Analysis of False Ceiling
Analysis of False Ceiling
Analysis of False Ceiling
Unit = P.Sft
Say 80 /- P Sft
CERTIFICATE
i) Certified that input rate of material and labour for item at Sr. No. and labour rate
at Sr. No. Are as per input rates displayed on Website of Finance Department for
the MRS, 2nd BI-ANNUAL-2017 (1st July-2017 to 31st December-2017) DISTRICT
LAYYAH
ii) Certified that rates for items at serial No. A1, C Are not available on the Website
of Finance Department for the MRS, 2nd BI-ANNUAL-2017 (1st July-2017 to 31st
December-2017) DISTRICT LAYYAH and as such the rate of Rs: 80/- has been
applied after ascertaining it from the market
TOTAL - A 3400.00
B) LABOUR
100 Sft P-Sft 3.00 300.00
CERTIFICATE
i) Certified that input rate of material and labour for item at Sr. No. and labour
rate at Sr. No. Are as per input rates displayed on Website of Finance Department
for the 1st BI-ANNUAL-2017(1ST January TO 30th June) District Layyah as such
the rate of Rs: 46/- has been applied after ascertaining it from the markets.
Layyah D.G.Khan