Rate Analysis
Rate Analysis
Rate Analysis
1 Cement No 300
7 Size stone No 16
8 Boulders Cft 10
9 Brick No 4.2
Labour
16 Foreman each 400
18 MC each 200
19 FC each 150
20 Bhisti each 200
Material
27 12mm thick ply Sft 40
29 MS Bolts Kgs 70
MS sheet Kgs 80
MS angle Kgs 70
31 Lime paste Kg 4
35 TW Veneer Sft 30
43 Putty Kg 20
52 Reinforcement KG 46
54 Coal Kg 5
55 Bonding material Kg 50
Total 396.48
Per Sqm 3.9648
Per Sft 0.37
B. EXCAVATION
Total 657.85
Per Sqm 6.5785
Per Sft 0.61
Assume 10 Cum
Labour
1 Mate Each 0.15 400.00 60.00
Total 1422.00
Per Cum 142.2
Per Cft 4.03
Assume 10 Cum
Labour
1 Mate Each 0.15 400.00 60.00
Total 1360
Add for tools and tackles @ 2% 27.20
Add for Saundries & contengencies @ 3% 40.80
Add 15% Contractor profit & Overheads 204.00
Total 1632.00
Per Cum 163.2
Per Cft 4.62
RATE ANALYSIS OF PLAIN CEMENT CONCRETE WORKS
Supplying and laying Plain cement Concrete works using 40mm and below size
Grade of
1 Concrete 1':4:8
Description Unit Qty Rate Amount
Assume for 1 cum
Material
1 cement Bag 3.40 300.00 1020.00
2 Sand Cum 0.50 1765.50 882.75
3 40mm coarse aggregate Cum 1.0046 706.20 709.45
Total
Labour
1Foreman Each 0.05 400.00 20.00
2Mason Each 0.15 350.00 52.50
3Male assistant Each 0.75 200.00 150.00
4Female assistant Each 0.80 150.00 120.00
Total
Tools & Equipments
1 Mixer machine Day 0.04 900 36
(a) Material
1.Cement Bag 17.56 300.00 5268.00
2. River Sand Cft 43.42 50.00 2171.00
3. 20mm Jelly Cft 85.00 24.00 2040.00
(b) Labour
1. For Mixing and Placing Cft 100.00 8.00 800.00
( c) Misc.
1. Add For Water Charges @ 1.5%
2. Add For Wastages @ 3%
3. Add For Contractor's Profit and Overheads
@ 15%
Total
Rate Per Cft
Rate Per Cum
(b) Labour
1. For Mixing and Placing Cft 100.00 9.00 900.00
( c) Misc.
1. Add For Water Charges @ 1.5%
2. Add For Wastages @ 3%
3. Add For Contractor's Profit and Overheads
Total
Rate Per Cft
Rate Per Cum
4 PCC 1:5:10
Unit - 100 Cft
(a) Material
1. Cement Bag 7.14 300.00 2142.00
2. River Sand Cft 47.57 50.00 2378.50
3. 20mm Jelly Cft 90.00 24.00 2160.00
(b) Labour
1. For Mixing and Placing Cft 100.00 6.00 600.00
( c) Misc.
1. Add For Water Charges @ 1.5%
2. Add For Wastages @ 3%
3. Add For Contractor's Profit and Overheads
Total
Rate Per Cft
Rate Per Cum
5 Supplying and laying Plain cement Concrete works using 40mm and below size
Grade of
concrete 1;3:6
Material
1 Cement Bag 4.2 300 1260.00
2 Sand Cum 0.485 1765.5 856.27
3 40mm coarse aggregate Cum 0.9702 706.2 685.16
Labour
1 Foreman Each 0.08 400 32.00
2 Mason Each 0.15 350 52.50
3 Male assistant Each 0.8 200 160.00
4 Female assistant Each 1 150 150.00
Total
Rate Per Cft
5 Supplying and laying Plain cement Concrete works using 20mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete 1;3:6
Assume for 1 cum
Material
1 Cement Bag 4.2 300 1260.00
2 Sand Cum 0.485 1765.5 856.27
3 20mm coarse aggregate Cum 0.9702 847.44 822.19
Labour
1 Foreman Each 0.085 400 34.00
2 Mason Each 0.16 350 56.00
3 Male assistant Each 0.8 200 160.00
4 Female assistant Each 1 150 150.00
Total
Rate Per Cft
6 Supplying and laying Plain cement Concrete works using 20mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete 1;2:4
Material
1 Cement Bag 6.02 300 1806.00
2 Sand Cum 0.4704 1765.5 830.49
3 20mm coarse aggregate Cum 0.9408 847.44 797.27
Labour
1 Foreman Each 0.1 400 40
2 Mason Each 0.16 350 56
3 Male assistant Each 0.85 200 170
4 Female assistant Each 1.1 150 165
Total
Rate Per Cft
7 Supplying and laying Plain cement Concrete works using 20mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days. Lean concrete/levelling course
Grade of
concrete Mix M 5
Labour
1 Foreman Each 0.075 400.00 30.00
2 Mason Each 0.15 350.00 52.50
3 Male assistant Each 0.75 200.00 150.00
4 Female assistant Each 0.9 150.00 135.00
Total
Rate Per Cft
8 Supplying and laying Plain cement Concrete works using 40mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days. Lean concrete/levelling course
Grade of
Concrete Mix M 7.5
Description Unit Qty Rate Amount
Assume for 1 cum
Material
1 cement Bag 3.40 300.00 1020.00
2 Sand Cum 0.361 1765.50 637.35
3 40mm coarse aggregate Cum 0.564 706.20 398.30
4 20mm coarse aggregate Cum 0.376 847.44 318.64
Total
Labour
1 Foreman Each 0.075 400.00 30.00
2 Mason Each 0.15 350.00 52.50
3 Male assistant Each 0.75 200.00 150.00
4 Female assistant Each 0.90 150.00 135.00
Total
Tools & Equipments
1 Mixer machine Day 0.04 900 36
9 Supplying and laying Plain cement Concrete works using 40mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete Mix M 10
Material
1 Cement Bag 4.2 300 1260.00
2 Sand Cum 0.368 847.44 311.86
3 40mm coarse aggregate Cum 0.564 706.2 398.30
3 20mm coarse aggregate Cum 0.376 847.44 318.64
Labour
1 Foreman Each 0.1 400 40.00
2 Mason Each 0.15 350 52.50
3 Male assistant Each 0.8 350 280.00
4 Female assistant Each 0.95 150 142.50
Total
Rate Per Cft
10 Supplying and laying Plain cement Concrete works using 40mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete Mix M15
Material
1 Cement Bag 6.02 300 1806.00
2 Sand Cum 0.359 1765.5 633.81
3 40mm coarse aggregate Cum 0.564 706.2 398.30
3 20mm coarse aggregate Cum 0.376 847.44 318.64
Labour
1 Foreman Each 0.1 400 40
2 Mason Each 0.2 350 70
3 Male assistant Each 0.8 200 160
4 Female assistant Each 1 150 150
Total
Rate Per Cft
11 Supplying and laying Plain cement Concrete works using 20mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete Mix M15
Material
1 Cement Bag 6.02 300 1806.00
2 Sand Cum 0.438 1765.5 773.29
3 20mm coarse aggregate Cum 0.69 847.44 584.73
3 12mm coarse aggregate Cum 0.23 847.44 194.91
Labour
1 Foreman Each 0.1 400 40
2 Mason Each 0.2 350.0 70.0
3 Male assistant Each 0.8 200.0 160.0
4 Female assistant Each 1 150.0 150.0
Total
Rate Per Cft
12 Supplying and laying Plain cement Concrete works using 12mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days
Grade of
concrete Mix M15
Material
1 Cement Bag 6.02 300 1806.00
2 Sand Cum 0.562 1765.5 992.21
3 12mm coarse aggregate Cum 0.9 847.44 762.70
Labour
1 Foreman Each 0.1 400.0 40
2 Mason Each 0.2 350.0 70.0
3 Male assistant Each 0.75 200.0 150
4 Female assistant Each 0.95 150.0 142.5
Total
Rate Per Cft
13 Supplying and laying Plain cement Concrete works using 20mm and below size
coarse aggregate, machine mixed, well tamped and cured with water for atleast 7
days.
Grade of
concrete Mix M 20
Labour
1 Foreman Each 0.10 400.00 40.00
2 Mason Each 0.20 350.00 70.00
3 Male assistant Each 0.75 200.00 150.00
4 Female assistant Each 0.95 150.00 142.5
Tools & equipments
1 Mixer machine day 0.035 900 31.5
Total
Rate Per Cft
Amount
2612.20
342.50
36.00
2990.70
448.60
3439.30
97.43
Amount
10279.00
154.19
308.37
1541.85
12283.41
122.83
4336.04
10379.00
155.69
311.37
1556.85
12402.91
124.03
4378.23
7280.5
109.2075
218.42
1092.08
8700.20
87.001975
3071.16972
2801.42
394.50
36.00
3231.92
484.79
3716.71
105.289
2938.45
400.00
45.00
3383.45
507.52
3890.97
110.226
3433.76
431
45
3909.76
586.46
4496.23
127.37
2189.94
367.50
36.00
2593.44
389.02
2982.45
84.49
Amount
2374.28
367.50
36.00
2777.78
416.67
3194.45
90.49
2288.79
515.00
37.50
2841.29
426.19
3267.49
92.563
3156.75
420
31.5
3608.25
541.24
4149.49
117.55
3358.93
420
31.5
3810.43
571.57
4382.00
124.14
3560.91
402.5
31.5
3994.91
599.24
4594.14
130.15
3889.04
402.50
31.5
4323.04
648.46
4971.50
140.84
RATE ANALYSIS OF REINFORCED CEMENT CONCRETE
SI No
Supplying and laying Reinforced cement concrete works using 20mm and below size coarse
aggregate, machine mixed, well tamped and cured with water for atleast 7 days above plinth level
For Columns & Retaining wall
1 Grade of
Concrete Mix M20
Assume for 1 cum
Description Unit Qty Rate Amount
Material
1 Cement bag 7.86 300.00 2358.00
2 Sand cum 0.50 1765.50 882.75
Labour
1Foreman each 0.18 400.00 70.00
2Mason each 0.30 350.00 105.00
3Male assistant each 1.05 200.00 210.00
4Female assistant each 1.25 150.00 187.50
Total 572.50
Tools & equipment
1 Weigh batcher day 0.05 500.00 25.00
2 Mixer machine day 0.05 900.00 45.00
Total 70.00
4760.69
Add for testing @ 2% 95.21
Add for Saundries & contengencies @ 3% 142.82
Add For Water Charges @ 1.5% 71.41
Add 15% Contractor profit & overheads 714.1035
TOTAL 5784.24
Rate Per Cft 163.86
(b) Labour
1. For Mixing and Placing Sft 100.00 5.00 500.00
4744.00
(c ) Misc..
1. Add For Water Charges @ 1.5% 71.16
2. Add For Wastages @ 3% 142.32
3. Add For Contractor's Profit and Overheads @ 15% 711.6
Total 5669.08
Rate Per Sft 56.69
Rate Per Sqm 609.43
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
2. River Sand Cft 50.00 50.00 2500.00
3. 20mm Jelly Cft 90.00 24.00 2160.00
(b) Labour
1. For Mixing & Placing Cft 100 8 800
2. For Shuttering Work Sft 400 12 4800
16935.00
(c ) Misc..
1. Add For Water Charges @ 1.5% 167.25
2. Add For Wastages @ 3% 334.5
3. Add For Contractor's Profit and Overheads @ 15% 1672.5
Total 19109.25
Rate Per Cft 133.2425
Rate Per Cum 4703.372
(b) Labour
1. For Mixing & Placing Cft 100.00 6.00 600.00
10255.00
(c ) Misc..
1. Add For Water Charges @ 1.5% 153.83
2. Add For Wastages @ 3% 307.65
3. Add For Contractor's Profit and Overheads @ 15% 1538.25
Total 12254.73
Rate Per Cft 122.55
Rate Per Cum 4325.92
(b) Labour
1. For Mixing & Placing Cft 30.00 8.00 240.00
2. For Shuttering Work Sft 90.00 15.00 1350.00
4056.00
(c ) Misc..
1. Add For Water Charges @ 1.5% 60.84
2. Add For Wastages @ 3% 121.68
3. Add For Contractor's Profit and Overheads @ 15% 608.4
Total 4846.92
Rate Per Cft 161.56
Rate Per Cum 5703.21
(b) Labour
1. For Mixing & Placing Cft 100.00 10.00 1000.00
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
2. For Shuttering Work Sft 175.00 12.00 2100.00
14435.00
(c ) Misc..
1. Add For Water Charges @ 1.5% 216.53
2. Add For Wastages @ 3% 433.05
3. Add For Contractor's Profit and Overheads @ 15% 2165.25
Total 17249.83
Rate Per Cft 172.50
Rate Per Cum 6089.19
7 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse
aggregate, machine mixed, well tamped and cured with water for atleast 7 days for Footing & raft
Grade of
Concrete Mix M20
Assume for 1 cum
Material
1 Cement Bag 7.86 300.00 2358.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.233 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
4013.94
Labour
1 Foreman Each 0.10 400.00 40.00
2 Mason Each 0.20 350.00 70.00
3 Male assistant Each 0.60 200.00 120.00
4 Female assistant Each 0.75 150.00 112.50
342.50
Tools & equipments
1 Weigh batcher day 0.05 500 25.0
2 Mixer machine day 0.05 900 45
70
4426.44
Add for testing @ 2% 88.53
Add for Saundries & contengencies @ 3% 132.79
Add For Water Charges @ 1.5% 66.40
Add 15% Contractor profit & overhead charges 663.97
Total 5378.13
Rate Per Cft 152.35
8 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse
aggregate, machine mixed, well tamped and cured with water for atleast 7 days above plinth level
for plinth beam
Grade of
Concrete Mix M20
Assume for 1 cum
Material
1 Cement Bag 7.86 300.00 2358.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.233 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
4013.94
Labour
1 Foreman Each 0.20 400.00 80.00
2 Mason Each 0.30 350.00 105.00
3 Male assistant Each 1.15 200.00 230.00
4 Female assistant Each 1.40 150.00 210.00
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
625.00
Tools & equipments
1 Weigh batcher day 0.05 500 25.0
2 Mixer machine day 0.05 900 45
70
4708.94
Add for testing @ 2% 94.18
Add for Saundries & contengencies @ 3% 141.27
Add For Water Charges @ 1.5% 70.63
Add 15% Contractor profit & overhead charges 706.34
Total 5721.36
Rate Per Cft 162.08
9 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse
aggregate, machine mixed, well tamped and cured with water for atleast 7 days for lintles and chejjs
etc.,
Grade of
Concrete Mix M20
Assume for 1 cum
Material
1 Cement Bag 7.86 300.00 2358.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.233 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
4013.94
Labour
1 Foreman Each 0.25 400.00 100.00
2 Mason Each 0.35 350.00 122.50
3 Male assistant Each 1.25 200.00 250.00
4 Female assistant Each 1.60 150.00 240.00
712.50
Tools & equipments
1 Weigh batcher day 0.05 500 25.0
2 Mixer machine day 0.05 900 45
70
4796.44
Add for scafolding, testing @ 3.6% 172.67
Add for cover blocks @ .5% 23.98
Add for hacking @ .5% 23.98
Add for Saundries & contengencies @ 3% 143.89
Add For Water Charges @ 1.5% 71.95
Add 15% Contractor profit & overhead charges 719.47
Total 5952.38
Rate Per Cft 168.62
9 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse
aggregate, machine mixed, well tamped and cured with water for atleast 7 days for Slabs and beams
Grade of
Concrete Mix M20
Assume for 1 cum
Material
1 Cement Bag 7.86 350.00 2751.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.233 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
4406.94
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
Labour
1 Foreman Each 0.25 400.00 100.00
2 Mason Each 0.35 350.00 122.50
3 Male assistant Each 1.25 200.00 250.00
4 Female assistant Each 1.60 150.00 240.00
712.50
Tools & equipments
1 Weigh batcher day 0.05 500 25.0
2 Mixer machine day 0.05 900 45
70
5189.44
Add for scafolding, testing @ 2% 103.79
Add for cover blocks @ .5% 25.95
Add for hacking @ .5% 25.95
Add for Saundries & contengencies @ 3% 155.68
Add For Water Charges @ 1.5% 77.84
Add 15% Contractor profit & overhead charges 778.42
Total 6357.06
Rate Per Cft 180.09
Grade of
Concrete Mix M25
Assume for 1 cum
Material
1 Cement Bag 8.64 300.00 2592.00
2 Sand Cum 0.47 1765.50 829.43
3 12mm coarse aggregate Cum 0.23 847.44 197.71
4 20mm aggregate Cum 0.71 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
4267.94
Labour
1 Foreman Each 0.20 400.00 80.00
2 Mason Each 0.30 350.00 105.00
3 Male assistant Each 1.15 200.00 230.00
4 Female assistant Each 1.40 150.00 210.00
625.00
Tools & equipments
1 Weigh batcher day 0.05 500 25
2 Mixer machine day 0.05 900 45
70
4962.94
Add for scafolding, testing @ 2% 99.26
Add for cover blocks @ .5% 24.81
Add for hacking @ .5% 24.81
Add for Saundries & contengencies @ 3% 148.89
Add For Water Charges @ 1.5% 74.44
Add 15% Contractor profit & overhead charges 744.44
Total 6079.60
Rate Per Cft 172.23
11 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse aggregate,
machine mixed, well tamped and cured with water for atleast 7 days above plinth level and upto V floor
level in beams, lintel, slabs etc.
Grade of
Concrete Mix M25
Assume for 1 cum
Material
1 Cement Bag 8.64 300.00 2592.00
2 Sand Cum 0.47 1765.50 829.43
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
3 12mm coarse aggregate Cum 0.23 847.44 197.71
4 20mm aggregate Cum 0.71 847.44 598.80
5 Ad mixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
4267.94
Labour
1 Foreman Each 0.25 400.00 100.00
2 Mason Each 0.35 350.00 122.50
3 Male assistant Each 1.25 200.00 250.00
4 Female assistant Each 1.60 150.00 240.00
712.50
Tools & equipments
1 Weigh batcher day 0.05 500 25
2 Mixer machine day 0.05 900 45
70
5050.44
Add 15% Contractor profit & overhead charges 757.57
Total 5808.01
Rate Per Cft 164.53
12 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse aggregate,
machine mixed, well tamped and cured with water for atleast 7 days above plinth level and upto V floor
level in walls, columns, struts, pillars etc.
Grade of
Concrete Mix M30
Assume for 1 cum
Material
1 Cement Bag 10.8 300 3240
2 Sand Cum 0.4698 1765.5 829.43
3 12mm coarse aggregate Cum 0.2333 847.44 197.71
4 20mm aggregate Cum 0.70666 847.44 598.85
5 Admixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
4915.99
Labour
1 Foreman Each 0.2 400 80.00
2 Mason Each 0.3 350 105.00
3 Male assistant Each 1.15 200 230.00
4 Female assistant Each 1.4 150 210.00
625.00
Tools & Equipments
1 Weigh batcher day 0.05 500 25.00
2 Mixer machine day 0.05 900 45.00 70.00
5610.99
Add 15% Contractor profit & overhead 841.64874
Total 6452.64
Rate Per Cft 182.79
13 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse aggregate,
machine mixed, well tamped and cured with water for atleast 7 days above plinth level and upto V floor
level beams, lintels, slabs etc.
Grade of
Concrete Mix M30
Assume for 1 cum
Material
1 Cement Bag 10.8 300 3240
2 Sand Cum 0.4698 1765.5 829.43
3 12mm coarse aggregate Cum 0.2333 847.44 197.71
4 20mm aggregate Cum 0.70666 847.44 598.85
5 Admixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
4915.99
Labour
1 Foreman Each 0.25 400 100.00
2 Mason Each 0.35 350 122.50
3 Male assistant Each 1.25 200 250.00
4 Female assistant Each 1.6 150 240.00
712.50
Tools & Equipments
1 Weigh batcher day 0.05 500 25.00
2 Mixer machine day 0.05 900 45.00 70.00
5698.49
Add 15% Contractor profit & overhead 854.77
Total 6553.27
Rate Per Cft 185.64
14 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse aggregate,
machine mixed, well tamped and cured with water for atleast 7 days above plinth level and upto V floor
level in walls, columns, struts, pillars etc.
Grade of
Concrete Mix M35
Assume for 1 cum
Material
1 Cement Bag 13.00 300.00 3900.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.2333 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Admixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
5575.94
Labour
1 Foreman Each 0.20 400.00 80.00
2 Mason Each 0.30 350.00 105.00
3 Male assistant Each 1.15 200.00 230.00
4 Female assistant Each 1.40 150.00 210.00
625.00
Tools & Equipments
1 Weigh batcher day 0.05 500.00 25.00
2 Mixer machine day 0.05 900.00 45.00 70.00
6270.94
Add 15% Contractor profit & Overhead 940.641
Total 7211.58
Rate Per Cft 204.29
15 Supplying and laying Reinforced cement concrete works using 20mm and below size coarse aggregate,
machine mixed, well tamped and cured with water for atleast 7 days above plinth level and upto V floor
level in beams, lintels, slabs etc.
Grade of
Concrete Mix M35
Assume for 1 cum
Material
1 Cement Bag 13.00 300.00 3900.00
2 Sand Cum 0.4698 1765.50 829.43
3 12mm coarse aggregate Cum 0.2333 847.44 197.71
4 20mm aggregate Cum 0.7066 847.44 598.80
5 Admixture Litre 0.20 150.00 30.00
6 Notional additional cost Cum 1.00 20.00 20.00
5575.94
Labour
1 Foreman Each 0.25 400.00 100.00
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
2 Mason Each 0.35 350.00 122.50
3 Male assistant Each 1.25 200.00 250.00
4 Female assistant Each 1.60 150.00 240.00
712.50
Tools & Equipments
1 Weigh batcher day 0.05 500.00 25.00
2 Mixer machine day 0.05 900.00 45.00 70.00
6358.44
Add 15% Contractor profit & Overhead 953.766
Total 7312.21
Rate Per Cft 207.14
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
Rate Analysis
Footing shuttring
Description Unit Qty Rate Amount Remarks
1 Column Shuttring
a Total 422.33
(b) Labour
Foreman Each 0.10 400.00 40.00
Carpenter Each 0.55 350.00 192.50
Helper Each 0.55 220.00 121.00
b Total 353.50
Total a + b 775.83
( c) Misc.
Material
1. Shuttring ply 12mm thick
1x3.66x3.05=11.16 Sqm
Add for wastage 10%=1.116 Sqm
12.3 Sqm Sqm 12.3 430 5289
Labour
Fore man Each 0.25 400 100
Carpenter Each 2.25 350 787.5
Helper Each 2.25 220 495
1382.5
2100.948
( c) Misc.
for slab
Material
12mm ply Sqm 6.7 430.4 2883.68
Timber 75x 50mm Cum 0.18 12358.5 2224.53
Timber 50x40mm Cum 0.0504 12358.5 622.8684
Closing ends 75x50mm Cum 0.0133 12358.5 164.36805
5895.4465
Consider for 15 repetition for ply &
wood 393.02976
Steel items
40mmx40mm square pipes MT 0.025 70 1.75
75mmx40mm ISMC MT 0.068 70 4.76
Adjustable prop head Nos 16 1500 24000
Spacer pipes MT 0.0443 70 3.101
25029.611
Consider for 200 repetition steel 125.14806
Consider 25% salvage value -31.28701
Labour
For making
Carpenter Each 0.8 350 280
Helper Each 0.8 220 176
456
Consider for 15 repetition for ply &
wood 30.4
For fixing
Fore man Each 0.25 400 100
Carpenter Each 1.35 350 472.5
Helper Each 1.35 220 297
869.5
1386.7908
( c) Misc.
Materials
MS sheet 14 guage Kg 188.4 80 15072
Angle iron 40x40x5mm Kg 252 70 17640
32712
Consider for 50 repetition for Steel 654.24
Consider 25% salvage value -163.56
Labour
Fore man Each 0.25 400 100
Carpenter Each 2.25 350 787.5
Helper Each 2.25 220 495
1382.5
2298.2838
( c) Misc.
2954.56
Add for Saundries & contengencies @ 3% 88.64
Add For Water Charges @ 1.5% 44.32
Add 15% Contractor profit & over heads 443.18
TOTAL 3530.69
Rate Per Cft 100.020
2 Clay Block Masonry 200mm thick
Supplying and laying Solid Block masonry in CM 1:6 in superstructure 200mm thick
Assume 30sqm 10m wide , 3m high
Description Unit Qty Rate Amount
Material
1 Cement Bag 4.65 300.00 1395.00
2 Sand Cum 1.00 1765.50 1765.50
3 Blocks Nos 375.00 35.00 13125.00
Total 16285.50
Labour
1 Foreman Each 0.10 400.00 40.00
2 Mason Each 3.75 350.00 1312.50
3 Male assistant Each 2.75 200.00 550.00
4 Female assistant Each 4.00 150.00 600.00
Total 2502.50
18788.00
Add for Saundries & contengencies @ 3% 563.64
Add For Water Charges @ 1.5% 281.82
Add 15% Contractor pfofit & overheads 2818.20
TOTAL 22451.66
Rate Per Sqm 748.39
Rate Per Sft 69.62
Labour
1 Foreman Each 0.10 400.00 40.00
2 Mason Each 3.75 350.00 1312.50
3 Male assistant Each 2.75 200.00 550.00
4 Female assistant Each 4.00 150.00 600.00
Total 2502.50
14254.73
Add for Saundries & contengencies @ 3% 427.64
Add For Water Charges @ 1.5% 213.82
Add 15% Contractor pfofit & overheads 2138.21
TOTAL 17034.40
Rate Per Sqm 567.81
Rate Per Sft 52.82
Supplying and laying Solid block masonry in CM 1:4 in Superstructure 100mm thick
Labour
1 Foreman Each 0.10 400.00 40.00
2 Mason Each 3.75 350.00 1312.50
3 Male assistant Each 2.75 200.00 550.00
4 Female assistant Each 4.00 150.00 600.00
5 Bar bender Each 0.35 350.00 122.5
6 Bar bender helper Each 0.35 220.00 77.00
Total 2702.00
13798.42
Add for Saundries & contengencies @ 3% 413.95
Add For Water Charges @ 1.5% 206.98
Add 15% Contractor pfofit & overheads 2069.7636
TOTAL 16489.12
Rate Per Sqm 549.64
Rate Per Sft 51.13
5 BRICKWORK FOR CORNICE ON TERRACE
Unit - 100 Cft
Supplying and laying Brick masonry in CM 1:4 in Superstructure.
Description Unit Qty Rate Amount
(a) Material
1. Brick Nos 1300.00 4.20 5460.00
2. Cement Bag 7.50 300.00 2250.00
3. River Sand Cft 30.00 50.00 1500.00
(b) Labour
1. For Cornice Brick Work Cft 100.00 10.00 1000.00
10210.00
(c ) Misc..
1. Add For Charges @ 1.5% 153.15
2. Add For Wastages @ 3% 306.3
3. Add For Contractor's Profit & Over 1531.5
Total 12200.95
Rate Per Cft 122.01
Rate Per Cum 4306.94
(b) Labour
1. For Perforated Brick Cft 100.00 8.00 800.00
6925
(c ) Misc..
1. Add For Charges @ 1.5% 103.88
2. Add For Wastages @ 3% 207.75
3. Add For Contractor's Profit & Over 1038.75
Total 8275.38
Rate Per Cft 82.75
Rate Per Cum 2921.21
(b) Labour
1. For Making Brick Jelly Cft 100.00 2.00 200.00
2. For Filling Brick Jelly Cft 100.00 1.50 150.00
3752.00
(c ) Misc..
1. Add For Charges @ 1.5%
2. Add For Wastages @ 3% 56.28
3. Add For Contractor's Profit & Over 112.56
562.8
Total 4483.64
Rate Per Cft 44.84
Rate Per Cum 1582.72
BURNT BRICK MASONRY
8 Supplying and laying Burnt brick masonry in CM 1:6 masonry in superstructure 230mm thick
Assume for 1 Cum
Material
1 Cement Bag 0.876 300 262.80
2 Sand Cum 0.25 1765.5 441.38
3 Bricks Nos 500 4.2 2100.00
Total 2804.18
Labour
1 Foreman Each 0.1 400 40.00
2 Mason Each 0.4 350 140.00
3 Male assistant Each 0.5 200 100.00
4 Female assistant Each 0.5 150 75.00
5 Bhisti Each 0.2 200 40.00
395.00
Add lift charges at the rate
of 10% Percent 10% 39.50 39.50
Total 3238.68
Add for pumps for water @ .5% 16.19
Add for Saundries & contengencies @ 3% 97.16
Add for water and electricity charges @ 1.5% 48.58
Add 15% Contractor profit & overhead 485.80125
Total 3886.41
Rate Per Cft 110.097
9 Supplying and laying Burnt brick masonry inCM 1:4 masonry in superstructure115mm thick,
Assume for 30 sqm 10m wide, 3m Ht
Material
1 Cement Bag 6.54 300 1962.00
2 Sand Cum 0.93 1765.5 1641.92
3 Bricks Nos 1800 4.2 7560.00
4 10mm and down aggregate Cum 0.32 24 7.68
5 8mm bars Mt 0.051 46000 2346.00
Total 13517.60
Labour
1 Foreman Each 0.15 400.00 60
2 Mason Each 4.00 350.00 1400.00
3 Male assistant Each 2.75 200.00 550.00
4 Female assistant Each 4.00 150.00 600.00
5 Bar bender Each 0.35 350.00 122.5
6 Bar bender helper Each 0.35 220.00 77.00
Total 2809.50
16327.10
Add for pumps for water @ .5% 81.64
Add for Saundries & contengencies @ 3% 489.81
Add for water and electricity charges @ 1.5% 244.91
Add 15% Contractor profit & overheads 2449.06
Total 19592.51
Rate Per Sqm 653.08
Rate Per Sft 60.70
RATE ANALYSIS OF PLATERING
1 CEILING PLASTERING
Providing and Laying CM 1:4 in 12mm thick plastering including scaffolding, curing
complete in ceiling with lime rendering
Assume 10sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 1.1 300 330
2 Sand Cum 0.144 1765.5 254.232
3 Lime kg 23.5 4 94
Total 678.232
Labour
1 Mason Each 2.25 350.00 787.50
2 Male assistant Each 4.30 200.00 860.00
3 Female assistant Each 0.20 150.00 30.00
Total 1677.50
Scaffolding 12.00
2367.732
Add for scafolding, pumps for water @ 2% 47.355
Add for Saundries & contengencies @ 3% 71.032
Add for Elecricity and water charges @ 1.5% 35.516
Add 15% Contractor profit & Overheads 355.160
TOTAL 2876.79438
Rate Per Sqm 287.68
Rate Per Sft 26.761
Providing and Laying CM 1:6 in 15mm thick plastering including scaffolding, curing
complete in walls with lime rendering
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 0.90 300.00 270.00
2 Sand cum 0.17 1765.50 303.67
3 Lime kg 23.50 4.00 94.00
Total 667.67
Labour
1 Mason Each 2.50 350.00 875.00
2 Male assistant Each 4.29 200.00 858.00
3 Female assistant Each 0.35 150.00 52.50
Total 1785.50
2453.17
Add for scafolding, pumps for water @ 2% 49.063
Add for Saundries & contengencies @ 3% 73.595
Add for Elecricity and water charges @ 1.5% 36.797
Add 15% Contractor profit & Overheads 367.97
TOTAL 2980.60
Rate Per Sqm 298.06
Rate Per Sft 27.73
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 0.90 300.00 270.00
2 Sand cum 0.17 1765.50 303.67
Total 573.67
Labour
1 Mason Each 1.50 350.00 525.00
2 Male assistant Each 2.29 200.00 458.00
3 Bhisti Each 0.15 200.00 30.00
Total 1013.00
1586.67
Add for scafolding, pumps for water @ 2% 31.733
Add for Saundries & contengencies @ 3% 47.600
Add for Elecricity and water charges @ 1.5% 23.800
Add 15% Contractor profit & Overheads 238.00
TOTAL 1927.80
Rate Per Sqm 192.78
Rate Per Sft 17.93
Providing and Laying CM 1:4 in 15mm thick water proof plastering including
scaffolding, curing complete in walls with Cement rendring
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 1.35 300.00 405.00
2 Sand cum 0.18 1765.50 323.97
3 Cement rendring Bag 0.47 300.00 141.00
4 Waterproof compound liter 0.263 150.00 39.38
Total 869.97
Labour
1 Mason Each 2.50 350.00 875.00
2 Male assistant Each 4.29 200.00 858.00
3 Bhisti Each 0.35 200.00 70.00
Total 1803.00
2672.97
Add for scafolding, pumps for water @ 2% 53.459
Add for Saundries & contengencies @ 3% 80.189
Add for Elecricity and water charges @ 1.5% 40.095
Add 15% Contractor profit & Overheads 400.95
TOTAL 3247.66
Rate Per Sqm 324.77
Rate Per Sft 30.21
3 EXTERNAL WALL PLASTERING
Providing and Laying CM 1:4 in 20mm thick plastering including scaffolding, curing
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 1.75 300.00 525.00
2 Sand cum 0.224 1765.50 395.47
Total 920.47
Labour
1 Foreman 0.10 400.00 40.00
2 Mason Each 1.90 350.00 665.00
3 Male assistant Each 3.85 200.00 770.00
4 Bhisti Each 0.30 200.00 60.00
Total 1535.00
2455.47
Add for scafolding,lead &lift, pumps for water @ 20% 491.094
Add for Saundries & contengencies @ 3% 73.664
Add for Elecricity and water charges @ 1.5% 36.832
Add 15% Contractor profit & Overheads 368.321
TOTAL 3425.38
Rate Per Sqm 342.54
Rate Per Sft 31.86
Providing and Laying CM 1:4 in 20mm thick waterproof plastering including scaffolding,
curing complete in walls with sponge finish externally
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 1.75 300.00 525.00
2 Sand cum 0.224 1765.50 395.47
3 Waterproof compound liter 0.263 150.00 39.38
Total 959.85
Labour
1 Foreman 0.10 400.00 40.00
2 Mason Each 1.90 350.00 665.00
3 Male assistant Each 3.85 200.00 770.00
4 Bhisti Each 0.30 200.00 60.00
Total 1535.00
2494.85
Add for scafolding,lead &lift, pumps for water @ 20% 498.969
Add for Saundries & contengencies @ 3% 74.845
Add for Elecricity and water charges @ 1.5% 37.423
Add 15% Contractor profit & Overheads 374.227
TOTAL 3480.31
Rate Per Sqm 348.03
Rate Per Sft 32.37
3 ROUGH PLASTER
Providing and Laying CM 1:6 in 12mm thick plastering including scaffolding, curing
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 1.75 300.00 525.00
2 Sand cum 0.144 1765.50 254.23
Total 779.23
Labour
1 Foreman 0.10 400.00 40.00
2 Mason Each 0.75 350.00 262.50
3 Male assistant Each 1.50 200.00 300.00
4 Bhisti Each 0.15 200.00 30.00
Total 632.50
1411.73
Add for scafolding, pumps for water @ 2% 28.235
Add for Saundries & contengencies @ 3% 42.352
Add for Elecricity and water charges @ 1.5% 21.176
Add 15% Contractor profit & Overheads 211.7598
TOTAL 1715.25
Rate Per Sqm 171.53
Rate Per Sft 15.96
(b) Labour
1. For 75mm Width Plaster Band
Work Rft 100.00 6.00 600.00
2. For Scaffolding and Curing @
25% (Labour Amount) 150.00
925.00
(c ) Misc.
1. Add For water Charges @
1.5% 13.88
2. Add For Wastages @ 5% 4.63
3. Add For Contractor's Profit
and Overheads @15% 135.00
Total 1078.50
Rate Per Rft 10.79
Rate Per Rmt 35.37
Total 1721.53
Rate Per Rft 17.22
Rate Per Rmt 56.47
(b) Labour
1. For 150mm Width Plaster
Band Work Rft 100.00 12.00 1200.00
2. For Scaffolding and curing @
25% (Labour Amount) 300.00
1850.00
( c) Misc.
1. Add For Water Charges @
1.5% 27.75
2. Add For Wastages @ 5% 92.50
3. Add For Contractor's Profit
and Overheads @ 15% 277.50
Total 2247.75
Rate Per Rft 22.4775
Rate Per Rmt 73.7262
(b) Labour
1. For 150mm Width Plaster
Band Work Rft 100.00 18.00 1800.00
2. For Scaffolding and curing @
25% (Labour Amount) 450.00
2719.0
( c) Misc.
1. Add For Water Charges @
1.5% 40.79
2. Add For Wastages @ 5% 135.95
3. Add For Contractor's Profit
and Overheads @ 15% 407.85
Total 3303.6
Rate Per Rft 33.03585
Rate Per Rmt 108.36
(b) Labour
1. For 150mm Width Plaster
Band Work Rft 100.00 20.00 2000.00
2. For Scaffolding and curing @
25% (Labour Amount) 500.00
3200.00
( c) Misc.
1. Add For Water Charges @
1.5% 48.00
2. Add For Wastages @ 5% 160.00
3. Add For Contractor's Profit
and Overheads @ 15% 480.00
Total 3888.00
Rate Per Rft 38.88
Rate Per Rmt 127.53
TOTAL 25.36
30.17
W.C.T @ 4% 1.21
TOTAL 31.38
9 PANI PATTI
TOTAL 20.24
24.08
W.C.T @ 4% 0.96
Providing and Laying CM 1:3 in 50mm thick Lath plastering including scaffolding, curing
Assume 10 Sqm
Description Unit Qty Rate Amount
Material
1 Cement Bag 5.85 300.00 1755.00
2 Sand cum 0.6 1765.50 1059.30
Total 2814.30
Labour
1 Foreman 0.10 400.00 40.00
2 Mason Each 1.90 350.00 665.00
3 Male assistant Each 3.85 200.00 770.00
4 Bhisti Each 0.30 200.00 60.00
Total 1535.00
4349.30
Add for scafolding, pumps for water @ 2% 86.986
Add for Saundries & contengencies @ 3% 130.479
Add for Elecricity and water charges @ 1.5% 65.240
Add 15% Contractor profit & Overheads 652.395
TOTAL 5284.40
Rate Per Sqm 528.44
Rate Per Sft 49.16
RATE ANALYSIS OF PAINT
(b) Labour
1. For one coat primer, Two coat putty and Two coat Royale Emulsion Sft 100.00 3.00 300.00
1058.45
( c ) Misc..
1. Add For Water Charges 15.88
2. Add for Wastages @ 1.5% 15.88
3. Add For Contractor's Profit and Overheads @ 15% 158.77
Total 1248.97
Rate per Sft 12.49
Rate per Sqm 134.26
(b) Labour
1. For one coat primer & Two Coat apex Paint Sft 100.00 3.00 300.00
911.60
( c ) Misc..
1. Add For Water Charges @ 1.5% 13.67
2. Add for Wastages @ 1.5% 13.67
3. Add For Contractor's Profit and Overheads @ 15% 136.74
Total 1075.69
Rate per Sft 10.76
Rate per Sqm 115.64
1 Scrapping 5.39
5 Conveying the existing shutter with paper for spraying purpose (Paper and 25.42
Total 472.46
Note : Rate / Sft Rs 44.00
(b) Labour
Painter each 0.65 350 227.5
Helper each 0.65 220 143
643.4
( c ) Misc..
Add for Carriage of material, brushes, sand paper, putti etc @ 5% 32.170
Add for scafolding @ 3% 19.302
Add for Saundries & contengencies @ 3% 19.302
Add for Elecricity and water charges @ 0.5% 3.217
Add 15% Contractor profit & Overheads 96.510
Total 813.90
Rate per Sqm 81.39
Rate per Sft 7.57
RATE ANALYSIS OF WATER PROOFING
(b) Labour
1. For Mixing, Placing and Leveling Sft 100.00 3.00 300.00
1959.5
( c) Misc..
1. Add For Water Charges @ 1.5% 29.39
2. Add For Wastages @ 5% 97.98
3. Add For Contractor's Profit and Overheads @ 15% 293.93
Total 2380.793
Rate Per Cft 142.8476
Rate Per Cum 5043.947
(b) Labour
1. For Mixing, Placing and Leveling Sft 100.00 3.50 350.00
3572.50
( c) Misc..
1. Add For Water Charges @ 1.5% 53.59
2. Add For Wastages @ 5% 178.63
3. Add For Contractor's Profit and Overheads @ 15% 535.88
Total 4340.588
Rate Per Cft 173.6235
Rate Per Cum 6130.646
(b) Labour
Foreman Each 1.25 400 500
Mason Each 2.75 350 962.5
MC Each 3.45 200 690
Beldar Each 5.7 220 1254
Bhisti Each 5.4 200 1080
10563.62
Add for scafolding, pumps for water @ 1% 105.636
Add for wire brush broom @ .75% 79.227
Add for rounding corners @ 3% 316.909
Add for Saundries & contengencies @ 3% 316.909
Add for Elecricity and water charges @ 1.5% 158.454
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
Add 15% Contractor profit & Overheads 1584.543
Total 13125.30
Rate Per Sqm 810.20
Rate Per Sft 75.30
(b) Labour
Foreman Each 1 400 400
Mason Each 2.5 350 875
MC Each 2.5 200 500
Beldar Each 3.5 220 770
Bhisti Each 1.05 200 210
6653.95
Add for scafolding, pumps for water @ 1% 66.540
Add for wire brush broom @ .75% 49.905
Add for rounding corners @ 3% 199.619
Add for Saundries & contengencies @ 3% 199.619
Add for Elecricity and water charges @ 1.5% 99.809
Add 15% Contractor profit & Overheads 998.093
Total 8267.53
Rate Per Cum 2755.84
Rate Per Cft 78.05
Labour
Foreman each 1.5 400 600
Sprayman each 4 200 800
Beldar each 4 220 880
13907
Add for prepration of surface, making the surface rough
cutting grooves etc. @ 2.1% 292.047
Add for wires brushes, chisels, brushes for applying
bitumin, carriage of APP modified polymeric membrane
etc. @ 1% 139.07
Add for Sundries & contingencies @ 3% 417.21
Add 15% Contractor profit & Overheads 2086.05
Total 16841.38
Rate Per Sqm 561.3792
Rate Per Sft 52.17279
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
#492/K,3rd Floor, 7th Cross, 7th Block West, K.R.Road, Jayanagar, Bangalore - 560 078
ROHINI PROJECT MANAGEMENT SOLUTIONS Telefax: 26764207.
E-mail: rohiniconsulting@rediffmail.com
RATE ANALYSIS OF FLOORING & DADOING WORKS
PROVIDING & LAYING OF CERAMIC TILE FLOORING IN 1:4 CEMENT MORTAR WITHOUT OVERHEADS
8
SI.no Description Unit Qty Rate Amount
A Material
1 Ceramic tile Sqm 1.00 430.40 430.40
2 cement Bag 0.225 300.00 67.50
3 Sand Cum 0.05 1765.50 88.28
White cement, joint
4 filler LS 20.00
5 Wastage @ 5% Sqm 0.05 430.40 21.52 627.70
B Labour
1 For Laying
Foreman Each 0.08 230 18.4
Mason Each 0.45 110 49.5
MC Each 0.45 90 40.5
Waterman Each 0.05 150 7.5
778.60
Add 1.5% towards Water & Electrical Charges 11.68
Add 15% Contractor profits & over heads 116.79
TOTAL 907.06
Rate Per Sft 84.38
PROVIDING & LAYING OF CERAMIC TILE SKIRTING IN 1:4 CEMENT MORTAR WITHOUT OVER HEADS
CERAMIC TILE SKIRTING WORK 100MM HIGH RATE WORKED OUT FOR 1 Rmt
9
SI.no Description Unit Qty Rate Amount
A Material
1 Ceramic tile Sqm 0.10 430.40 43.04
2 Cement Bag 0.225 300.00 67.50
3 Sand Cum 0.002 1765.50 3.53
White cement, joint
4 filler LS 2.00
5 Wastage @ 5% Sqm 0.005 43.04 0.22 116.29
B Labour
For Laying (with
1 cutting) Rmt 1.00 12.00 12.00
2 Miscellaneous works man day 0.10 350.00 35.00 47
163.29
Add 2% towards Water & Electrcal charges 3.27
Add 15% contractor profit & over heads 24.49
TOTAL 191.04
Rate Per Rft 58.25
PROVIDING & LAYING OF GRANITE FLOORING IN 1:3 CEMENT MORTAR WITHOUT OVER HEADS
GRANITE FLOORING RATE WORKED OUT FOR 1 Sqm
3
SI.no Description Unit Qty Rate Amount
A Material
1 Granite Sqm 1.00 2690 2690
2 Cement Bag 0.28 300 84
3 Sand Cum 0.05 1765.5 88.275
White cement, joint
4 filler LS 20
5 Polythene Sheet Sqm 1.00 8 8
5 Wastage @ 5% Sqm 0.05 2690 134.5 3024.775
B Labour
1 For Laying Sqm 1.00 215 360
2 Miscellaneous works man day 0.10 150 15 375
3399.775
Add 3% towards Water & Electrcal charges 101.99325
Add 15% contractor profit & over heads 509.96625
TOTAL 4011.73
Rate Per Sft 372.84
PROVIDING & LAYING OF GRANITE SKIRTING IN 1:3 CEMENT MORTAR WITHOUT OVER HEADS
363.28
Add 3% towards Water & Electrcal charges 10.90
Add 15% contractor profit & over heads 54.49
TOTAL 428.67
Rate Per Rft 130.69
PROVIDING & LAYING OF ITALIAN MARBLE SLAB FLOORING IN 1:3 CEMENT MORTAR WITHOUT OVER HEADS
5
ITALIAN MARBLE SLAB FLOORING 20MM THICK RATE WORKED OUT FOR 1 Sqm
4549.58
Add 3% towards Water & Electrcal charges 136.48725
Add 15% contractor profit & over heads 682.43625
TOTAL 5368.50
Rate Per Sft 499.40
PROVIDING & LAYING OF ITALIAN MARBLE SKIRTING IN 1:3 CEMENT MORTAR WITHOUT OVER HEADS
6
ITALIAN MARBLE SKIRTING 100MM HIGH RATE WORKED OUT FOR 1 Rmt
A Material
1 Marble tile Sqm 0.10 3766 376.6
2 Cement Bag 0.028 300.00 8.4
3 Sand Cum 0.002 1765.50 3.531
4 Wastage @ 5% Sqm 0.005 376.60 1.883 390.414
B Labour
1 For Laying (with cutting) Rmt 1.00 66 66
2 Miscellaneous works man day 0.10 350 35 101
491.414
Add 3% towards Water & Electrcal charges 14.74
Add 15% contractor profit & over heads 73.71
TOTAL 579.87
Rate Per Rft 176.79
PROVIDING & LAYING OF GRANITE DADOING IN 1:4 CEMENT MORTAR WITHOUT OVER HEADS
13
GRANITE DADOING RATE WORKED OUT FOR 1 Sqm
A Material
1 Granite Sqm 1.00 2690.00 2690.00
2 Cement Bag 0.27 300.00 81.00
3 Sand Cum 0.02 1765.50 35.31
4 White cement, joint filler LS 20.00
5 Wastage @ 5% Sqm 0.05 2690.00 134.50
2960.81
B Labour
1 For Laying (with cutting) Sqm 1.00 360.00 360.00
2 Miscellaneous works man day 0.10 350.00 35.00
395.00
3355.81
Add 1.5% towards Water & Electrcal charges 50.34
Add 15% contractor profit & over heads 503.3715
TOTAL 3909.52
Rate Per Sft 363.68
PROVIDING & LAYING OF CERAMIC TILE DADOING IN 1:4 CEMENT MORTAR WITHOUT OVER HEADS
14
CERAMIC TILE DADOING RATE WORKED OUT FOR 1 Sqm
A Material
1 Ceramic tile Sqm 1.00 430.40 430.40
2 Cement Bag 0.27 27.00 7.29
3 Sand Cum 0.02 14124.00 282.48
4 White cement, joint filler LS 20.00
5 Wastage @ 5% Sqm 0.05 430.40 21.52
761.69
B Labour
1 For Laying (with cutting) Sqm 1.00 120.00 120.00
2 Miscellaneous works man day 0.10 350.00 35.00
155.00
916.69
Add 1.5% towards Water & Electrcal charges 13.75
Add 15% contractor profit & over heads 137.5035
TOTAL 1067.94
Rate Per Sft 99.34
7
7 BLACK GRANITE COUNTER
Unit - 100Sft
(a) Material
1. 40mm Polished BlackSft 100.00 300.00 30000.00
2. For Block Oxide @ 1% 300.00
(b) Labour
1. For Cutting, Making
Holes For Wash Basin
& Fixing Sft 100.00 36.00 3600.00
33900.00
( c) Misc..
1. Add For Water Chages @ 1.5% 508.5
2. Add For Wastages @ 5% 1695
3. Add For Contracto's Profit & Overheads @ 15% 5085
Total 41188.50
Rate Per Sft 411.89
Rate Per Sqm 4427.76
10
Grano flooring 40mm thick with Floating Coat of neat Cement 1:1
1/2: 3
Per 10sqm.
Materials
Stone aggregate cum 0.282 847.44 238.97808
20mm thick
Stone aggregate cum 0.094 847.44 79.65936
12mm thick
Coarse sand cum 0.188 1765.5 331.914
Cement for concreting bags 3.25 300 975
Cement for top layer bags 0.45 300 135
Labour
Foreman No 0.15 400 60
Mason No 1.5 350 525
Belder No 1.5 220 330
Coolie No 1.5 200 300
Waterman No 0.15 200 30
Total (A) 3005.55
Add for Mixer, Pumps 75.14
for water etc @ 2.5%
(A)
Add for Sundries and 90.17
contingencies @ 3 %
(A)
Total (B) 3170.86
Add for OH and CP @ 634.17
20% of (B)
Cost for 40mm thick Sqm 3805.03
Grano flooring with
Floating Coat of neat
Cement concrete 1:1
1/2: 3
Rate per sft. Sft 35.36 Rs
1
HARD WOOD FLOORING
PROVIDING & LAYING OF IMPORTED VETRIFIED TILE FLOORING IN 1:4 CEMENT MORTAR WITHOUT OVERHEADS
IMPORTED VETRIFIED TILE RATE FLOORING RATE WORKED OUT FOR 1 Sqm
8
SI.no Description Unit Qty Rate Amount
A Material
1 Ceramic tile Sqm 1.00 1076.00 1076.00
2 cement Bag 0.225 300.00 67.50
3 Sand Cum 0.05 1765.50 88.28
White cement, joint
4 filler LS 20.00
5 Wastage @ 5% Sqm 0.05 1076.00 53.80 1305.58
B Labour
1 For Laying
Foreman Each 0.08 400 32
Mason Each 0.45 350 157.5
MC Each 0.45 200 90
Waterman Each 0.05 200 10
1610.08
Add 1.5% towards Water & Electrical Charges 24.15
Add 15% Contractor profits & over heads 241.51
TOTAL 1875.74
Rate Per Sft 174.49
A Material
1 20mm Sand stone Sqm 1.00 1614.00 1614.00
2 Cement Bag 0.27 300.00 81.00
3 Sand Cum 0.02 1765.50 35.31
4 White cement, joint filler LS 20.00
5 Wastage @ 5% Sqm 0.05 1614.00 80.70
1831.01
B Labour
1 For Laying (with cutting) Sqm 1.00 250.00 250.00
2 Miscellaneous works man day 0.10 150.00 15.00
265.00
2096.01
Add 1.5% towards Water & Electrcal charges 31.44
Add 15% contractor profit & over heads 314.4015
TOTAL 2441.85
Rate Per Sft 227.15
PROVIDING & LAYING OF GRANITE STAIR CASE IN 1:4 CEMENT MORTAR WITHOUT OVER HEADS
A Material
1 Granite Sqm 1.00 2690.00 2690.00
2 Cement Bag 0.27 300.00 81.00
3 Sand Cum 0.02 1765.50 35.31
4 White cement, joint filler LS 20.00
5 Wastage @ 5% Sqm 0.05 2690.00 134.50
2960.81
B Labour
1 For Laying (with cutting) Sqm 1.00 450.00 450.00
2 Miscellaneous works man day 0.10 150.00 15.00
465.00
3425.81
Add 1.5% towards Water & Electrcal charges 51.39
Add 15% contractor profit & over heads 513.8715
TOTAL 3991.07
Rate Per Sft 371.26
1 JOINERY - DOOR 3'9" x 7'0" Qty Unit Rate in Rs Amount in Rs
SIZE= 1.2m x 2.15m
Frame making & shutter making 1.05*2.15 2.2575 Sqm 2000 4515.00
Frame making & shutter making 1.05*2.15 2.2575 Sqm 400 903.00
2.75+2.75+(7*2.15
TW Frame ) 20.55*0.1*0.05*1.05 0.108 Cum 105930.00 11440.44
2.75*2.15*0.4*0.02
TW French door shutter 5*1.05 0.062 0.062 Cum 105930.00 6567.66