AS 11 - Construction Contracts
AS 11 - Construction Contracts
AS 11 - Construction Contracts
Duration of projects spans beyond one year and project work usually takes more than one
accounting year to get complete. it raises the issue for the recognition of revenue and costs
related to construction contract in the relevant period in which construction work was carried
out.
1. Construction Contract:
Contract entered for the construction of an individual asset or a group of assets that are inter-
dependent with respect to their design, function or operational use (airport and runway).
It includes contracts
2. Types
Segmenting:
For contracts involving group of assets, each asset is treated as a separate contract if:
(a) Each asset was subject to a separate proposals by contractor and
(b) The terms of each asset was negotiated separately and both the contractor and customer have
option to accept or reject the contract relating to each asset in the group of assets
(c) Each asset has identifiable revenue and cost on individual basis.
Combining:
For the contract involving group of assets, the contract as whole will be treated as a single
contract if:
(a) The contractor and customer both have a single contract for the construction of group of asset
(b) The assets in the group of assets are interdependent in terms of their design or use, and seems
to be the components of a single contract in commercial substance
(c) The parts of the whole contract will be completed in a continuous manner.
Amendment into Contract:
Construction contracts include an amendment clause for both contractor and customer. If the
customer chooses to amend the original contract in order to include the construction of an
additional asset. In such situation the additional asset will be taken as a separate contract if:
(a) The additional asset is materially different in terms of its design or function from the asset or
group of assets under the original contract;
(b) The contract price for the additional asset is subject to separate negotiation irrespective of the
original contract.
Contract Revenue
(1) Contract price decided as per the terms of the contract and
(2) Any revenue in respect of variations in the original contract work required by customer, if it
is probable:
(a) That variation and related amount of revenue will be approved by the customer; and
(b) Revenue related to variation is reliably measurable.
(a) That the contractor will meet the specified performance standards; and
(b) Revenue in respect of the incentive payment is reliably measurable.
Contract Costs
(2) Common cost attributable to contract on reasonable and consistent basis which includes:
(3) Other costs which is specifically related to the contract as per the contractual terms.
Note:
The costs that are incurred in securing the contract are also the part of the cost of the contract if:
(a) It is identifiable, and reliably measurable;
(b) the contract is obtained.
The recognition of contract revenue and cost depends upon the outcome of the contract.
The contract revenue and costs shall be recognized in statement of profit & loss, on the basis of
“stage of completion” of the contract, measured at the end of the accounting period.
Is measured at the end of reporting period using one of the following methods:
Survey Method:
Note:
a) If there is uncertainty for the recovery of the amount which has previously been recorded as
contract revenue in statement of profit or loss, then the such irrecoverable amount will be
recorded as an expense in statement of profit or loss, instead of adjustment to recognized
contract revenue
b) If in a particular situation, it is probable that entity will not be able, even to recover its
allowable cost incurred on the contract, then such cost should be recognized in statement of
profit or loss in the relevant period
If for a particular construction contract, the cost of performance of the contract exceeds the
contract revenue, it will be treated as onerous contract. In such circumstance entity is required to
recognize the expected loss in statement of profit or loss, in the period in which contract becomes
onerous.
Disclosure
3) The entity will present the following in the statement of financial position:
(a) Amount due from customer related to contract as an asset; and
(b) Amount due to customers related to contract as a liability.
4) The disclosure shall also include any contingent liabilities or assets as per requirements of
IAS 37 in respect of any contingent liabilities or asset which may arise from events as penalties
or expected losses.
Revenue x
Cost (x)
Profit x
- Rectification Cost of Error by Contractor (x)
- Provision for Onerous Contract (x)
Profit for the year x
Worked Examples
Example 1: (Contracts for which outcome is reliably measurable)
AB LTD is an entity engages in construction business & prepares its financial records to 31
December every year. In the current year ended 31December 2013 the company started two
contracts expected to take more than one year. Following are the extracts relating to each
contract at 31 December 2013:
Contract 1 2
$'000 $'000
Total contract price 11,000 2,400
Estimated total cost of contract at 01Jan-2013 8,000 1,800
Estimated total cost at 31 Dec 2013 8,000 2,500
Agreed work completed at 31 Dec 2013 6,600 1,680
Progress billings invoiced 31 Dec 2013 6,000 1,760
Costs incurred to 31 December 2013 7,800 1,440
The entity calculates the percentage of completion as the agreed value of work completed to
date, to the total contract price.
Required:
Prepare extracts of financial statements for the year ended 31 December 2013
Solution:
1 2
Contract
$’000 $’000
Total Contract Revenue 11,000 2,400
Work Certified at 31 Dec 2013 6,600 1,680
Percentage of Completion (6,600 / 11,000)*100 = (1,680 / 2,400)*100 =
*100 60% 70%
$’000 $’000
Total Contract Revenue 11,000 2,400
Total Contract Cost (8,000) (2,500)
Estimated Total Profit 3,000 (100)
$’000 $’000
Revenue 6,600 1,680
Cost (4,800) (1,750)
Profit/ (Loss) 1,800 (70)
- Rectification Cost of Error by Contractor - -
- Provision for Onerous Cont. (100-30) Remaining loss - (30)
Profit/ (Loss) for the year 1,800 (100)
$’000 $’000
Cost to date 7,800 1,440
Profit / (loss) to date 1,800 (100)
- Progress Billings (6,000) (1,760)
Due from / (to) 3,600 (420)
AB LTD is an entity engages in construction business. It started a contract for the construction of
a school building for one of its client, spanning 2 years. The price of the contract was agreed to
be $4 million.
The contract was started on 01, January 2013 but unfortunately construction material prices
started increasing materially from last few months after the start of the contract, due to
unforeseen reason.
AB LTD has intimated the customer for the increase in material price and requested for
compensation of additional costs, but yet, the entity is unsure about the compensation of the
additional costs.
Therefore, outcome of the contract is not reliably measurable at the end of the first accounting
period 31-12-2013, as to whether the contract will be profitable or not.
Following extracts are available from the records of AB LTD related to this contract at the first
year ended 31-12-2013:
$’000
Contract Price 4,000
Cost incurred to Date 2,400
Cost likely to be recoverable 2,000
Progress billings to customer 1,800
Required:
Prepare extracts of financial statements for the year ended 31-12-2013.
Solution:
As the outcome of the contract is not reliably measurable therefore, the contract revenue will be
recognized only upto the extent of costs incurred on the contract to date, to the extent it is
recoverable.
$’000
Revenue to date (up to extent, which is recoverable) 2,000
Cost to date (2,400)
Loss to date (400)