BP v. Libya
BP v. Libya
BP v. Libya
I. Historical background:
b. Cause of action
The Hunt Concession granted the holder the exclusive right for a
period of 50 years within a defined area, inter alia, to search for and
extract petroleum, to take it away by pipeline or otherwise and to use,
process, store, export and dispose of the same. For such purpose, the
holder had the right within the concession area to erect and maintain any
constructions, installations and works required for its activities and,
outside the concession area, to erect and operate transport, harbor and
terminal facilities.
(2) The said breaches were and are ineffective to terminate the
Concession Agreement, which remains in law valid and subsisting;
(5) The Claimant is the owner of its share of any crude oil
extracted from the area of the Concession Agreement after as well as
before 7 December 1971 and of all installations and other physical
assets, and the Libyan Government has no right to any such oil,
installations or physical assets, which it can enjoy or transfer to any
third party;
III. Issue
2. Applicable Law
The second issue is what law applies to the relationship between the
Claimant and the Respondent. It will be recalled that paragraph 7 of Clause
28 of the BP Concession contains an express provision on the law
governing the concession. The Claimant argues that Libyan law has been
excluded as the sole governing law and that the law governing the BP
Concession is public international law. Alternatively, the BP Concession
itself constitutes the sole source of law controlling the relationship
between the Parties. Orally, the Claimant submits that it does not place
emphasis on the word “sole”. In the further alternative the Claimant
submits that the legal position of the parties falls to be decided by
reference to “the general principles of law”.
Lastly, the Claimant submits for the purposes of the present stage of
the proceedings that so long as the BP Concession remains in force, the
Claimant is entitled to damages for actual loss caused to it by the
Respondent's breaches of contract up to the date of the Tribunal's final
Award. If and when the Claimant exercises its right to treat the BP
Concession as terminated, it will be entitled not only to damages flowing
from the specific breaches of contract (damnum emergens) but also
damages for loss of the benefit of the contract as a whole (lucrum cessans).
IV. Decision
V. Opinion
The sole provision in the Convention which has a direct bearing on the
issues dealt with here is that contained in Article 60, Paragraph 1, which
reads:
Sources: