TS Estimate
TS Estimate
TS Estimate
40330.00
22560.00
0.00
Name of Work
0
AMOUNT OF ESTIMATE
Rs 4330.16 Lakhs (Constructin Cost)
Rs 289.62 Lakhs (Maintenance Cost)
CE(R&B) NABARD & LWE Technical Sanction Memo. No: 03/EG/RCPLWE/2019-20/ DCE(RR)/EE/DEE1 /AEE5/2020
3 Name of work as given in the estimate Widening and Strengthening of Yerravaram-Addateegala-Ramavaram road fr
To
The Superintending Engineer(R&B),
(R&B)Circle,Kakinada
Name of Work:Widening and Strengthening of Yerravaram-Addateegala-Ramavaram road from Km 0/0 to 8/0 in East Godavari
GENERAL ABSTRACT
Sl. No. Particular Amount (Rs.)
PART-(A) KM
1 Road work ( BT 5.82Km + CC 2.18KM) 8 45839357
2 Pipe Culverts - 1R x1m 6 Nos 1503535
3 Slab Culverts-
1Vx2m span 4 Nos 2930775
4 Road Safety Interventions 243754
LS Provisions
5 LS for Seignarage Charges 2280000
6 L.S. for Price Adjustment 600000
7 NAC @ 0.1 % 50600
13
L.S Provision for shifting of utilities( Electrical poles) 100000
14
L.S for PMGSY Logo Board,KM Stones, HM Stones, 5th Stone etc 100000
PART- (B)
Technical sanction is hereby accorded for Rs.606.00 lakhs ( Rupees Six Hundred and SixLakhs only) for
construction cost based on SSR 2019-20 and Rs.36.37 lakhs( Rupees THirty Six Lakhs Thirty Seven
Thoousand only) for maintenance cost under RCPLWE ( Batch I)2019-20 as against the Administrative
Sanction of Rs. 606.00 Lakhs for construction and Rs.36.37 lakhs for maintenance accorded vide G.O
Rt.No.66 dt:28-02-2020 of T,R&B (R.II) Department(Sl.no.2) Department
Description of item
Routine
(with brief
S.l Reference to Quantity Unit Maintenance
specification and
No. MORD (length) (km) Amount in
reference to book of
Rs.
specification)
Rate per km
per year (in
Rs.)
CE(R&B)
SPECIFICATION REPORT
Specification Report accompanying the Estimate for the work " Widening and Strengthening of Yerravaram-Addateeg
Estimate Rs. Lakhs
1) Authority: G.O Rt No.66 of T,R&B R.Ii Department dt:28-02-2020
2). Necessity :
The proposed road comes under the category of Major District Road (MDR) and is very important road for the villagers
The existing road from Km 0/0 to 5/5 is an intermediate lane carriageway of width 5.5m, the stretch from Km 5/5 to
The project will be implemented as a vertical under Left Wing Extremism (LWE) to provide connectivity with necessa
As per the traffic census/3rd party survey , the CVPD is 426 As per Soil investigation results, t
Details of proposed Crust
5 Providing and applying tack coat with bitumen Emulsion @ 0.225Kgs per 1 sqm on prepared b
3 PCC M 10 Concrete mix using 40mm size HBG 100mm thick for leveling course.
4 CC pavement (M30) grade using 20mm & 10mm HBG 200mm thick for CC Pavement.
6). C.D. Works :
The existing Weak & narrow culverts are proposed for reconstruction with Pipe and Slab culverts to 9.00 m. fo
C. D. Works Proposals :-
(i). Reconstruction of Damaged Culverts with 1 Row 1000mm dia. of NP-4 class Hume Pipes. (at Km.0/4(2nos), 0/6, 1/2, 4/1
(ii) Reconstruction of existing 1V X 2.0 m. Span Slab Culverts @ Km 0/2, 0/6, 0/10, 6/10 (4 nos)
The SE is requested to ensure and stability of the structure as per site conditions and codal provisions before going t
6). Road Safety Intervensions :-
proposed as lumpsum provision
Provisions for Road Safety Intervensions.
1 Providing Centreline marking / Zebra Crossing
9). Rates ;
The estimate is prepared with 2019-20 common SSR for all Engineering Departments and latest G.
ABSTRACT ESTIMATE FOR ROAD PART
Widening and Strengthening of Yerravaram-Addateegala-Ramavaram road from
Name of the Work
Km 0/0 to 8/0 in East Godavari District
Sl.
Description of work Quantity Rate Per Amount (Rs.)
No.
1 2 3 4 5 6
Part I A: Road Portion
1 Forming embankment with borrowed useful earth from outside road boundary by
mechanical means upto SDR with all leads and lifts including pre-watering of soil at borrow
area, removal of top soil, excavation of soils at borrowed area, conveyance of soil,
depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading
and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement
of table 300-2 of MoRT&H, including all hire and operational charges of T&P , complete
for finished item of work as per technical specification cl 301 MoRD / MoRT&H specification
305 (5th revision) (Payment will be made based on level for finished item of work).
3 Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base
course on a well prepared sub-base and compacting with Vibratory Roller 80-100 kN weight
to achieve the desired density including lighting, barricading and maintenance of diversion,
etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406 MORD including
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc.,
Complete .
TOTAL 45,839,357
Add extra for Chevrons, continuous line at curve locations, stop lines
60
150
150 549.00 82,350
Sqm Per sqm
2 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded
from HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene Acrylonitrite) and reflective
panels with micro prismatic lens capable of providing total internal reflection of the light
entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D
4280 Type H and complying to Specifications of Category A of MORTH Circular No
RW/NH/33023/10-97 – DO III Dt 11.06. 1997. The height, width and length shall not exceed 50
mm, 100 mm and 100 mm and with minimum reflective area of 13 Sqcm on each side and the
slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated
cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height not less than 30+/- 2
mm) from the body is to be a minimum value of 700 Kgs. Fixing will be by drilling holes on the
road for the twin shanks to go inside, without nails and using epoxy resin based adhesive as per
manufacturer’s recommendation and complete as directed by the engineer.
4 18696.00 74,784
Nos each
4 Supplying and installation of Hazard Markers/Delinators using M.S. angle of size 55x55x6 mm
and 120cm high above ground level painted with two coats of black & white stripes of 15cm
wide with first quality synthetic enamel paint over one coat of appropria
2 10 20 2783.00 55,660
Nos each
TOTAL 243754
Bituminous Macadam
Km 0/200 to 0/550 1x1 350.00 5.5 0.050 96.25
Km 0/750 to 1/200 1x1 450.00 5.5 0.050 123.75
Km 1/280 t0 2/950 1x1 1670.00 5.5 0.050 459.25
Km 3/4 to 5/5 1x1 2100.00 5.5 0.050 577.50
Km 5/5 to 6/750 1x1 1250.00 5.50 0.050 343.75
5820.00 1600.50
0.00 (OR) Say 1601.00
Cum
6 Providing and applying tack coat with bitumen emulsion RS I using Emulsion pressure #REF!
distributor at the rate of 0.20-0.25 Kgs per sqm on the prepared bituminous surface
cleaned with mechanical broom for finished item of work as per Technical Specification
Clause 503 MORD and as directed by the Engineer-in-Charge and including contractors
profit & Over head charges,but excluding Seigniorage charges, GST etc., Complete .
SDBC
Km 0/200 to 0/550 1x1 350.00 5.5 0.025 48.13
Km 0/750 to 1/200 1x1 450.00 5.5 0.025 61.88
Km 1/280 t0 2/950 1x1 1670.00 5.5 0.025 229.63
Km 3/4 to 5/5 1x1 2100.00 5.5 0.025 288.75
Km 5/5 to 6/750 1x1 1250.00 5.50 0.025 171.88
5820.00 800.25
0.00 (OR) Say 801.00
Cum
8 Forming shoulders with borrowed useful seclected earth having MDD of not less than
1.75 gms/cc from outside road boundary by mechnical means with all leads and lifts
including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soils on the embankment, spreading
soils, breaking clods, sectioning and consolidation with vibratory road roller @ OMC to
meet requirement of table 300-2 of MORT&H including all hire and operational charges
of T&P , complete for finished item of work as per technical specification cl. 303 of
MoRD / 407 of MORT&H specification 305 (5th revision) (Payment will be made based
on levels for finished item of work)
Construction of Granular Sub-Base by providing well graded material(Table 400.1A MoRD) with
Grading III Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI Value less than 6
spreading in uniform layers with Motor grader on prepared surface, mixing by mix in place method
1 with rotavator at OMC, and compacting with Vibratory Roller to achieve the desired density,
complete as per Technical Specification Clause 401 MORD including contractors profit & Over head
charges, but excluding Seigniorage charges, GST etc., Complete .
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement
concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or
any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS :
383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher
using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of
125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per
3 drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate
vibrators and finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to
bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-
days, curing compound (where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501 MORD including contractors profit & Over head charges,
excluding Seigniorage charges, GST etc., Complete
2180 2398.00
(OR) Say 2398.00
Cum
ROAD - DATA
Widening and Strengthening of Yerravaram-Addateegala-Ramavaram road
Name of Work ::-
from Km 0/0 to 8/0 in East Godavari District
Sl.No. Quantity Description of Item Rate Amount (Rs.)
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical means
upto SDR with all leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of
soils at borrowed area, conveyance of soil, depositing the soil on the embankment, spreading soil, breaking
clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including all hire and operational charges of T&P , complete for
finished item of work as per technical specification cl 301 MoRD / MoRT&H specification 305 (5th revision)
(Payment will be made based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 18.84
1.00 day Mazdoor unskilled 420.00 420.00
0% Agency area allowance 0.00
438.84
(B) Machinery
1.67 hr Hydraulic Excavator1 cum bucket capacity @ 60 cum 2761.20 4602.00
800.00 t.km Tipper (for 1 Km )= 160 5 6.50 5197.63
Add10% of cost of carriage to cover cost of loading 519.76
and unloading
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2445.70 1222.85
1.00 hr Motor Grador for Grading @ 100 cum per hour 3020.40 3020.40
4.00 hr Water tanker 6 KL 655.20 2620.80
1.00 hr Vibratory roller 8T 2688.50 2688.50
19871.94
(C) Over head charges & Contractors Profit
12.500% OH & CP 12.5% on (A) + (B) 20310.78 2538.85
(D) Total of (A) + (B)+( C) 22849.63
Cost per 100 cum (D) + (E) 22849.63
Rate per Cum 228.50
Rate per 1 cum 228.00
1 Cum
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
2 scarified material with all leads and lifts upto 1000 Mtrs as per technical specification of MoRD
Specn. No.301.9/501.2.2 but excluding Seigniorage charges, GST etc., Complete .
Unit = sqm
Taking output = 100 sqm
(A) Labour
0.01 day Mate 471.00 4.71
0.25 day Mazdoor 420.00 105.00
0% Agency area allowance 0.00
Total 109.71
(B) Machinery
Tractor with ripper attachment @ 60 cum
0.08 hr 423.60 33.89
per hour
0.20 hr Front end loader 1 cum capacity 1594.70 318.94
0.23 hr Tipper 5.50 cum capacity, 4 trips/Hour 941.60 216.57
Total 569.40
(C) Over head charges & Contratcor profit
12.500% OH & CP12.5% on (A) + (B) 679.1184.89
Add Contractors Profit at 10% on (A)+(B)+© 0.00
Cost per 100 sqm 764.00
Rate per 1 sqm 7.64
Rate to be adopted 7.60
1 Sqm
3 Construction of Granular Sub-Base by providing well graded material(Table 400.1A MoRD) with
Grading III Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI Value less than
6 spreading in uniform layers with Motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with Vibratory Roller to achieve the desired
density, complete as per Technical Specification Clause 401 MORD including contractors profit &
Over head charges, but excluding Seigniorage charges, GST etc., Complete .
DATA-CD STRUCTURES
Widening and Strengthening of Yerravaram-Addateegala-
Name of Work :: Ramavaram road from Km 0/0 to 8/0 in East Godavari District
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the
excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge.
Unit : Cum Page 323 of MoRT&H SDB
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
Hydraualic Excavator 1 Cum bucket
6.00 hr 2761.20 hr 16567.20
capacity @ 60 cum/hr
Rate as per G.O. Ms No 10, Dt
240.00 cum cum 0.00
26/7/2005
(C) Over head charges
0.00% Over head charges 0% on (A) + (B) 20077.92 0.00
(D) Total of (A) + (B)+( C) 20077.92
(E) Add Contractors Profit at 10% on (D) 2007.79
Cost per 240 cum (D)+(E) 22085.71
Rate for 1 cum 92.02
Rate to be adopted 92.00
1 Cum
2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding
seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing,
laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th
Revision) and as directed by the Engineer-in-Charge for foundations.
(B) Material
12.00 cum Cost of Selective earth #REF! cum #REF!
Total #REF!
© Machinery
Plate compactor/Power rammer/road
2.50 hr 59.10 hr 147.75
roller
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges
7 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
foundation RCC items.
8 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
Sub structure of R.C.C items.
9 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
Super structure of R.C.C items.
10 Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical
direction so that the weep holes in each horizontal direction is staggered from the weep holes
laying above and below lines as shown in drawing including cost and conveyance of the A.C
pipes and labour charges for cutting to required length, placing the pipe with a slope of about
1V : 20H towards stream side face etc., complete for finished item of work for weep holes as per
SSR Data
11 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed by
the departmental officers as per drawing and Technical specifications as per clause 710.1.1 of
IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
Unit : Cum
Taking out put = 1 Cum Page 520 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
0.35 day Mason 472.00 day 165.20
0.75 day Mazdoor Unskilled 420.00 day 315.00
0% Agency area allowance 499.04 0.00
499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 Cost of stones spalls #REF! #REF!
#REF!
14 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire
and operational charges of all T&P as per approved drawings and as directed during execution
but excluding cost of steel and its fabrication charges for finished item as per SBD specification
1500, 1600, 1700 & 2704 as directed by the Engineer-in-Charge for Approach Slabs
15 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire
and operational charges of all T&P as per approved drawings and as directed during execution
but excluding cost of steel and its fabrication charges for finished item as per SBD specification
1500, 1600, 1700 & 2702 as directed by the Engineer-in-Charge for Wearing Coat over Deck
Slab
Unit = cum Page 477 SDB, Chapter-14
Taking output = 15 cum
(A) Labour
0.90 Day mate 471.00 day 423.90
1.50 Day Mason 472.00 day 708.00
21.00 Day Mazdoor 420.00 day 8820.00
17 Plastering in CM (1:3) Prop: 12 mm thick including cost and conveyance of all materials like
cement, sand,water etc.,to site on all materials,all operational, incidental charges and labour
charges such as mixing mortar,finishing,curing,etc.,complete for finished item of work.
19 #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling
the excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge.
5 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the
Engineer-in-Charge for Bed blocks & Backing walls
7.08 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
(b) approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
7.08 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
(c) approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
0.51/MT
7.12 Drainage spouts complete as per drawing and technical specifications Clause 1209 MORD &
2705 MORTH
Unit = 1 No
(A) Labour
0.03 no mate 471.00 1.00 14.13
0.01 no Mason skilled 0.00 1.00 0.00
0.02 no Black smith 495.00 1.00 9.90
0.22 no Mazdoor 420.00 1.00 92.40
0% Agency area allowance 102.30 0.00
TOTAL A= 116.43
(B) Material
corrosion resistanct structural steel
including 5% wastage (M087, Pg.29 of
0.004 MT SSR 2014-15) 59225.00 1.00 236.90
GI bolt 10mm Dia (M110, Pg.30 of SSR
6.00 nos 2014-15) 23.00 1.00 138.00
G I Pipe 100 mm dia B Class (Sl.32,
2.00 RM Pg.18 of SSR 2016-17) 785.00 1.00 1570.00
7.15 Provision of an Reinforced cement concrete crash barrier at the edges of the road,
approaches to bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it
is built and installed as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified
(B) Material
12.00 cum Cost of Gravel 91.12 cum 1093.44
Total 1093.44
© Machinery
2.50 hr Plate compactor/Power rammer/road roll 59.10 hr 147.75
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) 4345.83 543.23
(E) Total of (A) + (B)+( C)+(D) 4889.06
(F) Add Contractors Profit at 10% on (E) 488.91
Cost per 10 cum (E)+(F) 5377.96
Rate for 1 cum 537.80
Rate to be adopted 538.00
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Cum
7.20 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed
by the departmental officers as per drawing and Technical specifications as per clause
710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
(B) Material
1.20 cum Cost of Gravel #REF! cum #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 10 cum (E)+(F) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification 1500, 1600, 1700 & 2702 as directed by the Engineer-in-Charge for Wearing
Coat over Deck Slab
Unit = cum Page 477 SDB, Chapter-14
Taking output = 15 cum
(A) Labour
0.90 Day mate 471.00 day 423.90
1.50 Day Mason 472.00 day 708.00
21.00 Day Mazdoor 420.00 day 8820.00
Providing 25.4 mm mastic pads for Longitudinal joints, Transversal expansion joints and
13 Construction joints of approved quality including cost, conveyance and placing in position,
etc., complete as directed by the Engineer-in-charge.
Unit = Sqm
Rate as per Building SSR Item No.197 991.00
Providing and laying boulders apron for bed protection against scour with stone boulders
weighing not less than 40kg each complete as per drawing and specification. complete for
finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the
Engineer-in-Charge
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
14 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for levelling course.
16& Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm
20 size including cost, (excluding seigniorage) charges and conveyance of materials to site and
including labour charges for packing the stones for revetment etc., complete for finished item
of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-
Charge for Pitching of slopes
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
8 Provision of an Reinforced cement concrete crash barrier at the edges of the road,
approaches to bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it
is built and installed as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified
Unit = RM
Taking output = 10 RM
M40 Grade concrete
Unit = cum Page SDB, Chapter-12
Taking output = 120cum
(A) Labour
3.00 Day Mason 471.00 day 1413.00
18.84 Day Mazdoor 420.00 day 7912.80
0% Agency area allowance 9325.80 0.00
Total 9325.80
(B) Material
64.80 cum Cost of 20mm SS-5 HBG M/C metal #REF! cum #REF!
43.20 cum Cost of 10mm SS-5 HBG M/C metal #REF! cum #REF!
54.00 cum Sand at site #REF! cum #REF!
52.200 MT Cement at site #REF! MT #REF!
Total #REF!
(C) Machinery
6.00 hr Batching Plant @ 20 cum/hour 1107.10 hr 6642.60
6.00 hr Generator 100 KVA 1316.30 hr 7897.80
6.00 hr Loader 1 cum capacity 1 cum 1594.70 hr 9568.20
15.00 hr Transit Mixer 4 cum capacity for lead upt 2026.60 hr 30399.00
Transit Mixer 4 cum capacity lead
300.00 L 0.00 hr 0.00
beyond 1 Km, L - lead in Kilometer
6.00 hr Concrete Pump 1534.30 hr 9205.80
Total 63713.40
(D) Form work
10.00 % Form work @ 10 on (A)+(B)+( C) #REF! Cum #REF!
(E) Over head charges @
12.50% Add for Over head charges @ 5% on (A)+(B)+( C) #REF! #REF!
(F) Total of (A) + (B)+( C)+(D)+(E) #REF!
(G) Add Contractors Profit at 10% on (F) #REF!
Cost per 120 cum (F)+(G) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
952 702.0 1
sqm sqm
2 Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral
triangle made out of Type – XI of ASTMD 4956-09 wide angle cube cornered
micro Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full
background of White colour and letters/logos done by screen printing in Black
colour, boarders by screen printing in Red colour and fixed over 4MM Aluminium
Composite Material sheet having minimum 0.5 mm thick Aluminium skin on both
sides with back side painted grey colour and fixed over back support frame of
M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a
MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from
the ground level to the bottom of the board. The signpost should be painted
with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and
White colour with bands of 30cm of height. The signpost shall be firmly fixed
with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation
of size 450x450x600mm including cost and conveyance of all materials
,equipment, machinery and labour with all leads and lift, loading chages
necessary for satisfactory completion of the work as directed by Engineer -in-
Charge.
20 6226.0 1
Nos Nos
3 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic
body moulded from HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene
Acrylonitrite) and reflective panels with micro prismatic lens capable of providing
total internal reflection of the light entering the lens face and shall support a load
of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to
Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 – DO III
Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm
and 100 mm and with minimum reflective area of 13 Sqcm on each side and the
slope to the base shall be 35 +/- 5 degree. The strength of detachment of the
integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height
not less than 30+/- 2 mm) from the body is to be a minimum value of 700 Kgs.
Fixing will be by drilling holes on the road for the twin shanks to go inside,
without nails and using epoxy resin based adhesive as per manufacturer’s
recommendation and complete as directed by the engineer.
1118 316.0 1
Nos Nos
4 Providing and erecting a "W" metal beam crash barrier comprising of 3mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150X75X5mm spaced 2m centre-to-centre, 1.80m
high, 1.1m below ground/road level, all steel parts and fitments to be galvanised
by hot dip process, all fittings to conform to IS: 1367 and IS: 1364, metal beam
rail to be fixed on the vertical post with a spacer of channel section
150X75X5mm, 330mm long complete as per Clause 810.
1000 2615.0 1
Each Each
5 Providing Guard stones (1200 x 200 X 200 mm)
2000 102.0 1
Nos Nos
Total Amount
Amount (Rs.)
668304.0
124520.0
353288.0
2615000.0
204000.0
3965112
B) SR& CRN
Road Safety - DATA
Providing and laying of Hot Applied Thermoplastic compound 2.5 mm thick including reflecting glass beads on
bituminous surface at 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass bead
as per IRC:35, the finished surface to be level, uniform and free from streaks and holes etc. complete for
finished item of work (with all leads and Lifts).(Data communicate vide E-in-C(R&B) SR, Circular Memo No.
Road Signages/DCE(R)/EE2/ DEE7/ AEE(NGL)/2013-14; Dt 15-05-2013)
Rate per cum 702.00
Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out of Type – XI
of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC
67:2012 for full background of White colour and letters/logos done by screen printing in Black colour, boarders
by screen printing in Red colour and fixed over 4MM Aluminium Composite Material sheet having minimum
0.5 mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support
frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of
size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the board.
8.02 The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black
and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle
35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and
conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading chages
necessary for satisfactory completion of the work as directed by Engineer -in-Charge.
Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded from
HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene Acrylonitrite) and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support
a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category
A of MORTH Circular No RW/NH/33023/10-97 – DO III Dt 11.06. 1997. The height, width and length shall not
exceed 50 mm, 100 mm and 100 mm and with minimum reflective area of 13 Sqcm on each side and the
8.09 slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of
diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum
value of 700 Kgs. Fixing will be by drilling holes on the road for the twin shanks to go inside, without nails and
using epoxy resin based adhesive as per manufacturer’s recommendation and complete as directed by the
engineer.
3 Vibrated cement concrete M20 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges , centering, machine mixing, laying in position,
Compacting, Vibrating and curing including all other incidental and all other operational charges
of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision) for
body walls.
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 425.00 day 17.00
1.00 day Mazdoor unskilled 400.00 day 400.00
0% Agency area allowance 0.00
417.00
(B) Machinery
Hydraualic Excavator 1 Cum bucket capacity
1.67 hr 2821.50 hr 4711.91
@ 60 cum/hr
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 0.00 cum 0.00
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 425.00 day 17.00
1.00 day Mazdoor unskilled 400.00 day 400.00
0% Agency area allowance 0.00
417.00
(B) Machinery
Hydraualic Excavator 1 Cum bucket capacity
1.67 hr 2821.50 hr 4711.91
@ 60 cum/hr
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 0.00 cum 0.00
Page 73
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Cu
100.00 Compensation for earth from private land hr 0.00
m
0.00
(C) Over head charges
5% Over head charges 5% on (A) + (B) 15816.71 790.84
(D) Total of (A) + (B)+( C) 16607.54
6 Providing, laying Reinforced cement concrete Hume pipes of 1000 mm Dia., NP-4 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 1000mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
Page 74
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
6 Providing, laying Reinforced cement concrete Hume pipes of 600 mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 600 mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
Page 75
DATA-CD STRUCTURES
Name of Work :: Widening and Strengthening of Yerravaram-Addateegala-
Ramavaram road from Km 0/0 to 8/0 in East Godavari District
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling
the excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge. (Payment Based on Levels)
Unit : Cum Page 323 of MoRT&H SDB
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
Hydraualic Excavator 1 Cum bucket
6.00 hr 2761.20 hr 16567.20
capacity @ 60 cum/hr
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for levelling Course
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 Day Mate 471.00 day 405.06
1.50 Day Mason 472.00 day 708.00
20.00 Day Mazdoor 420.00 day 8400.00
0% Agency area allowance 9513.06 0.00
Total 9513.06
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal #REF! cum #REF!
4.05 cum Cost of 20mm SS-5 HBG M/C metal #REF! cum #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1.35 cum Cost of 10mm SS-5 HBG M/C metal #REF! cum #REF!
6.75 cum Sand at site #REF! cum #REF!
4.13 MT Cement at site 3882.00 MT 16032.66
Total #REF!
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 524.70 hr 3148.20
6.00 hr Generator set 35 KVA 987.70 hr 5926.20
hr Water tanker 6 KL capacity 655.20 hr 0.00
Total 9074.40
(D) Form work
% Form work @ 10% on (A)+(B)+( C) #REF! Cum #REF!
(E) Over head charges @ 5%
0.00% Add for Over head charges @ 5% on (A)+(B)+( C) #REF! #REF!
(F) Total of (A) + (B)+( C)+(D)+(E) #REF!
(G) Add Contractors Profit at 10% on (F) #REF!
Cost per 15 cum (F)+(G) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Providing and filling bedding of Granular material around the pipes of Hume pipe culverts
suitably compacted / rammed including cost, (excluding seigniorage) and conveyance of
materials to site etc., complete as per drawing and MoRT&H Specification 2900 ( 5th
Revision) and as directed by the Engineer-in-Charge.
Vibrated cement concrete M20 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges , centering, machine mixing, laying in position,
Compacting, Vibrating and curing including all other incidental and all other operational charges
of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision)
for foundation & Sub structure .
Providing, laying Reinforced cement concrete Hume pipes of 1000 mm Dia., NP-4 class for
pipe culverts including cost and conveyance of Pipes etc., complete and Labour charges for
laying, jointing of 1000mm dia. R.C.C Hume pipes in position including lifting, aligning,
lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and
2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-
Charge for finished item of work. (NP-4 Concrete Pipe on First Class Bedding in Single
Row)
Providing and laying filter material with Gravel underneath pitching in slopes including cost,
(excluding seigniorage) charges and conveyance of materials to site including labour charges
etc., complete for finished item of work as per MoRT&H Specification 2504 (5th Revision) and
as directed by the Engineer-in-Charge
Unit = cum Page 523 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.05 Day Mate 471.00 day 23.55
0.25 Day Mazdoor skilled 472.00 day 118.00
1.00 Day Mazdoor 420.00 day 420.00
0% Agency area allowance 561.55 0.00
Total 561.55
(B) Material
1.20 cum Cost of Gravel #REF! cum #REF!
Total #REF!
(C) Over head charges @ 5%
0.00% Over head charges 0% on (A) + (B) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 10 cum (E)+(F) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm
size including cost, (excluding seigniorage) charges and conveyance of materials to site and
including labour charges for packing the stones for revetment etc., complete for finished item
of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-
Charge for Pitching of slopes
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
0.00% Over head charges 0% on (A) + (B)+(C)+(D) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
Providing and laying Boulder's apron on River Bed for protection against scour with stone
boulders weighing not less than 40 k.g each complete as per drawing and technical
specification 300 mm thick with HBG stone of not less than 300 mm size including cost,
(excluding seigniorage) charges and conveyance of materials to site and including labour
charges for packing the stones for apron etc., complete for finished item of work as per
MoRT&H specification 2503 ( 5th revision ) and as directed by the Engineer-in-Charge for Bed
Protection.
Unit : Cum
Taking out put = 1 Cum Page 520 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
0.35 day Mason 472.00 day 165.20
0.75 day Mazdoor Unskilled 420.00 day 315.00
0% Agency area allowance 499.04 0.00
499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 Cost of stones spalls #REF! #REF!
#REF!
#REF!
(B) Material
6.00 cum Paint (Page No 20, Sno 71) 240.00 cum 1440.00
Total 1440.00
(C) Over head charges @ 5%
0.00% Over head charges 0% on (A) + (B) 2908.52 0.00
(E) Total of (A) + (B)+( C)+(D) 2908.52
(F) Add Contractors Profit at 10% on (E) 290.85
Cost per 40 Sqm (E)+(F) 3199.37
Rate for 1 Sqm 79.98
Rate to be adopted 80.00
1 Sqm
Filling in between body walls with gravel including cost,conveyance and (excluding
seigniorage) of all materials to site etc., complete as per Clause 710.1.4 of IRC : 78 and as
per MoRT&H Specification No. 2200 & 2907 (5th Revision) and as per Drawing and technical
specifications for finished item of work
Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed
by the departmental officers as per drawing and Technical specifications as per clause 710.1.1
of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for Curtainwalls
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification as directed by the Engineer-in-Charge for Foundation
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification as directed by the Engineer-in-Charge for superstructure
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for foundation RCC items.
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Page 449 of MoRT&H SDB
Unit = MT
Taking output = 1 MT
(A) Labour
0.40 no Mate 471.00 1.00 188.40
2.00 no Black smith 495.00 1.00 990.00
6.00 no Mazdoor 420.00 1.00 2520.00
0% Agency area allowance 2520.00 0.00
TOTAL A= 3698.40
(B) Material
1.05 MT HYSD bars including overlaps #REF! 1.00 #REF!
6.00 Kg Binding wire ( I&CAD SSR item no.3 ) 55.00 1.00 330.00
TOTAL B= #REF!
(A + B ) #REF!
0.00% (C) Over Head Charges on (A+B) #REF! #REF!
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
Page 489,490 of MoRT&H SDB
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 3360.00 0.00
TOTAL A= 5052.24
(B) Material
HYSD bars including 5% overlaps and
1.05 MT wastage #REF! 1.00 #REF!
8.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 440.00
TOTAL B= #REF!
(A + B ) #REF!
0.00% (C) Over Head Charges on (A+B) #REF! #REF!
Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical
direction so that the weep holes in each horizontal direction is staggered from the weep holes
laying above and below lines as shown in drawing including cost and conveyance of the A.C
pipes and labour charges for cutting to required length, placing the pipe with a slope of about
1V : 20H towards stream side face etc., complete for finished item of work for weep holes as
per SSR Data
Unit : Cum
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Taking out put = 100 Cum Page 70 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
1.00 day Mazdoor unskilled 420.00 day 420.00
0% Agency area allowance 0.00
438.84
(B) Machinery
Rate as per G.O. Ms No 10, Dt
100.00 cum 13.00 cum 1300.00
26/7/2005
800.00 t.km Tipper (for 10Kms=160x5=800) 6.50 t.km 5197.63
Add 10% of cost of carriage to cover
519.76
cost of80
Dozer loading
HP forand unloading
spreading @ 200 cum
0.50 hr 2445.70 cum 1222.85
per hour
Motor Grador for Grading @ 100 cum
1.00 hr 3020.40 hr 3020.40
per hour
4.00 hr Water tanker 6 KL 655.20 hr 2620.80
1.00 hr Vibratory roller 8T 2688.50 hr 2688.50
16569.94
(C) Over head charges
13% Over head charges 12.5% on (A) + (B) 17008.78 2126.10
(D) Total of (A) + (B)+( C) 19134.88
(E) Add Contractors Profit at 10% on (D) 1913.49
Cost per 100 cum (D) + (E) 21048.37
Rate per Cum 210.48
Rate per 1 cum 210.00
1 Cum
19 Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches
to bridge structures and medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion
joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by
the Engineer, all as specified 809 MORTH
Sl. Quantit
Description of work Rate Per Amount (Rs.)
No. y
1 2 3 4 5 6
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of
structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
excluding seignioarge charges for finished item of work as per technical specification
clause 305 MoRD/304 MoRT&H (5th Revision) but excluding Seigniorage charges, GST
etc., Complete and as directed by the Engineer-in-Charge.
600.0 1023.00
1023.00 94.10 per cum 96,264
Cum
2 Providing concrete for plain concrete M 10 grade using 40 mm , 20 mm ,10 mm Graded
hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted
by vibration including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th
revision) ,including contractors profit & Over head charges, but excluding Seigniorage
charges, GST etc., Complete for levelling course
600.0 93.00
93.00 4209.00 per cum 391,437
Cum
3 Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded
hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted
by vibration including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th
revision) ,including contractors profit & Over head charges, but excluding Seigniorage
charges, GST etc., Complete.
600.0 279
279.00 4302.00 per cum 1,200,258
Cum
4 Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed
in Substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision)
,including contractors profit & Over head charges,but excluding Seigniorage charges,
GST etc., Complete
Protection Work (Retaining
Wall) :-
(1.50+0.4
at Km.8/2 to 8/5 ( R/s) 1 100.00 2.70 256.50
0)/2
(1.20+0.4
at Km11/5-11/9 ( R/s) 1 200.00 2.20 352.00
0)/2
at Km. 13/4 to 13/6 (1.20+0.4
( L/S)
1 100.00 1.80 144.00
0)/2
at Km. 13/4 to 13/6 (1.20+0.4
( R/S)
1 100.00 1.80 144.00
0)/2
(1.20+0.4
at Km26/4-8 (L/s) 1 50.00 2.00 80.00
0)/2
(1.20+0.4
at Km. 26/4-8 (R/s) 1 50.00 2.00 80.00
0)/2
1056.50
1057.00 4550.00 per cum 4,809,350
Cum
5 Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full
width of the structures with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 709, 1200 MORD including contractors profit
& Over head charges but excluding Seigniorage charges, GST etc., Complete etc.
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 439.97
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 342.38
0.08 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 80.53
0.48 cum Sand at site 1093.40 cum 524.83
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2570.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
4.00 % Add @ 4% on (A)+(B)+(C) 147.06
Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3823.63 477.95
(F) Total of (A) + (B)+( C)+(D) 4301.58
Cost per 1 cum (E)+(F) 4301.58
Rate for 1 cum 4301.58
Rate to be adopted 4302.00
1 Cum
4 Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in
Substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807,
1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision) ,including contractors profit &
Over head charges,but excluding Seigniorage charges, GST etc., Complete
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 439.97
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 342.38
0.08 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 80.53
0.48 cum Sand at site 1093.40 cum 524.83
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2570.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.00 hr Generator set 35 KVA 842.20 hr 0.00
Total 209.88
(D) Form work charges @ 10%
10.00 % Add @ 10% on (A)+(B)+(C) 367.66
Over head charges & Contractors profit
12.50% OH&CP @ 12.5 % on (A+B) 4044.23 505.53
(F) Total of (A) + (B)+( C)+(D) 4549.76
Cost per 1 cum (E)+(F) 4549.76
Rate for 1 cum 4549.76
Rate to be adopted 4550.00
1 Cum
OK Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal
(HBG) mechanically mixed in Sub structure as per drawing and technical specifications Clauses 800,
1206 MORD / Sections 1500, 1700,2200 MORTH(5th revision) ,including contractors profit & Over
head charges but excluding Seigniorage charges, GST etc., Complete upto 5m height. - For Sub
Structure
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 770.36
0.36 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 362.38
0.45 cum Sand at site 1093.40 cum 492.03
0.404 MT Cement at site 4300.00 MT 1737.20
Total 3361.97
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
10.00 % Form work @ 10 % on (A)+(B)+( C) 4520.33 Cum 452.03
(E) Over head charges & Contractors profit
12.50% OH & CP @ 12.5 % on A+B+C+D 4972.36 621.55
(F) Total of (A) + (B)+( C)+(D)+(E) 5593.91
Cost per 1 cum (F)+(G) 5593.91
Rate for 1 cum 5593.91
Rate to be adopted 5594.00
1 Cum
OK Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal
(HBG) mechanically mixed in superstructure as per drawing and technical specifications Clauses 800&
1400 MORD ,including contractors profit & Over head charges but excluding Seigniorage charges, GST
etc., Complete upto 5m height. - For Super Structure (Deck slab)
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 770.36
0.36 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 362.38
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.45 cum Sand at site 1093.40 cum 492.03
0.4 MT Cement at site 4300.00 MT 1720.00
Total 3344.77
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
20.00 % Form work @ 20 % on (A)+(B)+( C) 4503.13 Cum 900.63
(E) Over head charges & Contractors profit @ 12.5%
12.50% Over Head charges @ 12.5 % on A+B+C+D 5403.76 675.47
(F) Total of (A) + (B)+( C)+(D)+(E) 6079.23
Cost per 120 cum (F)+(G) 6079.23
Rate for 1 cum 6079.23
Rate to be adopted 6079.00
1 Cum
OK Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm
metal (HBG) mechanically mixed excluding reinforcement complete as per drawing and technical
specifications Clauses 800 and 1404 MORD ,including contractors profit & Over head charges but
excluding Seigniorage charges, GST etc., Complete
Unit = cum
Taking output = 1cum
(A) Labour
0.10 Day mate 471.00 day 47.10
0.12 Day Mason 495.00 day 59.40
3.00 Day Mazdoor 420.00 day 1260.00
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 1490.70 0.00
Total 1490.70
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 770.36
0.36 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 362.38
0.45 cum Sand at site 1093.40 cum 492.03
0.43 MT Cement at site 4300.00 MT 1849.00
Total 3473.77
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
3.00 % Form work @ 3 % on (A)+(B)+( C) 5174.35 Cum 155.23
(E) Over head charges
Over Head charges & Contractor profit @ 12.5 % on
12.50% 5329.58 666.20
A+B+C+D
(F) Total of (A) + (B)+( C)+(D)+(E) 5995.78
Cost per 1 cum (F)+(G) 5995.78
Rate for 1 cum 5995.78
Rate to be adopted 5996.00
1 Cum
OK Supplying, fitting and placing HYSD bar reinforcement (Fe 415)in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202,1203 MORD for Bars below 36 mm dia
including over laps and wastage, where they are not welded ,including contractors profit & Over head
charges but excluding Seigniorage charges, GST etc., Complete- For Foundation
Unit = MT
Taking output = 1 MT
(A) Labour
0.40 no Mate 471.00 1.00 188.40
2.00 no Black smith 495.00 1.00 990.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
6.00 no Mazdoor 420.00 1.00 2520.00
0% Agency area allowance 3698.40 0.00
TOTAL A= 3698.40
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42353.40
(C) Contractor profit & Over Head 42353.40 5294.18
12.50%
Charges on (A+B)
OK Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per
drawings and technical specification Clauses 1000 & 1206 MORD for Bars below 36 mm dia including
over laps and wastage, where they are not welded ,including contractors profit & Over head charges
but excluding Seigniorage charges, GST etc., Complete - For Sub Structures
Unit = MT
Taking output = 1 MT
(A) Labour
0.34 no Mate 471.00 1.00 160.14
2.00 no Black smith 495.00 1.00 990.00
6.50 no Mazdoor 420.00 1.00 2730.00
0% Agency area allowance 3880.14 0.00
TOTAL A= 3880.14
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42535.14
© Contractor Profit & Over Head 42535.14 5316.89
12.50%
Charges on (A+B)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 47852.03
Rate per 1 MT 47852.03
Rate per 1 MT 47852.00
OK Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and
technical specifications Clauses 1000 and 1400 MORD, for Bars below 36 mm dia including over laps
and wastage, where they are not welded ,including contractors profit & Over head charges but
excluding Seigniorage charges, GST etc., Complete- For Super Structures
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 5052.24 0.00
TOTAL A= 5052.24
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
8.00 Kg Binding wire 55.00 1.00 440.00
TOTAL B= 38765.00
(A + B ) 43817.24
Over Head Charges & Contractors 43817.24 5477.16
12.50% (C)
profit @ 12.5% on (A+B)
S.No. Quantity Description of Item Rate per Amount (Rs.)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 49294.40
Rate per 1 MT 49294.40
Rate per 1 MT 49294.00
OK Providing and laying filter material(150mm thick) underneath pitching in slopes including cost,
(excluding seigniorage) charges and conveyance of materials to site including labour charges etc.,
complete for finished item of work as per technical specification Clause 1302 MORD/ MoRT&H
Specification 2504 (5th Revision) including contractors profit & Over head charges but excluding
Seigniorage charges, GST etc., Complete etc.and as directed by the Engineer-in-Charge
Unit = cum
Taking output = 1 cum
(A) Labour
0.05 Day Mate 471.00 day 23.55
0.25 Day Mazdoor skilled 472.00 day 118.00
1.02 Day Mazdoor 420.00 day 428.40
0% Agency area allowance 0.00
Total 569.95
(B) Material
1.20 cum Cost of Gravel 199.60 cum 239.52
Total 239.52
(C) Over head charges & Contractors profit
Over Head charges & Contractor profit @ 12.5 %
12.50% 809.47 101.18
on A+B+C
(E) Total of (A) + (B)+( C)+(D) 910.65
Cost per 10 cum (E)+(F) 910.65
Rate for 1 cum 910.65
Rate to be adopted 911.00
1 Cum
OK Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall,
return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of
1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 709,
1200 MORD including contractors profit & Over head charges but excluding Seigniorage charges, GST
etc., Complete etc.
Unit = RM
Taking output = 30 RM
Cement Mortar (1:3) (Out put = 1Cum)
(a) Material
0.51 MT Cost of Cement 4300.00 1.00 2193.00
1.05 cum Cost of Sand for mortor 1173.40 1.00 1232.07
TOTAL a= 3425.07
3425.07
(b) Labour
0.04 no Mate 471.00 1.00 18.84
0.90 no Mazdoor 420.00 1.00 378.00
0% Agency area allowance 396.84 0.00
TOTAL b= 396.84
Cost per 1 Cum (a+b) 3821.91
(A) Material
31.50 RM AC pipes 100mm dia 253.00 1.00 7969.50
0.00 no collars for AC pipe 15.00 1.00 0.00
0.00 no MS clamps 13.00 1.00 0.00
0.05 cum Cement mortar (1:3) 3821.91 1.00 191.10
TOTAL A= 8160.60
(B) Labour
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.03 no Mate 471.00 1.00 14.13
0.50 no Mason 500.00 1.00 250.00
0.25 no Mazdoor 420.00 1.00 105.00
369.13
0% Agency area allowance 738.26 0.00
TOTAL B= 738.26
(A + B ) 8898.86
Unit = cum
Taking output = 10 cum
(A) Labour
0.28 Day Mate 471 day 131.88
7 Day Mazdoor 420 day 2940
0 Agency area allowance 3071.88 0
Total 3071.88
(B) Material
12 cum Cost of Gravel 199.6 cum 2395.2
Total 2395.2
© Machinery
0.125 Over Head charges & Contractor profit @ 12.5 % on A+B+C 5647.59 705.94875
(E) Total of (A) + (B)+( C)+(D) 6353.53875
Cost per 10 cum (E)+(F) 6353.53875
Rate for 1 cum 635.353875
Rate to be adopted 635
1 Cum
OK Providing and laying filter media with granular crushed aggregates as per specification to a thickness
of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted
to firm condition complete as per drawing and technical specification Clause 710.14 of IRC, 78 &
2200 MORTH(5th revision), including contractors profit & Over head charges but excluding
Seigniorage charges, GST etc., Complete
Unit = cum
Taking output = 10 cum
(A) Labour
0.32 Day Mate 471.00 day 150.72
7.00 Day Mazdoor 420.00 day 2940.00
1.00 Day Mazdoor skiled 472.00 day 472.00
0% Agency area allowance 3562.72 0.00
Total 3562.72
(B) Material
6.00 cum Cost of 150mm size IRC soling stone 247.10 cum 1482.60
6.00 cum Cost of 40mm size IRC metal 716.60 cum 4299.60
S.No. Quantity Description of Item Rate per Amount (Rs.)
Total 5782.20
© Machinery
0.06 hr Water tanker 6 KL capacity 655.20 hr 39.31
Total 39.31
(D) Over head charges & Contractors profit
Over Head charges & Contractor profit @ 12.5 %
12.50% 9384.23 1173.03
on A+B+C
(E) Total of (A) + (B)+( C)+(D) 10557.26
Cost per 10 cum (E)+(F) 10557.26
Rate for 1 cum 1055.73
Rate to be adopted 1056.00
OK Providing and laying pitching on slopes laid over prepared filter media/ gravel backing as per drawing
and technical specifications Clause 1302 MORD / 2504 MORTH including cost and conveyance of all
materials and all labour charges etc., complete including contractors profit & Over head charges, but
excluding GST and seigniorage etc., complete
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 500.00 day 175.00
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 0.00
Total 508.84
(B) Material
1.00 cum Cost of SS Revetment 300m thick 316.60 cum 316.60
0.20 cum Cost of stone spalls 133.75 cum 26.75
Total 343.35
(D) Over head charges & Contractors profit
Over Head charges & Contractor profit @ 12.5 %
12.50% 852.19 106.52
on A+B+C
(E) Total of (A) + (B)+( C)+(D) 958.71
Cost per 1 cum (E)+(F) 958.71
Rate to be adopted 959.00
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight
as per Table 1300.1, no fragment weighing less than 25 / 40 kg laid dry complete as per drawing and
DOUBT technical specifications Clause 1301 MORD / 2503 MORTH(5th revision) including contractors profit &
Over head charges but excluding GST and Seignorage etc. complete. - For Protection Work
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick 316.60 cum 316.60
0.20 cum Cost of stone spalls 133.75 cum 26.75
Total 343.35
(C) Over head charges & Contractors profit
0.13 OH & CP @ 12.5% ON A+B 852.19 106.52
(D) Total of (A) + (B)+( C) 958.71
Cost per 1 cum D 958.71
Rate to be adopted 959.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
OK Drainage spouts complete as per drawing and technical specifications Clause 1404.5 MORD & 2705
MORTH(5th revision)ncluding cost and conveyance of all materials and all labour charges etc.,
complete including contractors profit & Over head charges, but excluding GST and seigniorage etc.,
complete
Unit = 1 No
(A) Labour
0.03 no Mate 471.00 1.00 14.13
0.01 no Mason skilled 500.00 1.00 5.00
0.02 no Black smith 495.00 1.00 9.90
0.40 no Mazdoor 420.00 1.00 168.00
0% Agency area allowance 197.03 0.00
TOTAL A= 197.03
(B) Material
corrosion resistanct structural steel
0.004 MT 38500.00 1.00 154.00
including 5% wastage
1.00 RM G I Pipe 100 mm dia B Class 698.00 1.00 698.00
TOTAL B= 852.00
(A + B ) 1049.03
5.00 % 1049.03 52.45
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction
OK joints of approved quality including cost, conveyance and placing in position, etc., complete as
directed by the Engineer-in-charge.
Unit = Sqm
Rate as per Building SSR Item Unit = Sqm 839.00
1585.6
28.3
7.4
ABSTRACT CUM DETAILED ESTIMATE FOR PIPE CULVERTS
Reconstruction of Damaged Culverts with 1 Row 1000mm dia. of NP-4 class Hume Pipes. (at
Km.0/4(2nos), 0/6, 1/2, 4/10, 6/2 (Total : 6 Nos)
NO. of Culverts 6
Sl. Amount
Description of work Quantity Rate Per
No. (Rs.)
1 2 3 4 5 6
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of
structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
excluding seignioarge charges for finished item of work as per technical specification
clause 305 MoRD/304 MoRT&H (5th Revision) but excluding Seigniorage charges, GST
etc., Complete and as directed by the Engineer-in-Charge.
foundations of
2 6.40 1.40 1.50 26.88
Bodywalls.
foundations of Pipe
1 6.60 1.60 1.80 19.008
portion.
45.888
for 1 Culvert 45.888
For 6 No. of CUlverts 275.328
Say 280.00 94.10 per Cum 26,348
Cum
2 Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20
mm ,10 mm Graded hard stone aggregate (HBG), mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as per
drawings and technical specifications Clause 802, 803,1101,1202 & 1203 MORD and
1500, 1700 & 2100 MORTH ,including contractors profit & Over head charges, but
excluding Seigniorage charges, GST etc., Complete for pipe bedding
(1.25+0.4)
for Bodywalls. 2 6.40 2.45 25.87
/2
(0.608+ ((22/7) x 1.20 x
deduct Pipe portion 2
1.025)/2 1.20)/4
-1.85
26.32
for 1 Culvert 26.32
For 6 No. of CUlverts 157.934
158.00 4550.00 per Cum 718,900
Cum
ABSTRACT CUM DETAILED ESTIMATE FOR PIPE CULVERTS
foundations of
2 8.10 1.40 2.50 56.7
Bodywalls.
foundations of Pipe
1 6.60 3.30 1.50 32.67
portion.
89.37
for 1 Culvert 89.37
For 3 No. of CUlverts 268.11
Say269.00 94.10 per Cum 25,313
Cum
2 Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20
mm ,10 mm Graded hard stone aggregate (HBG), mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as per
drawings and technical specifications Clause 802, 803,1101,1202 & 1203 MORD and
1500, 1700 & 2100 MORTH ,including contractors profit & Over head charges, but
excluding Seigniorage charges, GST etc., Complete for pipe bedding
for Foundations of
Body Walls
2 8.10 1.40 0.15 3.40
Bed Concrete under
Pipe portion.
1 7.96 3.30 0.34 8.93
12.33
for 1 Culvert 12.33
For 3 No. of CUlverts 36.99936
37.00 4209.00 per Cum 155,733
Cum
3 Providing Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG)
mechanically mixed in substructure complete as per drawings and technical
specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 &
2200 MORTH ,including contractors profit & Over head charges,but excluding
Seigniorage charges, GST etc., Complete - For Body walls
(1.25+0.4)/
for Bodywalls. 2 8.10 2.45 32.74
2
(0.608+ ((22/7) x 1.20 x
deduct Pipe 4
1.025)/2 1.20)/4
-3.70
Parapets over
2 7.00 0.40 0.45 2.52
Bodywalls.
31.57
for 1 Culvert 31.57
For 3 No. of CUlverts 94.71
95.00 4550.00 per Cum 432,250
Cum
4 Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
DATA-PIPE CULVERTS
Name of Work ::- Widening and Strengthening of Yerravaram-Addateegala-Ramavaram road
from Km 0/0 to 8/0 in East Godavari District
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
Hydraualic Excavator 1 Cum bucket capacity @
6.00 cum 2761.20 cum 16567.20
60 cum/hr
(C) Over Head Charges & Contractors profit
Over Head Charges & Contrators profit 12.5 % on
12.50% 20077.92 2509.74
(A+B)
(D) Total of (A) + (B)+( C) 22587.66
Cost per 240 cum (D)+(E) 22587.66
Rate for 1 cum 94.12
Rate to be adopted 94.10
1 Cum
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm
Graded hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by
2 vibration including curing for 14 days complete as per drawings and technical specifications Clause 802,
803,1101,1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over head
charges, but excluding Seigniorage charges, GST etc., Complete for pipe bedding
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.576 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 527.96
0.288 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 410.86
0.096 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 96.63
0.48 cum Sand at site 1093.40 cum 524.83
0.250 MT Cement at site 4300.00 MT 1075.00
Total 2635.28
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
Total 209.88
(D) Form work charges @ 4%
% Add @ 4% on (A)+(B)+(C) 0.00
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of mas
2 3 0.5 0.5 1.5
for 1 Culvert 1.5
for 37 NO. of culverts 55.5
56.00 721.00 per cum 40,376
Cum
2
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and te
Abutments 1 9 4 1.85 66.6
Wing walls 4 4.35 1.93 2 67.164
133.76
for 1 Culvert 133.76
for 37 NO. of culverts 4949.27
4950.00 94.10 per cum 465,795
Cum
3 Filling in foundation trenches with Sand as per drawing and technical specification Clause
305.3.9 MORD & 304 MORTH ,including contractors profit & Over head charges, but
excluding Seigniorage charges, GST etc., Complete .
2 9 0.35 8.98
(1.6+1.25)/2
Wing walls 4 4.35 1.93 0.4 13.43
4 4.55 1.53 0.4 11.14
4 4.55 0.4
(1.53+1.13)/2 9.6824
69.8711
for 1 Culvert 69.87
for 37 NO. of culverts 2585.23
2586.00 4302.00 per cum 11,124,972
Cum
5
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete
for abutments
2 9 0.3 0.85 4.59
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed
Bed Blocks 2 9 0.325 0.2 1.17
for 1 Culvert 1.17
for 37 NO. of culverts 43.29
44.00 5307.00 per cum 233,508
Sl. Description of work Rate Per Amount (Rs.)
No. Quantity
Cum
7
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and
AT 80kgs/cum 93.60 kgs
for 1 Culvert 0.09
for 37 NO. of culverts 3.46
3.50 47852.00 per MT 167,482
MT
8
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanic
for Deck slab 1 9 1.6 0.2 2.88
for 1 Culvert 2.88
for 37 NO. of culverts 106.56
107.00 6079.00 per cum 650,453
Cum
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technic
662 Kgs 662
for 1 Culvert 0.66
for 37 NO. of culverts 24.49
24.50 49294.00 per MT 1,207,703
MT
10 Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face complete as per drawing and
technical specification Clauses 709, 1200 MORD including contractors profit & Over head
charges but excluding Seigniorage charges, GST etc., Complete etc.
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per T
at Sill level 1 9 (0.7)/2 0.35 1.10
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of app
At backing walls & 2 9 0.2 3.6
deck slab
for 1 Culvert 3.60
for 37 NO. of culverts 133.20
134.00 839.00 per Sqm 112,426
SQM
(Tentative section)
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back
filling the excavation earth to the extent required etc., complete excluding seignioarge
1 charges for finished item of work as per technical specification clause 305 MoRD/MoRT&H
specification 304(5th Revision) but excluding Seigniorage charges, GST etc., Complete
and as directed by the Engineer-in-Charge.
134.275
for 1 Culvert 134.275
for 4 No. of culverts 537.1
538 94.10 per cum 50,626
Cum
Filling in foundation trenches with Sand as per drawing and technical specification Clause
2 305.3.9 MORD & 304 MORTH ,including contractors profit & Over head charges, but
excluding Seigniorage charges, GST etc., Complete .
For Raft under
Abutments
1 4.70 9.3 0.15 6.56
Wing walls 4 1.30 2.80 0.15 2.18
8.74
for 1 Culvert 8.74
for 4 No. of culverts 34.96
35.00 1441.00 per cum 50,435
Cum
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,
10 mm Graded hard stone aggregate (HBG), mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days complete as per drawings and
3
technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100
MORTH(5th revision) ,including contractors profit & Over head charges, but excluding
Seigniorage charges, GST etc., Complete -- for Levelling Course
For Raft under
Abutments
1 4.40 9 0.15 5.94
Wing walls 4 1.00 2.50 0.15 1.50
7.44
for 1 Culvert 7.44
for 4 No. of culverts 29.76
30.00 4209.00 per cum 126,270
Cum
Sl. No. Description of work Quantity Rate Per Amount (Rs.)
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded
hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications
4
Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th revision)
,including contractors profit & Over head charges, but excluding Seigniorage charges, GST
etc., Complete for foundations
For Raft
under 1 4.40 9
0.6 23.76
Abutments
Wing walls 4 1.00 2.50 0.6 6
29.76
for 1 Culvert 29.76
for 4 No. of culverts 119.04
120.00 4302.00 per cum 516,240
Cum
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804, 805,
5 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision) ,including
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc.,
Complete - For Abutments & wing walls of slab culvert
Below Sill Level
for abutments 2 9 (1.6+1.2)/2 0.4 10.08
for Box wings 4 1 (1.9+1.5)/2 0.4 2.72
Above Sill Level
Abutments up
to bottom of 2 9 2.5 46.35
bed blocks (1.2+0.86)/2
(1+2.95)/
for Box wings 4 2.22 17.54
2 (1.5+0.5)/2
76.69
for 1 Culvert 76.69
for 4 No. of culverts 306.75
307.00 4550.00 per cum 1,396,850
Cum
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal
(HBG) mechanically mixed in sub structure complete as per drawings and technical
specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 &
6 2200 MORTH(5th revision) ,including contractors profit & Over head charges but excluding
Seigniorage charges, GST etc., Complete (upto 5m height) -for Bed blocks & Backing
walls
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per
drawing and technical specifications Clauses 1000 and 1400 MORD, for Bars below 36 mm
9 dia including over laps and wastage, where they are not welded ,including contractors
profit & Over head charges but excluding Seigniorage charges, GST etc., Complete- For
Super Structures
Providing and laying filter media with granular crushed aggregates as per specification to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind abutment, wing wall, return
10
wall to the full height, compacted to firm condition complete as per drawing and technical
specification Clause 710.14 of IRC, 78 & 2200 MORTH(5th revision), including contractors
profit & Over head charges but excluding Seigniorage charges, GST etc., Complete
Behind
abutments
2 (9+7)/2 0.6 2.325 22.32
(0.4+1.4)/
behind Wings 4 0.6 1.72 3.72
2
26.04
for 1 Culvert 26.04
for 4 No. of culverts 104.14
105.00 1056.00 per Cum 110,880
cum
Abutment (1.2+0.86)/
portion
2 7.5 15.45
2
19.45
for 1 Culvert 19.45
for 4 No. of culverts 77.8
78.00 334.00 per Rm 26,052
Rm
Sl. No. Description of work Quantity Rate Per Amount (Rs.)
Backfilling behind abutment, wing wall and return wall complete as per drawings &
technical specification Clause 1206.3 MoRD/ 710.14 of IRC, 78 & 2200 MORTH(5th
12
revision), including contractors profit & Over head charges but excluding Seigniorage
charges, GST etc., Complete
Gravel fill up
2 9.00 1 0.40 7.20
to Sill
(5.8+7.2)/
Above sill 2 (1+1.9)/2 2.325 43.83
2
for 1 Culvert 51.03
for 4 No. of culverts 204.11
205.00 635.00 per Cum 130,175
CUm
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and
13 Construction joints of approved quality including cost, conveyance and placing in position,
etc., complete as directed by the Engineer-in-charge.
For joints to
Wings
4 (1.6+1.2)/2 0.4 2.24
Total
2,930,775
Amount
1 2 3 4 5
#REF!
1
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
2 3 0.5 0.5 1.5
2.00 721.00 per cum
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
Abutments 2 9 2.7 2.85 138.51
3 Filling in foundation trenches with Sand as per drawing and technical specification
Clause 305.3.9 MORD & 304 MORTH ,including contractors profit & Over head charges,
but excluding Seigniorage charges, GST etc., Complete .
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure co
for 2 9 0.3 1.85 9.99
abutments
2 9 0.3 2.28 12.312
2 9 (0+0.7)/2 2.28 14.36
81.48
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically
Bed Blocks 2 9 0.325 0.15 0.88
0.90 5307.00 per cum
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mec
for Deck slab 1 9 3.1 0.28 7.81
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and te
As per SP 13 2000Kgs
2000
2.00 49294.00 per MT
Sl. No.
Description of work Quantity Rate Per
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as
at Sill level 1 9 (2.1+1.5)/ 0.3 4.86
2
4.90 959.00 per Cum
10
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints
At backing walls 2 9 0.28 5.04
& deck slab
Total Amount
Amount (Rs.)
6
#REF!
1,442
Cum
21,549
Cum
18,733
Cum
Amount (Rs.)
357,066
Cum
370,825
Cum
4,776
Cum
48,024
Cum
98,588
MT
Amount (Rs.)
RM
4,699
CUM
4,195
SQM
929,897
CE(R&B)NABARD
ABSTRACT ESTIMATE FOR SLAB CULVERT
Name of the Work Widening and Strengthening of Yerravaram-Addateegala-Ramavaram
road from Km 0/0 to 8/0 in East Godavari District
Sl. No.
Description of work Quantity Rate Per
1 2 3 4 5
NO. of works
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
2 5 0.5 0.5 2.5
for 1 Culvert 2.5
for 5 NO. of culverts 12.5
13.00 721.00 per cum
Cum
2
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
Abutments 2 9 2.7 2.5 121.5
Wing walls 4 3.9 2.14 2.7 90.14
211.64
for 1 Culvert 211.64
for 5 NO. of culverts 1058.18
1059.00 94.10 per cum
Cum
3 Filling in foundation trenches with Sand as per drawing and technical specification
Clause 305.3.9 MORD & 304 MORTH ,including contractors profit & Over head charges,
but excluding Seigniorage charges, GST etc., Complete .
Abutments 2 9 2.7 0.15 7.29
82.69
for 1 Culvert 82.69
for 5 NO. of culverts 413.46
414.00 4302.00 per cum
Cum
5
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure co
for 2 9 0.3 1.85 9.99
abutments
2 9 0.3 2.35 12.69
2 9 (0+0.7)/2 2.35 14.81
83.92
for 1 Culvert 83.92
for 5 NO. of culverts 419.62
420.00 4550.00 per cum
Cum
6
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically
Bed Blocks 2 9 0.325 0.2 1.17
for 1 Culvert 1.17
Sl. No.
Description of work Quantity Rate Per
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings
AT 80 Kgs/cum 93.60 Kgs
for 1 Culvert 0.09
for 5 NO. of culverts 0.47
0.50 47852.00 per MT
MT
8
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mec
for Deck slab 1 9 4.1 0.35 12.92
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and te
2556Kgs
2556
11
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as
at Sill level 1 9 (3.1+2.7)/ 0.3 7.83
2
for 1 Culvert 7.83
for 5 NO. of culverts 39.15
Sl. No.
Description of work Quantity Rate Per
40.00 959.00 per Cum
CUM
12
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints
2 9 0.35 6.3
At backing walls
& deck slab
Total Amount
Amount (Rs.)
6
5
4 ( 5nos)
9,373
99,652
89,342
Amount (Rs.)
1,781,028
1,911,000
Amount (Rs.)
31,842
23,926
395,135
630,963
RM
Amount (Rs.)
38,360
26848.00
5037469.00
CE(R&B)
DATA-SLAB CULVERT
Name of Work :: Widening and Strengthening of Yerravaram-Addateegala-Ramavaram
road from Km 0/0 to 8/0 in East Godavari District
S.No. Quantity Description of Item Rate per Amount (Rs.)
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per
drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation
earth to the extent required etc., complete excluding seignioarge charges for finished item of work
as per technical specification clause 305 MoRD/MoRT&H specification 304(5th Revision) but
excluding Seigniorage charges, GST etc., Complete and as directed by the Engineer-in-Charge.
1
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
6.00 hr Hydraulic excavator 2761.20 cum 16567.20
(B) Material
1.20 cum Cost of sand 958.40 cum 1150.08
Total 1150.08
© Machinery
2.50 hr Plate compactor/Power rammer/road roll 0.00 hr 0.00
0.05 hr Water tanker 6 KL capacity 0.00 hr 0.00
Total 0.00
(D) Over head charges
12.5% Over head charges on A+B 1280.79 160.10
(E) Total of (A) + (B)+( C)+(D) 1440.89
(F) Add Contractors Profit at 10% on (E) 0.00
Cost per 1 cum (E)+(F) 1440.89
Rate for 1 cum 1440.89
Rate to be adopted 1441.00
1 Cum
S.No. Quantity Description of Item Rate per Amount (Rs.)
3 Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm
Graded hard stone aggregate (HBG), mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications Clause
802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th revision) ,including contractors
profit & Over head charges, but excluding Seigniorage charges, GST etc., Complete
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.576 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 527.96
0.288 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 410.86
0.096 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 96.63
0.48 cum Sand at site 1093.40 cum 524.83
0.250 MT Cement at site 4300.00 MT 1075.00
Total 2635.28
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
0.00 % Add @ 4% on (A)+(B)+(C) 0.00
(E) Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3741.64 467.71
(F) Total of (A) + (B)+( C)+(D) 4209.35
Cost per 1 cum (E)+(F) 4209.35
Rate for 1 cum 4209.35
Rate to be adopted 4209.00
1 Cum
4 Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone
aggregate (HBG), mechanically mixed, placed in foundation and compacted by vibration including
curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 &
1203 MORD and 1500, 1700 & 2100 MORTH(5th revision) ,including contractors profit & Over head
charges, but excluding Seigniorage charges, GST etc., Complete for foundations
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 439.97
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 342.38
0.08 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 80.53
0.48 cum Sand at site 1093.40 cum 524.83
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2570.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
4.00 % Add @ 4% on (A)+(B)+(C) 147.06
S.No. Quantity Description of Item Rate per Amount (Rs.)
Over head charges & Contractors profit
S.No. Quantity Description of Item Rate per Amount (Rs.)
12.50% OH& CP 12.5 % on (A+B) 3823.63 477.95
(F) Total of (A) + (B)+( C)+(D) 4301.58
Cost per 1 cum (E)+(F) 4301.58
Rate for 1 cum 4301.58
Rate to be adopted 4302.00
1 Cum
5 Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807,
1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision) ,including contractors profit &
Over head charges,but excluding Seigniorage charges, GST etc., Complete - For Abutments &
wing walls of slab culvert
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 916.60 cum 439.97
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 342.38
0.08 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 80.53
0.48 cum Sand at site 1093.40 cum 524.83
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2570.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 842.20 hr 0.00
Total 209.88
(D) Form work charges @ 10%
10.00 % Add @ 10% on (A)+(B)+(C) 367.66
Over head charges & Contractors profit
12.50% OH&CP @ 12.5 % on (A+B) 4044.23 505.53
(F) Total of (A) + (B)+( C)+(D) 4549.76
Cost per 1 cum (E)+(F) 4549.76
Rate for 1 cum 4549.76
Rate to be adopted 4550.00
1 Cum
6 Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG)
mechanically mixed in sub structure complete as per drawings and technical specification Clauses
802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision)
,including contractors profit & Over head charges but excluding Seigniorage charges, GST etc.,
Complete (upto 5m height) -for Bed blocks & Backing walls
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 770.36
0.36 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 362.38
0.45 cum Sand at site 1093.40 cum 492.03
0.35 MT Cement at site 4300.00 MT 1505.00
Total 3129.77
(C) Machinery
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
S.No. Quantity Description of Item Rate per Amount (Rs.)
(D) Form work
10.00 % Form work @10 on (A)+(B)+( C) 4288.13 Cum 428.81
(E) Over head charges
12.50% Over Head charges& Contractor profit @ 12.5 % 4716.94 589.62
on A+B+C+D
(F) Total of (A) + (B)+( C)+(D)+(E) 5306.56
Cost per 1 cum (F)+(G) 5306.56
Rate for 1 cum 5306.56
Rate to be adopted 5307.00
1 Cum
7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per
drawings and technical specification Clauses 1000 & 1206 MORD for Bars below 36 mm dia including
over laps and wastage, where they are not welded ,including contractors profit & Over head charges
but excluding Seigniorage charges, GST etc., Complete - For Sub Structures
Unit = MT
Taking output = 1 MT
(A) Labour
0.34 no Mate 471.00 1.00 160.14
2.00 no Black smith 495.00 1.00 990.00
6.50 no Mazdoor 420.00 1.00 2730.00
0% Agency area allowance 3880.14 0.00
TOTAL A= 3880.14
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42535.14
Contractor Profit & Over Head 42535.14 5316.89
12.50% (C )
Charges on (A+B)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 47852.03
Rate per 1 MT 47852.03
Rate per 1 MT 47852.00
8 Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal
(HBG) mechanically mixed in superstructure as per drawing and technical specifications Clauses 800&
1400 MORD ,including contractors profit & Over head charges but excluding Seigniorage charges,
GST etc., Complete upto 5m height. - For Super Structure (Deck slab)
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1426.60 cum 770.36
0.36 cum Cost of 10mm SS-5 HBG M/C metal 1006.60 cum 362.38
0.45 cum Sand at site 1093.40 cum 492.03
0.4 MT Cement at site 4300.00 MT 1720.00
Total 3344.77
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
20.00 % Form work @ 20 % on (A)+(B)+( C) 4503.13 Cum 900.63
(E) Over head charges & Contractors profit @ 12.5%
12.50% Over Head charges @ 12.5 % on A+B+C+D 5403.76 675.47
(F) Total of (A) + (B)+( C)+(D)+(E) 6079.23
S.No. Quantity Description of Item Rate per Amount (Rs.)
Cost per 1 cum (F)+(G) 6079.23
Rate for 1 cum 6079.23
S.No. Quantity Description of Item Rate per Amount (Rs.)
Rate to be adopted 6079.00
1 Cum
9 Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing
and technical specifications Clauses 1000 and 1400 MORD, for Bars below 36 mm dia including over
laps and wastage, where they are not welded ,including contractors profit & Over head charges but
excluding Seigniorage charges, GST etc., Complete- For Super Structures
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 5052.24 0.00
TOTAL A = 5052.24
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
8.00 Kg Binding wire 55.00 1.00 440.00
TOTAL B= 38765.00
(A + B ) 43817.24
12.50% (C ) Over Head Charges & Contractors 43817.24 5477.16
profit @ 12.5% on (A+B)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 49294.40
Rate per 1 MT 49294.40
Rate per 1 MT 49294.00
10 Providing and laying filter media with granular crushed aggregates as per specification to a thickness
of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall, return wall to the full height,
compacted to firm condition complete as per drawing and technical specification Clause 710.14 of
IRC, 78 & 2200 MORTH(5th revision), including contractors profit & Over head charges but excluding
Seigniorage charges, GST etc., Complete
Unit = cum
Taking output = 10 cum
(A) Labour
0.32 Day Mate 471.00 day 150.72
7.00 Day Mazdoor 420.00 day 2940.00
1.00 Day Mazdoor skiled 472.00 day 472.00
0% Agency area allowance 3562.72 0.00
Total 3562.72
(B) Material
6.00 cum Cost of 150mm size IRC soling stone 247.10 cum 1482.60
6.00 cum Cost of 40mm size IRC metal 716.60 cum 4299.60
Total 5782.20
© Machinery
0.06 hr Water tanker 6 KL capacity 655.20 hr 39.31
Total 39.31
(D) Over head charges
Over Head charges & Contractor profit @ 12.5 %
12.50% 9384.23 1173.03
on A+B+C
(E) Total of (A) + (B)+( C)+(D) 10557.26
Cost per 10 cum (E)+(F) 10557.26
Rate for 1 cum 1055.73
Rate to be adopted 1056.00
1 Cum
S.No. Quantity Description of Item Rate per Amount (Rs.)
11 Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100
Unit = RM
Taking output = 30 RM
Cement Mortar (1:3) (Out put = 1Cum)
(a) Material
0.51 MT Cost of Cement 4300.00 1.00 2193.00
1.05 cum Cost of Sand for mortor 1173.40 1.00 1232.07
TOTAL a= 3425.07
3425.07
(b) Labour
0.04 no Mate 471.00 1.00 18.84
0.90 no Mazdoor 420.00 1.00 378.00
0% Agency area allowance 396.84 0.00
TOTAL b= 396.84
Cost per 1 Cum (a+b) 3821.91
(A) Material
31.50 RM AC pipes 100mm dia 253.00 1.00 7969.50
0.00 no collars for AC pipe 15.00 1.00 0.00
0.00 no MS clamps 13.00 1.00 0.00
0.05 cum Cement mortar (1:3) 3821.91 1.00 191.10
TOTAL A= 8160.60
(B) Labour
0.03 no Mate 471.00 1.00 14.13
0.50 no Mason 500.00 1.00 250.00
0.25 no Mazdoor 420.00 1.00 105.00
369.13
0% Agency area allowance 738.26 0.00
TOTAL B= 738.26
(A + B ) 8898.86
( C) Over Head Charges & Contractor 8898.86 1112.36
12.50%
profir @ 12.5 % On A+B
30.00 RM TOTAL Cost for 30 RM = (A+B+C+D+E) 10011.22
Rate per 1 RM 333.71
Rate per 1 RM 334.00
12 Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1206.3 MoRD/ 7
Unit = cum
Taking output = 10 cum
(A) Labour
0.28 Day Mate 471.00 day 131.88
7.00 Day Mazdoor 420.00 day 2940.00
0.00 Agency area allowance 3071.88 0.00
Total 3071.88
(B) Material
12.00 cum Cost of Gravel 199.60 cum 2395.20
Total 2395.20
S.No. Quantity Description of Item Rate per Amount (Rs.)
(C ) Machinery
2.50 hr Plate compactor/Power rammer/road roll 59.10 hr 147.75
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges & Contractors profit
Over Head charges & Contractor profit @ 12.5 %
12.50% 5647.59 705.95
on A+B+C
(E) Total of (A) + (B)+( C)+(D) 6353.54
Cost per 10 cum (E)+(F) 6353.54
Rate for 1 cum 635.35
Rate to be adopted 635.00
1 Cum
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction
OK joints of approved quality including cost, conveyance and placing in position, etc., complete as
directed by the Engineer-in-charge.
Unit = Sqm
Rate as per Building SSR Item Unit = Sqm 839.00
DETAILED ESTIMATES FOR Traffic
Name of work : Improvement of Radial Road No.30 i.e from Hyderabad Central University Depot to Vattinagulapally Vi
2 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic
15321 316.0 1
nos sqm
3 Providing and fixing informatory/ facilatative sign board size 600x800 mm made
136 7432.0 1
Nos Nos
4 Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral
triangle made out of Type – XI of ASTMD 4956-09 High Intensity Prismatic
Retro reflective sheeting and confirming to IRC 67:2012 for full background of
White colour and letters
312 6226.0 1
Nos Nos
5 Supplying and installation of Hazard Markers/Delinators using M.S. angle of size
55x55x6 mm and 120cm high above ground level painted with two coats of black
& white stripes of 15cm wide with first quality synthetic enamel paint over one
coat of appropria
20 4003.0 1
Nos Nos
6 Supplying and installation of delineators (Roadway indicators) not less than
800mm high above ground level. The delineator shall have a core and shell
construction which shall be made of tough, high impact resistant, injection-
molded, thermoplastic outer
1379 1541.0 1
Nos Nos
7 Providing and fixing Mandatory / Regulatory sign boards size 900 mm circle
made out of Type – XI of ASTMD 4956-09 wide angle cube cornered micro
Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full
background of White colour and letters/logos done by screen printing in Black
colour, boarders by screen printing in Red colour and fixed over 4MM Aluminium
Composite Material sheet having minimum 0.5 mm thick Aluminium skin on both
sides with back side painted grey colour and fixed over back support frame of
M.S angle 25x25x3mm all roundand fixing with 35x35x4mm and mounted on a
MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from
the ground levelto the bottom of the board. The signpost should be painted
with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and
White colour with bands of 30cm of height. The signpost shall be firmly fixed
with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation
of size 450x450x600mm including cost and conveyance of all materials
,equipment, machinery and labour with all leads and lift, loading charges
necessary for satisfactory completion of the work as directed by Engineer -in-
Charge.
136 9342.0 1
Nos Nos
8 Providing and fixing Village name board size 900x450 mm made out of Type – IV
of ASTMD 4956-09 High Intensity Prismatic Prismatic Retro reflective sheeting
and confirming to IRC 67:2012 for full background of Green Colour & White
Letters and fixed over 3
0 5477.0 1
Nos Nos
9 Providing & fixing junctin boards of size 1500 x 1200 mm made out of Type – IV
of ASTMD 4956-09 High Intensity Prismatic Retro reflective sheeting and
confirming to IRC 67:2012 for full background of Green Colour & White Letters
and fixed over 4MM Allumi
22 26998.0 1
Nos Nos
Manufacturing Supplying and fixing
10 Kilometer stone - Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position including painting and
printing etc
5th Kilometere Stone (precast) 16 3468.0 1
Ordinary Kilometer stone 32 2044.0 1
Hectmeter stone 184 593.00 1
12 Construction of cement concrete kerb with top and bottom width 115 and 165
mm respectively, 440 mm high as shown in drawing in M 20 grade PCC, kerb
stone laid with kerb laying machine, all complete as per clause 408 (5th revision)
and as directed by the E
4799 393.0 1
RM RM
9 painting 2 coats after filling the surface with synthetic enamel paint in all shades
on new plastered concrete surface as per Tech Specification 800 MORTH (5th
revision) and as directed by the Engineer in charge
14708 91.0 1
sqm sqm
18183 232.0 1
sqm sqm
Total Amount
Amount (Rs.)
6860646.0
4841436.0
1010752.0
1942512.0
80060.0
2125039.0
1270512.0
0.0
593956.0
55488.0
65408.0
109112.0
1886007.0
1338428.0
4218456.0
26397812
ABSTRACT ESTIMATE FOR BOX CULVERTS
0
Name of the Work
Sl. No.
Description of work Quantity Rate Per Amount (Rs.)
1 2 3 4 5 6
Box Culverts - 1V of 8M X 7 M (@ SD Road: 6/6-8,6/8-10,7/2-4(3nos) & VD road: 2/0-2,9/2-4(A) 2nos
1
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprisi
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Grade
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG)
Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm metal
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, re
Drainage spouts complete as per drawing and technical specifications Clause 1404.5 MORD & 2705 MORTH
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joint
9 150 mm soling stone HBG metal 6 86.60 90.50 70.00 0.00 247.10 Cum
17 HBG Stone chips 2.36mm and below 6 86.60 350.00 0.00 0.00 436.60 Cum
18 Quarry Rubbish 6 86.60 84.75 0.00 0.00 171.35 Cum
19 Gravel 6 86.60 113.00 0.00 0.00 199.60 Cum
20 selected earth 5 75.30 86.00 0.00 0.00 Err:522 Cum
B) FOR C.D. WORKS
1 40 mm SS-5 HBG metal M/C 6 86.60 608.00 70.00 152.00 916.60 Cum
2 25 mm SS-5 HBG M/C metal 6 86.60 976.00 70.00 244.00 1376.60 Cum
3 20 mm SS-5 HBG M/C metal 6 86.60 1016.00 70.00 254.00 1426.60 Cum
4 12 mm SS-5 HBG M/C metal 6 86.60 808.00 70.00 202.00 1166.60 Cum
5 10 mm SS-5 HBG M/C metal 6 86.60 680.00 70.00 170.00 1006.60 Cum
6 6 mm SS-5 HBG M/C metal 6 86.60 524.00 70.00 131.00 811.60 Cum
7 Sand for Concrete 54 583.40 510.00 0.00 0.00 1093.40 Cum
Ref ::- For Emulsion (Bulk) :- HPCL Price List With Effect From 16-02-2020
For Bulk BitumenVG10, VG30:- HPCL Price List With Effect From 01-03-2020
8 109.20 8 109.20
9 120.50 9 120.50
10 131.80 10 131.80
11 143.10 11 143.10
12 154.40 12 154.40
13 165.70 13 165.70
14 177.00 14 177.00
15 188.30 15 188.30
16 199.60 16 199.60
17 210.90 17 210.90
18 222.20 18 222.20
19 233.50 19 233.50
20 244.80 20 244.80
21 256.10 21 256.10
22 267.40 22 267.40
23 278.70 23 278.70
24 290.00 24 290.00
25 301.30 25 301.30
26 312.60 26 312.60
27 323.90 27 323.90
28 335.20 28 335.20
29 346.50 29 346.50
30 357.80 30 357.80
31 367.20 31 367.20
32 376.60 32 376.60
33 386.00 33 386.00
34 395.40 34 395.40
35 404.80 35 404.80
36 414.20 36 414.20
37 423.60 37 423.60
38 433.00 38 433.00
39 442.40 39 442.40
40 451.80 40 451.80
41 461.20 41 461.20
42 470.60 42 470.60
43 480.00 43 480.00
44 489.40 44 489.40
45 498.80 45 498.80
46 508.20 46 508.20
47 517.60 47 517.60
48 527.00 48 527.00
49 536.40 49 536.40
50 545.80 50 545.80
51 555.20 51 555.20
52 564.60 52 564.60
53 574.00 53 574.00
54 583.40 54 583.40
55 592.80 55 592.80
56 602.20 56 602.20
57 611.60 57 611.60
58 621.00 58 621.00
59 630.40 59 630.40
60 639.80 60 639.80
61 649.20 61 649.20
62 658.60 62 658.60
63 668.00 63 668.00
64 677.40 64 677.40
65 686.80 65 686.80
66 696.20 66 696.20
67 705.60 67 705.60
68 715.00 68 715.00
69 724.40 69 724.40
70 733.80 70 733.80
71 743.20 71 743.20
72 752.60 72 752.60
73 762.00 73 762.00
74 771.40 74 771.40
75 780.80 75 780.80
76 790.20 76 790.20
77 799.60 77 799.60
78 809.00 78 809.00
79 818.40 79 818.40
80 827.80 80 827.80
81 837.20 81 837.20
82 846.60 82 846.60
83 856.00 83 856.00
84 865.40 84 865.40
85 874.80 85 874.80
86 884.20 86 884.20
87 893.60 87 893.60
88 903.00 88 903.00
89 912.40 89 912.40
90 921.80 90 921.80
91 931.20 91 931.20
92 940.60 92 940.60
93 950.00 93 950.00
94 959.40 94 959.40
95 968.80 95 968.80
96 978.20 96 978.20
97 987.60 97 987.60
98 997.00 98 997.00
99 1006.40 99 1006.40
100 1015.80 100 1015.80
101 1025.20 101 1025.20
102 1034.60 102 1034.60
103 1044.00 103 1044.00
104 1053.40 104 1053.40
105 1062.80 105 1062.80
106 1072.20 106 1072.20
107 1081.60 107 1081.60
108 1091.00 108 1091.00
109 1100.40 109 1100.40
110 1109.80 110 1109.80
111 1119.20 111 1119.20
112 1128.60 112 1128.60
113 1138.00 113 1138.00
114 1147.40 114 1147.40
115 1156.80 115 1156.80
116 1166.20 116 1166.20
117 1175.60 117 1175.60
118 1185.00 118 1185.00
119 1194.40 119 1194.40
120 1203.80 120 1203.80
121 1213.20 121 1213.20
122 1222.60 122 1222.60
123 1232.00 123 1232.00
124 1241.40 124 1241.40
125 1250.80 125 1250.80
126 1260.20 126 1260.20
127 1269.60 127 1269.60
128 1279.00 128 1279.00
129 1288.40 129 1288.40
130 1297.80 130 1297.80
131 1307.20 131 1307.20
132 1316.60 132 1316.60
133 1326.00 133 1326.00
134 1335.40 134 1335.40
135 1344.80 135 1344.80
136 1354.20 136 1354.20
137 1363.60 137 1363.60
138 1373.00 138 1373.00
139 1382.40 139 1382.40
140 1391.80 140 1391.80
141 1401.20 141 1401.20
142 1410.60 142 1410.60
143 1420.00 143 1420.00
144 1429.40 144 1429.40
145 1438.80 145 1438.80
146 1448.20 146 1448.20
147 1457.60 147 1457.60
148 1467.00 148 1467.00
149 1476.40 149 1476.40
150 1485.80 150 1485.80
151 1495.20 151 1495.20
152 1504.60 152 1504.60
153 1514.00 153 1514.00
154 1523.40 154 1523.40
155 1532.80 155 1532.80
156 1542.20 156 1542.20
157 1551.60 157 1551.60
158 1561.00 158 1561.00
159 1570.40 159 1570.40
160 1579.80 160 1579.80
161 1589.20 161 1589.20
162 1598.60 162 1598.60
163 1608.00 163 1608.00
164 1617.40 164 1617.40
165 1626.80 165 1626.80
166 1636.20 166 1636.20
167 1645.60 167 1645.60
168 1655.00 168 1655.00
169 1664.40 169 1664.40
170 1673.80 170 1673.80
171 1683.20 171 1683.20
172 1692.60 172 1692.60
173 1702.00 173 1702.00
174 1711.40 174 1711.40
175 1720.80 175 1720.80
176 1730.20 176 1730.20
177 1739.60 177 1739.60
178 1749.00 178 1749.00
179 1758.40 179 1758.40
180 1767.80 180 1767.80
181 1777.20 181 1777.20
182 1786.60 182 1786.60
183 1796.00 183 1796.00
184 1805.40 184 1805.40
185 1814.80 185 1814.80
186 1824.20 186 1824.20
187 1833.60 187 1833.60
188 1843.00 188 1843.00
189 1852.40 189 1852.40
190 1861.80 190 1861.80
191 1871.20 191 1871.20
192 1880.60 192 1880.60
193 1890.00 193 1890.00
194 1899.40 194 1899.40
195 1908.80 195 1908.80
196 1918.20 196 1918.20
197 1927.60 197 1927.60
198 1937.00 198 1937.00
199 1946.40 199 1946.40
200 1955.80 200 1955.80
Cost of Materials, Labour
SSR 2019-20
Material Rates
60 to 63 mm IRC & MoRTH HBG metal 399.05
S.No.
50 to 55 mm IRC & MoRTH HBG metal 434.30
40 to 45 mm IRC & MoRTH HBG metal 560.00
Granite for SS Revetment 300mm (HBG) 163.80 1
Granite for SS Revetment 225mm (HBG) 168.55 2
SS Revetment work 225mm 145.00 3
SS Revetment work 300mm 160.00 4
SS Revetment work 450mm 148.55 5
Laterite for Revetment 225mm 129.50 6
Laterite for Revetment 300mm 151.43 7
Jeddy stone above 450mm to 600mm 196.20
Quarry spall(Field picked metal)
47.15
Av. Of rate 25mm & 40mm
150 mm soling stone HBG metal 90.50
40 to 45 mm IRC & MoRTH HBG M/C metal 560.00
25 to 27 mm IRC & MoRTH HBG M/C metal 899.05
19 to 22 mm IRC & MoRTH HBG M/C metal 937.15
12 to 14 mm IRC & MoRTH HBG M/C metal 742.85 37.84711526
9.5 to 11.20 mm IRC & MoRTH HBG M/C meta 624.75
5 to 7 mm IRC & MoRTH HBG M/C metal 480.00
2.36 to 5 mm IRC & MoRTH HBG M/C metal 350.00
HBG Stone chips 2.36mm and below 350.00
Gravel 113.00
40 mm SS-5 m/c HBG metal 608.00 209.7962417
25 mm SS-5 m/c HBG metal 976.00
20 mm SS-5 m/c HBG metal 1016.00
12 mm SS-5 m/c HBG metal 808.00
10 mm SS-5 m/c HBG metal 680.00
6 mm SS-5 m/c HBG metal 524.00
Sand for Mortar 590.00
Sand for concrete 510.00
Sand for Filling 375.00
1st class
500.00
460 2nd class
853.90
items S.No.61
0.15
SEIGNIORAGE CHARGES
Seigniorag
Sno Item Qty Co-eff Rate Amount in Rs.
e
3 PCC M15 for Body Walls Metal 158.00 0.80 90.00 11376.00
4 Filling in between body walls with gravel 68.00 1.2 45.00 3672.00
gravel
Slab Culverts
1 Earthwork in excavation for Earth 538.00 1 45.00 24210.00
foundation of structures
2 Sand filling in foundation Sand 35.00 1.20 100.00 4200.00
3 PCC M10 for Levelling Course Metal 30.00 0.96 90.00 2592.00