ANALYSIS OF RATE FOR THE ITEM

Providing and fixing of False ceiling consisting of lamenated Gypsum Board


(one side laminated)of size 600mm x 600 mmx 9-10 mm over ' aluminium
Tee's 1"x 1"size at 2'-0"x2-0"center to center longituidlnally and
transversally &alminium angle of size 1" x 1" at cornes/ends,including all
accessries such as steel hanging wire, hooks, screws,nails, rowel plugs,
Cross Joints etc. complete in all respect,and as approved by the Engineer
Incharge.
Detail of Cost=100 Sft

Unit = P.Sft

Sr. Item Qty Unit Rate Amount


A METERIAL :
P/O Gypsum Board false ceiling best
i) quality i/c wastage.

10 x 10 100 Sft P Sft @ 50.00 Rs: 5000/-


Cost of G.I Wire 20-SWG for hanging
ii) false ceiling.
(L.S) Rs: 50/-
iii) Cost of Rawal Plugs. (L.S) Rs: 50/-
iv) Cost of screws / Nail etc. (L.S) Rs: 50/-
v) Cost of fitting Meterial (L.S) Rs: 50/-
vi) Cost of aluminum Tee / Angle.
2x5x10 100 Rft P Sft @ 7.00 Rs: 700/-
B LABOUR CHARGES :
1 Labour Charges for fixing false
ceiling i/c drilling, fastening of G.I
Wires leveling of false ceiling.
100 Sft P Sft @ 8.00 Rs: 800/-

Total Rs: 6700/-


Add 20% Contractor's Profit & Over
head charges on Rs. Rs: 1340/-
Total: = Rs: 8040/-

Unit Rate P Sft = 8040 / 100 80.40 P Sft

Say 80 /- P Sft

CERTIFICATE
i) Certified that input rate of material and labour for item at Sr. No. and labour rate
at Sr. No. Are as per input rates displayed on Website of Finance Department for
the MRS, 2nd BI-ANNUAL-2017 (1st July-2017 to 31st December-2017) DISTRICT
LAYYAH
ii) Certified that rates for items at serial No. A1, C Are not available on the Website
of Finance Department for the MRS, 2nd BI-ANNUAL-2017 (1st July-2017 to 31st
December-2017) DISTRICT LAYYAH and as such the rate of Rs: 80/- has been
applied after ascertaining it from the market

Sub Engineer Sub Divisional Officer Executive Engineer


Buildings Sub Division Buildings Division
Layyah Layyah
ANALYSIS OF RATE FOR THE ITEM "PROVIDING AND LAYING FALSE CEILING MADE OF
PLASTER OF PARIS I/C COST OF WIRE,NAIL,SCREW ETC FOR HANGING THE PLATES
COMPLETE IN ALL RESPECT AS APPROVED BY THE ENGINEER INCHARGE.

Take 100 Sft for analysis purpose.


UNIT OF RATE = P-SFT
Sr. No: DESCRIPTION OF ITEMS QUANTITY UNIT RATE AMOUNT
A) MATERIAL.
False ceiling made of plaster of
Paris i/c cost of wire for
hanging the plates etc.
complete as directed and
approved by the Engineer In
1 charge. 100 Sft

100 Sft P-Sft 34.00 3400.00

TOTAL - A 3400.00
B) LABOUR
100 Sft P-Sft 3.00 300.00

CARRIAGE CHARGES Lum Sum 100

10% SUNDRIES 0.5 30.00


TOTAL - B 430.00
G- TOTAL (A+B) 3830.00

ADD 20% CONTRACROR'S PROFIT + OVER HEAD CHRAGES 766


OVER ALL TOTAL 4596.00
4596.00
RATE PER Sft = 46.0
100
Say Rs:= 46/- Sft

CERTIFICATE

i) Certified that input rate of material and labour for item at Sr. No. and labour
rate at Sr. No. Are as per input rates displayed on Website of Finance Department
for the 1st BI-ANNUAL-2017(1ST January TO 30th June) District Layyah as such
the rate of Rs: 46/- has been applied after ascertaining it from the markets.