Sobremonte, Regine I. (MT-RSW-02)
Sobremonte, Regine I. (MT-RSW-02)
Sobremonte, Regine I. (MT-RSW-02)
PILE FOUNDATION beneath spread and piled foundations (a) Spread foundation (b)
Single pile
Pile foundations are deep foundations. They are formed by long, 2. FRICTION PILE
slender, columnar elements typically made from steel or reinforced
concrete, or sometimes timber. A foundation is described as piled when its This type of pile utilizes
depth is more than three times breadth (ref. Atkinson, 2007). the frictional resistance
force between
Although the use of pile foundation cost more than shallow 5 foundation, it the pile surface and
is combination of skin friction essential to be employed for some conditions. adjacent soil to transfer
Such Conditions Are Enumerated Below: the superstructure load.
Depending on the subsoil
strata condition,
resistance force due
to friction can develop in
a definite pile length of
on the full length.
5. ANCHOR PILE
Are piles used to resist uplift or inclined tensile? forces in the
surrounding ground. They are used as: (1)
Reaction piles for pile testing. (2) Piles to resist uplift forces from
flotation.
Fig.16. Timber Piles
Fig.17. Protecting timber piles from decay (a) By precast concrete upper
Fig.13. Fender pile
section above water level (b) By extending pile cap below water level.
7. BETTER PILE
They are used for resist large horizontal forces or inclined
forces.
Fig.18. Protecting timber piles from splitting during driving (a) Protecting head
by mild steel hoop (b) Protecting toe by cast steel point.
8. SHEET PILE
They are used as bulk heads or as impervious cutoff to reduce
seepage and uplift under hydraulic structures.
2. CONCRETE PILES Piles are built by making a hole in the ground and then filling it with
concrete. These piles may be divided to two: (a) cased (b)
uncased. Both types may have a pedestal at the bottom
▪ BULB PILES
3. STEEL PILES
Are either pipe pile or rolled section steel H- section piles.
Pipe pile can be driven into the ground with their ends open or Fig.32. Different stages in construction of composite piles
close. Wide-flange and I-section steel beams can also be used
as piles. H-section piles are usually preferred because their web
and flange thickness are equal. 4. SAND PILES
These piles are formed by making hole in ground and fill with
the sand and well rammed. The sand to be used should be moist
at time of placing. Bore hole diameter usually 30 cm. length of
sand pile is kept about 12 times its diameter. The top of sand pile
is filled with concrete. Sand pile are placed at 2 to 3 m spacing.
Load test should be carried out determining the bearing
capacity of sand pile. Properly compacted sand pile can carry
load up to 100 tone/m2 or more.
5. JACKED PILE
These piles are jacked into the ground by applying a
Fig.34. Placement of Fig.35. Installation of Fig.36. Repetition of
Pile
downward force by a hydraulic jack.
Pile Process