Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

In The Hon'Ble High Court of Delhi at Delhi

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

IN THE HON’BLE HIGH COURT OF DELHI AT DELHI

C.M.(M) NO…………………… OF 2018


IN
EXECUTION PETITION NO 164/2017

IN THE MATTER OF:


M/s S&S Technocrate (P) Ltd ……….Petitioner

Versus
Shri Rathi Steel Ltd …………Respondent

REJOINDER ON BEHALF OF PETITINER TO THE REPLY


FILED BY THE RESPONDENT NO.1.

MOST RESPECTFULLY SHOWETH:-

Preliminary submissions:
1. It is at the outset humbly submitted that Decree Holder has

filed a 7 page reply which is completely against the decree

passed by the hon’ble Delhi high court. The amount of

interest charged by decree holder in their calculation sheet is

exorbitant, from an economic standpoint therefore it is

completely unjustified.
2. It is submitted that amount arrived at from 04.08.2009 till

date of filing 28.04.2013 is Rs. 46,27,254. Thereafter taking

Rs. 46,27,254 as principal and calculating further interest on

the same for the period of 29.04.2013 to 4.09.2015 is

absolutely unjustified and unwarranted. Respondents in their

own sweet will have appropriated the amount towards

interest and towards basic amount and had charged interest

on the sum of Rs. 46,27,254 taking it as a principal amount

for the abovesaid period which was not at all the intention of

the decree originally passed on 10.10.2014.

3. It is submitted that interest of 16% from 04.08.2009 till the

date of disbursement of 45 lakh bank guarantee submitted by

petitioner i.e. 17.09.2015 amounts to Rs. 28,32,220/- which

in total amounts to Rs. 57,25,641/-, accordingly on

submission of bank guarantee remaining amount of

12,25,641/- was pending to be paid by the petitioner and the

amount of Rs 12,25,641 is liable to be charged with interest

of 16% till the realisation of amount and not the amount as

arrived by the Respondents whereby interest has been

calculated on interest.
4. That the interest which has to be paid as per decree dated 10

October 2014 from 04.08.2009 to 17.09.2015 was Rs.

57,09,683/- (Rupees Fifty Seven Lakh Nine Thousand Six

Hundred and Eighty Three only). Out of the said amount

petitioner paid an amount of Rs. 45,00,000/- (Rupees Forty

Five Lakhs only) on 17.09.2015. the balance amount

remaining was Rs. 12,09,683/- (Rupees Twelve Lakh Nine

Thousand Six Hundred and Eighty Three only).

5. That thereafter petitioner further paid a sum of Rs.

17,40,000/- (Rupees Seventeen Lakh Forty Thousand only)

on 17.01.2018 towards the remaining amount. From the date

of payment of Rs. 45,00,000/- (Rupees Forty Five Lakhs

only) i.e. 17.09.2015 till 17.01.2018 amount of interest was

Rs. 4,83,873/- (Rupees Four Lakh Eighty Three Thousand

Eight Hundred and Seventy Three only).

6. That interest from 17.09.2015 till 17.01.2018 amounting to

Rs. 4,83,873/- (Rupees Four Lakh Eighty Three Thousand

Eight Hundred and Seventy Three only) added to remaining

amount of Rs. 12,09,683/- (Rupees Twelve Lakh Nine

Thousand Six Hundred and Eighty Three only) totalled to an

amount of Rs. 16,93,556/- (Rupees Sixteen Lakh Ninety


Three Thousand Five Hundred and Fifty Six Only) was due on

part of petitioner as on 17.01.2018.

7. That the petitioner paid an amount of Rs 17,40,000/-

(Rupees Seventeen Lakh Forty Thousand only) towards the

above stated amount on 17.01.2018. Thereafter it was

calculated that an amount of Rs. 46,443/- (Forty-Six

Thousand Four Hundred and Forty-Three only) was paid in

excess. Further an amount of 2,21,203/- was due towards

cost. Which after deduction amounted to Rs. 1,74,760/- (One

Lakh Seventy Four Thousand Seven Hundred and Sixty only).

Therefore total amount payable by the petitioner is Rs.

1,74,760/- (One Lakh Seventy Four Thousand Seven Hundred

and Sixty only).

8. It is submitted that the judgement quoted by the Ld ADJ Ms.

Priya Mahendra under which it is stated that Kerala State

Electricity Board vs Kurien E. Kalathil (2018) 4 SCC 793

REPLY TO PRELIMINARY OBJECTIONS:-

9. That the contents of Para No.1 to 3 of preliminary objection

of the Reply are absolutely wrong and hence the same are

vehemently denied. It is specifically denied that no cause or


occasion for the Applicant to file the present application, the

present application is gross abuse misuse of the process of

law. hence the application of the applicant is liable to be

dismissed.

REJOINDER TO THE PARAWISE REPLY:


1. That the contents of para 1 to 7 of the para wise reply so

far as it does not admit of the contents of corresponding

para of the application are wrong and denied and the

contents of corresponding para of the application are re-

asserted and reiterated.

2. That the contents of Para No. 8 of the para wise reply is

absolutely wrong and hence the same are vehemently

denied. It is submitted that the calculation sheet

submitted by the respondent is wrong and hence merit no

response.

3. That the contents of para 9 of the para wise reply so far

as it does not admit of the contents of corresponding para

of the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.

REJOINDER TO REPLY TO THE GROUNDS:


1. That the contents of para A of the grounds so far as it

does not admit of the contents of corresponding para of

the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.

2. That the contents of para B of the grounds so far as it

does not admit of the contents of corresponding para of

the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.

3. That the contents of para C of the grounds so far as it

does not admit of the contents of corresponding para of

the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.

4. That the contents of para D of the grounds so far as it

does not admit of the contents of corresponding para of

the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.
5. That the contents of para E to F of the grounds so far as

it does not admit of the contents of corresponding para

of the application are wrong and denied and the

contents of corresponding para of the application are

re-asserted and reiterated

6. That the contents of para G to I of the grounds so far as

it does not admit of the contents of corresponding para

of the application are wrong and denied and the

contents of corresponding para of the application are

re-asserted and reiterated.

7. That the contents of para J of the grounds so far as it

does not admit of the contents of corresponding para of

the application are wrong and denied and the contents

of corresponding para of the application are re-asserted

and reiterated.

8. That the contents of para 10 to 12 of the grounds so far

as it does not admit of the contents of corresponding

para of the application are wrong and denied and the

contents of corresponding para of the application are

re-asserted and reiterated.


9. That the contents of reply to Prayer clause are

absolutely wrong and hence the same are vehemently

denied. On the contrary it is respectfully submitted that

the prayer made in the corresponding prayer clause of

the complaint are reiterated as correct.

PRAYER

Last Para of the reply is a prayer to this Hon’ble

Court which merits no consideration. On the

contrary the complainant prays before this Hon’ble

Court that the relief prayed in the complaint may

kindly be granted in favour of the complainant and

against the opposite party.

New Delhi Petitiner through

Counsels

Filed on:

You might also like