CHP 4:construction of Roads: By: R.V. K
CHP 4:construction of Roads: By: R.V. K
CHP 4:construction of Roads: By: R.V. K
ROADS
BY: R.V. K
TYPES OF PAVEMENTS
•Un Surfaced
–Earthen roads
–Gravel roads
•Surfaced
–Bituminous Road
–Cement Concrete Road
•Un Conventional
–Block Pavement
Further classification
Flexible Pavements
– Earthen Roads
–Gravel Roads
–Bituminous Roads
Rigid Pavements
–Reinforced Concrete
– Plane Concrete Roads
FLEXIBLE PAVEMENT RIGID PAVEMENT
Types of Pavements
Wheel Load Distribution
Flexible Rigid
Properties Flexible Rigid
Design Empirical method Designed and analyzed by using the elastic
Principle Based on load distribution theory
characteristics of the
components
Material Granular material Made of Cement Concrete either plan,
reinforced or prestressed concrete
Flexural Low or negligible flexible Associated with rigidity or flexural strength
Strength strength or slab action so the load is distributed over
a wide area of subgrade soil.
Normal Elastic deformation Acts as beam or cantilever
Loading
Excessive Local depression Causes Cracks
Loading
Stress Transmits vertical and Tensile Stress and Temperature Increases
compressive stresses to the
lower layers
• Cement
• Cement concrete (plain, reinforced,
prestressed)
• Stabilized materials
• Recycled materials
Tests
• Tests on soil-CBR test
• Tests on agg- Abrasion,Impact,Shape test
• Tests on bitumen-Penetration,Softening,flash
n fire point etc
EARTHEN ROADS
General Terms used in Earthwork
of Roads
1. Borrow Pits
2. Balancing Earthwork
3. Lead & Lift
4. Spoil Bank
Borrow Pits
• Small pits dug parallel to the road alignment
on both sides of the road formation to draw
extra earth required to fill in embankment.
Spoil Bank
• Extra earth excavated and to be dumped on
the road sides in road in cutting.
• Dumped in regular shape for future use.
Balancing Earthwork
• While constructing road, it is desirable for a
segment of road, that the quantity of earthwork
in cutting and embankment should be nearly
equal if the soil available is good for the use.
• If possible, keeping in mind the limiting values of
gradients and curves, the alignment is so fixed to
have the equal quantity of earthwork in cutting
and banking.
• This is known as balancing earthwork.
Lead & Lift
• Lead: Horizontal distance travelled by the
earth to be moved for banking or dumping.
• Lift : Vertical distance travelled by the
earthwork after excavating.
Construction Procedure for Earthen Road
• Preparation of Sub-Grade: Arranging sub-grade in
proper gradient & camber.
• The sub-grade is rolled & watered to have OMC &
compacted to MDD.
• Over it, a layer of soil 10cm thick is sprayed,
rolled, & finished to have required camber &
gradient.
• 4-5 days curing.
• Opening to traffic.
• Watering for 10 days after opening to traffic.
2 63-40 83 100
63 90-100
50 30-70
40 0-15
20 0-5
3 50-20 63 100
50 95-100
40 35-70
20 0-10
IRC Recommendations for Grading of
Screenings
Classification Size of Screenings Sieve size % by weight
Grading mm mm passing the sieve
12.5 100
A 12.5 10.0 90-100
4.75 10-30
0.15 0-8
10.0 100
B 10.0 4.75 85-100
0.15 10-30
Construction Procedure of WBM
Roads
• 1. Preparation of Sub Grade
• 2. Preparation of Base Course
• 3. Intermediate Layer
• 4. Wearing Surface
• 5. Shoulders
Shoulder Wearing Course Shoulder
Intermediate Course
Base Course
Sub Grade
Precautions in Rolling WBM Roads
• Roller to be used- 8-10 Tonnes
• Rolling should be done from edges to the centre
• The successive rolling strips should be overlapped
• Length of each rolling should be <=200m.
• Water should be sprinkled and not poured by
buckets
• The rolling should be done for 80 passes or until
the aggregates are broken.
RIGID PAVEMENTS :
• --soil subgrade.
• --drainage layer.
• --sub-base course generally constructed
using lean cement concrete or ‘dry lean
concrete’
• --separation membrane laid on top of base
course.
• --CC pavement slabs Using ‘ paving quality
concrete’ (PQC)
• --construction of different types of joints in
CC pavements.
• DIFFERENT TYPES OF CC PAVEMENTS:
Jointed Plain Concrete Pavement (JPCP)
• – does not use any reinforcing steel
Mild steel sections and blocks for making joint grooves for finishing
purpose
• METHODS OF CONSTRUCTION OF CC PAVEMENTS :
• The compressed
filler board may
partly recover and
joint sealer moves
down.
JOINT SEALER
Top portion of gap at expansion joint above the joint filler is sealed to
prevent entry of water and grit into pavement through expansion joint
Hence, for effective sealing of joint for a long period, it is essential that
sealing compounds posses these properties :
1. Adhesion to cement concrete edges.
2. Extensibility without fracture.
3. Resistance to ingress of grit.
4. Durability.