Aramco Standard Reference Rev 2
Aramco Standard Reference Rev 2
Aramco Standard Reference Rev 2
Construction of Equipments.
1CA2PXXX=Service
Service
Corrosion Allowance
Line Material
Pressure Ratings
Butt welded fittings Wrought Fittings (Elbows) : Make by bending the Pipe
ASME B16.9 = Steel butt welding fittings CS ASTM A234Gr.WP B/C
ASME B16.28 = Short radius elbows SS ASTM A403 WP304/WP304L; A403 WP 316/316L
Alloy ASTM A234 WP1/WP5/WP7/WP9/P11
LTCS ASTM 420 WPL6
Socket & Threaded fittings Cast Fittings : Pouring of Molten metal & making shape
ASME B16.11 : - Forged steel socket CS ASTM A216 B/C, A352 LCB/C.
Welding & threaded fittings SS ASTM A217 CA15; A296 CA15
Alloy ASTM A217 WC1/WC5/WC6/WC9
Valves Gasket
ASME B16.10 = Dimension of valves ASME B16.20 = Metallic Gasket
ASME B16.34 = Connection Valves ASME B16.21 = Nonmetallic gasket
Pipe = Hallow shape use for transmission of fluids/liquids/gases/ from one end to other end.
Gr. = Grade
TP = Tubular Product
WP = Weld able Cast.
N = Normalization (Type of Heat Treatment).
CS = Carbon Steel
SS = Stainless Steel
Pipe = 3 Types
1. ERW Pipe (Electric Resistance Weld) (Above 85% Efficiency).
2. Seamless Pipe (Above 90 % Efficiency).
3. Spiral Pipe (Above 70 % Efficiency).
Material Specification for Pipes / Fittings / Valve for more details refer SAES-L-105
01-SAMSS-035 = API Pipes 02-SAMSS-001 = low Tem. Service Fittings 04-SAMSS-001 = Gate Valve
01-SAMSS-332 = Grade B Pipes 02-SAMSS-005 = Butt Weld Fittings 04-SAMSS-003 = Low Temp Valve
01-SAMSS-333 = Grade C Pipes 02-SAMSS-011 = Flanges 04-SAMSS-005 = Check Valve
Control Valve: 1. Rotatory Motion & Linear motion to control the flow.
2. This Valve is motorized. (Actuators & Motors are used)(MOV).
3. Used to Control the flow as a result control in liquid level, pressure & temp.
Gate Valve: 1. Seat (Plate) is moved up & down to control the flow.
2. It seals the surface between Gate and Seat. (A & M).
3. it’s often used in liquid services.
Plug Valve: 1. Plug rotate in the body of Valve to control the flow.
2. Plug valves have one or more hollow passageways going sideways through
The plug, so that fluid can flow through the plug when the valve is open.
Check Valve: 1. Swing, Disc & Ball are used to control the flow.
2. It allows to flow fluid in one direction.
3. The pressure of forward fluid flow opens the valve (Swing, disc or ball) and the
pressure from backflow closes it, forcing the (Swing, Disc or Ball) against seat.
API-598:Testing of Valves
Testing depends upon Ratings of Valve (150#, 300#, 600#, 900#, and 1200#).
Types of Testing
1) Seat Test (30Sec - 2Min) Max can be done by
i) Pneumatic Test ii) Hydro Test
Seat Test will be carried out by two methods and done as per Data Sheet & Vendor.
During testing we have to check the leakage from Packing & Seat.
2) Shell Test (30Sec – 2 Min) Max
1. Hydro Test
Seat test shall be carried out for (30Sec – 2 Mint).
During testing we have to check the leakage.
During testing we have to check Bubble & Count the bubble.
2" - 3" 8
4" 10
Branch Connection as per SAES-L-110 para 12 shall be made.
And as per ASME B31.3 304.
SAES-L-150: Pressure Testing for Plant Piping and Pipe Lines. As per para 7 & 8
Test shall be conducted 1.5 times the design pressure.
All Joints shall be exposed for visual leakage.
No painting shall be done on weld joints.
System shall be pressurized for 30 minutes at 100% & pressure has be
Increased as 30%, 60% and 100%.
All punch A items shall be cleared.
Test Preparation
New piping systems shall be cleaned in accordance with SAES-L-350.
Soft Seated Valves & Control Valves shall be removed.
Flushing.
Flushing of piping as per SAES-L-150.
Remove temporary supports after flushing & Draining of system.
Water Flushing.
All CS piping systems shall be flushed using high pressure [60.8 mPa (8.8 ksi) minimum] As per SAES-L-350.
Stainless steel lines chloride content shall be less than 50 mg/L with dew point -1°C.
Level 3 Inspection Daily/Weekly/Bi-Weekly basis. W Witness (Work can be proceed with permission)
SAEP-1160: Tracking & Reporting of Welding, NDT & Test Package preparation.
Contents of Package.
SCHEDULE Q
1. General 2. Quality Management System Requirments (QMSR).
3. Documents Requirments. 4. Management Responsibility
5. Resource Management 6. Project Realization/Execution.
7. Measurements/Analysis/improvement.
Attachment i: Contractor & Sub-Con personal Qualification.
Attachment ii: Company Standards & Procedures containing quality requirments.
Attachment iii: Quality requirments for material.
Attachment IV: Quality requirments for construction phase.
Attachment v: Quality system deliverables.
All procedures & Qualification shall be submitted for Review/Approval 21 day’s prior to start of work.
Work Personnel Personnel
Special Process Procedure Qualification Procedure Qualification Qualification
for Mechanical A = Approval Req Approval Req = Yes/No Approval Req = Yes/No
R = Review Req
Welding/Brazing A Yes Yes
NDT A Yes Yes
PMI A No Yes
HT A No No
Pressure testing A No No
Valve Test A No No
Coating & Lining A No Yes
Gasket & Bolt torquing A No No
Hot taps & Tie inns A No No
HVAC testing A No No
RTR pipe works A No Yes
5. Maintain calibration certificate log status with expiry dates.
6. Quality personnel requirments for Project.
Position Contractor Sub-Contractor
QA Manager One (1) Full Time N/A
QC Manager One (1) Full Time One (1) Full Time
One (1) full time per discipline One (1) full time per discipline
QCS (Supervisor)
for each eight (8) inspectors for each eight (8) inspectors
One (1) Full Time for (5) Sub- One (1) Full Time for (15)
Piping Inspector
Con Inspector workers
Valves Testing One (1) Full Time One (1) Full Time
Subsequent submittals to
Title First Submittal to COMPANY
COMPANY
Quality Plan: Paragraph 3.2 of Twenty one (21) calendar days after the effective Within 7 calendar days of each
Schedule "Q" date of Contract and for any significant changes revision requirement
Organization Chart(s) Paragraph
5.12 of Schedule "Q" With Quality Plan submittal When changes occur
Supports:
Shoe Support.
Saddle Support.
Leg Support.
Dummy Support (Trunnion Supports).
Anchor Support
Cantilever Support.
Guide Support.
Spring Support.
Hanger Support.
Special Support.
LRE 90° Elbow = 1.5 X Dia of Elbow in Inches X 25.4 45° Elbow = 15.7 X Dia of Elbow
= 1.5 X 10” X 25.4 = 15.7 X 10
= 381 MM. = 157
SRE 90° Elbow = 1 X Dia of Elbow X 25.4 SRE 45° Elbow = 10.5 X Dia of Elbow
= 1 X 10 X 25.4 = 10.5 X 10
= 254 = 157
Note: Take the Length of the elbow and subtract from the total length of the pipe to get actual length of pipe
Example: Actual Length of Pipe = Elbow - Total Length of Pipe.
Actual Length of Pipe = 10” 90° Elbow – 2000 MM Pipe.
= 381 – 2000.
= 1619 mm.
What is Schedule Q?
1. Minimum Quality has to maintained by Contractor or Sub-Contractor during execution of work at different
Stages.
1. Quality Management System Requirments.
2. Documents Requirments.
3. Management Responsibilities.
4. Resource Management.
5. Project Execution.
Responsibilities of QC Inspector.
1. Surveillance & Monitor the activities as Site.
2. Work shall be executed as per Standards, Codes & Specification.
3. Work shall be done as Approved ITP / Drawings / IFC drawings (Issued for Construction).
4. Updated drawings shall be used at Site.
5. Raising RFI & Closing RFI.
6. Maintain the documents & reports on daily basis and update the data for tracing.
7. Perform internal inspections before raising RFI.
8. Assure availability of tools & Equipments during inspection.
9. Familiar with Codes & Standards.
10. Inspection of work done by Construction.
11. Witnessing & Monitoring during execution of work.
12. Work shall be carried out with Safety.
13. Tool box meeting & explaining the work to construction to maintain quality.
14. Guide the construction as per the priority of work.
15. Issue NCR to construction whenever required.
PMCC: Partial Mechanical Completion Certificate will be issued to Construction of completion of above activities.
Note: Punch B & C or other minor works will be changed to Master Punch that will be given by
Pre-Comm & Commissioning team. And will be cleared by them.
Log Book Entry: It’s given when there is any violation in work. (Work Executed against Codes & Standards)
NCR: For more refer SAEP-381 Escalation Process.
NCR: Non Conformance report is given for the repeated violation within 6 months.
NCR: Contents.
1) Root Cause 2) Corrective Action 3) Preventive Action. 4) ACD (Agreed Closing Date)
(Has to be replied within 7 working days).
2) ACD (Agreed Closing Date) when we are going to close NCR there is no time limit.
If NCR is not closed in ACD we can change the date 1 Time.
Pre-Commissioning:
Commissioning:
14. Material Handling & Storage same as Metallic Piping. SAES-S-070 & SAES-H-200.
All material should shall be protected for direct sun light.
All Material should keep in building or shade.
Solvents, Chemicals, bounding agents & Cements shall be kept at 26.7°C Max.
15. Test Preparation as per Metallic piping. SAEP-1106
16. General Requirements for Hydro Testing as per SAES-A-004.
17. Pressure Testing for Plant Piping & Pipe Lines SAES-L-150.
Hydro Test is conducted for 2 Hr. for the joints exposed for visual leakage.
Hydro Test is conducted for 24 Hr. for the joints backfilled and recorded on Pressure Recorder.
All the activities as same as Metallic Piping.
Bolt tightening procedures and maximum torque for bolting on nonmetallic flanges shall be in accordance with
ASTM D4024.
NOTE: All the activities will be same as above ground piping except few.