Attachment 1 TOP Binder Index

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 56

AL DUR PHASE II

INDEPENDENT WATER AND POWER PROJECT

OWNER: CONTRACTOR:

TURN OVER PACKAGE – 0WJC-INTAKE SYSTEM 1

SUB SYSTEM:

1WAZ001 – INTAKE PUMP AND HYDRAULIC UNIT STREAM 1

AD2-C2-W0-WAZ01-QEE-SIS-00024
OWNER: CONTRACTOR:

TABLE OF CONTENTS
SECTION DESCRIPTION PAGE

1 ECC Package
1.1 Erection Completion Certificate
1.2 Reference Documentation
1.2.1 P&ID with system identified
1.2.2 ECC Battery Limits Definition
1.2.3 Functional Description and O&M Manuals List
1.2.4 Lay out identifying system area
1.2.5 Data Sheets
1.2.6 Single Line Diagram
1.2.7 Equipment List
1.2.7.1 Mechanical Equipment Lists
1.2.7.2 Electrical Equipment Lists
1.2.7.3 I&C Equipment Lists
1.2.8 Lines Lists
1.2.9 Valves Lists
1.2.10 Cables Lists
1.2.11 Codes and Standards List
1.3 Mechanical / Electrical / I&C Erection Documents
1.3.1 Mechanical Erection Documents

1.3.2 Electrical Erection Documents

1.3.3 I&C Erection Documents


Resulted from
1.4 Red Line Construction activity
( If available)

1.5 NCRs between EPC and Vendors


1.6 ECC PunchList
2 CCC Package
OWNER: CONTRACTOR:

2.1 PRE-COMMISSIONING PROTOCOLS


2.1.1 Pre-Commissioning Procedures
2.1.1.1 Mechanical Pre-Commissioning Procedures

2.1.1.2 Electrical Pre-Commissioning Procedures

2.1.1.3 I&C Pre-Commissioning Procedures

2.1.2 Calibration Certificates


2.1.3 Completed and Signed Protocols
2.1.3.1 Mechanical Completed and Signed Protocol

2.1.3.2 Electrical Completed and Signed Protocol

2.1.3.3 I&C Completed and Signed Protocol

2.2 COMMISSIONING PROTOCOLS


2.2.1 Commissioning Tests Procedures
2.2.2 Commissioning Tests Reports
2.2.3 Calibration Certificates (if applicable)
2.2.4 Commissioning Completion Certificates CCC signed
3 FUNCTIONAL TEST PROTOCOLS: Performance & Reliability Tests

3.1 Reliability and Performance Test Procedures

3.2 Reliability and Performance Test reports

3.3 Calibration Certificates

3.4 Test Calculation Sheets(if applicable)

4 TURN-OVER PUNCHLIST

4.1 PunchList
Provided within thirty (30)

5 RED LINE/AS BUILT DRAWINGS days after Provisional

Acceptance.

5.1 Red line / As built drawing


6 TOP Transfer Certificate

6.1 TOP Transfer Certificate


OWNER: CONTRACTOR:
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.ECC Package

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.1 Erection Completion Certificate

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II INDEPENDENT WATER AND POWER PROJECT


ERECTION COMPLETION CERTIFICATE

Construction turn over to Commissioning the following system:

System

ECC No.

Date

EPC Construction Manager EPC Quality Manager

Name and date

Signature

ECC package documentation list attached:

Commissioning acceptance:
EPC Commissioning
Acceptance Partial acceptance Rejection
manager

Name and date

Signature

Owner review and comments:


OWNER: CONTRACTOR:

Name/Signature/date

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2 Reference Documentation

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.1 P&ID with system identified

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.2 ECC Battery Limits Definition

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

ECC Battery Limits Definition


ITEAM Description KKS Code Drawing No.

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.3 Functional Description and O&M manuals list

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.4 Lay out identifying system area

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.5 Data sheets

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.6 Single Line Diagram

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.7 Equipment Lists

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Equipments
ITEAM NAME of Equipment KKS Mark

1 DISTRIBUTION BOARD WEA-DB-LP-N-002

2 DISTRIBUTION BOARD WEA-DB-LP-N-003

3 DISTRIBUTION BOARD WEA-DB-LP-E-002

4 48W, 6800 LM, 4000K LED LIGHT FIXTURE, IP 65 N/A


48W, 6800 LM, 4000K LED LIGHT FIXTURE, IP 65
5 N/A
WITH EMERGENCY PACK
6 100W LED FLOOD LIGHT N/A

7 15W LED BULKHEAD LIGHT N/A


13A SPN TWIN SWITCHED SOCKET OUTLET –METAL
8 N/A
CLAD
3P+N+E SURFACE MOUNTED INDUSTRIAL SOCKET
9 N/A
OUTLET-16A, 415V IP65
10 20A 1 GANG 1 WAY SWITCH-METAL CLAD N/A

11 20A 1 GANG 2 WAY SWITCH-METAL CLAD N/A


OWNER: CONTRACTOR:

12 20A 2 GANG 2 WAY SWITCH-METAL CLAD N/A

13 13A SPN SINGLE SWITCHED SOCKET IP 65 N/A

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.8 Lines List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Lines
ITEAM NAME of Instruments KKS Mark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.9 Valves List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Valves

ITEAM Line and Isometric description KKS Mark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.10 Cables List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.11 Codes and Standards List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.3 Mechanical / Electrical / I&C Documents


OWNER: CONTRACTOR:

ECC PACKAGE NAME

ECC PACKAGE CODE

List of Electrical RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS ACCEPTED
1 SPML-ALD-RFI-C-5714
AFTER ERECTION_LV SWITCHGEAR STREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6095 ACCEPTED
2
AFTER ERECTION_DCS ROOM STREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-5844 ACCEPTED
3
AFTER ERECTION_DCS ROOM STREAM-2
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6524 ACCEPTED
4
AFTER ERECTION_CORRIDOR
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6886 ACCEPTED
5
AFTER ERECTION_MV SWITCHGEAR SREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7073 ACCEPTED
6
AFTER ERECTION_UPS ROOM
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7127 ACCEPTED
7
AFTER ERECTION_LV COMMON ROOM
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7622 ACCEPTED
8
AFTER ERECTION_BATTERY ROOM
OWNER: CONTRACTOR:

VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-8055 ACCEPTED


9
AFTER ERECTION_LV SWITCH GEAR STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SPML-ALD-RFI-C-5715 ACCEPTED
10
SWITCHGEAR STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ DCS SPML-ALD-RFI-C-6096 ACCEPTED
11
ROOM STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ DCS SPML-ALD-RFI-C-5843 ACCEPTED
12
ROOM STREAM-2
13 VISUAL INSPECTION OF CABLES AFTER LAYING_ CORRIDOR SPML-ALD-RFI-C-6523 ACCEPTED

VISUAL INSPECTION OF CABLES AFTER LAYING_ MV SPML-ALD-RFI-C-6884 ACCEPTED


14
SWITCHGEAR SREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ UPS SPML-ALD-RFI-C-7074 ACCEPTED
15
ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SPML-ALD-RFI-C-7125 ACCEPTED
16
COMMON ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ BATTERY SPML-ALD-RFI-C-7621 ACCEPTED
17
ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SWITCH SPML-ALD-RFI-C-8056 ACCEPTED
18
GEAR STREAM-1
VISUAL INSPECTION AFTER ERECTION_ LV SWITCH GEAR SPML-ALD-RFI-C-5713 ACCEPTED
19
STREAM-1

List of Electrical RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
VISUAL INSPECTION AFTER ERECTION_ DCS ROOM SPML-ALD-RFI-C-6094
20 ACCEPTED
STREAM-1
VISUAL INSPECTION AFTER ERECTION_ DCS ROOM SPML-ALD-RFI-C-5842 ACCEPTED
21
STREAM-2
22 VISUAL INSPECTION AFTER ERECTION_ CORRIDOR SPML-ALD-RFI-C-6525 ACCEPTED

VISUAL INSPECTION AFTER ERECTION_ MV SPML-ALD-RFI-C-6885 ACCEPTED


23
SWITCHGEAR SREAM-1
24 VISUAL INSPECTION AFTER ERECTION_ UPS ROOM SPML-ALD-RFI-C-7072 ACCEPTED

VISUAL INSPECTION AFTER ERECTION_ LV SPML-ALD-RFI-C-7126 ACCEPTED


25
COMMON ROOM
VISUAL INSPECTION AFTER ERECTION_ BATTERY SPML-ALD-RFI-C-7620 ACCEPTED
26
ROOM
VISUAL INSPECTION AFTER ERECTION_ LV SWITCH SPML-ALD-RFI-C-8057 ACCEPTED
27
GEAR STREAM-1
VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7710 ACCEPTED
28
AFTER ERECTION_WEA-DB-LP-N-002
OWNER: CONTRACTOR:

VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7711 ACCEPTED


29
AFTER ERECTION_WEA-DB-LP-N-003
VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7712 ACCEPTED
30
AFTER ERECTION_WEA-DB-LP-E-002
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7783 ACCEPTED
31 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-N-002
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7784 ACCEPTED
32 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-N-003
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7785 ACCEPTED
33 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-E-002

List of I&C RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.4 Red Line


(Resulted from Construction activity)
OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.5 NCRs between EPC and Vendors


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

NCR List
Issued Closed
ITEAM Description NCR No. From To
date date
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.6 ECC PUNCHLIST

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

ECC PUNCH LIST LOG SHEET


See Appendix 7.3 Master Punch list LOG of《AD2-C3-00-YDC-GGP-CON-00028 Project
Punch List Procedure》
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2. CCC Package

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.1 PRE-COMMISSIONING PROTOCOLS


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

List of pre-commissioning procedures


ITEAM NAME procedure No. STATUS

5
OWNER: CONTRACTOR:

List of pre-commissioning protocols


INSPECTION
ITEAM NAME RFI No.
STATUS
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2 COMMISSIONING PROTOCOLS


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.1 Commissioning Test Procedures


OWNER: CONTRACTOR:

List of commissioning procedures


ITEAM NAME Procedure No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.2 Commissioning Test Reports


OWNER: CONTRACTOR:

List of commissioning test reports


ITEAM NAME RFI No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.3 Calibration Certificates (if applicable)


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.4 Commissioning Completion Certificates


OWNER: CONTRACTOR:

AL DUR PHASE II INDEPENDENT WATER AND POWER PROJECT


COMMISSIONING COMPLETION CERTIFICATE

System

TAG number

Date

Acceptance result The system and sub-system commissioning work are qualified completed.

SUPPORTING DOCUMENTATION:

Refer to Section 4.1 to 4.4 for the related documentation.


OWNER: CONTRACTOR:

Remark:

ISSUED BY EPC Commissioning EPC HAYA Commissioning


Engineer Commissioning Manager Manager
SIGNATURE

NAME

DATE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3. FOUNDATION TEST PROTOCOLS:


PERFORMANCE & RELIABILITY TESTS
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.1 Reliability and Performance Test Procedures


OWNER: CONTRACTOR:

List of Reliability and Performance Test Procedures


ITEAM NAME Procedure No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.2 Reliability and Performance Test Reports


OWNER: CONTRACTOR:

List of Reliability and Performance Test reports


ITEAM NAME RFI No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.3 Calibration Certificates


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.4 Test Calibration Certificates(if applicable)


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

4. TURN-OVER PUNCHLIST
OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

MASTER PUNCH LIST LOG SHEET


See Appendix 7.3 Master Punch list LOG of《AD2-C3-00-YDC-GGP-CON-00028 Project
Punch List Procedure》
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

5. RED LINE/ AS BUILT DRAWING

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

6. TOP Transfer Certificate


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE