Drill Stem Testing, DST
Drill Stem Testing, DST
DST Tools
Type of DST tolls depends on the testing well, cased or open hole.
1- Surface pressure control equipments
It is a collection of valves, flanges and nipples set on well head, used to control on
flow rate and internal closed or flowing pressure.
2- Drill pipe
Drill pipe used as connection between surface equipment and test equipment.
3- Reverse circulation sub
This sub valve used to circulation the drill mud (reveres circulation, from annulus
to inside drill pipe), for killing the well and control on well after the test was
finish or in emergency cases, and the valve used to empty the drill test stem from
fluids when pull out of hole. During the tools run in hole this valve remain closed
and still closed until the test was finished, after that its open to control on well.
4- Drill collar
Used to set the packer and open or close tester valve by its weight.
5- Reverser circulation ports
Also, used to reveres circulation of drill mud after the test was complete.
6- Closed in pressure valve
The valve used to close the drill stem after the test was finish.
7- Flow choke
The flow choke with a specific diameter (5/8 inch) used to fluid flow through it
and to calculations purpose.
8- Tester valve
This valve used to control on fluid movement (flow or close), the valve is closed
by put the drill stem under tension, or open it by slack off the stem. (Some times
the valve called multi flow evaluator MFE).
9- Upper pressure recorder
This instrument includes pressure record that consists from spiral tube that moves
according to amount of supply pressure, the tube shifting is transit through a small
needle to a black chart (previously, set on it lines with a specific pressure). All
operations that occur during the test will recorded on the black chart as pressure
versus time profile.
10- Hydraulic jar
It is a motional nipple, used to release the test stem in stuck case.
11- Safety joint
This joint is useful in case of stem stuck. When stem does not release, could back
the part of stem by open it from the safety joint.
12- Packer
It is the important part of the test stem; consist from steel and rubber part. After
set the packer by supply a certain weight, the rubber part will isolate the upper of
well from the formation (remove the hydrostatic pressure from the formation).
After the test on formation was completed, then the packer return to its normal
situation by removes the supplied weight, and the formation will be under control
by the hydrostatic mud column pressure.
13- Perforated pipe
Through this pipe the oil and gas enter inside the test stem.
14- Temperature recorder
This recorder used to record tested formation temperature.
15- Bottom pressure recorder
Its second pressure instrument also used to record flowing and closed bottom-hole
pressure.
16- Tail pipe anchor
Tail pipe anchor is the last part of test stem used for support purpose.