Description Uom Quantity Rate Amount Dismantle Construction of in Side Wall

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

Description Uom Quantity Rate Amount

Dismantle
Labur No's 6 400 2400
Construction Of In Side Wall
Bricks No's 8600 7 60200
Cement Kg 1084 8 8676
Sand Mt 1.60 1125 1795
Plastering Cement Kg 110 8 880
Labur Sft 285.459 24 6851
Construction Of Out Side Items
Cement Kg 3500 8 28000
Sand Mt 2.54 1125 2853
Labur Sft 805.14 24 19323
Flore Filling (Dust) Cum 7.24 650 4706
Flore Filling (CC) Sqm 67.87 10 679
Cement Cum 1628 8 13024
Sand Mt 3.028 1125 3407
Aggregate Mt 5.331 320 1706
Labur No's 6 400 2400
Mason No's 1 600 600
Rcc Wall
Cement Cum 1260 8 10080
Sand Mt 2.3436 1125 2637
Aggregate Mt 4.1256 320 1320
Labur No's 4 400 1600
Mason No's 1 600 600
Centring Sqm 39 250 9750
183486
Paint 15000
Lighting 5000
203486
Length Width Height
Brick Size
0.19 0.09 0.09

Length Height Thickness


Brick Work
9.8 1.95 0.9
Cement Sand SUM
Mortar Ratio
1 6 7
Mortar Thickness 0.01

ALL OUTPUT DATA


Volume of 1 Brick Without Mortar 0.001539
Volume of 1 Brick With Mortar 0.002
Volume of Brick wall 17.199
Number Of Brick Required 8600
Wet Dry
Mortar Required 3.9636 5.271588

Cement Quantity Sand Quantity


Bags CUM KG CUM CFT
22 0.753084 1084.441 4.518504 159.5484

Sl.No
1
2
3
4

Sl.No
1
2
Plaster Quantity
Description Quantity Unit
Proportion of Mortor 1 6
Area of Plastering 74.8 sq.m
Thickness of plastering 70 mm
Volume of plater 5.236 cu.m.

8.3776 cu.m.
Adding 50% for voids and 10% for unevenness Dry Mortar =
Cement 1.1968 cu.m
Cement bags 35 numbers
7.181 cu.m
Sand
2.54 brass

Cost of Material
Description 0.09 Unit Rate Total Cost
Cement 35 number 400 14000
Sand 7.181 cu.m 4000 28723
Total Cost of Materials 42723