GENERAL FOUNDATION
SPECIFICATIONS
CESL-POG-CS-GEN-SPC-004
BS British Standard
EN European Standard
Page 2 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
TABLE OF CONTENTS
Page 3 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
1.0 INTRODUCTION
Promenade Oil and Gas Company Limited has awarded Cakasa Engineering
Services Limited (CESL) a Work Order to carry out Detail Engineering Design
(DED) in conformance with design specifications and industry standards necessary
for the successful completion of the Proposed Petroleum Products Depot at Ijegun,
Lagos State.
1.1 Definitions
Company - The party who initiates the project and ultimately specifies the technical
requirements, which is PROMENADE OIL AND GAS COMPANY LIMITED.
Contractor - The party who carries out all or part of the engineering of a project,
which is CAKASA ENGINEERING SERVICES LIMITED.
Page 4 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
2.0 SPECIFICATIONS, CODES AND STANDARDS
The design shall comply fully with statutory and regulations requirement,
International Standards, & Codes of Practice and industry-published guidelines.
Unless the edition of any code, standard or document is specifically mentioned, the
latest editions shall apply and where conflict exists between requirements of these
documents, it shall be addressed to the COMPANY for clarification.
In terms of use of information, the applicable National code takes precedence over
COMPANY’s specification UNLESS the COMPANY’s specification is more stringent
than the National code, in which case the specification shall be followed.
Page 5 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
Table 2: International Codes, Specifications and Standards
Codes Title
ISO ICS 91 Construction Materials and Building
Scheduling, dimensioning, bending and cutting of steel
EN/BS 8666
reinforcement for concrete.
Specification for Galvanized Ferrous or Stainless Steel
EN 13101:2002
Manhole Steps
Steel plate, sheet and strip. Specification for stainless and
EN10088-2
heat-resisting steel plate, sheet and strip
Specification for hot rolled products of non-structural steels
BS- EN 10025
and their technical delivery conditions.
Design, Construction, Operation, Maintenance and Inspection
API 2610
of terminal & Tank Facilities
API 650 Welded Tanks for Oil Storage
EC 1 - BS EN 1991-1-4 Actions on structures. General actions. Wind actions
Page 6 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
3.0 PARTICULAR SPECIFICATION
All Tanks shall be founded on Pile foundations, while all shelters and equipment
shall be supported on adequately designed and constructed raft foundations.
Piping, Valves, Gauges, Meters and all other appurtenances shall also be
adequately supported.
The foundation type and depth shall be based on the results of the subsoil
investigation and outcome of design calculations for the equipment or structure to
be supported.
¾ Working Area
The working area will be as defined by the COMPANY, which shall be within the
confines of Tomaro facility. Provision of access to the work site shall be the
responsibility of the construction contractor/piling contractor. All temporary
structures shall be removed on completion of the works, unless the COMPANY
advises otherwise.
Working area shall include, as a minimum, the plant areas, the flare area, offset
areas for working space, construction/piling Contractor’s workshop and/or
prefabrication yard (if applicable). Areas outside the immediate site that might be
affected by the works should be surveyed and adequately protected. Such a survey
should include:
Page 7 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
• Site boundaries and building lines
• Mobilisation
• Site Preparation
1. Site Clearance
2. Stripping of topsoil
3. Existing Infrastructures
• Temporary Structures
• Earthworks
2. Excavations
3. Fills
4. Shoring
• Setting Out
1. Benchmarks
2. Equipment
3. Approvals
Page 8 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
¾ Other Works proceeding at the same time
Site Clearance and Bulk Earthworks where required may be undertaken in
conjunction with foundation works.
¾ Submission of Information
Where appropriate, the submission of information as listed in Table 1.1 of the
Institution for Civil Engineers’ Specification for Piling and Embedded and Retaining
Walls’ 1996 shall be made to the COMPANY and at the time stated. The detailed
requirements are listed under the clause number indicated in the relevant portions
of the table.
• Resource availability
Page 9 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
permanent works. Details arising from any necessary constructional features such
as access, timbering, shoring, temporary drains, pump discharge lines,
compressed-air locks and other temporary obstructions should be bore in mind.
Foundations and substructure are design with adequate factor of safety under all
conditions that may occur during the construction of the entire work. The processes
of excavation, filling, pumping etc. should be arranged so as to avoid endangering
the strength or stability of the partially completed structure.
¾ Excavations
Sides and bottoms of excavations should be adequately supported and protected
against traffic, exposure to weather (rain and drying conditions) and the action of
water (floodwater or the removal of groundwater). Stability of the sides of
excavations should also take into consideration surcharge loads as a result of
proximity of mechanical plant, spoil and material dumps to the edge of excavations.
¾ Shoring
Shoring drawings will be produced by the piling contractor and shall be approved by
the COMPANY.
All shoring works shall be approved by the COMPANY and subject to periodic
inspection. Shoring shall be positioned and taken to such depth that would
guarantee adequate support while allowing enough working space for demolition
and other building operations.
Shoring systems shall be structurally designed and may utilize steel sections,
tubular scaffolding, timber or a combination of these. Timber shores should be
regularly inspected for swell or shrink.
Page 10 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
¾ Setting Out
The Site Datum will be as indicated on the Contract Drawings, and shall be
identified to the construction contractor/piling contractor on site by means of
coloured survey pillars. All levels will be quoted relative to Location Datum.
Final ground and finished levels shall be as indicated on the contract drawing and
would be such that effectively drains the plant. Method of drainage, including layout,
gradients etc shall be specified and agreed with the COMPANY. Final levels shall
also allow enough room (clearance) for piping, maintenance, operations and
possibly aeration.
Certified equipment shall be used for setting out. These include automatic levels,
spirit levels, and laser beam levels, Theodolites, Global Positioning System (GPS),
amongst others. The COMPANY shall approve the setting out before profiling and
commencement of foundation construction.
The Piling Contractors’ design shall comprise the calculation of individual pile
lengths based on the ground conditions revealed by the site investigation. The
design shall ensure that the piles have enough capacity to carry the Specified
Working Loads (SWL) within the specified limits for load-settlement behaviour. All
pile at built-up locations shall be Continuous Flight Auger (CFA) piles while at other
locations shall be Driven Cast in-situ Piles designed with appropriate factors of
safety in determining Pile Bearing Resistance.
Reinforcement shall comply with the provisions of EN 1992 for resisting stresses
due to lifting, stacking, and transport of the pile and any uplift or bending transmitted
from the superstructure. It should also be capable of resisting tensile forces due to
ground heave resulting from the installation of other piles close by or from
excavations carried out after the piles have been installed.
Page 11 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
The Piling Contractor shall provide with his tender a schedule of sizes and lengths
of the working piles, including reinforcement and their corresponding allowable
capacities to meet the requirements of the specification.
The Piling Contractor shall submit with his Tender a provisional programme for the
execution of the Works. He shall submit a detailed programme prior to
commencement of the Works.
Safety precautions shall comply with all current safety legislation and with
COMPANY’s safety policy.
The Piling Contractor shall provide and maintain on site sufficient, proper and
efficient lifesaving appliances. The appliances must be conspicuous and available
for use at all times. Site operatives shall be conversant with the use of the safety
equipment.
As part of pre-mobilization for piling, the Piling Contractor shall submit a Quality
Assurance plan for review and approval. For precast concrete, the mix design shall
comply with EN 1992, concrete grade shall be a minimum of C25/30 or C30/37 and
minimum concrete cover shall be 50mm for cased and 75mm. The following
Page 12 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
information shall also be provided in the Quality Assurance plan, as a minimum for
pile production:
• mix design
• source of cement
A Work Method Statement, Piling & Test Procedures should also be made available
for the COMPANY’s review and approval.
The Piling Contractor shall probe the site for buried service and utility lines and
submit report to COMPANY for approval. The Piling Contractor shall obtain
necessary permit before excavation and make good any damaged lines. All works
are to be carried out with the utmost attention to HSE.
All materials and work shall be in accordance with Sections 1, 2 and 20 of the
reference ICE Specification.
All fabricated steel components used in the manufacture of precast concrete piles
shall as a minimum comply with EN10025.
The specified working load for piles to be installed at the project site shall be based
on the results of detailed geotechnical site investigation.
¾ Grades of Concrete
The grade of concrete shall be C25/30.The minimum strength of concrete for the
piles shall be 30N/mm2 at 28 days for cube test and 25N/mm2 at 28 days for
Page 13 of 14
DED for Proposed Petroleum Product Depot, Ijegun, Lagos State CESL-POG-CS-GEN-SPC-004
Earthworks Specification Rev. C1
cylinder test with minimum cement content of 340kg/m3 as specified in concrete
specification.
¾ Supervision
All the piling work shall be supervised by the COMPANY and shall not be
subcontracted to the piling Contractor. No pile shall be installed or tested without
witnessing by authorized supervision.
Page 14 of 14