Tender 3926 K
Tender 3926 K
Tender 3926 K
NAME OF WORK
Percentage quoted :
Amount of Contract :
Date of Commencement :
The EMD of 38,200/- shall be paid via Online mode using NEFT /RTGS or paymentgateway
mode only.
In case of EMD exemption, valid E.M.D. Exemption Certificate shall be uploaded at the time
of submission.
Total Security Deposit 4% (four percent) Rs.1,52,700.00 (50% in cash at the time of
Agreement and 50% from R.A.bills).
Time sitpulated for completion 6(Six) Calendar months which will include the monsoon
period.
Sealed online B-1 tenders for the following work are invited by the Executive Engineer, INTRGRATED
UNIT(M) P.W NAGPUR from the contractors Registered with Government of Maharashtra Public Work
Department in appropriate class.
E- TENDER SCHEDULE
(1) Tender form, conditions of contract, specifications and contract drawings can be downloaded
from the e-tendering portal of Public Works Department, Government of Maharashtra i.e.
https://pwd.maharashtra.etenders.in. Further information regarding the work can be obtained
from the above office
(2) The fees of tender document amounting Rs. 1,000 (Rs. One thousand ) through payment
gateway. The fees of tender document will be non refundable.
(3) The offer of the Contractor shall remain valid for acceptance for a minimum period of 90
days from the date fixed for opening of Envelope No. 2 ( quoted offer) and thereafter until it
is withdrawn by the Contractor by notice in writing duly addressed to the authority
opening the tender and sent by Registered Post Acknowledgement Due.
(4) The tender notice shall form a part of the contract agreement.
(5) If the tenderer is a firm or company then they shall in their forwarding letter mention the
names of all the partners of the firm or the company (as the case may be) and the name
of the partner who holds the power o f attorney if any, authorizing him to conduct
transaction on behalf of the Firm or Company.
(6) Right is reserved to revise or amend the contract documents fully or part thereof
prior to the date notified for the receipt of tender. Such deviations/ amendments if
any, shall be communicated in the form of corrigendum or by a letter as may be considered
suitable. The above revision will not vitiate the tendering process.
(11) Tenders which do not fulfill all or any conditions or are incomplete in any
respect are liable to summarily rejection.
The Bid Data that is prepared online is required to be encrypted and the hash value of the Bid
Data is required to be signed electronically using a Digital Certificate (Class-II or Class-III). This is
required to maintain the security of the Bid Data and also to establish the identity of the Contractor
transacting on the System.
The Digital Certificates are issued by an approved Certifying Authority authorized by the
Controller of Certifying Authorities of Government of India through their Authorized Representatives
upon receipt of documents required to obtain a Digital Certificate.
Bid data / information for a particular Tender may be submitted only using the Digital Certificate which
is used to encrypt the data / information and sign the hash value during the Bid Preparation and Hash
Submission stage. In case during the process of preparing and submitting a Bid for a particular Tender,
the Contractor loses his / her Digital Signature Certificate (i.e. due to virus attack, hardware problem,
operating system problem); he / she may not be able to submit the Bid online. Hence, the Users are
The Service is provided in order to facilitate payment of Tender Fees/Earnest Money Deposit online.
The Merchant or the Payment Gateway Service Provider(s) do not make any representation of any
kind, express or implied, as to the operation of the Payment Gateway other than what is specified in
the Website for this purpose. By accepting/ agreeing to these Terms and Conditions, the User
expressly agrees that his/ her use of the aforesaid online payment service is entirely at own risk and
responsibility of the User
4 TENDERING PROCEDURE : -
Issue of Blank Tender Forms.
Tender Forms can be purchased from the e-Tendering Portal of Public Works Department,
Government of Maharashtra i.e. https://pwd.maharashtra.etenders.in after paying Tender Fees
via online mode as per the Tender Schedule.
4.1 EARNEST MONEY :-
i) Earnest money of minimum Rs. 38,200 shall be paid online using NEFT / RTG or payment
gateway mode OR If exemption certificate is available then valid certificate of exemption
from payment of earnest money shall be scanned from original copy. Earnest Money in the
form of cheques or any other form except above will not be accepted.
ii) Tenderer of those who do not deposit earnest money in one of the above acceptable form
shall be summarily rejected.
iii) The amount of earnest money will be refunded to the unsuccessful tenderers on deciding
about the acceptance or otherwise of the tender or on lapsing of the validity period, whichever
is earlier. In case of successful tenderer, it will be refunded on his payment of initial Security
Contractor No of Correction Executive Engineer 13
Deposit will be adjusted towards a part of security deposit to be paid after awarding of the
work. If successful tenderer does not pay the Security Deposit in the prescribed time limit,
and complete the agreement bond, his earnest money deposit will be forfeited to the
Government.
iv) In case of Joint Venture, Earnest money Exemption certificate in individual capacity will not be
accepted. Earnest money shall be paid via online using NEFT/RTGS or payment gateway
mode. The Security Deposit, additional security deposit etc. in the form of T.D.R./F.D.R.
issued in the name of Joint Venture Company drawn by scheduled bank having branches in
Maharashtra and pledged, in the name of Executive Engineer, INTRGRATED UNIT(M) P.W
NAGPUR for the period of one year will be considered.
4.2.2 Deleted
4.2.3 Deleted
4.2.4 All tenderers are cautioned that tenders containing any deviation from the contractual
terms and conditions, specifications or other requirements and conditional tenders will be
treated as non responsive.
4.2.5 Tenderers should have valid Class II / III Digital Signature Certificate (DSC) obtained from
any Certifying Authorities. In case of requirement of DSC, interested Bidders should
go to http://maharashtra.etenders.in/mah/DigitaICertLasp and follow the procedure mentioned in
the document 'Procedure for application of Digital Certificate'.
4.2.6 The Tenderers have to make a payment of Rs 1054/- online as service charges
for the use of Electronic Tendering during Online Bid Data Decryption and Re- encryption
stage of the Tender.
4.2.7 For any assistance on the use of Electronic Tendering System, the Users may call the below
numbers:
Landline No. - 020 - 2531 5555 / 56
Landline No. - 022 - 2661 1117 (Ext 25 / 26)
4.2.8 Tenderers should install the Mandatory Components available on the Home
Page of http://maharashtra.etenders.in under the section 'Mandatory Components' and make
the necessary Browser Settings provided under section 'Internet Explorer Settings'
4.2.9 Guidelines to Bidders on the operations of Electronic Tendering System of Public Works
5. SUBMISSION OF TENDER:-
Refer to Section 'Guidelines to Bidders on the operations of Electronic Tendering System
of Public Works Department'
6. OPENING OF TENDER :-
On the date specified in the Tender Schedule following procedure will be adopted.
Offer to be submitted online. The t enderer shall enter his percentage rates in words
and figures " below / above" . In case there is a difference between percentage
written in figures and words, the lower offer will be taken as final.
The contractor shall quote th eir of f er as per details given in the main tender and also
based on the detailed set of conditions issued/Additional stipulations made by the
Department as informed to him by a letter from Chief Engineer/Superintending Engineer
after Pre-Tender Conference. Tenderer quote their offer only unconditional.
7 SECURITY DEPOSIT :
The successful tenderer shall have to pay half the security deposit in approved security form
(preferably in the form of National Saving Certificate) or in cash or in the form of Bank
Guarantee (in the form as prescribed by Government) from any Schedule Bank or Nationalized
Bank and balance Security Deposit will be recoverable through the bills at the percentage as
shown in item (s) of the Memorandum in printed B-1 form or as may be decided by the
Executive Engineer during course of execution of the work looking to the position and
circumstances that may prevail, whose orders will be final and binding on the contractor.
The security deposit for the due performance of the contract shall be as detailed in the Tender
Documents elsewhere. Fifty percent of the security deposit will have to be deposited within ten
days (including Government holidays) of the acceptance of the tender and the remaining fifty
exemption certificate is available then scanned copy of valid certificate of exemption from
payment of Earnest Money shall be uploaded. Additional Security deposit (if required )
then scanned copy of FDR/TDR shall be uploaded online.
iii)
iv) List of Plants & machinery readily available with the tenderer for use on this Work and
list of machinery proposed to be utilized on this work but not readily available and manner in
which it is proposed to be procured (Information to be given in Statement No. II)
v) Details of work of similar type and magnitude carried out by the tenderer during last three year
(Information to be given in Statement No. III)
vi) Details of Technical Personnel on the rolls of the tenderer. (Information to be given in
Statement No. IV)
vii) Undertaking for deployment for machinery (Self declaration) in prescribed format.
(Information to be given in Form No. I).
viii) Self declaration in respect of genuineness of documents contained in Envelope No. 1 in
prescribed Profarma. (Information to be given in Form No. II).
ix) Registered Partnership Deed, Memorandum of Articles of Association, if the tenderer
is a Partnership Firm. Power of Attorney and Firm Registration Certificate if any.
x) Tender copy issued and-digitally signed by the department.
Contractor No of Correction Executive Engineer 19
Work Description
Scope of Work
1.Cleaning the site removing bushes, including removal of roots upto 20cm. Circumference and disposal of
above stuffs upto a lead of 10mtr. or as directed by Engineer-In-Charge.
2.Excavation for roadway in earth soil of all sorts sand, gravel or soft murum
3. Providing double under reamed piles of specified diameter with following grade of concrete
4 Excavation for foundation in earth, soils of all types, sand, gravel and soft murum,
5.Excavation for foundation in earth, soils of all types, sand, gravel and soft murum,
5 Providing soling using 80 mm size granite / quartzite / gneiss / trap metal in 15 cm. layer
6 Providing and laying in situ, cement concrete M-10Grade /(1:3:6) of trap metal for foundation and bedding
7 .Providing and laying in situ cement concrete of M-20 grade of trapmetal for R.C.C. work in foundations
like raft, grillages, strip foundations and footings of R.C.C.columns and steel stanchions I
8. Providing and laying 50 mm thick layer in cement mortar 1:8 below plinth beam including floating,
watering, curing and leveling and ramming the bed if necessary before laying the layer etc. complete.
9. Providing and casting in situ cement concrete of M-20 grade of trap metal for R.C.C. columns
10 Providing and casting in situ cement concrete of M-20 grade of trap metal for R.C.C. beams and lintels
11 Filling in plinth and floors with contractors approved material / murum / stone dust in 15 cm. to 20 cm.
layers including watering and compaction complete.( Including Royalty)
12 Providing Fly ash lime Brick masonry ( Bricks conforming to I.S.12894 : 1990 and of size 19 cm x 9 cm x
9 cm)in cement mortar 1:6 in super structure including striking joints, racking out joints watering and
scaffolding complete.
13 Providing and casting in situ cement concrete M-15 of trap/ granite/quartzite/gneiss metal for coping to
plinth or parapet, moulded or chamfered
14 Providing and casting in situ cement concrete of M-15 grade of trap metal for plain or molded sills,
cornice, jambs, block in course, or architraves
15 Providing and fixing in position reinforcement of various diameters for R.C.C. pile caps, footings,
foundations, slabs, beams and columns, canopies, staircases, newels, chajjas, lintels, pardies, coping, fins,
arches etc.
16 Providing expansion joints with 25 mm thick bituminous pad as per detailed drawings.
17 Providing sand faced plaster for external portion in cement mortar using Kharsalia / Kasaba or similar
type of sand,
18 Providing and applying three coats of water proof cement paint of approved manufacture and of
approved colour to new plastered surfaces
19 Providing and Fixing UPVC pipes of 110 mm diameter and required length for relieving water pressure
stone filter as directed complete.(For relieving water pressure in raft)
20 Providing internal cement plaster 6 mm thick in a single coat in cement mortar 1:3 to concrete surface in
all positions including scaffolding and curing. Providing groove at joint of B.B.Masonry and concrete
members complete.
21 Providing and fabricating structural steel work in rolled sections like joists, channels, angles, tees etc. as
per detailed design and drawings
22 Dismantling the R.C.C. work 1:2:4 and sorting out the materials such as steel etc. as directed and
stacking them within the specified lead as directed.
23 Dismantling brick masonry in lime or cement mortar and stacking the materials as directed with all leads,
lifts etc. complete.
24 Providing and fixing mild steel grill gate with angle iron frame 50 mm x 50 mm x 6 mm M.S. Pipe box
frame and other pipe 50 x 30 mm as per the detailed drawing including hinges, pivot blocks locking
arrangement welding, revetting with oil painting in three coats of approved colour shade.
25 Providing and casting in situ cement concrete of M-20 grade of trap / granite /quartzite /gneiss metal for
R.C.C slabs and landings as per detailed design and drawings including steel centering, plywood /steel
formwork, steel props, compaction, finishing uneven and honeycombed surface with C.M. 1:3 of sufficient
minimum thickness to give a smooth and even surface or roughening the surface if special finish is to be
26 provided and curing etc. complete. (Excluding reinforcement, including cover block) The Cement Mortar
1:3 plaster is considered for rendering uneven and honey combed surface only. Newly laid concrete shall be
covered by gunny bag, plastic, tarpaulin etc. (Wooden centering will not be allowed)
27 Supplying and fixing in position anodised extruded aluminium extruded section Two track sliding
windows upto 1.2 metre height, outer frame made from section of over all size 62 mm x 45 mm, bottom
28 Providing internal cement plaster 20mm thick in a single coat in cement mortar 1:4 to concrete, brick
surfaces in all positions including scaffolding and curing. Providing groove at joint of B.B.Masonry and
concrete members complete.
29 Providing internal cement plaster 12 mm thick in a single coat in cement mortar 1:4 to concrete or brick
surface in all positions including scaffolding and curing complete. Providing groove at joint of B.B.Masonry
and concrete members complete.
30 Providing and fixing 18 guage M.S. sheet door with frame work 40 x 40 x 6 mm M.S. Angle including
locking arrangements, hold fast including applying anticorrossive primer coat of red lead paint and 2 coats
of oil paint and 12mm square bar at bottom as per specification complete.
31 Providing and fixing mild steel grill work for windows, ventilators, etc. 20 kg/sqm as per drawing
including fixtures necessary welding and painting with one coat of anticorrosive paint and two coats of oil
painting complete.
32 Providing and applying washable Acrylic emulsion paint of approved colour and shade to surface in two
coats including scaffolding, preparing the surface to receive paint etc. complete.
33 Providing and laying cement concrete flooring 50 mm thick with 1:2:4 cement concrete
35 Providing and Laying concrete pipes of I.S.NP.2 class of required diameter in proper line, level and slope
36 Providing and fixing reinforced cement concrete cover of 7.5cm thick over manhole and inspection
chamber
37 Providing and fixing UPVC SOIL / VENT / WASTE SWR pipe of required diameter conforming to I.S.-
13592, and I.S.-4985
38 Providing and fixing mat finish stainless steel lettering of various heights as directed by engineer in
charge including material, labour, cleaning etc. complete.
39 Providing and filling in the foundation and plinth with sand of approved quality including watering,
compaction complete.
40 Transportation of material obtained from debris of various sorts including necessary excavation/ loosing
including loading, unloading and conveying and disposing as directed.
41 Providing and erecting 1.20 m. high chain link fencing with chain link having hole size 65 mm x 65 mm
(ii) In the event of his tender being accepted, subject to the provision of sub clause (iii) below,
the said amount of earnest money shall be appropriated towards the amount deposit payable
by him under condition of General Conditions of Contract.
(iii) If after submitting the tender, the contractor withdraws his offer or modifies the same or if
after the acceptance of his tender the contractor fails or neglects to furnish the balance of
security deposit, without prejudice to any other rights and powers of the Government
hereunder, or in law, Government shall be entitled to forfeit the full amount of the earnest
money deposited by him.
iv)In the event of his tender not being accepted, the amount of earnest money deposited by the
contractors shall, unless it is prior thereof forfeited under the provision of sub-clause (ii) above,
be refunded to him on his passing receipt therefore.
3) Receipt for payments made on account of any work, when executed by a firm, should also be
signed by all the partners. Except where the contractors are described in their tender as a firm,
in which case the receipts shall be signed in the name of the firm by one of the partners, or by
some other person having authority to give effectual receipts for the firm.
4) Any person who submits a tender shall fill up the usual printed form including the column of
estimated quantities stating at what rate he is willing to undertake all item of the work. Tenders
which propose any alteration in the work specified in the said form of invitation to tender, or in
the time allowed for carrying out the work or which contain any other conditions of any sort, will
be liable for rejection. No single tender shall include more than one work, but contractors who
(f) Give schedule where (f) Time allowed for the work from date of written order to
necessary , showing dates commence is 6(Six) months including monsoon should this
by which various items to
be completed. tender be accepted.
Contractor
Signature of
Contractor before (Address)
submission of tender.
Dated the ______________day of __________ 2015
Witness
Signature of witness
to Contractor’s (Address)
Signature. Dated the _______________day of __________ 2015
Executive Engineer
Integrated Unit (M) P.W Nagpur
All compensation or other sum of money payable by the contractor to government under
the terms of his contract may be deducted from or paid by the sale of sufficient part of his
security deposit or from the interest arising there from or from any sums which may be
due or may become due by Government to the contractor under any other contract or
transaction of any nature on any account whatsoever, and in the event of his security
deposit being reduced by reason of any such deduction or sale as aforesaid the contractor
shall within ten days there after make good in cash or Government securities endorsed as
aforesaid, any sums or sums which may have been deducted from or raised by sale of his
security deposits or may part thereof. The security deposit referred to, when paid in cash
may, at the cost of the depositor, be converted into interest bearing securities provided
that the depositor has expressly desired this in writing.
Action when Clause 3 : In any case in which under any clause or clauses of this contracts the
whole of contractor shall have rendered himself liable to pay compensation amounting to the whole
Security of his security deposit (whether paid in one sum or deducted by installments) or in the
Deposit is case of abandonment of the work owing to serious illness or death of the contractor or any
forfeited. other cause, the Executive Engineer on behalf of the Governor of Maharashtra shall have
power to adopt any of the following courses as he may deem best suited to the interest of
Government.
b) To carry out of work or any part of the work departmentally debiting the contractor with
the cost of the work, expenditure incurred on tools and plant, and charges on additional
supervisory staff including the cost of work charged establishment employed for getting
unexecuted part of the work completed and crediting him with the value of the work done
departmentally in all respects in the same manner and at the same rates as if it had been
carried out by the contractor under the terms of the contract. The certificate of the
Executive Engineer as to the cost of the work and other allied expenses so included and
the value of the work so done departmentally shall be final and conclusive against the
contractor.
c) To order that the work of the contractor be measured up and to take such part thereof
as shall be unexecuted out of his hands and to give it to another contractor to complete, in
which case all expenses incurred on advertisement for fixing a new contracting agency,
additional supervisory staff including the cost of work charged establishment and cost of
the work executed by the new contract agency will be debited to contractor and the value
of the work done or executed through the new contractor shall be credited to the
contractor in all respects and in the same manner and at the same rates as if it had been
carried out by the contractor under the terms of his contract. This certificate of the
Executive Engineer as to all the cost of the work and other expenses incurred as
aforesaid for or in getting the unexecuted work done by the new contractor and as to the
value of the work done by the new contractor and as to the value of the work so done
shall be final and conclusive against contractor.
In case the contract shall be rescinded under clause (a) above, the contractor shall
not be entitled to recover or be paid any sum for any work thereto actually performed by
him under this contract unless and until the Executive Engineer shall have certified in
writing the performance of such work and the amount payable to him in respect thereof he
shall only be entitled to be paid the amount so certified. In the event of either of the
courses referred to in clause (b) or (c) being adopted and the cost of the work executed
departmentally or through a new contractor and other allied expenses exceeding the value
of such work credited to the contractor, the amount of excess value shall be deducted
from any money due to the contractor by the Govt. under the contract or otherwise,
howsoever or from his security deposit or the sale proceeds thereof provided howsoever,
that the contractor shall have no claim against government even if certified value of the
work done departmentally or through a new contract except the certified cost of such work
and allied expenses provided always that whichever of the three courses mentioned in
clause (a) (b) or (c) is adopted by the Executive Engineer, the contractor shall have no
claim to compensation for any loss sustained by reason of him having no claim to
compensation for any materials, or entered into engagement or made any advance on
account of or with a view of the execution of the work or the performance of contract.
Action when Clause 4 : If the progress of any particular portion of the work is unsatisfactory the
process of Executive Engineer shall not with standing that the general progress of the work is
particular work satisfactory in accordance with clause 2 be entitled to take action under clause 3 (b) after
is giving the contractor 10 days notice in writing and the contractor will have no claim for
unsatisfactory compensation for any loss sustained by him owing to such action.
Payments Clause 8: No payment shall be made for any work estimated to cost less than Rs. One
on thousand till after the whole of the said work shall have been completed and a certificate
intermediate of completion given. But in the case of the works estimated to cost more than Rs. One
certificate to thousand, the contractor shall not submitting a monthly bill there off be entitled to receive
be regarded payment proportionate to the part of the work then approved and passed by the Engineer-
as advance. in-charge whose certificate of such approval and passing of the sum payable shall final
and conclusive against the contractor. All such intermediate payment shall be regarded as
payment by way of advance against the final payment only and not preclude the Engineer-
in-charge from requiring any bad, unsound, imperfect or unskillful work to be removed and
taken away and reconstructed or rejected, nor shall any such payment be considered as
an admission of the due performance of the contractor or any part thereof, in any respect
of the occurring of any claim, nor shall it conclude, determine or affect in any way the
powers of the Engineer-in-charge as to final settlement and adjustment of the accounts or
otherwise or in any other way vary or affect the contract. The final bill shall be submitted
by the Contractor within one months of the date fixed for the completion of the work
otherwise the Engineer-in-charge’s certificate of the measurement and of the total amount
payable for the work shall be final and binding on all parties.
Payment at Clause 9: The rates for several items of work estimated to cost more than Rs. One
reduced rates thousand agreed to within shall be valid only when the item concerned is accepted as
on account of having been completed fully in accordance with the sanctioned specifications. In case
items of work where the items of work are not accepted as so completed the Engineer-in-charge may
not accepted make payment on account of such items at such reduced rates as he may consider
as completed reasonable in preparation of final or on account bills.
to be at the
discretion of
the Engineer
in charge.
Bill to be Clause 10 : A bill shall be submitted by the contractor each month on or before the date
submitted fixed by the Engineer-in-charge for all work executed submitted in the previous month,
monthly and the Engineer-in-charge shall take or cause to be taken the requisite measurement for
the purpose of having the same verified and the claim so far as it is admissible shall be
adjusted, if possible within ten days from the presentation of the bill. If the contractor does
not submit the bill within time fixed as aforesaid, the Engineer-in-charge may depute a
subordinate to measure up the said work in the presence of the contractor or his duly
authorised agent whose counter signature to the measurement list shall be sufficient
warrant and the Engineer-in-charge may prepare a bill from such list which shall be
binding on the contractor in all respects.
Stores Clause 12: If the specification or estimate of the work provides for the use of any special
supplied by description of materials to be supplied from the P.W.D. store or if it is required that the
Government contractor shall use certain stores to be provided by the Engineer-in-charge (such material
. and stores, and the prices to be charged therefore as hereinafter mentioned being so far
as practicable for the convenience of the contractor but not so in any way to control the
meaning or effect of this construction specified in the schedule or memorandum hereto
annexed) the contractor shall be supplied with such materials and stores as may be
required from time to time to be used by him for the purpose of the construction only, and
values of the full quantity of materials and stores as supplied shall be set off or reduced
from any sums then due, or here after to become due to the contractor under the contract
or otherwise or from the security deposits, or the proceeds of sale thereof, if the deposit is
held in Government, and shall on no account be removed from the site of the work and
shall at all times be open to inspection by the Engineer-in-charge. Any such material
unused and is perfectly in good condition at the time of completion or determination of the
contract shall be returned to the Public Works Department stores, if the Engineer-in-
charge so requires by a notice in writing given under his hand, but the contractor shall not
be entitled to return any such materials except with such consent and he shall have no
claim for compensation on account of any such material supplied to him as aforesaid but
remaining unused by him or for any wastage into damage thereto.
Store Clause 12 A : All store of contractor material such as cement ,steel Bitumen etc
Material Supplied by the contractor at his own cost should be kept by the contractor under lock and
key and will be accessible for inspection by the Executive Engineer or his agent at all
times
Work to be Clause 13 : The contractor shall execute the whole and every part of the work like
executed in manner and both as regards materials and every other respect in strict accordance with
accordance specifications. The contractor shall also confirm exactly fully and faithfully to the designs,
with drawings and instructions in writing relating to the work signed by the Engineer-in-charge
specificatio and lodged in his office and to which the contractor shall be entitled to have access for the
n, drawing, purpose of inspection at such office or at the site of work during office hours. The
orders etc. contractor will be entitled to receive three sets of contracts drawings and working
drawings as well as one certified copy of the accepted tender along with the work order
free of cost. Further copies of the contract drawings and working drawings, if required by
him, shall be supplied at the rate of Rs. 500 /- per set of contact drawing and Rs. 150/- per
working drawing except where otherwise specified.
Alteration in Clause 14: The Engineer-in-charge shall have power to make any alterations in, or
Specificatio additions to, the original specifications, drawings, designs and instructions, that may
ns and appear to him to be necessary or advisable during the progress of the work and the
designs not contractor shall be bound to carry out the work in accordance with any instructions in this
to invalidate connection which may be given to him in writing signed by the Engineer-in-charge and
contract. such alteration shall not invalidate the contract, and any additional work which the
contractor may be directed to do in the manner above specified as a part of the work shall
be carried out by the contractor in the same conditions in all respects on which he agreed
to the main work and at the same rates as per specified in the tender for the main work.
And if the additional or altered work, includes any class of work for which no rate is
Changes in Clause 28: In the case of a tender by partners any change in the construction of a firm
the shall be forthwith notified by the contractor to the Engineer-in-charge for his information.
constitution
of the firm to
be notified.
Clause 29: All works to be executed under the contact shall be executed under the
direction and subject to the approval in all respects of the Superintending Engineer of the
Circle for the time being, who shall be entitled to direct at what point or points and in what
manner they are commenced and from time to time carried out.
Work to be Clause 30 (1): Except where otherwise specified in the contract and subject to the power
under delegated to him by Government under the code rules then in force, the decision of the
direction and Superintending Engineer of the Circle for the time being shall be final, conclusive and
control of binding on all parties to the contract upon all questions relating to the meaning of the
Superintendi specifications ,designs ,drawings and instructions herein before mentioned and as to the
ng Engineer. quality of the workmanship or material used on the work or as to any other question,
claim, right, matter or things whatsoever, in any way arising out of or relating to the
contract designs, drawing, specifications, estimates, instructions , orders of these
conditions or otherwise concerning the works or the execution or failure to execute the
same whether arising during the progress of the work or after the completion or
abandonment thereof.
(2) The contractor may within thirty days of receipt by him of any order passed by the
Superintending Engineer of the Circle as aforesaid appeal against it to the Chief Engineer
concerned with the contract, work or project provided that -
(a) The accepted value of the contract exceeds Rs. 10 lacks (Rupees Ten Lakhs)
(b) Amount of claim is not less than Rs. 1.00 lakh (Rupees one lakh)
(3) If the contractor is not satisfied with the order passed by the Chief Engineer as
aforesaid the contractor may within thirty days of receipt by him of any such order, appeal
against it to the concerned Secretary, Public Works Department who, if convinced the
prima-facie the contractor’s claim rejected by the Superintending Engineer / Chief
Engineer is not frivolous and that there is some substance in the claim of the contractor as
would merit a detailed examination and decision by the Standing Committee, shall put up
to the Standing Committee at Government level for suitable decision.
Store of Clause 31: The contractor shall obtain from the P.W.D. stores all stores and article of
European or European or American manufacture which may be required for the work, or any part of the
American work or in making up any article required therefore or in connection therewith unless he
manufactures has obtained permission in writing from the Engineer-in-charge to obtain such stores and
to be articles elsewhere. The value of such stores and articles as may be supplied to the
obtained contractor by Engineer-in-charge will be debited to the contractor in his account at the
from the rates shown in the Schedule in form “A” attached to contract and if they are not entered in
Action where Clause 33: In the case of any class of work for which there is no such specification as in
no mentioned in Rule-1, such work shall be carried out in accordance with the Divisional
specification. specifications, and in the event of there being no Divisional specification, then in such
case the work shall be carried out in all respects in accordance with the instruction and
requirement of the Engineer-in-charge.
Definition of Clause 34 : The expression ‘works’ or ‘work’ where used in these condition shall, unless
work. there be something in the subject or context repugnant to such construction be
constructed to mean the work or the work contractor to be executed under or in virtue of
the contract, whether temporary or permanent and whether original altered substituted or
additional.
Contractor’s Clause 35: The percentage referred to in the tender shall be deducted from / added to the
percentage gross amount of the bill before deducting the value of any stock issued.
whether
applied to net
or gross
amount of
bill.
Quarry fees Clause 36: All quarry fees, royalties,Octri dues and ground rent for stacking materials if
and royalties any, should be paid by the contractor.
Compensatio Clause 37: The contractor shall be responsible for and shall pay compensation to his
n under Workmen payable under the Workmen’s compensation Act, 1923 (VIII of 1923),
Workman’s (hereinafter compensation is payable and or paid by Government as principal under the
Compensatio subsection (1) of section 12 of the said Act on behalf of the contractor this shall be
n Act. recoverable by Government from the contractor under sub section (2) of the said section.
Such compensation shall be recovered in the manner laid down in clause 1 above.
Clause 37 A: The contractor shall be responsible for and shall pay expenses of providing
Medical aid to any workmen who may suffer a bodily injury as a result on an accident. If
such expenses are incurred by Government the same shall be recoverable from the
contractor forthwith and be deducted without prejudice to any other remedy of
Government from any amount due or that may become due to the contractor.
Clause 37 B : The contractor shall provide all necessary personal safety equipment and
first-aid apparatus available for the use of the persons employed on the site and shall
maintain the same in condition suitable for immediate use at any time and shall comply
with the following regulation in connection therewith :
(a) The worker shall be required to use the equipment so provided by the
contractor and the contractor shall take adequate steps to ensure proper use
of the equipment by those concerned.
Claim for Clause 38: (1) Quantities shown in the tender are approximate and no claim shall be
quantity of entertained for quantities of work executed being either more or less than those entered in
works the tender or estimate.
entered in
the tender or
estimate.
(2) Quantities in respect of the several items shown in the tender are approximate and no
revision in the tendered rates shall be permitted in respect of any of the items so long as,
subject to any special provision contained in the specifications prescribing a different
percentage of permissible variation in the quantity of the item does not exceed the tender
quantity by more than 25 percent and so long as the value of the excess quantity beyond
this limit at the rate of the items specified in the tender, is not more than Rs.5,000/-
(3) The contractor shall if ordered in writing by the Engineer so to do, also carry out any
quantities in excess of the limit mentioned in sub-clause (i) hereof on the same conditions
as and in accordance with the specifications in the tender and at the rates (i) derived from
the rates entered in the current schedule of rates and in the absence of such rates (ii) at
the rates prevailing in the market. The said rates increased or decreased as the case
may be, by the percentage which the total tendered amount bears to the estimated cost of
the work as put to tender based upon the schedule of rates applicable to the year in
which the tenders were accepted (For the purpose of operation of this clause, this cost
shall be as worked out from D.S.R. prevailing at the time of acceptance of tender.)
4) Claims arising out of reduction in the tendered quantity of any item beyond 25 percent
will be governed by the provision of clause 15 only when the amount of such reduction
beyond 25 percent at the rate of the item specified in the tender is more than Rs.5,000/-
(This clause is not applicable to extra items)
Employment Clause 39: The contractor shall employ any female, convict or other labour of a particular
of female or kind of class if ordered in writing to do so by the Engineer-in-charge.
other labour.
Claim for Clause 40 : No compensation shall be allowed for any delay caused in the starting of the
compensatio work on account of acquisition of land and in the case of the clearance work of any delay
n for delay in in according sanction to estimates.
starting work
Clause 48: The rates to be quoted by the contractor must be inclusive of sales tax No
extra payment on this account will be made to the contractor
Clause 48 A : The contractors are bound to pay to the labourers wages according to the
Minimum Wages Act 1948 applicable to the Zone in accordance with the order issued in
Government P.W.D./Circular No. MWA/ 1063, dated 07/12/1968.
Clause 49: In case of materials that remains surplus with the contractor for those issued
for the work contracted from the date of ascertainment of the materials being surplus be
taken as the date of sale for the purpose of sales tax and the sale tax will be recovered on
such sale.
Clause 50: The contractor shall employ the unskilled labour to be employed by him on the
said work only from locally available labours and shall give preference to those persons
enrolled under Maharashtra Government Employment and Self Employment Department
Scheme. Provided, however, that if the required unskilled laboured are not available
locally, the contractor shall in the first instance employ such number of persons as is
available and thereafter may with previous permission, in writing of the Engineer-in-charge
of the said work obtained the rest of requirement of unskilled the labour from outside the
above scheme.
Clause 51: Deleted
Clause 52: All amount whatsoever which the contractor is liable to pay to the Government
in connection with the execution of the work including the amount payable in respect of (1)
Material and / or stores supplied / issued hereunder by the Government to the contractor,
(2) Hire charges in-respect of heavy plant machinery and equipment given on hire by the
Government to the contractor, for execution by him of the work and / or on which the
advance have been given by the Government to the contractor shall be deemed to be
arrears of the lands revenue and the Government may without prejudice to any other
rights and remedies of the Government recover the same from the contractor as arrears of
land revenue.
V1 = 0.85 x P x K1 x L1 - L0
100 L0
WHERE
V1 = Amount of price variation in Rupees to be allowed.
P = Cost of work done during the quarter under consideration Minus
the cost of Cement, steel., and bitumen calculated at the basic Star rates as
applicable for the tender consumed during the quarter under Consideration.
These Star rates are specified here
Star Rates
(1) Cement Rs. 5800.00 Per MT
(2) Steel TMT/HYSD Rs. 46000.00 Per MT
V2 = 0.85 x P x K2 x M1 - M0
100 Mo
WHERE
V2 = Amount of price variation in Rupees to be allowed for material Component
P = Same as worked out for labour component.
K2 = Percentage of Material Component as indicated above
M0 = Basic Wholesale Price Index shall be average wholesale price
index for the Quarter preceding the month in which the last
date Prescribed for receipt of tender falls.
M1 = Average Wholesale Price Index during the quarter under
Consideration
V3 = 0.85 x P x K3 x P1 - P0
100 P0
WHERE
V3 = Amount of price variation in Rupees to be allowed for POL component
P = Same as worked out for labour component.
K3 = Percentage of Petrol, Oil and Lubricant component
Po = Average Price of HSD at Mumbai during the quarter preceding the
Month in which the last date prescribed for receipt of tender falls.
Pi = Average Price of HSD at Mumbai during the quarter under
consideration
V5 = S0 (Sl1 - Sl0 ) x T
Sl0
WHERE
V5 = Amount of price variation in Rupees to be allowed for HYSD / Mild Steel
TMT Steel component.
S0 = Basic Star rate of TMT Steel in rupees per metric tonne as considered for
working out value of P.
Sl1 = Average Steel Index as per the RBI Bulletin during the quarter under
consideration.
Sl0 = Average of Steel Index as per the RBI Bulletin during the quarter preceding
the month in which the last date prescribed for receipt of tender falls.
T = Tonnage of steel used in the permanent works for the quarter under
consideration.
(5) FORMULA FOR CEMENT COMPONENT
V6 = C0 (Cl1 - Cl0 ) x T
Cl0
WHERE
V6 = Amount of price escalation in Rupees to be allowed for cement component.
C0 = Basic rate of cement in rupees per metric tonne as considered for working
out value of P.
Cl1 = Average cement Index published in the RBI Bulletin for the quarter under
consideration.
Cl0 = Average of cement Index published in the RBI Bulletin for the quarter
preceding the month in which to the last date prescribed for receipt of
tender falls.
T = Tonnage of cement used in the permanent works for the quarter under
consideration.
V4 = Q B ( B 1 - B0 )
WHERE
V4 = Amount of price variation in Rupees to be allowed for Bitumen component.
QB = Quantity of Bitumen (Grade) in metric tonnes used in the permanent works
and approved enabling works during the quarter under consideration.
B1 = Current average ex-refinery price per metric tonne of Bitumen (Grade) under
Consideration including taxes (octroi, excise, sales tax) during the quarter
under consideration.
B0 = Basic Star rate of Bitumen in rupees per metric tone as considered for
working out value of P or average ex-refinery price in rupees per metric
tonne including taxes (octori, excise, sales tax) of Bitumen for the grade of
bitumen under consideration prevailing quarter preceding the month in
which the last date prescribed for receipt of tender, falls, whichever is
higher.
relevant contract provisions the price adjustment amount for the balance work from the
date of levy of such compensation shall be worked out by pegging the indices L1, M1, B i
P1, CI1,and SI1 to the levels corresponding to the date from which such compensation is
levied.
ii) This price variation clause shall be applicable to this contract in B-1 form nut shall not apply to
piece works. The Price variation shall be determined during each quarter as per formula given
above in this clause.
iii) The price variation under this clause shall not be payable for the extra items required
to be executed during the completion of the work and also on the excess quantities
payable under the provisions of Clause 38 of the contract formB-1 since the rates payable
for the extra items or the extra quantities under the clause 38 are to be fixed as per the
current DSR or as mutually agreed subject to yearly revision till completion of such work.
In other words, when the completion/execution of extra items as well as extra quantities
under clause 38 of the contract form B-1 extends beyond the operative date of the DSR,
from the rates payable for the same beyond the date shall be revised with reference to
the next current DSR prevalent at that time on year to year basis or revised rates, in
accordance with mutual agreement thereon, as provided for in the contract, whichever is
less.
iv) This clause is operative both ways, i.e. if the price variation as calculated above is in
on the plus side, payment on account of the price variation shall be allowed to the
Note: In case provisions of this form B-1 conflicts with those in detailed cyclostyled provisions and
conditions attached to this tender. The detailed cyclostyled provision and conditions would prevail
over those in this form ‘ B-1”
11.1 The stacking and storage of building materials at site shall be in such a manner as to prevent
deterioration or inclusion of foreign materials and to ensure the preservation of the quantity,
properties and fitness of the work, suitable precautions shall be taken by contractor to protect the
materials against atmospheric action, fire and other hazards. The materials likely to be carried
away by wind shall be stored in suitable stores or with suitable barricades and where there is
likelihood of subsidence of soil, heavy materials shall be stored on paved platforms, suitable
(e) The contractor shall make sufficient arrangement for draining away the surface and
suage water as well as water from the bathing and washing places and shall dispose of
the waste water in such away as not cause any nuisance.
f) The contractor shall engage a medical officer with a traveling dispensary for a camp
containing 500 or more person if there is no Government or other dispensary situated
within eight Kilometers from the camp. In case of an emergency contractor shall at his cost,
free transport for quick medical help to his sick workers..
g) The contractor shall provide the necessary staff for affecting the satisfactory conservancy
and cleanliness of the camp to the satisfaction of the Engineer -in charge .At least one
sweeper per 200 person should engaged.
h) The Assistant Director of public health shall be consulted before opening a labour camp
and his instruction on matters such as water supply, sanitary, convenience, the camp
site, accommodation and food supply shall be followed by the contractor.
i) In addition to above all provision of the relevant labour act pertaining to basic amenities
to be provide to the labour shall be applicable which will be arranged by the contractor
J) The contractor shall make arrangement for all anti malaria measures to be provided for
the labour employed on the work. The anti malaria measures shall be as directed by the
Public Health Officer.
22. The contractor except as provided in special conditions which follow shall if necessary
construct at his cost temporary roads and maintain these in proper conditions till
completion of the work at his own cost.
23. The contractor except as provided in special conditions which follow shall have to at his
own expenses make all preliminary arrangements for labour, water, electricity and
material etc. immediately after getting the work order. The Government may render
necessary assistance in this regard by way of letters of recommendations, if so
requested by the contractor. No claim for any extra payment or applications for
extension of time on the grounds of any difficulty in connection with the above matters
will be entertained.
24. WORKING METHODS AND PROGRESS SCHEDULES :
24.1 The contractor shall submit within the time stipulated by the Engineer-in-charge in
writing the details as actual methods that would be adopted by the contractor for the
execution of any items as required by Engineer at each of the location supported by
necessary detailed drawing and sketches including those of the plant and machinery
that would be used their locations arrangement for conveying and handling materials
etc., and obtain prior approval of the Engineer-in-charge well in advance of starting of
such item of works. The Engineer-in-charge reserves the right to suggest modifications
or make corrections in the method proposed by the contractor whether accepted
previously or not at any stage of the work to obtain the desired accuracy, quality and
progress which shall be binding on the contractor no claim on account of such change in
method of execution will be entertained by Government so long as specification of the
item remain unaltered.
24.2 The contractor shall furnish within one month of the order to start the work programme
of work in quadruplicate indicating the date of actual start, the monthly progress
expected to be achieved and anticipated completion date of each major item of work to
27.3 The final bill shall be submitted by the contractor within one month of the date of issue
of completion certificate. The final bill shall be paid within six months of initial
submission.
27.4 Recovery of secured advance shall be effected through bills proportionately as per
consumption of materials in the work billed for.
27.5 The contractor can have true copy of the bills paid to him after paying charges for
photocopying the same.
CONTROLLED CONCRETE :
Acceptance criteria shall be as per IS : 456 – 2000 (With latest amendments)
NORMAL MIX CONCRETE :
Acceptance criteria shall be as per IS : 456 – 2000 (With latest amendments)
(4) For providing Electric Wiring, Duct tubes of the required diameter and length shall be
provided through walls, beams and floors, slabs as and when directed without any extra
cost.
(5) (a) The contractor shall make his own arrangement for receiving all materials, tools, etc.
required for the work.
(b) No extra charges for carriages of water will be allowed.
(c) The rates for all items are inclusive of all charges such as carting, lifting, etc. No
extra payment for any lead and lift will be paid for any items.
(d) A frequency of testing shall be as per relevant works specification. In case such
frequency is not specified in the works specification then the IS code will be referred and
for other cases where IS code do not stipulated the frequency of testing, it will be as
directed by Engineer in charge and should be furnished in specified test abstract
Annexure I
(e)The Contract should not be sublet without written permission of Executive Engineer
(f) Tender condition of tender notice will be binding on contractor and etc tender notice
will form a part of agreement
40. WEIGH BATCHING: The following instructions shall be followed as regards to
preliminary designs of mix and methods of batching of plain cement concrete and reinforced
cement concrete. The preliminary mix design and batching for various grades of concrete shall
be governed by the guidelines as per I.S. 456-2000. It will be the responsibility of the contractor
to obtain the mix design for various cement concrete grades at his cost from the P.W.D
laboratory.
41. MISCELLANEOUS:
41.1 ERASER:
Person tendering are informed that no erasers or any alteration by them in the text of
the documents set herewith will be allowed and any such eraser or an alteration will be
disregarded. If there is any error in writing no overwriting should be done but the wrong
words or figures should be struck out and the correct one written above or near it in an
unambiguous way. Such correction should be initialed and dated.
41.2 ACCEPTANCE:
Intimation of acceptance of tender will be given by a telegram or a letter sent by
registered post to the address given below the signature of the tenderer in the tenders.
The tenders which do not fulfill any of the above conditions or those in the form and
which are incomplete in any respect shall be liable for rejection.
41.10 If the standard specifications fall short for the items quoted in the schedule of this
contract reference shall be made to the latest Indian Standard Specifications, I.R.C.
codes, and MOST specification if any of items of this contract do not fall in reference
quoted above, the decision and specifications as directed shall be final.
43.3 Contractor shall observe the rules and regulations empowered by traffic police for
smooth flow of traffic on the diversion road and shall not be entitled for claim any
compensation arising thereof.
44. DEFINITIONS: Unless included by or repugnant to the contents
(a) Government: The expression “Government” as used in the tender documents shall
mean the Public Works Department of the Government of Maharashtra.
(b) Chief Engineer: The expression ‘The Chief Engineer’ as used in the tender papers shall
mean Chief Engineer P.W .Region Nagpur.
(c) Superintending Engineer: The expression ‘Superintending Engineer’ as used in the
tender papers shall mean the officer of Superintending Engineer’s ranks (by whatever
designation he may be known) under whose control the work lies for the time being.
(d) Engineer-in-charge: The expression Engineer or Engineer-in-charge as used in the
tender paper shall mean the Engineer-in-charge of the work.
(e) Contractor: The expression ‘Contractor’ as used in the tender papers shall mean the
successful tenderer that is the tenderer whose tender has been accepted and who has
been authorised to proceed with the work.
(f) Contract: The expression ‘Contract’ as used in the tender papers shall mean the deed of
contract together with all its original accompaniments and those later incorporated in it
by mutual consent.
(g) Plant: The expression ‘Plant’ as used in the tender papers shall mean every temporary
accessory necessary or considered necessary by the Engineer to execute, construct,
complete and maintain the work and all altered, modified, substituted and additional
NAME OF WORK;- : CONSTRUCTION OF COMPOUND WALL (BALANCE LENGTH) AND IMPROVEMENT OF DRAINGED LINE TO E.S.I.S. 150
BEDDED HOSPITAL AT SOMWARIPETH NAGPUR
Sr. Name of Material Approximate Quantity to unit Rate at which the material Remarks
No. be stipulated will be charged to
Contractor
In Figures In words
1 2 3 4 5 6 7
---------- Nil--------------
STATEMENT SHOWING (APPROXIMIATELY) QUANTITY TO BE BROUGHT BY THE CONTRACTOR AT HIS OWN COST FOR THE WORK
NAME OF WORK;- : CONSTRUCTION OF COMPOUND WALL (BALANCE LENGTH) AND IMPROVEMENT OF DRAINGED LINE TO E.S.I.S. 150
BEDDED HOSPITAL AT SOMWARIPETH NAGPUR
1 2 3 4 5
STATEMENT SHOWING RECOVERY STATEMENT OF DISMANTLED MATERIALTO BE GOT TO THE CONTRACTOR FROM
DISMANTLING ITEMS
NAME OF WORK;- : CONSTRUCTION OF COMPOUND WALL (BALANCE LENGTH) AND IMPROVEMENT OF DRAINGED LINE TO E.S.I.S. 150
BEDDED HOSPITAL AT SOMWARIPETH NAGPUR
Sr. Name of Material Approximate Quantity to unit Rate at which the material Remarks
No. be stipulated will be charged to
Contractor
In Figures In words
1 2 3 4 5 6 7
An Amount RS 4714/-Rs Four Thousand Seven Hundred Fourteen only Shall be Recovered from contractor RA Bill on account of cost of
Dismantled Material
I/ we hereby declare that I/we have made myself/our selves thoroughly conversant with
the local conditions regarding all materials such as stones,murum,sand etc and labour on
which I/we have based my /our rates for this Work. The specification ,lead & lift for this work
have been carefully studied and understood by me before submitting the tender. I/we
undertake to use only the best material approved by the Engineer- in- charge or his duly
representative before starting the work and to abide by his decision.
I/We shall maintain /rectify the entire work as per as per standard specification of
P.W.D (Red Book ) and M.O.R T and .H specification as soon as damage occurs up to the
expiry defect liability period without putting forth any reasons.
I hereby undertake to pay the labourers engaged on the work as per Maharashtra
Contract Labour (Regulation and Abolition rule 1971) or at the rate revised by the Competent
Authority time to time applicable to the zone concerned.
CONTRACTOR’S SIGNATURE.
TESTING STATEMENT
Sr Items Qty as Specified Required Test actual taken Total Deficiency Remarks
No per frequency test as at test in testing
execution per Site Laboratory
frequency office
1 2 3 4 5 6 7 8 9 10
Contractors: - ___________________________________________________
Name: - ___________________________________________________
Sr. Name Agree Tendered Date Stipulate Value Value of Probable Rem
No of ment Amount. of d date of of work Balance date of arks
. work No. (Rs. in comm completi already work to completio
lakhs) encem on. done. be n.
ent. (Rs. In executed
lakhs) (Rs.
In lakhs)
1 2 3 4 5 6 7 8 9 10
Sample Form
Sample Form
Note : This is only a standard form. Details are to be furnished in this format by tenderer with
supporting document.
LIST OF PLANT AND MACHINERY READILY AVAILABLE WITH THE TENDERER FOR THIS
WORK -
Sr. Name of No. of Kind and Capacity Age and Present Remarks
No Equipment Units make condition. Location.
1 2 3 4 5 6 7 8
Sample Form
Note : 1) This is only a standard form. Details are to be furnished in this format by
tenderer with supporting document.
2) List of machinery proposed to be utilized on this work but not immediately available
and the manner which it is procured shall be given in above proforma in column
no.8.
.
Signature of bidder
DETAILS OF WORKS OF SIMILAR TYPE AND MAGNITUDE CARRIED OUT THE CONTRACTOR.
Sr. Name Name and Place Agree Date Tender Total Actual (Principle
No of address of and ment of ed Cost of date of features
. work the country No. comm cost. work compl in brief.)
organizatio encem done. etion
(Rs. In
n for whom ent
lakhs) (Rs. In
the work
lakhs)
was done.
1 2 3 4 5 6 7 8 9 10
Sample Form
Note : This is only a standard form; details are to be furnished in this format in the form of type
written statements which shall be enclosed in Envelope No.1.
Remarks
Sr. Designation Name Qualification Whether Experience of Period
No of working in execution of for which
person field or in similar works. the
office. person is
working
with the
tenderer.
1 2 3 4 5 6 7 8
Sample Form
Sample Form
Grand Total :-
Note : This is only a standard form. Details are to be furnished in this format by tenderer with
supporting document.
Sample Form
Name of work:-
Applicant/Contractor Name……
Address ……………………..
E-mail ……… Mobile No…………
website
Name of Work:-
1. I, the undersigned, do hereby certify that all the documents and statements made in
the required attachments are true and correct. In case the contents of envelope No.1
and other documents pertaining to the tender submitted by me are found to be
incorrect or false, I shall be liable for prosecution and punishment under section 199
and 200 of IPC 1960 and/or any other law applicable thereto.
2. The undersigned also hereby certifies that neither our firm M/s.
_______________________________________ have not abandoned any work in
Public Work Department in Maharashtra nor any contract awarded to us for such
works have not been rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request(s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by the
Department to verify this statement or regarding my (our) competence and general
reputation.
4. The undersigned understand and agrees that further qualifying information may be
requested and agrees to furnish any such information at the request of the
Department under relevant laws.
Applicant/Contractor Name……
Place :- Address ……………………..
E-mail ……… Mobile No…………
Date :- Website
(a) Due performance and observance by the Contractor of the terms, covenants and conditions on
the part of the contractor contained in the said Agreement and
(b) Due and punctual payment by the Contractor to the Government of all sums of money, losses,
damages, costs, charges, penalties and expenses payable to the Government by the contractor
under or in respect of the said Agreement.
2. Undertake to pay to the Government on demand and without demur and notwithstanding any
dispute or disputes raised by the Contractor(s) in any suit or proceeding filed in any Court of
Tribunal relating thereto the said sum of Rs.
____________________________________________ ( Rupees
_____________________________________________________ only. ) or such less sum
may be demanded by the Government from us, our liability hereunder being absolute and
unequivocal and agree that.
3.(a) The guarantee herein contained shall remain in full force and effect during the subsistence of
the said Agreement and that the same will continue to be enforceable till all the dues of the
(c) Our liability herein under shall be joint and several with that of the Contractor as if we were the
principal debtors in respect of the said sum of Rs. __________________________________
(Rupees _____________________________________ only.) and
(d) We shall not revoke this guarantee during its currency except with the previous consent in
writing of the Government.
(1) __________________________
(2) __________________________
300 mm dia
Providing and fixing reinforced cement concrete cover of 7.5cm thick over manhole As directed by Engineer In
38.
and inspection chamber including mild steel reinforcement, curing testing etc. charge
complete. (1.15 m x 0.6 m. size) (Prior approval of sample and brand by Ex.Engineer is
necessary before use.)
Providing and fixing UPVC SOIL / VENT / WASTE SWR pipe of required diameter As directed by Engineer In
39.
conforming to I.S.-13592, and I.S.-4985 to withstand continuous internal hydraulic charge
pressure of 4 kg/cm2 including necessary fixtures and fittings, such as bends, tees,
single junctions, double junctions and joining with rubber rings and lubricants, on wall
by means of clips or in ground including necessary excavation, laying refilling, trench
testing etc. complete. (Prior approval of sample and brand by Ex.Engineer is
necessary before use.)
Providing and fixing mat finish stainless steel lettering of various heights as directed by As directed by Engineer In
40.
engineer in charge including material, labour, cleaning etc. complete. charge
Providing and filling in the foundation and plinth with sand of approved quality As directed by Engineer In
41.
including watering, compaction complete. charge. Bd- Av 3 / page 264
Transportation of material obtained from debris of various sorts including necessary As directed by Engineer In
42.
excavation/ loosing including loading, unloading and conveying and disposing as charge
directed.
Providing and erecting 1.20 m. high chain link fencing with chain link having hole size As directed by Engineer In
43.
65 mm x 65 mm supported on M.S.angle post of size 50 mm x 50 mm x 6 mm with charge
M.S. flat of size 50 mm x 5 mm for fastening chain link with post angle at 2.40 m c/c
including excavating pits for foundation fixing post in C.C. 1:4:8 of size 45 cm x 45 cm
x 45 cm fixing chain link with 3.25 mm ( 10 guage ) G.I. wire and M.S. flat of size 40
mm x 5 mm provided at top and bottom and with oil paint etc. complete.