Time Cost Trade-Off
Time Cost Trade-Off
Time Cost Trade-Off
Sources:
Gray Clifford F., Larson Erik W. , Project management: the
managerial process, McGraw-Hill
Gido Jack, Clements James P. , Successful Project
management, Cengage
Mantel S., Meredith J., Shafer S., Project management core
textbook, Wiley
1
Time-Cost Trade-Off
Network Compression :
2
Time-Cost Trade-Off
Note:
The processes, methodologies and sequencing adopted
while developing the initial estimates & first schedule are
decided on ‘stand-alone’ basis i.e. each activity
considered individually on its own.
Crunching of Activities
Activity duration is estimated on the basis of the basic
relationship between “Work”, “Resources required”
& Time .
Hence for the given quantum of work, the estimated
duration can be reduced by increasing the
resourced deployed on the job.
e.g. The work of digging a trench for underground pipe
line if carried out manually may be equivalent to 20 man-
days. Hence, a team of 4 workers can finish the job in 5 days.
if we increase the workers to 5, the same work will get done
5
in 4 days.
Time-Cost Trade-Off
This process of reducing the activity duration by
increasing the resources is known as crunching.
While crunching the activity, the additional resources may either
be hired extra or are obtained by reducing the resource allocation
on some non-critical activity scheduled in parallel to the critical
activity.
The first alternative will reduce the total floats available on
the non-critical activities without changing their estimated
durations by the amount of crunching while the second
alternative will also increase the duration of the non-critical
activity by stretching them.
6
Time-Cost Trade-Off
7
Time-Cost Trade-Off
8
Time-Cost Trade-Off
Direct costs:
The direct costs refer to the cost of direct materials and
direct labour utilized in performing the project activities.
C Total Costs
O
S Direct
T Costs
Indirect
Costs
Crashing of Activities:
The activity duration is initially estimated on the basis
of application of normal process, normal methodologies
and normal work practices and skill sets that would
complete the activity in the most economical manner.
13
Time-Cost Trade-Off
Total Cost
P
R
O
J
E Direct Cost
C
T
Minimum Indirect Costs
C Normal
Possible
O Duration
Duration
S Optimum Duration,
T Minimum Cost
PROJECT DURATION
17
Time-Cost Trade-Off
C Normal
O
S
T
ACTIVITY DURATION
18
Time-Cost Trade-Off
Relationship between cost and time in Crashing:
The extra direct cost to be incurred per unit time of crashing is
indicated by the slope of the cost curve and is known as cost
slope. The cost slope can be calculated as under:
23
Time-Cost Trade-Off
(b) Additional critical path(s) get created due to
successive reduction of floats available on non-critical
activities:
Any further reduction in project duration would be possible
only by crashing activities on all the critical paths
simultaneously.
Cost of crashing would therefore be the total of cost slopes of
all activities to be crashed.
If this total is less than the indirect cost per unit time, crashing
can be continued till reaching the cost-sum of activities to be
crashed again gets higher than the indirect cost per unit time.
24
Time-Cost Trade-Off
25
Time-Cost Trade-Off
Illustration:
The table below gives the activity relationships for a small
project having eight activities.
The estimated activity durations are given under two conditions;
one by using the normal method and the other by using the
alternate method taking shorter time.
The details of direct costs for each activity using both of the
method are also given.
The indirect costs relating to site management etc. are Rs.
3,500/- per day. Based on the information, we have to find the
minimum cost schedule.
26
Time-Cost Trade-Off
DURATION COST
ACTIVITY PREDECESSORS (Days) COST Rs. SLOPE
27
H D,E 4 1 12000 18000 2000
Time-Cost Trade-Off
Adding all the direct costs for activities being performed by
normal method, the total direct cost (Normal) is Rs. 75,000.
To find the indirect cost, we have to find the normal duration
for the project.
In the above network, different paths can be traced with their
normal and crash durations:
P1 - A – B – D – H = 16 / 8
P2 - A – B – E – H = 12 / 6
P3 - A – B – E – G = 12 / 7
P4 - A – C – E – H = 11 / 5
P5 - A – C – E – G = 11 / 6
28
P6 - A – C – F – G = 13 / 7
Time-Cost Trade-Off
Therefore, Path P1 is the Critical Path and the Project Duration
is 16 days by using normal processes.
The total indirect cost @ Rs. 3,500 per day for 16 days will be
Rs. 56,000.
Therefore the total project cost will be Rs. 75,000 + Rs. 56,000
= Rs. 131,000
Even after crashing activities, the minimum duration would be 8
days. However, we have to find out if reducing duration to 8 days
will be economical.
Hence crashing is carried out for the critical activities
in order of their respective cost slopes one by one and
29
effect of crashing on total cost is calculated.
Time-Cost Trade-Off
30
Time-Cost Trade-Off
STEP CRASH BY P1 P2 P3 P4 P5 P6 DIRECT INDIRECT TOTAL
ACTIVITY DAYS COST COST COST
31
Various Steps in crashing
Time-Cost Trade-Off
32
Time-Cost Trade-Off
Thank You
33