Hydraulic Elevator Installation Checklist: Schindler 330A
Hydraulic Elevator Installation Checklist: Schindler 330A
Hydraulic Elevator Installation Checklist: Schindler 330A
7. Vibration isolation of the unit normally will not be Borehole applications only
needed when the unit is attached to a concrete Jack hole drilling — Schindler must have clear access
foundation. If used on an upper floor, 2” deflection for truck-mounted drill rig (unless inside drilling is
springs properly sized and installed are suggested. If required in an existing building). Contractor to locate
used on wooden floors, springs are mandatory. the jack hole for the driller and remove jack hole spoils
8. The pipe from the power unit to the hoistway after drilling is complete. (See Detail A below.)
should be “vibrationally” isolated from the wall and
Detail A
the perimeter of the pipe sealed with the appropri- Jack Hole
ate acoustical sealant to prevent acoustical leaks or
flanking paths for vibration noise. ”A”
Jack Hole
Rear
Ventilation requirements
The following guidelines are to be followed to maintain
acceptable elevator equipment room temperatures:
1. Machine room temperature must be maintained
Front
between 55° and 90° F. ”A”
Hoistyway Plan
2. A vented door should be avoided. Air removal
should be done by ducting the air from the room to
the outside if possible. A forced removal of the air to Bottom Car
Landing Travel
another part of the building or building exterior is Jack Hole
”A” Pit Depth
20 4740 240
25 5740 290
30 6740 350
40 8740 450
50 10740 550
www.us.schindler.com