G.2 Prepare surface and apply one coat of acralic filler m2 78.91 298.00 23,515.78 Analysis 94
and two coats of approved type emulsion paint on
internal plaster surfaces as directed.
H PAVING
FLOOR PAVING
H.1 20mm thick 1:3 cement rendering including m2 48.00 654.00 31,392.00 Analysis 19
smooth cement finish on concrete floor .
J METAL WORK
6
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
J.1 Supplying and fixing of Door Type SD1,1800 X Nr 4.00 77,046.00 308,184.00 Analysis 21
2100mm Overall Size, GI sliding Door,Automated &
manually openable,slides one Directions and
remain a gap on top. (Rate shall be included all
necessary fittings and accessories).
J.2 Supplying and fixing of Window Type W7,1800 X Nr 2.00 23,735.00 47,470.00 Analysis 89
700mm Overall Size, Steel grill window.(Rate shall
be included all necessary fittings and accessories).
J.3 Supplying and fixing of Window Type W8,2800 X Nr 4.00 60,694.00 242,776.00 Analysis 90
1300mm Overall Size, Steel grill window.(Rate shall
be included all necessary fittings and accessories).
J.4 Supplying and fixing of GI sliding gate ,type G1, Nr 1.00 128,932.00 128,932.00 Analysis 23
3000 x 1600mm Overall Size slides two directions,
& gate columns for entrance including all necessary
fittings.
J.5 Supplying and fixing of GI gate Type G3,900 X Nr 2.00 19,066.00 38,132.00 Analysis 24
1600mm Overall Size,Opens with out hinges &
fixed to chain link fence in open holding area. (Rate
is included all necessary fittings and accessories).
7
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
K PLUMBING WORKS
ACCESSORIES
K.4 Supplying and fixing of Plastic Tap Nr 1.00 294.00 294.00 Analysis 37
L ELECTRICAL WORKS
L.1 15w CFL pendent lamp with wiring Nr 1.00 5,850.00 5,850.00 Analysis 80
L.2 Access way Lights with wiring Nr 1.00 8,200.00 8,200.00 Analysis 81
M MISCELLANEOUS
M.1 Construction of Food & Water Trough size nr 1.00 13,024.00 13,024.00 Analysis 39
4500x700mm, Brick fill and Out side cement
rendered finish.
M.2 Construction of 300mm wide, 150mm deep RCC m 8.00 2,271.00 18,168.00 Analysis 41
Drain including necessary formwok and finishing
works.
8
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
M.3 Construction of 150 x 150mm Kerb as directed by m 40.00 1,167.00 46,680.00 Analysis 54
Engineer.
M.4 PVC coated G - 10 Green mesh GI Chain link fence m 33.00 9,030.00 297,990.00 Analysis 42
(1.8m hight) fixed with nut bolts including tension
wires and all other necessary accessories.
M.5 Laying 300mm Rever Sand layer in Open Area as m2 120.00 899.00 107,880.00 Analysis 45
directed by Engineer.
M.7 Construction of 600x600x1200mm size Soakage Pit nr 2.00 2,012.00 4,024.00 Analysis 46
for collect waste water for Two holding units.
M.8 Laying gravel in Access gravel area between two Item 4,060.00 Analysis 47
Shelters.
M.10 Supplying and turfing with buffalo grass sods m2 18.60 651.00 12,108.60 Analysis 96
including compacting
Rate included for Preparation of land in required
slope ,Fertilizing land with coir dust compost &
organic soil including watering as required.
M.11 Watering & maintain the turf area for three months m2 18.60 279.00 5,189.40 Analysis 97
9
Description
Times Length(m) Width(m) Height(m)
Lean conctree
Wall 32.80 0.3
Column 4 0.90 0.9
4 0.75 0.75
G25 concrete
for floor Concrete 8.00 6.00
for pavement 8.00 1.1
B2 4 8.2 0.2
2 8.2 0.4
B3 2 8 0.2
1 8 0.3
B4 2 2 0.2
1 2 0.2
Block Work
Sheltered Area 1 8.00 4.340
1 8.00 3.100
2 8.40 4.34
ddt SD1 4 1.80 2.10
W7 2 1.80 0.70
W8 4 2.80 1.30
Ventilation Openings 48 0.15 0.15
reveals 4 2.8
4 2.1
2 1.8
8 2.8
8 1.3
skirting 1 28.00
brick work
Sides & middle partition 1 0.7 0.3
FRONT WALL 1 5.5 0.3
walls 2 0.7 0.3
Rubble work
2 16.5 0.3 0.6
761.40 761.40 m2
3.40
2.36 5.76
2.34
0.94
1.56
1.56 6.40
12.16 m3
4.8 4.80 m3
65.60 65.60 m2
9.84
3.24
2.25 15.33 m2
48.00
8.80 56.80 m2
1.32 1.32 m3
12.7
0.64
1.31
0.48
0.08 2.51
0.81
0.10 0.91 m3
1.01 1.01 m3
1.48
0.05 1.42 m3
1.91 1.91 m2
0.80
0.24
9.60 10.64 m2
3.20
3.20 6.40
6.56
6.56 13.12
3.20
2.40 5.60
0.80
0.40 1.20
26.32 m2
3.60
1.80 5.40 m2
20.16 20.16 m2
9.84
0.96 8.88 m2
0.11 0.11 t
0.03 0.03 t
0.30 0.30 t
0.09 0.09 t
0.10 0.10 t
0.11 0.11 t
5.90 5.90
0.56
0.56
5.34 m3
34.72
24.80
72.912 132.43
15.12
2.52
14.56
1.08 33.28
99.15 m2
9.84 9.84 m2
50.84 50.84 m2
8.00 8.00 m
6.20 6.20 m
9.84
9.84 m2
72.91
34.72
24.80 132.43
15.12
14.56
5.12 34.80
2
195.26 m
28.8
21.6 50.4
12.96 12.96
37.44 m2
157.82 m2
11.2
8.4
3.6
22.4
10.4 56.00 m
112.00 m
48.00 48.00 m2
28.00 28.00 m 15
0.21
1.65
0.42 2.28 m2
4.05 4.05 m2
4.05
0.84
0.42
1.65 6.96 m2
5.40
5.40 m3
0.00 m3
5.40 m3
5.94
5.94 m3
0.12 0.12 m3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
RATE ANALYSIS 27%
Site clearing and preparation of the site including removal of top soil up to a depth of 150mm
Analysis 1 and extend up to 3m beyond the outer walls of the building & disposed off as directed by
engineer.
Excavation for foundation in any material except rock requiring blasting, up to a depth of 1.5m
Analysis 2
from existing levels.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m3
1.0 Labour 627.00
2.0 tools 5% 31.35
Sub total 1 - normal excavation rate 658.35
Item Ref No Description Unit Qty Rate Amount Remarks
Total m3 325.88
Profit & Overhead 27% 87.99
Total for pit 413.87
Total for 1m3 919.71
say 920.00
Filling under floors with approved imported earth in layers not exceeding 150mm including
Analysis 3
watering and ramming up to a depth not exceeding 1.5m .
20
Anti-termite treatment to building area according to a approved specialist contractor's
Analysis 4
specification and technical literature.
Analysis 5 50mm thick Grade 15 lean concrete under wall & column foundation .
21
Grade 25 reinforced concrete in Column footing including placing, leveling and vibrating.
Analysis 7 Reinforcement and form work measured separately
Analysis 8 Smooth finished form work to be in 12mm thk plywood for contact surfaces used at three times.
1.0 Plywood (if one sheet use 3 times) m2 0.42 1,059.03 441.26
2.0 Labour 319.00
3.0 Allow for necessary props 100.00
4.0 allow for transport sheets 4.41
Sub total 1 864.68
Profit & Overhead 27% 233.46
Total 1,098.14
Say 1,099.00
Analysis 9 Reinforcement
22
Analysis 10 Random rubble masonry in cement and sand( 1:5 )mortar in foundations.
Analysis 11 200mm thick block walls with 1:5 cement & sand mortar for walls
Horizontal damp proof course DPC ,width more than 300mm, two coats of approved bituminous,
Analysis 12 material and blinded with river sand on and including 20mm thick 1:3 cement sand screed on
rubble foundation.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
1.0 Cement 50Kg 0.242 817.68 197.88
2.0 Sand m3 0.002 2,826.86 5.65
3.0 DPC Tar lt 0.500 256.25 128.13
4.0 Skilled Labour hr 1.100 150.00 165.00
5.0 Unskilled Labour hr 2.200 100.00 220.00
Sub total 1 716.66
Profit & Overhead 27% 193.50
Total per 1m2 910.15
Say 911.00
23
Analysis 13 Horizontal damp proof membrane DPM girth > 300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The rate shall included for laps & wastage.
Say 122.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
1.0 Heat insulation material(All
inclusive) m2 1.00 250.00 250.00
Total 721.84
Say 722.00
24
C Roof Frame work
2.0 8mm thk 225x225 MS Base Plate nrs 10.00 350.00 3,500.00
3.0 8mm thk 225x225 MS Sole Plate nrs 10.00 350.00 3,500.00
Supplying & fixing of Zn/Al roofing sheets on steel frame work for Roof as per detail drawing
Analysis 14
(rate including with Steel frame work .)
Rate for 1 m2
1.0 Zn/Al Sheets (for roof ) m2 1.00 1,162.45 1,162.45 Refer - A
2.0 Heat Insulation Layer m2 1.00 722.00 722.00 Refer - B
3.0 Roof frame work m2 1.00 1,763.00 1,763.00 Refer - C
Sub total 1 3,647.45
Profit & Overhead 27% 984.81
Total 4,632.26
Say 4,633.00
25
Supply & fixing of Zn Aluminum square gutter approved by Engineer with all type of necessary
Analysis 15 fittings.
Item Ref No Description Unit Qty Rate Amount Remarks
Data for 11m
Rate for 1 m2
1.0 Zn/Al gutter m 11.00 436.24 4,798.64
2.0 100x16 'C' Purlin m 11.00 525.00 5,775.00
3.0 6mm thk 200x200 MS Plate nr 4.00 206.00 824.00
4.0 12mm Anchor Bolt nr 16.00 95.00 1,520.00
5.0 Labour for laying channels m 11.00 60.00 660.00
6.0 Labour for fixing Zn/Al gutter m 11.00 230.00 2,530.00
7.0 Allow for fixing and other accersories 317.21
Sub Total 16,424.85
Profit & Overhead 27% 4,434.71
Total 1m 1,896.32
Say 1,897.00
Analysis 16 Supplying & fixing of Reinforced Concrete Roof Canopy as per detail drawing.
Say 50,014.00
Straight 100x100mm square type Zn/Al coated approved colour bonded plain steel sheet down
Analysis 17
pipe fixed to wall with and including standard down pipe brackets (clips)at 600mm centers.
Item Reference
Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
1.0 Zn/Al down pipe m 1.1 432.96 476.26
2.0 Allow screws other accersories 23.81
3.0 Labour 230.00
Sub Total 730.07
Profit & Overhead 27% 197.12
Total for 1m 927.19
Say 927.00
Plinth plastering with 20mm thick 1:3 cement sand plaster finished smooth with colour cement
Analysis 18
floating
26
Reference
Item item No Description Unit Qty Rate Amount Remarks
Analysis 19 20mm thick 1:3 cement rendering including smooth cement finish on concrete floor .
Analysis 20 20mm thick 1:3 cement sand bedding for 75mm skirting
Reference
Item item No Description Unit Qty Rate Amount Remarks
Rate per 1m
27
Supplying and fixing of Door Type SD1,1800 X 2100mm Overall Size, GI sliding Door,slides one
Analysis 21 Direction along "C" Channels and fixed on to window profile on top and bottom rail fixed in to
wall. (Rate is included all necessary fittings and accessories).
Supplying and fixing of Window Type W1,5800x1300mm Overall Size, GI Fixed window.(Rate is
Analysis 22 included all necessary fittings and accessories).
Supplying and fixing of GI sliding gate ,type G1, 3000 x 1600mm Overall Size & gate columns for
Analysis 23 entrance including all necessary fittings.
28
Sub total 1 106,156.52
27% 22,775.34
Profit & Overhead
Total 128,932.00
Supplying and fixing of GI gate Type G3,900 X 1600mm Overall Size. (Rate is included all
Analysis 24
necessary fittings and accessories).
27% 4,053.33
Profit & Overhead
Total 19,066.00
Supplying and fixing of GI gate Type G4,900 X 2100mm Overall Size. (Rate is included all
Analysis 25
necessary fittings and accessories).
Supplying and fixing of GI sliding gate ,type G2, 3000 x 2100mm Overall Size slides two directions,
Analysis 26
& gate columns for entrance including all necessary fittings.
29
4.0 weels nr 8.00 1,000.00 8,000.00
5.0 Flush Bolt nr 2.00 650.00 1,300.00
6.0 Pad Lock Holders nr 1.00 650.00 650.00
7.0 transport 5,675.63
8.0 Allow for welding kg 286.70 55.00 15,768.72
9.0 Painting Steel m2 7.54 441.00 3,326.40 Analysis - 32
10.0 Gate Column nr 2.00 10,509.00 21,018.00 Analysis - 27
Sub total 1 118,798.69
27% 16,006.11
Profit & Overhead
Total 134,805.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per nr
1.0 Excavation m3 0.10 920.00 92.22 Analysis-2
2.0 Grade 25 Concrete m3 0.14 17,500.00 2,418.61 Analysis-7
3.0 Form Work m2 3.50 1,099.00 3,846.50 Analysis-8
4.0 Reinforcement kg 11.05 197.00 2,176.85 Analysis-9
5.0 Plaster m2 2.39 440.00 1,052.04 Refer - P
6.0 Paint m2 2.30 401.00 922.30 Refer - D
Sub total 1 10,508.52
Say 10,509.00
For 2nr of gate columns 21,018.00
Supplying and fixing of Window Type W2,1300 x 4800mm Overall Size, GI fixed window. (Rate is
Analysis 28 included all necessary fittings and accessories).
Total 76,834.00
30
Supplying and fixing of Window Type W3,1300 x 4800mm Overall Size, GI fixed window. (Rate is
Analysis 29 included all necessary fittings and accessories).
27% 19,160.99
Profit & Overhead
Total 90,128.00
Supplying and fixing of Door Type SD3,3000 X 2100mm Overall Size, GI sliding Door,slides one
Analysis 30 Direction along "C" Channels and fixed on top and bottom to wall. (Rate is included all necessary
fittings and accessories).
27% 24,143.92
Profit & Overhead
Total 113,566.00
Supplying and fixing of Window Type W5,1300 x 4800mm Overall Size, GI fixed window. (Rate is
Analysis 31
included all necessary fittings and accessories).
31
Sub total 1 64,522.63
27% 16,674.07
Profit & Overhead
Total 81,197.00
Analysis 32 Steel paint One Coat of Anticorosive & two coats of enamel paint for final finish of the profiles
Say 441.00
32
D Painting external walls
Say 401.00
Rate per nr
Say 9,585.00
Analysis 34 Supplying and fixing of T1000 dia. PVC pipes including all specials
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
32mm dia
1.0 32mm piping m 1.100 185.00 203.50
2.0 Other Acccessories-for specialiest 50.88
3.0 Other Acccessories-for nails ,clips,joints 20.35
4.0 Labour m 1.00 77.00 77.00
Sub total 1 351.73
Profit & Overhead 27% 94.97
Total per 1m 446.69
Say 447.00
33
Analysis 35 Supplying and fixing of T1000 dia. PVC pipes including all specials
Say 675.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
110mm dia
1.0 110mm piping m 1.100
1,750.89 1,925.98
2.0 Other Acccessories-for specialiest 481.50
3.0 Other Acccessories-for nails ,clips,joints 192.60
4.0 Excavation m3 2.00 658.35 1,316.70 Analysis-2
5.0 Labour m 1.00 77.00 77.00
Sub total 1 3,993.77
Profit & Overhead 27% 1,078.32
Total per 1m 5,072.09
Say 5,073.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Say 294.00
34
Analysis 38 Supplying and fixing of Tap
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Say 517.00
Say 1,380.00
Analysis 39 Construction of Food & Water Trough size 4500x700mm, Brick fill and Out side cement rendered
finish.
Total 13,023.64
Say 13,024.00
Analysis 40 Construction of Reinforced Concrete of Water Trough size 1000 x 800mm, at 3000mm height
with water supply line and drain outlet & line for Cleaning purpose below.
35
Item Ref No Description Unit Qty Rate Amount Remarks
Total 18,564.16
Say 18,565.00
Analysis 41 Construction of 300mm wide, 150mm deep RCC Drain including necessary formwok and finishing
works.
Data for 6m
Rate per 1m
1.0 Excavation for drain m3 0.608 658.35 399.95 Analysis-2
2.0 Concrete work m3 0.473 17,500.00 8,268.75 Analysis-7
3.0 Formwork m2 2.903 1,099.00 3,189.85 Analysis-8
4.0 20mm thk Rendering m2 2.700 654.00 1,765.80 Analysis-19
Total 13,624.35
Say for 1m 2,271.00
36
PVC coated G - 10 Green mesh GI Chain link fence (1.8m hight) fixed with nut bolts including
Analysis 42 tension wires and all other necessary accessories.
PVC coated G - 10 Green mesh GI Chain link fence (2.1m hight) fixed with nut bolts including
Analysis 43
tension wires and all other necessary accessories.
37
Gravel Road
Say 746.00
38
H Approved Soil Excavation Rate Analysis per 2.83m3
Say 1,204.00
Say 97.00
39
Approved Soil Spread & Rolled in Strips Where Aberage Width is
less than 1.2 metres for Toad Windening including Roller Hire
K Rate Analysis per 2.83m3
Charges, fuel & Watering (Loose Volume)[SSCM 601.1 - 4]
L Cutting New Side Drains in Ord. Soil Rate Analysis per 2.83m3
Say 523.00
M Cutting New Side Drains in Med. Soil Rate Analysis per 2.83m3
5.0 Coir string for cutting side drains Item 1.0000 20.00
(per 2.83 cu.m)
Say 740.00
40
N Cutting New Side Drains in Hard Soil Rate Analysis per 2.83m3
Say 956.00
P Cutting New Side Drains In Unclassified Soil Rate Analysis per 3m3
2.0 Cutting New Side Drains in Med. Cu.m 1.0000 740.00 740.00 Refer - M
Soil
3.0 Cutting New Side Drains in Hard Cu.m 1.0000 956.00 956.00 Refer - N
Soil
Sub total 1 3m3 2,219.00
27% 199.71
Add. Profit & Overhead
Say 940.00
41
Allow for water for mixing by
8.0 machine Cu.m 8.50 20.00 170.00
27% 24,696.79
Add. Profit & Overhead
Sub total 2 for 8.5m3 116,166.38
S Supplying and turfing with suitable grass type sods including Rate Analysis per 100m2
compacting
Say 472.00
T Watering & maintaining the turf area for three months Rate Analysis per 83.33m2
42
Say 278.00
U Form edges of the road with 1:2:4(20) concrete strip size Rate Analysis per 1m
50x200mm including form work.
Say 291.00
43
Analysis 46 Construction of 600x600x1200mm size soakage pit for collect waste water for Two holding unit.
Say 2,012.00
Say 4,060.00
Say 5,100.00
45
Sub total 1 235,205.98
Say 235,210.00
W Approved quarry dust filling to make up levels . including watering and ramming .
Y Supplying and fixing of T600 dia. PVC pipes including all specials
27% 536.46
Profit & Overhead
Total per 1m 2,523.33
Say 2,524.00
Z Plastering internal & external walls with 15mm thick 1:5 cement sand plaster finished semi rough.
46
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
Say 440.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Say 24,464.00
75mm dia GI Posts to make a Canopy above Chain Link fence to cover top to grow Creeper for
Analysis 55
shade height 7500mm from Floor level 2500 c/c.
48
Analysis 56 Supply and laying of matt finished none slip homogeneous tiles including 20mm thk cement
and sand (1:3)screed bedding on concrete floors.
Supply and laying of galazed ceramic wall tiles including 12mm thk cement and sand
Analysis 57
(1:5)screed bedding on walls.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
1.0 200X400mm wall tile no 13.13 300.00 3,937.50
2.0 Cement 50Kg 0.086 817.68 70.41
3.0 Sand m3 0.015 2,826.86 43.06
4.0 Labour m2 1.00 467.50 467.50
5.0 allow for tile grout m2 1.00 7.50 7.50
Sub total 1 4,525.97
Profit & Overhead 27% 1,222.01
Total per 1m2 5,747.98
Say 5,748.00
Analysis 58 Painting internal walls with one coat of primer & two coats of imulsion paint.
49
Analysis 59 Construction of sewer man hole internal size: 450x450x600 mm
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per item
1.0 Excavation m3 0.99 920.00 910.80 Analysis-2
2.0 Back filling m3 0.51 1,580.00 799.05 Analysis-3
3.0 Conc wk (1:2:4) m3 0.36 16,161.00 5,866.44 Analysis-6
4.0 Reinforcement kg 36.30 197.00 7,151.10 Analysis-9
5.0 Form work m2 5.05 1,099.00 5,548.85 Analysis-8
6.0 Plastering m2 2.11 440.00 929.28 Refer - Z
8.0 Allow for MS Handle 150.00
9.0 Allow for pipe wk & other 1,200.00
Sub total 1 22,555.52
Profit & Overhead 27% 364.50
Total per 1m 22,920.02
Say 22,921.00
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1nr
25mm dia
1.0 25mm stop valve nr 1.0 1,550.00 1,550.00
2.0 Other Accessories 77.50
3.0 Labour nr 1.0 143.00 143.00
Sub total 1 1,770.50
Profit & Overhead 27% 478.04
Total per 1nr. 2,248.54
Say 2,249.00
50
Analysis 62 Supplying and fixing of 20 mm dia T1000 type. PVC pipes including all specials - Under ground
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
20mm dia
1.0 20mm piping m 1.05 35.00 36.75
2.0 Other Accessories-for specialist 3.68
Other Accessories-for nails ,clips,
3.0 1.84
joints
4.0 Labour m 1.0 77.00 77.00
Sub total 1 119.26
Profit & Overhead 27% 32.20
Total per 1m 151.46
Say 151.00
Analysis 63 Supplying and fixing of 25 mm dia T1000 type. PVC pipes including all specials - Under ground
Analysis 64 Supplying and fixing of 63 mm dia T600 dia. PVC pipes including all specials - under ground
Analysis 65 150mm thick block walls with 1:5 cement & sand mortar for walls
Analysis 66 Supply and fixing of Closed coupled ceramic glazed Water Closet
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate for 1Nr
1.0 Brass Bib tap nr 1.0 3,800.00 3,800.00
2.0 Labour item 220.00
3.0 allow for transport item 20.00
Sub total 1 4,040.00
Profit & Overhead 27% 1,090.80
Total per 1nr. 5,130.80
Say 5,131.00
52
Analysis 69 Supply and fixing of mirror ( 600 x600 )
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate for 1Nr
1.0 mirror ( 450 x600 ) nr 1.0 1,597.62 1,597.62
2.0 other accessories item 15.98
3.0 Labour item 143.00
4.0 Allow for transport item 47.93
5.0 preparing edges m 2.100 410.00 861.00
Sub total 1 2,665.53
Profit & Overhead 27% 719.69
Total per 1nr. 3,385.22
Say 3,386.00
A1 painting - timber
Analysis 70 D1 (900X2100)mm
Rate per 1 Nr
Material
1.0 5"X3" Door frame ( jack ) m 4.41 2,050.00 9,040.50
2.0 1`` thk Door sash ( jack ) m2 2.08 4,843.80 10,070.26
Labour
4.0 Making frame m 4.41 220.00 970.20
5.0 Making Sash m 2
2.08 1,100.00 2,286.90
6.0 Fixing Charges No 1.00 550.00 550.00
7.0 Fixing Door Lock. No 1.00 462.00 462.00
Door Accessories
8.0 4"x4" Brass Butt Hinges. Nr 3.00 570.00 1,710.00
9.0 flush bolt Nr 1.00 1,200.00 1,200.00
10.0 Union mortis Door Lock Nr 1.00 1,500.00 1,500.00
11.0 Add Transport item 132.30
12.0 Painting m2 6.09 835.00 5,082.65 Refer A1
13.0 Transport timber 573.32
Sub Total 1 33,578.13
Profit & Overhead 27% 9,066.09
Sub Total 2 42,644.22
53
Total Per 1 m2 22,563.08
Say 22,564.00
Window Accessories
8.0 4"x3" Hinges pairs. Nr 4.00 297.50 1,190.00
9.0 Casement stay Nr 2.00 275.00 550.00
10.0 Fastners Nr 2.00 275.00 550.00
11.0 Window Ring Nr 2.00 95.00 190.00
12.0 Add Transport item 74.40
13.0 Painting m 2
4.15 835.00 3,467.55 Refer A1
14.0 Transport timber 343.75
Sub Total 24,429.62
Profit & Overhead 6,596.00
Sub Total 2 31,025.62
Total Per 1 m2 17,236.45
Say 17,237.00
Labour
2.0 Making frame m 3.99 209.00 833.91
2
3.0 Painting m 1.40 835.00 1,166.08
Grill
4.0 12 x 6 mm flat iron. m 6.20 77.59 481.03
5.0 25mm GI Rod. m 16.80 523.00 8,786.40
6.0 Painting m2 1.32 441.00 581.96
7.0 Transport timber 184.53
Sub Total 18,184.90
Profit & Overhead 4,909.92
Sub Total 2 23,094.82
2
Total Per 1 m 23,094.82
Say 23,095.00
54
Analysis 73 Timber Door - D1
Item Reference Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
1.0 Door m2 2.10 22,564.00 47,384.40 Analysis 70
Say 61,935.00
Window Accessories
6.0 4"x3" Hinges pairs. Nr 2.00 297.50 595.00
7.0 Casement stay Nr 1.00 275.00 275.00
8.0 Fastners Nr 1.00 275.00 275.00
9.0 Window Ring Nr 1.00 95.00 95.00
10.0 Add Transport item 37.20
2
11.0 Painting m 2.33 835.00 1,942.44 Refer A1
Sub Total 13,523.43
Profit & Overhead 3,651.33
Sub Total 2 17,174.75
Say 17,175.00
4.0 15w pendent lamp with CFL bulb nr 1.00 1,600.00 1,600.00
57
Analysis 84 13A socket outlets
58
Total Plant and Machinary 20,264.00
Supplying and fixing of Window Type W7,1800 X 700mm Overall Size, Steel grill window.(Rate
Analysis 89
shall be included all necessary fittings and accessories).
Supplying and fixing of Window Type W8,2800 X 1300mm Overall Size, Steel grill window.(Rate
Analysis 90
shall be included all necessary fittings and accessories).
59
Sub total 1 47,790.82
Profit & Overhead 27% 12,903.52
Total 60,694.00
Analysis 91 Plastering internal & external walls with 15mm thick 1:5 cement sand plaster finished semi rough
Analysis 92 Plastering external and inertnal reveals with 15mm thick 1:5 cement sand plaster finished semi
rough
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
Sand m3 0.003 2,826.86 8.48
Cement 50 Kg 0.013 817.68 10.63
Labour 143.00
add 2% of labor for scafolding 2.86
Sub total 164.97
Profit & Overhead 27% 44.54
Total per 1m2 209.51
Say 210.00
Analysis 94 Painting internal walls with one coat of primer & two coats of imulsion paint.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Imulsion Lit 0.200 534.40 106.88
Labour item 110.00
add 2% of labor for scafolding 2.14
Allow for brushes 15.00
Sub total 234.02
Profit & Overhead 27% 63.18
60
Total per 1m2 297.20
Say for GF 298.00
61
Analysis 94 Painting internal walls with one coat of primer & two coats of imulsion paint.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Imulsion Lit 0.200 534.40 106.88
Labour item 110.00
add 2% of labor for scafolding 2.14
Allow for brushes 15.00
Sub total 234.02
Profit & Overhead 0% -
Total per 1m2 234.02
Say for GF 235.00
Analysis 95 Prepare 150mmx150mm Ventilation Openings in to 30 angle, in block walls according to the detail
drawings.
Analysis 96 Supplying and turfing with buffalo grass sods including compacting.
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m2
Data for 100m2
1.0 Unskilled labour for Preparation hr 50.00 100.00 5,000.00
of land in required slope including
trimming ,leveling and
compaction
Analysis 97 Watering & maintaining the turf area for three months.
62
4.0 Water Bouser (6000L) day 1.00 6,000.00 6,000.00
Analysis 98 Supplying and fixing of Window Type W9,3000 X 1300mm Overall Size, GI fixed window.(Rate
shall be included all necessary fittings and accessories).
Supplying and fixing of Window Type W10,2500 X 1300mm Overall Size, GI fixed window.(Rate
Analysis 99 shall be included all necessary fittings and accessories).
Total 54,909.00
Analysis 100 Supplying and fixing of 40 mm dia T600 dia. PVC pipes including all specials - under ground
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Rate per 1m
40mm dia
1.0 40mm piping m 1.05 135.00 141.75
2.0 Other Accessories-for specialist 14.18
63
Analysis 101 Supplying and fixing of 50 mm dia T600 dia. PVC pipes including all specials - under ground
Reference
Item Description Unit Qty Rate Amount Remarks
item No
Say 5,406.00
64
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
A PRELIMINARIES
A.1 Allow for construction and maintaining contractor P.sum 30,000.00
stores for work
A.4 Setting out work and approval of the engineer P.sum 10,000.00
A.5 Allow for clearing site after completion of work P.sum 1,500.00
B.2 Excavation for column footings in any material m3 2.37 627.00 1,485.99
except rock requiring blasting, up to a depth of
1.5m from existing ground level
B.3 Excavation for wall foundation in any material m3 6.02 31.35 188.73
except rock requiring blasting, up to a depth of
0.75m from existing levels
B.4 Filling under floors with approved imported earth m3 8.35 920.00 7,682.00
in layers not exceeding 150mm including watering
and ramming up to a depth not exceeding 1.5m .
B.5 Back filling to excavation with approved imported m3 1.04 1.00 1.04
earth in layers not exceeding 150mm including
watering and ramming up to a depth not
exceeding 1.5m .
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
C CONCRETE WORK
Rate shall include for:
C.1 50mm thick Grade 15 lean concrete under wall & m2 12.62 1.00 12.62
column foundation
C.4 100mm thick grade 20 ground floor slab including m2 24.79 1,580.00 39,168.20
reinforcement (As per the drawing)
C.5 75mm thick grade 20 ground floor slab including m2 8.17 1.00 8.17
reinforcement (As per the drawing)
Form work
Rate of form work is included for all necessary
boarding, supports, erecting, framing, cutting
angles, cleaning, wetting and any surface
treatment before and after placing of concrete.
2
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
C.8 for Roof Beams m2 7.16 1,068.00 7,646.88
Reinforcement
Rate shall be included for supplying, cleaning,
cutting, bending, fabricating, placing and the
provision of all necessary temporary fixings and
supports etc. including binding wires, bends,
hooks, tying wires, distance blocks, steel
separators/spacers (designed laps and m.s. chairs
if any included in quantities).
C.14 6mm dia.Mild steel for shear link kg 78.99 197.00 15,561.03
D MASONRY WORK
Rate shall included for lifting, handling, weighting Note
all rough and fair cutting, plumbing angles, normal
straight cutting, forming rebated reveals and
raking out joints for plastering.
Up to DPC level
Random rubble masonry
D.1 Random rubble masonry in cement and sand( 1:5 ) m3 7.39 10,471.00 77,338.81
mortar in foundations.
D.3 200mm thick block walls with 1:5 cement & sand m2 3.18 2,281.00 7,253.58
mortar for internal walls
3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
E.2 Horizontal damp proof membrane DPM girth > m2 29.12 122.00 3,552.64
300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The
rate shall included for laps & wastage
4
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
F.1 Supplying & fixing of Zn/Al roofing sheets on steel m2 39.64 4,633.00 183,652.12
frame work for Roof as per detail drawing (rate
including with Steel frame work .)
G PLASTERING
Up to DPC level
G.1 Plinth plastering with 20mm thick 1:3 cement m2 11.32 654.00 7,403.28
sand plaster finished smooth with colour cement
floating
G.3 15mm thick cement & sand (1:5) plaster finished m2 79.21 450.00 35,644.50
semi rough with wood float on internal faces on
block / concrete surfaces.
G.4 15mm thick cement & sand (1:5) plaster finished m 60.90 210.00 12,789.00
semi rough with wood float on internal and
external faces, width less than or equal to 100mm,
on block/concrete surfaces,reveals to openings
H PAINTING
H.1 Prepare and apply one primer coat and two coats m2 127.39 377.00 48,026.03
of weather shield emulsion paint of approved
colour to external surfaces of walls
5
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
H.2 Prepare and apply one coat of primer and two m2 79.21 670.00 53,070.70
coats of emulsion paint of approved colour and
quality to internal faces of walls. Rate is included
for preparing the surface with skim coat.
J PAVING
FLOOR PAVING
J.1 20mm thick 1:3 cement rendering including m2 30.40 654.00 19,881.60
smooth cement finish on concrete floor .
J.3 Supplying and laying of non slip homogeneous m2 2.56 5,337.00 13,662.72
floor tiles 300 x 300mm size in an approved
manufacture, colour and design laid on and
including 20 mm thick cement and sand 1:3
bedding and pointing with tile grout to match the
colour of tiles to the toilet and washing areas.
WALL PAVINGS
J.4 Supplying and laying of 200x300mm, glazed m2 9.60 5,748.00 55,180.80
ceramics wall tiles for 1500mm height in bath
rooms including 25mm thk cement and sand
(1:3)screed bedding and pointing with tile grout to
match the colour of tiles
6
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
K CAPENTRY WORKS
K.2 Supply and fixing of Type D3, PVC 750x2800mm Nr. 1.00 112,473.00 112,473.00
Overall size, PVC frame single sash door.The lovers
consist with GI grill on top as per the detail
drawing. (Rate is included all necessary fittings
and accessories).
K.3 Supply and fixing of Type SD4, Steel sliding door Nr. 1.00 112,473.00 112,473.00
(750x2800mm Overall size) as per the detail
drawing. (Rate is included all necessary fittings
and accessories).
K.4 Supply and fixing of Type F, timber of Nr. 1.00 112,473.00 112,473.00
650x1300mm Overall size, timber frame top hung
window.The lovers consist with GI grill on top as
per the detail drawing. (Rate is included all
necessary fittings and accessories).
L PLUMBING WORKS
7
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
L.4 -do- 40mm dia. m 1.80 361.00 649.80
K.11 Supplying & installation of closed coupled ceramic nr 1.00 20,202.00 20,202.00
glazed Water Closet complete with all necessary
accessories
K.12 Supplying & fixing of 20 mm brass bib taps nr 1.00 5,131.00 5,131.00
K.16 150 x150mm PVC floor gullies with water trap and nr 1.00 2,334.00 2,334.00
stainless steel grating (PC sum for gully - Rs.840.00
)
8
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
L ELECTRICAL WORKS
Consumer units
L.1 Single phase consumer units P.Sum 25,000.00
01 No. 40A, 2-pole ISO
Earth Bar
Socket Outlets
L.2 Supply & installation of 13A shuttered switched Nr 3.00 5,271.00 15,813.00
single socket outlet to comply with BS 1363.
Wiring (including supply of all material required )
of 13A socket outlets using approved type 2.5mm 2
Cu/PVC/PVC, 2C cable & 2.5mm 2 earth cable
drawn through securely fixed concealed PVC
conduit.(Wiring should be in ring circuits)
Light Fittings
L.3 15w CFL pendent lamp with wiring Nr 4.00 5,850.00 23,400.00
Fans
L.4 Supply & installation of 1400mm 5 weep ceiling Nr 1.00 8,294.00 8,294.00
fan (European/Japanese make), complete with
regulator, - Guarantee cards should be provided
from accredited agent.
9
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
A.2 Excavation for foundation in any material except m3 6.00 920.00 5,520.00
rock requiring blasting, up to a depth of 1.5m
from existing levels
A.3 Filling under floors with approved imported earth m3 13.00 1,580.00 20,540.00
in layers not exceeding 150mm including watering
and ramming up to a depth not exceeding 1.5m .
B CONCRETE WORK
Up to DPC level
B.1 50mm thick Grade 15 lean concrete under wall & m2 9.00 534.00 4,806.00
column foundation
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
B.5 Grade 25 reinforced concrete in Column shaft m3 0.50 17,500.00 8,750.00
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
Form work
Rate of form work is included for all necessary
boarding, supports, erecting, framing, cutting
angles, cleaning, wetting and any surface
treatment before and after placing of concrete.
Up to DPC level
Reinforcement
Rate shall be included for supplying, cleaning,
cutting, bending, fabricating, placing and the
provision of all necessary temporary fixings and
supports etc. including binding wires, bends,
hooks, tying wires, distance blocks, steel
separators/spacers (designed laps and m.s. chairs
if any included in quantities).
2
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
Up to DPC level
C MASONRY WORK
Rate shall included for lifting, handling, weighting Note
all rough and fair cutting, plumbing angles, normal
straight cutting, forming rebated reveals and
raking out joints for plastering.
Up to DPC level
Random rubble masonry
C.1 Random rubble masonry in cement and sand( 1:5 ) m3 5.00 10,471.00 52,355.00
mortar in foundations.
D.2 Horizontal damp proof membrane DPM girth > m2 7.20 122.00 878.40
300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The
rate shall included for laps & wastage
3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
E.1 Supplying & fixing of Zn/Al roofing sheets on steel m2 59.00 4,633.00 273,347.00
frame work for Roof as per detail drawing (rate
including with Steel frame work .)
E.2 Supply & fixing of Zn Aluminum square gutter m 4.10 1,897.00 7,777.70
approved by Engineer with all type of necessary
fittings.
E.3 Straight 100x100mm square type Zn/Al coated m 6.00 927.00 5,562.00
approved colour bonded plain steel sheet down
pipe fixed to wall with and including standard
down pipe brackets (clips)at 600mm centers.
F PLASTERING
Up to DPC level
F.1 Plinth plastering with 20mm thick 1:3 cement m2 9.42 654.00 6,160.68
sand plaster finished smooth with colour cement
floating
F.3 15mm thick cement & sand (1:5) plaster finished m2 125.00 450.00 56,250.00
semi rough with wood float on internal faces on
brick / concrete surfaces.
F.4 15mm thick cement & sand (1:5) plaster finished m 52.00 210.00 10,920.00
semi rough with wood float on internal and
external reveals
G PAINTING
4
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
G.1 Prepare and apply one primer coat and two coats m2 60.00 377.00 22,620.00
of weather shield emulsion paint of approved
colour to external surfaces of walls
G.2 Prepare and apply one coat of primer and two m2 125.00 670.00 83,750.00
coats of emulsion paint of approved colour and
quality to internal faces of walls. Rate is included
for preparing the surface with skim coat.
H PAVING
FLOOR PAVING
H.1 20mm thick 1:3 cement rendering including m2 35.00 654.00 22,890.00
smooth cement finish on concrete floor .
H.3 Supplying and laying of non slip homogeneous m2 3.25 5,337.00 17,345.25
floor tiles 300 x 300mm size in an approved
manufacture, colour and design laid on and
including 20 mm thick cement and sand 1:3
bedding and pointing with tile grout to match the
colour of tiles to the toilet and washing areas.
WALL PAVINGS
H.4 Supplying and laying of 200x300mm, glazed m2 14.00 5,748.00 80,472.00
ceramics wall tiles for height and length
1200x900mm back of the wash basin in washing
area including 25mm thk cement and sand
(1:3)screed bedding and pointing with tile grout to
match the colour of tiles
5
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
J CAPENTRY WORKS
J.2 Supply and fixing of Type D1, Timber Door Nr. 3.00 112,473.00 337,419.00
900×2500mm
J.3 Supplying and fixing of Type D3,PVC Door Nr 2.00 12,192.00 24,384.00
K PLUMBING WORKS
6
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
K.5 Construction of manhole internal size: nr 1.00 22,921.00 22,921.00
450x450x600 mm depth and 150 mm thk. Gr. 20
R.C.C. base, 150 mm thk. R.C.C. walls and R.C.C
cover slab as per the drawing.
K.6 Construction of water seal catch pit internal size: nr 1.00 14,752.00 14,752.00
300x300x600 mm depth and 150 mm thk. Gr. 20
R.C.C. base, 150 mm thk. R.C.C. walls and R.C.C
cover slab as per the drawing.
K.11 Supplying & installation of closed coupled ceramic nr 1.00 20,202.00 20,202.00
glazed Water Closet complete with all necessary
accessories
K.12 Supplying & fixing of 20 mm brass bib taps nr 1.00 5,131.00 5,131.00
K.16 150 x150mm PVC floor gullies with water trap and nr 1.00 2,334.00 2,334.00
stainless steel grating (PC sum for gully - Rs.840.00
)
7
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
Rs. Cts. Rs. Cts.
L ELECTRICAL WORKS
Consumer units
L.1 Single phase consumer units P.Sum 25,000.00
01 No. 40A, 2-pole ISO
Earth Bar
Socket Outlets
L.2 Supply & installation of 13A shuttered switched Nr 3.00 5,271.00 15,813.00
single socket outlet to comply with BS 1363.
Wiring (including supply of all material required )
of 13A socket outlets using approved type 2.5mm 2
Cu/PVC/PVC, 2C cable & 2.5mm 2 earth cable
drawn through securely fixed concealed PVC
conduit.(Wiring should be in ring circuits)
Light Fittings
L.3 15w CFL pendent lamp with wiring Nr 4.00 5,850.00 23,400.00
Fans
L.4 Supply & installation of 1400mm 5 weep ceiling Nr 1.00 8,294.00 8,294.00
fan (European/Japanese make), complete with
regulator, - Guarantee cards should be provided
from accredited agent.
8
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPER'S ROOM
BILL OF QUANTITIES
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
F PLASTERING 106,370.00
G PAINTING 53,265.60
H PAVING 127,465.65
1
Description
Times Length(m) Width(m) Height(m)
Lean conctree
Wall 21.20 0.3
Column 2 0.9 0.9
G20concrete
for floor Concrete 9.20 4.00
100mm
G25 concrete
for Copping Beam 9.24 0.23 0.15
Block Work
1 9.20 4.500
2 4.00 3.500
2 1.80 3.000
ddt DW1 1 1.80 2.80
DW 1 2.40 2.80
D3 1 0.75 2.80
F 1 0.65 1.30
Ddt
DW1 1 1.80 2.80
DW 1 2.40 2.80
F 1 0.65 1.30
Plastering internal
5 1.80 3.5
9.2 4.5
Ddt
D3 1 1.8 4.5
Plastering internal
reveals
DW1 1 1.8
2 2.8
DW 1 2.4
2 2.8
D3 1 0.8
2 2.8
F 2 0.65
2 1.3
Tiling
floor 1.80 1.8
brick work
Sides & middle partition 1 0.7 0.3
FRONT WALL 1 5.5 0.3
walls 2 0.7 0.3
Rendering
bottom 1 4.50 0.90
side walls 4 0.70 0.3
middle partition 2 0.70 0.3
FRONT WALL 1 5.50 0.3
Rubble work
2 22.30 0.3 0.6
1.30
24.4
1.66 7
2.16 31.4
5.11 5.11 m3 82
11.04 11.04 m3
6.36
1.62 7.98 m2
36.80
36.80 m2
0.31 0.31 m3
0.41
0.41 m3
0.28 0.28 m3
0.95
0.02 0.94 m3
1.63
2.77 2.77 m2
1.80
1.80 m2
5.04 5.04 m2
6.36
6.36 m2
3.82 3.82
0.00
3.82 m3
41.40
28.00
10.8 80.20
5.04
6.72
2.1
0.845
14.705
65.50 m2
4.00 4.00 m
6.00 6.00 m
6.36 9.42
2
6.36 m
41.40
28.00
0.00 69.40
5.04
6.72
0.845 12.61
56.80 m2
56.80
31.5
41.40
8.1 8.1
m2
121.60 m2
1.80
5.60
2.40
5.60
0.75
5.60
1.30 2,118,860,277.50
2.60 25.65 m 242896.24
51.3 m
8,723.31
36.80
3.24
33.56
32.60 32.60 m 38400
3.24 3.24
15.12
1.35
13.77
0.21
1.65
0.42 2.28 m2
4.05 4.05 m2
4.05
0.84
0.42
1.65 6.96 m2
6.69
6.69 m3
0.00 m3
6.69 m3
8.03
8.03 m3
0.16 0.16 m3
7.3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
F PLASTERING 276,505.08
G PAINTING 53,265.60
H PAVING 72,259.20
M MISCELLANEOUS 607,912.00
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
A.2 Excavation for foundation in any material except m3 20.29 920.00 18,668.64 Analysis 2
rock requiring blasting, up to a depth of 1.5m from
existing levels
A.3 Filling under floors with approved imported earth m3 10.08 1,580.00 15,926.40 Analysis 3
in layers not exceeding 150mm including watering
and ramming up to a depth not exceeding 1.5m .
A.4 Excavation site for necessary levels in holding areas m3 1,200.00 717.00 860,400.00 Analysis 87
not exceeding 1.5m depth in any material except
rock requiring blasting and return filling.
A.5 Filling Excavated area with approved available m3 500.00 540.65 270,325.09 Analysis 88
earth in layers not exceeding 150mm including
watering and ramming up to a depth not exceeding
1.5m .
A.6 Anti-termite treatment to building area according m2 72.00 178.00 12,816.00 Analysis 4
to a approved specialist contractor's specification
and technical literature (Rate shall be included for
5 years warranty).
B CONCRETE WORK
Up to DPC level
B.1 50mm thick Grade 15 lean concrete under wall & m2 22.24 534.00 11,876.16 Analysis 5
column foundation
B.2 Grade 25 reinforced concrete in Column footing m3 1.66 17,500.00 29,039.06 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
B.3 Grade 25 reinforced concrete in plinth beams m3 1.76 17,500.00 30,801.09 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
B.5 Grade 25 reinforced concrete in Column shaft m3 1.68 17,500.00 29,400.00 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately.
B.6 225x150mm Copping Beam in Grade 25 concrete m3 1.26 17,500.00 21,971.25 Analysis 7
including necessary reinforcement and form work
finishes measured separately.
-
Form work
Rate of form work is included for all necessary
boarding, supports, erecting, framing, cutting
angles, cleaning, wetting and any surface treatment
before and after placing of concrete.
Up to DPC level
B.7 for Column footing m2 12.00 1,099.00 13,188.00 Analysis 8
B.8 for Plinth Beam m2 11.04 1,099.00 12,132.96 Analysis 8
-
DPC level to Roof level
B.9 for Copping Beam m2 11.16 1,099.00 12,264.84 Analysis 8
2
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
Reinforcement
Up to DPC level
B.11 for Column footing t 0.17 197,000.00 32,689.69 Analysis 9
-
DPC level to Roof level
Up to DPC level
Random rubble masonry
C.1 Random rubble masonry in cement and sand( 1:5 ) m3 5.94 10,471.00 62,174.18 Analysis 10
mortar in foundations.
3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
C.3 Prepare 150mmx150mm Ventilation Openings in to nrs 40.00 550.00 22,000.00 Analysis 95
30 angle, in block walls according to the detail
drawings.
4
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
D.2 Horizontal damp proof membrane DPM girth > m2 75.64 122.00 9,228.08 Analysis 13
300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The
rate shall included for laps & wastage
E.1 Supplying & fixing of Zn/Al roofing sheets on steel m2 90.00 4,633.00 416,970.00 Analysis 14
frame work for Roof as per detail drawing (rate
including with Steel frame work .)
E.2 Supplying & fixing of 6000 x 1200mm Reinforced m3 1.44 50,014.00 72,020.16 Analysis 16
Concrete Roof Canopy in 100mm thk as per detail
drawing
E.3 Supply & fixing of Zn Aluminum square gutter m 12.00 1,897.00 22,764.00 Analysis 15
approved by Engineer with all type of necessary
fittings.
E.4 Straight 100x100mm square type Zn/Al coated m 7.00 927.00 6,489.00 Analysis 17
approved colour bonded plain steel sheet down
pipe fixed to wall with and including standard down
pipe brackets (clips)at 600mm centers.
5
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
F PLASTERING
F.1 15mm thick cement & sand (1:5) plaster finished m2 468.14 450.00 210,664.80 Analysis 91
semi rough with wood float on internal and
external faces on block / concrete surfaces.
F.2 15mm thick cement & sand (1:5) plaster finished m 180.80 210.00 37,968.00 Analysis 92
semi rough with wood float on internal and
external reveals.
F.3 Smooth cement finish plastering with 20mm thick m2 37.80 557.00 21,054.60 Analysis 18
1:3 cement sand plaster to Internal surfaces of
walls up to 1.8m hight as directed.
F.4 Plinth plastering with 20mm thick 1:3 cement sand m2 12.24 557.00 6,817.68 Analysis 18
plaster finished smooth with colour cement
floating.
G PAINTING
G.1 Prepare surface and apply one coat of water m2 78.91 377.00 29,749.82 Analysis 93
proofing primer and two coats of approved type
weathershield paint to external plastered surfaces
of walls as directed.
G.2 Prepare surface and apply one coat of acralic filler m2 78.91 298.00 23,515.78 Analysis 94
and two coats of approved type emulsion paint on
internal plaster surfaces as directed.
H PAVING
FLOOR PAVING
H.1 20mm thick 1:3 cement rendering including m2 100.80 654.00 65,923.20 Analysis 19
smooth cement finish on concrete floor .
J METAL WORK
6
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
J.1 Supplying and fixing of Door Type SD1,1800 X Nr 6.00 77,046.00 462,276.00 Analysis 21
2100mm Overall Size, GI sliding Door,Automated &
manually openable,slides one Directions and
remain a gap on top. (Rate shall be included all
necessary fittings and accessories).
J.2 Supplying and fixing of Window Type W7,1800 X Nr 4.00 23,735.00 94,940.00 Analysis 89
700mm Overall Size, Steel grill window.(Rate shall
be included all necessary fittings and accessories).
J.3 Supplying and fixing of Window Type W9,3000 X Nr 4.00 64,551.00 258,204.00 Analysis 98
1300mm Overall Size, GI fixed window.(Rate shall
be included all necessary fittings and accessories).
J.4 Supplying and fixing of GI sliding gate ,type G1, Nr 1.00 128,932.00 128,932.00 Analysis 23
3000 x 1600mm Overall Size slides two directions,
& gate columns for entrance including all necessary
fittings.
J.5 Supplying and fixing of GI gate Type G3,900 X Nr 2.00 19,066.00 38,132.00 Analysis 24
1600mm Overall Size,Opens with out hinges &
fixed to chain link fence in open holding area. (Rate
is included all necessary fittings and accessories).
7
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
K PLUMBING WORKS
ACCESSORIES
K.4 Supplying and fixing of Plastic Tap Nr 1.00 294.00 294.00 Analysis 37
L ELECTRICAL WORKS
L.1 15w CFL pendent lamp with wiring Nr 1.00 5,850.00 5,850.00 Analysis 80
L.2 Access way Lights with wiring Nr 1.00 8,200.00 8,200.00 Analysis 81
M MISCELLANEOUS
M.1 Construction of Food & Water Trough size nr 2.00 13,024.00 26,048.00 Analysis 39
4500x700mm, Brick fill and Out side cement
rendered finish.
M.2 Construction of 300mm wide, 150mm deep RCC m 12.00 2,271.00 27,252.00 Analysis 41
Drain including necessary formwok and finishing
works.
8
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
M.3 Construction of 150 x 150mm Kerb as directed by m 30.00 1,167.00 35,010.00 Analysis 54
Engineer.
M.4 PVC coated G - 10 Green mesh GI Chain link fence m 33.00 9,030.00 297,990.00 Analysis 42
(1.8m hight) fixed with nut bolts including tension
wires and all other necessary accessories.
M.5 Laying 300mm Rever Sand layer in Open Area as m2 180.00 899.00 161,820.00 Analysis 45
directed by Engineer.
M.7 Construction of 600x600x1200mm size Soakage Pit nr 2.00 2,012.00 4,024.00 Analysis 46
for collect waste water for Two holding units.
M.8 Laying gravel in Access gravel area between two Item 5,100.00 Analysis 47
Shelters.
M.10 Supplying and turfing with buffalo grass sods m2 27.60 651.00 17,967.60 Analysis 96
including compacting
Rate included for Preparation of land in required
slope ,Fertilizing land with coir dust compost &
organic soil including watering as required.
M.11 Watering & maintain the turf area for three months m2 27.60 279.00 7,700.40 Analysis 97
9
Description
Times Length(m) Width(m) Height(m)
Lean conctree
Wall 40.80 0.3
Column 10 1 1
G25 concrete
for floor Concrete 12.00 6.00
for pavement 12.00 1.2
B2 2 12 0.2
1 12 0.2
B3 4 8.2 0.2
2 8.2 0.4
Block Work
Sheltered Area 1 12.00 4.740
1 12.00 3.500
2 8.40 4.740
ddt SD1 6 1.80 2.10
W7 4 1.80 0.70
W9 4 3.00 1.30
Ventilation Openings 48 0.15 0.15
reveals
SD1 6 1.8
12 2.1
W9 8 3.0
8 1.3
W7 8 1.8
8 0.7
skirting 1 36.00
brick work
Sides & middle partition 1 0.7 0.3
FRONT WALL 1 5.5 0.3
walls 2 0.7 0.3
Rendering
bottom 1 4.50 0.90
side walls 4 0.70 0.3
middle partition 2 0.70 0.3
FRONT WALL 1 5.50 0.3
Chain Link Fence
Rubble work
2 19.20 0.3 0.6
930.60 930.60 m2
10.50
5.76
4.03
20.29 20.29 m3
10.08 10.08 m3
72.00 72.00 m2
12.24
10.00 22.24 m2
72.00
14.40 86.40 m2
1.26 1.26 m3
1.44 1.44 m3
0.96
0.48
1.31
2.75 m3
1.41
0.25 1.66 m3
1.68 1.68 m3
1.84
0.08 1.76 m3
11.16 11.16 m2
1.20
0.24
14.40 15.84 m2
4.80
4.80 9.60
4.80
2.40 7.20
6.56
6.56 13.12
29.92 m2
7.50
4.50 12.00 m2
33.60 33.60 m2
12.24
1.20 11.04 m2
0.14 0.14 t
0.10 0.10 t
0.33 0.33 t
0.17 0.17 t
0.17 0.17 t
0.12 0.12 t
7.34 7.34
1.41
1.41
5.94 m3
56.88
42.00
79.632 178.51
22.68
5.04
15.6
1.08 44.4
134.11 m2
12.24 12.24 m2
75.64 75.64 m2
90.00 90.00 m2
12.00 12.00 m
7.00 7.00 m
12.24
12.24 m2
79.63
113.76
84.00 277.39
22.68
15.60
5.04 43.32
2
468.14 m
36.00
18.00 54.00
16.2 16.2
37.80 m2
430.34 m2
10.80
25.20
24.00
10.40
14.40
5.60 90.40 m
180.8 m
100.80 100.80 m2
36.00 36.00 m 15
0.21
1.65
0.42 2.28 m2
4.05 4.05 m2
4.05
0.84
0.42
1.65 6.96 m2
5.76
5.76 m3
0.00 m3
5.76 m3
6.91
6.91 m3
0.12 0.12 m3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
F PLASTERING 300,440.88
G PAINTING 53,265.60
H PAVING 76,696.00
M MISCELLANEOUS 554,356.30
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
A.2 Excavation for foundation in any material except m3 18.52 920.00 17,034.72 Analysis 2
rock requiring blasting, up to a depth of 1.5m from
existing levels
A.3 Filling under floors with approved imported earth m3 10.64 1,580.00 16,811.20 Analysis 3
in layers not exceeding 150mm including watering
and ramming up to a depth not exceeding 1.5m .
A.4 Excavation site for necessary levels in holding areas m3 1,200.00 717.00 860,400.00 Analysis 87
not exceeding 1.5m depth in any material except
rock requiring blasting and return filling.
A.5 Filling Excavated area with approved available m3 500.00 540.65 270,325.09 Analysis 88
earth in layers not exceeding 150mm including
watering and ramming up to a depth not exceeding
1.5m .
A.6 Anti-termite treatment to building area according m2 106.40 178.00 18,939.20 Analysis 4
to a approved specialist contractor's specification
and technical literature (Rate shall be included for
5 years warranty).
B CONCRETE WORK
Up to DPC level
B.1 50mm thick Grade 15 lean concrete under wall & m2 23.15 534.00 12,359.43 Analysis 5
column foundation
B.2 Grade 25 reinforced concrete in Column footing m3 1.66 17,500.00 29,039.06 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
1
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
B.3 Grade 25 reinforced concrete in plinth beams m3 2.55 17,500.00 44,661.09 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately
B.5 Grade 25 reinforced concrete in Column shaft m3 1.68 17,500.00 29,400.00 Analysis 7
including placing, leveling and vibrating.
Reinforcement and form work measured
separately.
B.6 225x150mm Copping Beam in Grade 25 concrete m3 1.55 17,500.00 27,050.63 Analysis 7
including necessary reinforcement and form work
finishes measured separately.
-
Form work
Rate of form work is included for all necessary
boarding, supports, erecting, framing, cutting
angles, cleaning, wetting and any surface treatment
before and after placing of concrete.
Up to DPC level
B.7 for Column footing m2 12.00 1,099.00 13,188.00 Analysis 8
B.8 for Plinth Beam m2 16.32 1,099.00 17,935.68 Analysis 8
-
DPC level to Roof level
B.9 for Copping Beam m2 13.74 1,099.00 15,100.26 Analysis 8
2
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
Reinforcement
Up to DPC level
B.11 for Column footing t 0.17 197,000.00 32,689.69 Analysis 9
-
DPC level to Roof level
Up to DPC level
Random rubble masonry
C.1 Random rubble masonry in cement and sand( 1:5 ) m3 9.11 10,471.00 95,346.31 Analysis 10
mortar in foundations.
3
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
4
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
D.2 Horizontal damp proof membrane DPM girth > m2 80.08 122.00 9,769.76 Analysis 13
300mm; consisting of gauge 1000 polythene
membrane laid on compacted earth filling . The
rate shall included for laps & wastage
E.1 Supplying & fixing of Zn/Al roofing sheets on steel m2 106.40 4,633.00 492,951.20 Analysis 14
frame work for Roof as per detail drawing (rate
including with Steel frame work .)
E.2 Supplying & fixing of 6000 x 1200mm Reinforced m3 1.52 50,014.00 76,021.28 Analysis 16
Concrete Roof Canopy in 100mm thk as per detail
drawing
E.3 Supply & fixing of Zn Aluminum square gutter m 15.20 1,897.00 28,834.40 Analysis 15
approved by Engineer with all type of necessary
fittings.
E.4 Straight 100x100mm square type Zn/Al coated m 7.00 927.00 6,489.00 Analysis 17
approved colour bonded plain steel sheet down
pipe fixed to wall with and including standard down
pipe brackets (clips)at 600mm centers.
5
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
F PLASTERING
F.1 15mm thick cement & sand (1:5) plaster finished m2 496.00 450.00 223,200.00 Analysis 91
semi rough with wood float on internal and
external faces on block / concrete surfaces.
F.2 15mm thick cement & sand (1:5) plaster finished m 214.40 210.00 45,024.00 Analysis 92
semi rough with wood float on internal and
external reveals.
F.3 Smooth cement finish plastering with 20mm thick m2 40.32 557.00 22,458.24 Analysis 18
1:3 cement sand plaster to Internal surfaces of
walls up to 1.8m hight as directed.
F.4 Plinth plastering with 20mm thick 1:3 cement sand m2 17.52 557.00 9,758.64 Analysis 18
plaster finished smooth with colour cement
floating.
G PAINTING
G.1 Prepare surface and apply one coat of water m2 78.91 377.00 29,749.82 Analysis 93
proofing primer and two coats of approved type
weathershield paint to external plastered surfaces
of walls as directed.
G.2 Prepare surface and apply one coat of acralic filler m2 78.91 298.00 23,515.78 Analysis 94
and two coats of approved type emulsion paint on
internal plaster surfaces as directed.
H PAVING
FLOOR PAVING
H.1 20mm thick 1:3 cement rendering including m2 106.40 654.00 69,585.60 Analysis 19
smooth cement finish on concrete floor .
J METAL WORK
6
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
J.1 Supplying and fixing of Door Type SD1,1800 X Nr 10.00 77,046.00 770,460.00 Analysis 21
2100mm Overall Size, GI sliding Door,Automated &
manually openable,slides one Directions and
remain a gap on top. (Rate shall be included all
necessary fittings and accessories).
J.2 Supplying and fixing of Window Type W7,1800 X Nr 6.00 23,735.00 142,410.00 Analysis 89
700mm Overall Size, Steel grill window.(Rate shall
be included all necessary fittings and accessories).
J.3 Supplying and fixing of Window Type W10,2500 X Nr 6.00 54,909.00 329,454.00 Analysis 99
1300mm Overall Size, GI fixed window.(Rate shall
be included all necessary fittings and accessories).
J.4 Supplying and fixing of GI sliding gate ,type G1, Nr 1.00 128,932.00 128,932.00 Analysis 23
3000 x 1600mm Overall Size slides two directions,
& gate columns for entrance including all necessary
fittings.
J.5 Supplying and fixing of GI gate Type G3,900 X Nr 2.00 19,066.00 38,132.00 Analysis 24
1600mm Overall Size,Opens with out hinges &
fixed to chain link fence in open holding area. (Rate
is included all necessary fittings and accessories).
7
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
K PLUMBING WORKS
ACCESSORIES
K.4 Supplying and fixing of Plastic Tap Nr 1.00 294.00 294.00 Analysis 37
L ELECTRICAL WORKS
L.1 15w CFL pendent lamp with wiring Nr 1.00 5,850.00 5,850.00 Analysis 80
L.2 Access way Lights with wiring Nr 1.00 8,200.00 8,200.00 Analysis 81
M MISCELLANEOUS
M.1 Construction of 300mm wide, 150mm deep RCC m 15.20 2,271.00 34,519.20 Analysis 41
Drain including necessary formwok and finishing
works.
M.2 Construction of 150 x 150mm Kerb as directed by m 44.30 1,167.00 51,698.10 Analysis 54
Engineer.
8
ASIAN ZONE-SAFARI PARK-RIDIYAGAMA
BILL OF QUANTITIES
Note: Power Supply and Water Supply for this construction must be provided by the Client.
Hence cost of the above is not included for this Estimate
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY REMARKS
Rs. Cts. Rs. Cts.
M.3 PVC coated G - 10 Green mesh GI Chain link fence m 22.70 9,030.00 204,981.00 Analysis 42
(1.8m hight) fixed with nut bolts including tension
wires and all other necessary accessories.
M.4 Laying 300mm Rever Sand layer in Open Area as m2 228.00 899.00 204,972.00 Analysis 45
directed by Engineer.
M.6 Construction of 600x600x1200mm size Soakage Pit nr 2.00 2,012.00 4,024.00 Analysis 46
for collect waste water for Two holding units.
M.7 Laying gravel in Access gravel area between two Item 6,563.00 Analysis 47
Shelters.
M.9 Supplying and turfing with buffalo grass sods m2 24.30 651.00 15,819.30 Analysis 96
including compacting
M.10 Rate included for Preparation of land in required
slope ,Fertilizing land with coir dust compost &
organic soil including watering as required.
M.11 Watering & maintain the turf area for three m2 24.30 279.00 6,779.70 Analysis 97
months.
9
Description
Times Length(m) Width(m) Height(m)
Lean conctree
Wall 58.40 0.3
Column 10 0.75 0.75
G25 concrete
for floor Concrete 15.20 5.00
for pavement 15.20 1
Block Work
Sheltered Area 1 15.20 4.650
1 15.20 3.500
2 7.00 4.650
ddt SD1 10 1.80 2.10
W7 6 1.80 0.70
W10 6 3.00 1.30
Ventilation Openings
reveals
SD1 6 1.8
12 2.1
W10 12 2.5
12 1.3
W7 8 1.8
16 0.7
floor rendering 1 15.20 7.00
skirting 1 40.40
brick work
Sides & middle partition 1 0.7 0.3
FRONT WALL 1 5.5 0.3
walls 2 0.7 0.3
Rendering
bottom 1 4.50 0.90
side walls 4 0.70 0.3
middle partition 2 0.70 0.3
FRONT WALL 1 5.50 0.3
Rubble work
2 22.30 0.3 0.6
1040.76 1040.76 m2
4.50
7.30
6.72
18.52 18.52 m3
10.64 10.64 m3
106.40 106.40 m2
17.52
5.63 23.15 m2
76.00
15.20 91.20 m2
1.55 1.55 m3
1.52 1.52 m3
1.41
0.25 1.66 m3
1.42 1.42 m3
2.63
0.08 2.55 m3
13.74 13.74 m2
1.52
0.20
15.20 16.92 m2
7.50
4.50 12.00 m2
25.20 25.20 m2
17.52
1.20 16.32 m2
0.20 0.20 t
0.12 0.12 t
0.17 0.17 t
0.14 0.14 t
0.12 0.12 t
10.51 10.51
1.41
1.41
9.11 m3
70.68
53.20
65.1 188.98
37.8
7.56
23.4
68.76
120.22 m2
17.52 17.52 m2
80.08 80.08 m2
106.40 106.40 m2
15.20 15.20 m
7.00 7.00 m
17.52
17.52 m2
65.10
141.36
106.40 312.86
37.80
19.50
7.56 64.86
2
496.00 m
54.72
18.00 72.72
32.4 32.4
40.32 m2
455.68 m2
10.80
25.20
30.00
15.60
14.40
11.20 107.20 m
214.4 m
106.40 106.40 m2
40.40 40.40 m 15
0.21
1.65
0.42 2.28 m2
4.05 4.05 m2
4.05
0.84
0.42
1.65 6.96 m2
6.69
6.69 m3
0.00 m3
6.69 m3
8.03
8.03 m3
0.16 0.16 m3
7.3
MATERIALS
Rates for
No. Item Description Qty Sooriyawewa
(Rs Cts)
1 Cement Supiri 50kg-1bag 817.68
Lankem Mr.Madugoda
071- 1266266 / 071-4606055
Ceylon Steel
-Mr.yapa
071- 1266266 / 071-4606055
Ceylon Steel
-Mr.yapa
Sri Sun Steel 077-3017269- Mr.Jayachandran
hewamannage 718182753
UKG Hardware
Mr.Janaka 077-6417082
RN -Mr. Sampath -
Informax / RN Constructions
077-3487036
Ashai / Link / Decone
Ginasena / Solex
NT
Rate (LKR)
ROOFING SHEETS
Asbestos roofing sheets 12' x3' 6" Rino
Asbestos roofing sheets 10' x3' 6" Rino
Asbestos roofing sheets 8' x3' 6" Rino
Asbestos roofing sheets 6' x3' 6" Rino
Plywood sheet 12mm thk 8"x4"
Plywood sheet 12mm thk 8"x4"
Plywood sheet 15mmthk 8"x4"
Plywood sheet 18mmthk 8"x4"
Plywood sheet 6mmthk 8"x4"
PLYWOOD DOORS
3' X 7' DOOR
3' X 6'9" DOOR
2 1/2' X 7' DOOR
2 1/2' X 6'9" DOOR
GLASS
2mm thick plain glass
3mm thick plain glass Galle Picture palace
4mm thick plain glass
5mm thick plain glass Galle Picture palace
6mm thick plain glass
STEEL
FOR TRUSSES
1 Rectangular hollow section 100X50X3 Janatha Steel
2 Rectangular hollow section 50X50X3 Janatha Steel
3
Lysaght C purlins 150x65x20 Colonial
4 C channel 75X150 Colonial
5 C channel 50X100 Colonial
6 Flat Iron bars 5mm X 20mm Janatha Steel
7 Mild steel plates 10mm Janatha Steel
8 Mild steel plates 6mm Janatha Steel
Mild steel plates 3mm Janatha Steel
9 20mm bolts 60mm length Janatha Steel
10 16mm bolts 60mm length Janatha Steel
11 12nn bolts 60mm length Janatha Steel
12 rag bolts 16mm dia. 400long Janatha Steel
13 steel beams
14 Angle Iron 25X25X5 Janatha Steel
15 Angle Iron 30X30X5 Janatha Steel
16 Angle Iron 40X40X5 Janatha Steel
17 Angle Iron 50X50X6 Janatha Steel
18 Angle Iron 60X60X6 Janatha Steel
19 Angle Iron 65X65X6 Janatha Steel
20 GI Pipes 1 1/2" dia NIW
21 GI Pipes 1" dia NIW
22 PVC Coated wire mesh 3 1/2" high NIW
23 PVC Coated wire mesh 5" high NIW
24 PVC Coated wire mesh 6' 11" high NIW
GALVERNISING
Galvernising steel girders Lanka transformers
STEEL GIRDERS
1 Steel girders 457X152X52 Colonoal
TIMBER
1 Coconut
Attonia
Class 1 timber
Ginisapu 9"x1"
Mango
TEAK
1 Teak 3"x4"
2 Teak 1"x4"
3 Teak 1"x6"
4 Teak 1"x12"
5 Teak 3/4"x 3"
THULANG
1 Thulang 2"x4"
2 Thulang 3"x4"
3 Thulang 1 1/8" timber planks
4 Thulang 1"X 6" timber planks
5 Thulang 1"x2"
6 Thulang 7"x2"
7 Thulang 1"x4"
MANGO /KOTTAMBA /
1 Kottamba 2"x2"
2 Kottamba 2"x4"
3 Kottamba
4 Kottamba 1" timber planks
IRON MONGERY
1 Casement Stays 10" long Darmarathna
2 Casement Stays 12" long Darmarathna
3 Hinges 4"x 2 1/2" Darmarathna
4 Hinges 5"x 2 1/2" Darmarathna
5 Hinges 5"x 3" Darmarathna
6 Hinges 3"x 2" Darmarathna
7 Hinges 3"x 2 1/2" Darmarathna
8 Hinges 4"x 2" Darmarathna
9 Hinges 4"x 2 1/2" Darmarathna
10 Rings Darmarathna
11 Barrel Bolts 4" Darmarathna
12 Barrel Bolts 6" Darmarathna
13 Barrel Bolts 9" Darmarathna
14 Casement Fastners Darmarathna
PVC FITTINGS
1 Ball Valve 50mm dia Anton
2 Ball Valve 110mm dia Anton
3 Foot Valve 50mm dia Anton
4 Socket 75mm Anton
5 Socket 110mm Anton
6 Pipes dia 20mm Nominal 20mm dia pipes Anton
7 Pipes dia 25mm Nominal 25mm dia pipes Anton
8 Pipes dia 32mm Nominal 32mm dia pipes Anton
9 Pipes dia 40mm Nominal 40mm dia pipes Anton
SANITORY FITTINGS
1 bottle trap 1 1/2" Cromium plated bottle trap
2 waste plug chain 1 1/2" waste plug chain
Chromoum plated brass to suit
3 Angle Valve
20mm dia pipes(German)
4 angle valve 1/2" angle valve
5 Bib Tap Chromoum plated brass (Germany)
1 1/4" dia cromium plated bottle
6 bottle trap
trap
low level water cistern white
16 cistern
vitreous China (9l)
PRECAST ITEMS
1 Garden Chair With out finishes
ELECTRICAL ITEMS
Isolater 32A, 2P Isolater Moeller
Isolater 63A, 2P, Isolater Moeller
RCCB 40A, 2P RCCB Moeller
MCB 6A, SP, MCB Moeller
MCB 6A-16A, SP, MCB Moeller
MCD 20A, SP, MCD Moeller
FITTINGS
Globe type decorative wall lamp
Wall lamp
100W
TS
1No. 1,260.87 1-Nov-07 1st half 2008
1No. 1,030.43 1-Nov-07 1st half 2008
1No. 869.57 1-Nov-07 1st half 2008
1No. 608.70 1-Nov-07 1st half 2008
1st half 2008
1st half 2008
1st half 2008
1st half 2008
1No. 1,750.00 9-Sep-11 Local 1st half 2008
1No. 2,250.00 17-Dec-12 Maleyshiyan 1st half 2008
1No. 3,035.71 17-Dec-12 Maleyshiyan 1st half 2008
1No. 3,122.96 23-Sep-10 gintota
1No. 1,307.07 23-Sep-10 gintota
WOOD DOORS
1No.
1No.
1No.
1No.
45.00
80.00
S
5.8m 4,600.00 5-May-05 1st half 2008
5.8m 3,350.00 6-May-05 1st half 2008
1st half 2008
5.8m 8,695.00 1st half 2008
5.8m 3,100.00 7-May-05 1st half 2008
5.8m 2,200.00 8-May-05 1st half 2008
5.7m 300.00 8-May-05 1st half 2008
8' X4' 22,500.00 9-May-05 1st half 2008
8' X4' 13,500.00 10-Jun-05 1st half 2008
8' X4' 6,500.00 10-Jun-05 1st half 2008
1No. 75.00 10-May-05 1st half 2008
1No. 45.00 10-May-05 1st half 2008
1No. 18.00 10-May-05 1st half 2008
1No. 275.00 10-May-05 1st half 2008
1kg 100.00 11-May-05 1st half 2008
5.8m 900.00 12-Jun-05 1st half 2008
5.8m 1,000.00 13-Jun-05 1st half 2008
5.8m 1,500.00 14-Jun-05 1st half 2008
5.8m 2,200.00 15-Jun-05 1st half 2008
5.8m 2,300.00 16-Jun-05 1st half 2008
5.8m 2,900.00 17-Jun-05 1st half 2008
18ft 1,850.00 23-Mar-06 1st half 2008
18ft 1,175.00 23-Mar-06 1st half 2008
50ft 4,110.00 23-Mar-06 1st half 2008
50ft 6,150.00 23-Mar-06 1st half 2008
50ft 8,630.00 23-Mar-06 1st half 2008
NG
1kg
ERS
12m 55,000.00 1-Apr-06 1st half 2008
CA treatement)
1lnft 170.50 5-May-05 1st half 2008
1lnft 247.50 5-May-05 1st half 2008
1lnft 170.50 6-Nov-05 1st half 2008
1lnft 330.00 1st half 2008
1lnft 148.50 8-May-05 1st half 2008
1lnft 110.00 7-Nov-05 1st half 2008
1lnft 82.50 10-May-05 1st half 2008
1lnft 71.50 5-Apr-05 1st half 2008
1lnft 440.00 8-Nov-05 1st half 2008
1lnft 143.00 9-Nov-05 1st half 2008
1lnft 236.50 10-Nov-05 1st half 2008
1lnft 264.00 10-Nov-05 1st half 2008
1lnft 385.00 10-May-05 1st half 2008
1lnft 46.20 10-May-05 1st half 2008
1lnft 24.20 10-May-05 1st half 2008
GO /KOTTAMBA /ALBESIYA
1lnft 12.00 8-May-08
1lnft 30.00 8-May-08
1lnft
1lnft 60.00 8-May-08
RY
nr 110 29-Apr-06 1st half 2008
nr 180 29-Apr-06 1st half 2008
nr 145 29-Apr-06 1st half 2008
nr 200 29-Apr-06 1st half 2008
nr 210 29-Apr-06 1st half 2008
nr 55 29-Apr-06 1st half 2008
nr 65 29-Apr-06 1st half 2008
nr 75 29-Apr-06 1st half 2008
nr 100 29-Apr-06 1st half 2008
nr 45 29-Apr-06 1st half 2008
nr 130.00 29-Apr-06 1st half 2008
nr 150.00 29-Apr-06 1st half 2008
nr 200.00 29-Apr-06 1st half 2008
nr 110.00 29-Apr-06 1st half 2008
FITTINGS
1No. 228 10-Feb-05 1st half 2008
1No. 1945 11-Feb-05 1st half 2008
1No. 296 12-Feb-05 1st half 2008
1No. 52 13-Feb-05 1st half 2008
1No. 145 14-Feb-05 1st half 2008
4m 171.5625 24-Aug-05 1st half 2008
4m 369.705357142857 24-Aug-05 1st half 2008
4m 603.276785714286 24-Aug-05 1st half 2008
4m 813.892857142857 24-Aug-05 1st half 2008
s & Windows
ft2 675 12-Jun-06 1st half 2008
RY FITTINGS
1No. 875 8-Jun-05 1st half 2008
1No. 275 23-Jun-05 1st half 2008
1No. 790 15-May-05 1st half 2008
1No. 350 4-Jun-05 1st half 2008
1No. 660 11-May-05 1st half 2008
MS
1No. 2500 16-May-05 1st half 2008
1st half 2008
1st half 2008
1st half 2008
1st half 2008
EMS
1No. 875.00 16-Jun-05 1st half 2008
1No. 1,275.00 17-Jun-05 1st half 2008
1No. 2,375.00 18-Jun-05 1st half 2008
1No. 235.00 19-Jun-05 1st half 2008
1No. 235.00 20-Jun-05 1st half 2008
1No. 235.00 21-Jun-05 1st half 2008
20,000.00
878.40
1,621.60 390
12,972.80
16,865.00
750.00
73.20 9.1
676.80 8,580.00
879.84 150.00
880.00 173.00
7,040.00 95
990.6
292.80 1105
707.20
7,354.88
7,355.00
757.20
6,057.60
7,875.00
109.80
390.20
507.26
4,058.00
6.25
6.25
18.8
12.5
8,232.00
5,775.00
AFRICAN ZONE-SAFARI PARK-RIDIYAGAMA
KEEPERS AREA
BILL OF QUANTITIES
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
F PLASTERING 100,330.68
G PAINTING 106,370.00
H PAVING 127,465.65
M MISCELLANEOUS #REF!
GRAVEL ROAD
BILL OF QUANTITIES
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
C TURFING 2,268,420.00
A Construction of Gravel
Road and Side Drain
2,859,878.00
Total Carried to summary
A.2 Side Drains
A.2.1 Cutting New Side Drains In m3 476.00 940.00 447,440.00
Unclassified Soil
853,340.00
Total Carried to summary
A.3 Turfing with Suitable Grass
Sods
2,268,420.00
Total Carried to summary
AFRICAN ZONE-SAFARI PARK-RIDIYAGAMA
ANIMAL HOLDING AREA - CONSTRUCTION OF EXTERNAL DRAINAGE
SYSTEM
BILL OF QUANTITIES
SUMMARY
AMOUNT
ITEM NO DESCRIPTION
Rs. Cts.
1,650.00 1,650.00
432.00
1,215.00
360.00
2,520.00
600.00
PROPOSED SAFARI PARK - RIDIYAGAMA
ASIAN ZONE