Objectives Questions Unit 1 CHP 1-Introduction To Operations Research I
Objectives Questions Unit 1 CHP 1-Introduction To Operations Research I
Objectives Questions Unit 1 CHP 1-Introduction To Operations Research I
Unit 1
Chp 1- Introduction to Operations Research
I. Fill in the Blanks:-
1. Decision making is one of the ________ of Operations Research.
2. Credit policy Analysis and risks etc. are the areas of Applications of Operations Research in ______
Function.
3. Product selection, Product Introduction timing, Advertising strategy etc. are the areas of Applications
of Operations Research in ______ Function.
4. Operations Research is only a tool of analysis and not the complete decision-making process. This is
one of the _______ of Operations Research.
5. Operations Research models help in improved decision making and reduce the risk of making
erroneous decisions which is one of the ______ of O.R.
[Ans: (1) Characteristics / Features; (2) Accounting; (3) Marketing; (4) Limitations; (5) Advantages]
II. Mutiple choice Questions:-
1. Operations Research (OR), which is a very powerful tool for _____ .
a) Research b) Decision-making
c) Operations d) None of the above
2. Who coined the term Operations Research?
a) J.F. McCloskey b) F.N.Trefethen
c) P.F. Adams d) Both A and B
3. The term v was coined in the year _____ .
a) 1950 b) 1940
c) 1978 d) 1960
4. This innovative science of Operations Research was disclosed during ____ .
a) Civil War b) World War I
c) World War II d) Industrial Revolution
5. Operations Research was known as an ability to win a war without really going in to a _____ .
a) Battle field b) Fighting
c) War d) Both A and B
6. Who defined Operations Research as scientific method of providing executive departments with a
quantative basis for decisions regarding the operations under their control ?
a) Morse and Kimball (1946) b) P.M.S. Backett (1948)
c) E.L. Arnoff and M.J. Netzorg d) None of the above
7. Who defined Operations Research as scientific approach to problem solving for executive
management ?
a) E.L. Arnoff b) P.M.S. Backett
c) H.M. Wagner d) None of the above
8. Who defined Operations Research as an aid for the executive in marketing his decisions by providing
him with the quantitative information based on the scientific method analysis ?
a) Kitte b) H.M. Wagner
c) E.L. Arnoff d) None of the above
9. Operations Research has the characteristics the it is done by a term of ___ .
a) Scientists b) Mathematicians
c) Academics d) All of the above
10.There is a great scope for _____ working as a term to solve problems of defence by using the
Operations Research approach.
1
a) Economists b) Administrators
c) Statisticians and Technicians d) All of the above
11. Operations Research emphasizes on the overall approach to the system. This characteristics of
Operations Research is often referred as _____ .
a) System Orientation b) Decision-making
c) Interdisciplinary Team Approach d) None of the above
12. Operations Research cannot give perfect _____ to problems.
a) Answers b) Solutions
c) Both A and B d) Decisions
13. Operations Research simply helps in improving the _______ of the solution but does not
result in a perfect solution.
a) Quality b) Clarity
c) Look d) None of the above
14. Operations Research involves______ attack of complex problems to arrive at the optimum
solution.
a) Scientific b) Systematic
c) Both A and B d) Statistical
15. Operations Research is a ______ .
a) Science b) Art
c) Mathematics d) Both Aand B
[Ans: (1-b), (2-d), (3-b), (4-c), (5-d), (6-a), (7-c), (8-a), (9-a), (10-d), (11-d), (12-c), (13-a), (14-c), (15-d)]
2
Q.1 Fill in the blanks :-
1. A mathematical programming problem is one that seeks to maximize an objective function subject to the
constraints. If both the objective function and the constraints are linear, the problem is referred to as a
____ problem.
2. _____ are a function in which each variable appears in a separate term raised to the first power and is
multiplied by a constant (which could be 0).
3. _____ are linear functions that are restricted to be “less than or equal to”, “equal to”, or “greater than or
equal to” a constant.
4. The maximum or minimization of some quantity is the _____ in all linear programming problems.
5. _____ variables can never be negative.
6. The _____ property of linear programming models indicates that the decision variables cannot be
restricted to integer values and can take on any fractional value.
7. The objective function 3x+2y+4xy violates the assumption of _____.
8. The _____ property of linear programming models indicates that the rate of change, or slope, of the
objective function or a constraint is constant.
9. The_____ step in formulating a linear programming model is to define the decision variables.
10. _____ variables are mathematical symbols representing levels of activity.
[Ans: (1) - linear programming; (2) - linear functions; (3) - linear constraints; (4) - objective; (5) -
Decision; (6) - Divisibility; (7) - Proportionality; (8) - Proportionality or linearity; (9) - first; (10) -
Decision]
15. Who developed Linear Programming for the purpose of scheduling the complicated procurement
activities of the United States Air Force?
a) George B. Dantzig b) James B. Dantzig
c) George B. Dante d) George V. Dantzig
4
16. _____ assumptions means the prior knowledge of all the coefficients in the objective function, the
coefficients of the constraints and the resource value.
a) Proportionality b) Certainty
c) Finite choices d) Continuity
17. The word ‘Linear’ means that the relationships are represented by____.
a) Diagonal lines b) Curved lines
c) Straight lines d) Slanting lines
18. The word ‘programming’ means taking decisions _____.
a) Systematically b) Rapidly
c) Slowly d) Instantly
19. LP is a major innovation since _______ in the fields of business decision-making, particularly
under condition of certainty.
a) Industrial Revolution b) World War I
c) World War II d) French Revolution
20. Linear Programming has been successful applied in ____.
a) Agricultural b) Industrial applications
c) Both A & B d) Manufacturing
21. The method of formal calculations often termed as Linear Programming was developed later in which
year ?
a) 1947 b) 1988
c) 1957 d) 1944
[Ans: (1-a), (2-d), (3-d), (4-a), (5-d), (6-b), (7-d), (8-a), (9-b), (10-d), (11-d), (12-d), (13-d), (14-d),
(15-a),(16-b),(17-c),(18-a),(19-c),(20-c),(21-a)]
II. True or False:-
1. The terms in the objective function or constraints are additive.
2. A linear programming problem may have more than one set of solutions.
3. In a linear programming problem, all models parameters are assumed to be known with certainty.
4. Linear programming is a model consisting of linear relationships representing a firm’s decisions given an
objective and resource constraints.
5. A constraint is a linear relationship a restriction on decision making.
6. The objective function is a linear relationship reflecting on decision making.
7. A linear programming model consists of only decision variables of an operation.
8. Proportionality means the slope of a constraint is proportional to the slope of the objective function.
9. The terms in the objective function or constraints are multiplicative.
10. The values of decision variables are continuous or divisible.
11. In linear programming models, objective function can only be maximized.
12. All linear programming models exhibit a set of constraints.
13. Linear programming models exhibit linearity among all constraint relationships and the objective
function.
14. In linear programming models, the objective function always consists of either maximizing or
minimizing some value.
15. A parameter is a numerical value in the objective function and constraints.
5
16. A linear programming model consists of decision variables, constraints, but no
objective function.
17. The right hand side element of each constraint is non-negative
[Ans: True:1,2,3,5,6,10,12,13,14,15,17 ; False:4,7,8,9,11,16
15. IF one of the constraint of an equation in an LP problem has an unbounded solution then
a) Solution to such LP problem must be degenerate
b) Feasible region should have a line segment
c) Alternative solutions exist
d) None of the above
16. Graphic method can be applied to solve a LPP when there are only _____ variable
a) Four b) More than One
c) Two d) Three
17. If the feasible region of a LPP is empty, the solution is _____ .
a) Infeasible b) Unbounded
c) Alternative d) None of the above
[Ans. : (1 - d); (2 - a); (3 - d); (4 - a); (5 - d); (6 - c); (7 - d); (8 - a); (9 - a); (10 - c)
(11 - a); (12 - b); (13 - c); (14 - a); (15 - b); (16 - c); (17 - a)]
12. An objective function is necessary in a maximization problem but is not required in a minimization problem.
13. A constraint is a mathematical expression in linear programming that maximises or minimizes some quantity.
14. The objective function shown is a legitimate expression in linear programming :
Max Profit = 7X + 8Y + 5XY.
15. The decision variables in a profit maximization product mix problem must all be positive.
16. The minimum value of the objective function Z = ax + by in a linear programming problem always occurs
at only one corner point of the feasible region.
18. If the feasible region for a linear programming problem is bounded, then the objective function
Z = ax + by has both a maximum and a minimum value on feasible region.
18. A graphical solution is limited to solving linear programming problems with only two decision variables.
8
19. The iso-profit solution method can only be used to solve maximization problems.
20. Any linear programming problem can be solved using the graphical solution.
[Ans . : True : 1, 4, 7, 8, 11, 15, 17, 18, 20; False : 2, 3, 5, 6, 9, 10, 12, 13, 14, 16, 19]
18. In an optimal Simple table, Shadow Price of Resource is indicated by corresponding slack
variable value in _____ row.
19. If there is a tie between at least 2 least positive replacement ratios, then there is a _____ in solution.
20. The solution is _____ if all values of opportunity cost i.e. ∆ are zero or negative. (∆ ≤ 0)
[Ans. : (1) - standard, (2) - slack, (3) - surplus, (4) - scarce or binding, (5) - abundant,
(6) - slack, (7) - surplus, (8) - column, (9) - basic, (10) - + M, (11) - artificial, (12) - dual,
(13) - infeasible, (14) - degenerate, (15) - unique, (16) – unbounded, (17) - Shadow Price,
(18) – Zj, (19) – degeneracy, (20) - optimum]
10
17. Please state which statement is true.
i) All linear programming problems may not have unique solutions
ii) the artificial variable technique is not a device that does not get the starting basic feasible
solution.
a) Both (i) and (ii) b) (ii) only
c) (i) only d) Both are incorrect
18. _____ which is a subclass of a linear programming problem (LPP).
a) Programming problem b) Transportation problem
c) Computer problem d) Both are incorrect
19. If in a LPP , the solution of a variable can be made infinity large without violating the
constraints, the solution is _____ .
a) Infeasible b) Unbounded
c) Alternative d) None of the above
20. In simplex method, we add _____ variables in the case of ‘=’.
a) Slack Variable b) Surplus Variable
c) Artificial Variable d) None of the above
21. In simplex method, if there is tie between a decision variable and a slack (or surplus) variable,
_____ should be selected.
a) Slack variable b) Surplus variable
c) Decision variable d) None of the above
22. A BFS of a LPP is said to be ______ if at least one of the basic variable is zero.
a) Degenerate b) Non-degenerate
c) Infeasible d) Unbounded
23. Every LPP is associated with another LPP is called _____.
a) Primal b) Dual
c) Non-linear programming d) None of the above
24. Dual of the dual is _____.
a) Primal b) Dual
c) Alternative d) None of the above
[Ans. : (1 – a); (2 – d); (3 – c); (4 – b); (5 – c); (6 – c); (7 – c); (8 – c); (9 – a); (10 – a);
(11 – b); (12 – b); (13 – d); (14 – a); (15 – c); (16 – b); (17 – c); (18 – b); (19 – b); (20 – c);
(21 – c); (22 – a); (23 – b); (24 – a)]
Column A Column B
1. Inequality ≥ a) + Artificial Variable
2. Equality = b) Co-efficient of the variables in the objective function.
3. Inequality ≤ c) Replacement Ratios negative or infinity
4. Pivot Element d) + slack Variable
5. Cj Row e) - surplus + Artificial Variable
6. Big M f) Intersection of key row and key column
7. Unbounded Simplex Solution g) Tie between at least 2 least positive
Replacement Ratios
8. At least one value of bi ( Solution ) = 0 h) Penalty Method
UNIT - II
CHP. 5 - ASSIGNMENT PROBLEM: HUNGARIAN METHOD
I. Fill in the Blanks :
1. The _____ method used to obtain optimum solution of Assignment problem.
2. The purpose of a _____ row or column in an assignment problem is to obtain balance between
total activities and total resources.
3. If the number of facilities are equal to the number of jobs, the given assignment problem is of
_____ type.
4. Assigning subjects to the _____ is an application of Assignment method of O.R.
5. If the assignment elements are time elements in given assignment problem, then it is of _____ type.
6. If number of rows are not equal to the number of columns, then we have to convert _____ problem
to the balanced stage to find optimal assignment.
12
7. When minimum number of horizontal and vertical lines (N) drawn to cover all zeros in reduced matrix
becomes equal to order of matrix (n) , then _____ Solution is obtained.
8. A _____ job or facility is an imaginary job/facility with zero cost or time introduced to make an
unbalanced assignment problem balanced.
[Ans. : (1) – Hungarian, (2) – dummy, (3) – balanced, (4) – teachers, (5) – Minimization,
(6) – unbalanced, (7) – optimal, (8) – dummy]
5. One disadvantage of using North-West Corner rule to find initial solution to the transportation problem is that
a) It is complicated to use
b) It does not take into account cost of transportation
c) It leads to degenerate initial solution
d) All of the above
6. The solution to a transportation problem with ‘m’ rows (supplies) & ‘n’ columns (destination)
is feasible if number of positive allocations are :
a) m + n b) m*n c) m + n – 1 d) m + n + 1
7. If an opportunity cost value is used for an unused cell to test optimality, it should be
a) Equal to zero b) Most negative number
c) Most positive number d) Any value
8. During an iteration while moving from one solution to the next, degeneracy may occur when
a) The closed path indicates a diagonal move
15
b) Two or more occupied cells are on the closed path but neither of them represents a corner of the path.
c) Two or more occupied cells on the closed path with minus sign are tied for lowest circled value.
d) Either of the above
9. The large negative opportunity cost value in an unused cell in a transportation table is chosen
to improve the current solution because
a) It represents per unit cost reduction b) It represents per unit cost improvement
c) It ensure no rim requirement violation d) None of the above
10. In a Transportation Problem, the smallest quantity is chosen at the corners of the closed path
with negative sign to be assigned at unused cell because
a) It improves the total cost b) It does not disturb rim conditions
c) It ensure feasible solution d) All of the above
11. When total supply is equal to total demand in a transportation problem, the problem is said to be
a) Balanced b) Unbalanced
c) Degenerate d) None of the above
12. Which of the following methods is used to verify the optimality of the current solution of the
transportation problem
a) Least cost method b) Vogel’s approximation method
c) Modified distribution method d) All of the above
13. If Total Supply is equal to Total Demand and the Matrix elements are Time elements then the
problem is
a) Balanced and Minimization Transportation Problem
b) Unbalanced and Minimization Transportation Problem
c) Balanced and Minimization Assignment Problem
d) Unbalanced and Minimization Assignment Problem
14. The solution of any transportation problem is obtained in how many stages?
a) Five b) Four c) Three d) Two
15. An optimal solution is the _____ stage of a solution obtained by improving the initial solution
a) Third b) First c) Second d) Final
16. MODI method is used to obtain _____
a) Optimal solutions b) Optimality test
c) Both A and B d) Optimization
17. Any feasible solution to a transportation problem containing m origins and n destinations is
said to be _____ .
a) Independent b) Degenerate c) Non-degenerate d) Both A and B
18. A path formed by allowing horizontal and vertical lines and the entire corner cells of which are occupied
is called a _____ .
a) Occupied path b) Open path
c) Closed path d) None of the above
19. Transportation algorithm can be used for minimizing the transportation cost of _____ from
O origins and D destinations.
a) Goods b) Products
c) Items d) None of the above
20. If demand is lesser than supply then dummy demand node is added to make it a _____ .
a) Simple problem b) Balanced problem
c) Transportation problem d) None of the above
[Ans. : (1 – b); (2 – a); (3 – b); (4 – b); (5 – b); (6 - c); (7 - b); (8 - c); (9 - a); (10 –c);
(11 - a); (12 – c); (13 – a); (14 – d); (15 – c); (16 – c); (17 – c); (18 – c); (19 – a);(20-b)]
16
III. True or False :
1. According to transportation problem number of basic (Occupied) cells should be exactly m + n + 1, so that
it becomes non-degerate.
2. If Total Supply is not equal to Total Demand and the Matrix elements then are Sales elements then the
problem is Unbalanced and Maximization Transportation Problem.
3. If Total Supply is equal to Total Demand and the Matrix elements are cost elements then
the problem is Unbalanced and Minimization Transportation Problem.
4. To test optamility in Transportation Problem, Least Cost Method (Matrix Minimum Method) is used.
5. If at least one unit is allocated to a prohibited cost cell (Cost indicated by M), we get infeasible solution.
6. Basic (Occupied) cells indicate positive values and non-basic (Un-occupied) cells have zero value for flow.
7. Most negative number is to be used as opportunity cost value for an unused cell to test optimality.
8. Minimization and Balanced Transportation problem is converted to Maximization and Balanced condition
to get regret matrix and to find further IFS and optimal Solution.
10. One of the methods to get regret matrix is multiply by – 1 to all Transportation elements of a Maximization
and balanced transportation problem.
10. MODI method is the best method to get Initial Feasible Transportation solution.
[Ans. : True : 2, 5, 6, 7, 9; False : 1, 3, 4, 8, 10]
IV. Match the Column :
Column A Column B
1. Prohibition in Transportation a) Alternate optimal Transportation Solution available
UNIT 3
CHP. 7- NETWORK ANALYSIS
I. Fill in the Blanks :
1. CPM is deterministic in nature where as PERT is ______ in nature.
2. The critical path is the _______ path through the network.
3. Critical path activities can have zero or ______ values for slack.
4. PERT uses _________ time estimates and CPM use a single time estimate.
5. ________ Float is the amount of time that the activity completion time can be delayed without
affecting the earliest start time of the immediate successor activity in the network.
6. The process of reducing total time that it takes to complete a project by employing additional resources
is called _______ .
7. PERT often assumes that the time estimates follow the ______ probability distribution.
8. In PERT/CPM, a (n) ________ is a time consuming job or task.
9. In an AON network representation, the ______ represents the activities.
17
10. _______ assumes that activity times are probabilistic.
11. _______ assumes that activity times are deterministic.
12. In CPM, we assume that resources are expended in a ________ fashion.
13. If we have a project that we have not done before, then _______ is probably to be preferred
over CPM, as a project management scheme.
14. Pert stands for Program evaluation and Review _______ .
15. The critical path represents the _______ time required to complete the project.
16. A (n) _______ is a point in time that marks the beginning or end of an activity.
17. _______ Float is the amount of time that the completion time of an activity can be delayed without
affecting project completion time.
18. In PERT, Most Likely Time ≥ ________ Time.
19. In PERT, _______ time represents the longest time the activity could take if everything goes wrong.
20. Major events in a projects are often referred to as ______ .
21. The earliest start (ES) of an activity is the largest earliest finish (EF) of the immediate___________.
22. Critical path activities that have a ________ value for slack are behind schedule.
23. During crashing process only _______ activities are crashed so as to reduce time of completion of
project.
24. __________ path means the second longest path in the network, which is shorter than the critical path
but longer than all other paths in the network.
[Ans. : (1 – probabilistic), (2 – longest), (3 - negative), (4 – three), (5 – Free), (6 - crashing),(7 – beta ),
(8 – activity), (9 – Node), (10 – PERT), (11 – CPM), (12 - linear), (13 – PERT), (14 - Technique),
(15 – longest), (16 – Event), (17 – Total), (18 – Optimistic), (19 – Pessimistic), (20 – Milestones ),
(21 – predecessors), (22 – negative), (23 - critical), (24 – Sub-critical)]
2. What network model enables engineer managers to schedule, monitor, and control large and
complex projects by employing three time estimate for each activity?
a) Forecasting b) Program evaluation review technique
c) Critical path method d) Simulation
3. For a project manager to have an effective means of identifying and communicating the planned activities
and their interrelationships, he must use a network technique. One of the network techniques is commonly
known as CPM. What does CPM stands for?
a) Critical plan method b) Coordinated plan method
c) Critical project method d) Critical path method
4. For a project manager to have an effective means of identifying and communicating the planned activities
and their interrelationships, he must use a network technique. One of the network techniques is commonly
known as PERT. What does Pert stands for?
a) Project evaluation review technique b) Program evaluation review technique
c) Path evaluation review technique d) Program execution review technique
5. What is the benefit of using PERT/CPM network as integral component of project
management?
a) They furnish a consistent framework for planning, scheduling, monitoring and controlling
project.
b) They illustrate the interdependencies of all tasks
c) They can be used to estimate the expected project completion dares as well as the
probability that the project will be completed by a specific date
d) All of the above
18
6. The CPM was developed by Rand and Walker in which year?
a) 1957 b) 1958
c) 1959 d) 1960
7. In what year was PERT developed?
a) 1957 b) 1959
c) 1960 d) 1958
8. In a PERT/CPM network, computing the critical path requires
a) determining the total project duration
b) assigning the earliest finish time for an activity as the earliest start time for the next
c) that the latest finishing time for an activity not delay the overall project beyond initial
expectation
d) a sophisticated and complex computer program
9. At the completion of the forward and backward passes, the slack for an activity is given by the
a) difference between early start and early finish
b) difference between early start and latest finish
c) difference between latest start and early finish
d) amount of idle labor on the critical path
10. The basic difference between PERT and CPM is that
a) PERT deals with events and CPM with activities
b) Critical Path is determined in PERT only
c) Costs are considered on CPM only and not in PERT
d) Guessed times are used in PERT and evaluated times in CPM
11. In a PERT network, the earliest (activity) start time is the
a) Earliest time that an activity can be finished without delaying the entire project.
b) Latest time that an activity can be started without delaying the entire project.
c) Earliest time that an activity can start without violation of precedence requirements.
d) Latest time that an activity can be finished without delaying the entire project
12. The time by which activity completion time can be delayed without affecting the start of
succeeding activities, is known as :
a) Interfering float b) Total float
c) Duration d) Free float
19
a) Two or more activities have the same starting events.
b) Two or more activities have different ending events.
c) Two or more activities have the same ending events.
d) The network contains two or more activities that have identical starting and ending events.
18. PERT analysis computes the variance of the total project completion time as
a) The sum of the variances of all activities in the project.
b) The sum of the variances of all activities not on the critical path.
c) The variance of the final activity of the project.
d) The sum of the variances of all activities on the critical path.
19. If an activity has zero activity slack it
a) means that the project is expected to be delayed.
b) must be a dummy activity.
c) is on the critical path.
d) all of the above
20. Pick the wrong relationship:
a) Interfering float = Total float – Free float
b) Total float = Free float + Independent float
c) Total float ≥ Free float ≥ Independent float
d) Free float = Total float – Head event slack
21. Choose the correct condition of the following:
a) Crash Direct Cost > Normal Direct Cost, Crash time > Normal time
b) Crash Direct Cost < Normal Direct Cost, Crash time > Normal time
c) Crash Direct Cost < Normal Direct Cost, Crash time < Normal time
d) Crash Direct Cost > Normal Direct Cost, Crash time < Normal time
22. Indirect cost ______ when the project is crashed
a) Increases b) Decreases
c) Becomes zero d) None of the above
23. Which of these statements regarding time – cost trade - offs in CPM networks is true?
a) Crashing is not possible unless there are multiple critical paths.
b) Crashing a project often reduces the duration of non-critical, activities.
c) Activities not on the critical path can never by on the critical path, even after crashing.
d) Crashing shortens the project duration by assigning more resources to one or more of the
critical tasks.
24. Activity to be crashed is selected based on :
a) critical activity with minimum crash cost
b) non-critical activity with minimum crash cost
c) critical activity with maximum crash cost
d) non-critical activity with maximum crash cost
25. Which of the following is not a concept associated with CPM
a) Normal Time b) Probability
c) Normal Cost c) Crash Cost
[Ans.: (1. – b); (2. – b); (3. – d); (4. – a); (5. – d); (6. – a); (7. – d); (8. – b); (9. – a); (10. – d);
(11 – c); (12 – d); (13 – a); (14 – c); (15 – b); (16 – b); (17 – d); (18 – d); (19 – c); (20 – b) ;
(21 – d); (22 – b); (23 – d) ; (24 – a) ; (25 – b)]
20
7. The dummy activity has an expected time of zero by definition.
8. Early start time (ES) is computed from right to left (backward pass).
9. PERT, but not CPM, has the ability to consider the precedence relationships in a project.
10. The shortest of all paths through the network is the critical path.
11. The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing
projects while CPM uses cost estimates.
12. Slack is the amount of time an activity can be delayed without delaying the entire project.
13. Every network has at least one critical path.
14. The critical path can be determined by use of either the “forward pass” or the “backward pass”.
15. The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
16. The standard deviation of project duration is the average of the standard deviation of all activities on the
critical path.
17. In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes
substantially more than its expected time.
18. PERT stands for Program Efficiency and Review Techniques.
19. There can be multiple critical paths on the same project, all with different durations.
20. In PERT, an activity that has slack can be delayed without affecting the start of any other activity.
21. When using PERT, the project variance is computed by summing the variance of all the
activities of the project.
22. In CPM, when we crash an activity, we always crash it to the minimum time possible.
23. CPM is more appropriate than PERT for managing projects that are unfamiliar and for which we
can only estimate activity durations.
24. PERT is more appropriate than CPM for managing projects that are familiar and repeatative.
25. On a network diagram, a successor activity is an activity that can be started only after the given activity is
finished.
26. In CPM, we assume that activity times are deterministic, while in PERT we assume that activity times
probabilistic.
27. When crashing a project, it is possible that the reduction in the current critical path causes a non-critical
path or paths to become critical path or paths.
28. The ES of an activity that has only one predecessor is simply the EF of that predecessor.
29. Crashing an activity that is on non - critical path will reduce the project duration.
30. Direct cost increases when the project is crashed.
31. An activity with the least cost slope is to be considered first for crashing.
32. The other named for fast tracking a project is called crashing.
33. CPM and PERT are quantitative analysis tools designed to plan, schedule and control small as well
as large projects.
34. PERT is a deterministic analysis tool allowing for precise times of activities within a project.
35. PERT had its beginnings in a military department of the United States.
36. CPM is a probabilistic analysis of managing a project.
37. An event is a point in time that marks the beginning or ending of an activity.
38. In AOA system, a network is a graphical display of a project that contains both activities and events.
39. The optimistic time is the greatest amount of time that could be required to complete an activity.
40. PERT is a network technique similar to CPM, but PERT allows for project crashing.
41. The most likely completion time of an activity is used to represent that activity’s time within a
project.
42. The expected completion time and variance of an activity is approximated by the normal distribution in
a PERT analysis.
43. PERT was developed for a project for which activity or task times were uncertain.
44. CPM was developed for use in managing projects which are repeated and about which we
have good information as to activity or task completion times.
45. With PERT, we are able to calculate the probability of finishing the project on a particular day.
46. With CPM, we are able to calculate the probability of finishing the project on a particular day.
47. A PERT or CPM network shows activities and activity sequences.
21
48. One of the most difficult aspects of using PERT is defining the activities so that they have measurable
/observable starts and finishes.
49. Before drawing a PERT or CPM network, we must identify each activity and their immediate predecessors.
50. The three time estimates employed in PERT are: optimistic time, average time, and pessimistic time.
51. In the PERT process, if an activity has zero variance it must be on the critical path.
52. Given the variability of the activity completion time, the original critical path we identify in our
PERT analysis may not always be the actual critical path as the project takes place.
53. In PERT, the activity completion times are modeled using the beta distribution.
54. In PERT, the mean and variance of the activity time are estimated on the basis of the ‘pessimistic’,
‘most likely’ and ‘optimistic’ completion times.
55. In PERT, the earliest finish time in one activity will always be the earliest start time of the following activity.
56. In PERT, the earliest start time for an activity is equal to the latest of the earliest finish time of all
all of its immediate predecessors.
57. Dummy activity does not consume time or resources.
58. In AON system of Network diagram, events are not shown in the diagram.
59. In PERT, Variance is calculated as square root of standard deviation.
60. In Time – Cost Trade off in Project Crashing, as project duration is crashed Direct Cost
increases and Indirect cost decreases.
[Ans. : True : 1, 3, 6, 7, 12, 13, 17, 25, 26, 27, 28, 30, 31, 33, 35, 37, 38, 43, 44, 45, 47, 48,
49, 52, 53, 54, 56, 57, 58, 60
False : 2, 4, 5, 8, 9, 10, 11, 14, 15, 16, 18, 19, 20, 21, 22, 23, 24, 29, 32, 34, 36, 39, 40, 41, 42,
46, 50, 51, 55, 59]
Column A Column B
1. Optimistic Time a) Free Float – Slack of Tail Event
2. Total Float b) Time estimate in PERT by considering
worst delays
3. Earliest Finish Time c) Probablistic Model
4. Most Likely Time d) Latest Start Time – Earliest Start Time
5. CPM e) Free Float – Slack of Head Event
6. Free Float f) Shortest and Ideal Time estimate in PERT
7. Normal Cost g) Earliest Start Time + Time Duration of
Activity
8. Pessimistic Time h) less than crash cost
9. Independent Float i) greater than crash time
10. PERT j) Time estimate in PERT by considering
normal delays
11. Standard Deviation Square k) Deterministic Model
12. Normal Time l) Variance
[Ans. : (1 – f), (2 – d), (3 – g), (4 – j), (5 – k), (6 – e), (7 – h), (8 – b), (9 – a), (10 – c), (11 – l),
(12 – i)]
UNIT 4
CHP. 8 - JOB SEQUENCING PROBLEMS
I. Fill in the Blanks :
1. _____ time is the time on a machine, for which a machine does not have a job to process.
2. _____ time is the time required by each job on each machine.
3. _____ order (sequence ) refers to the order (sequence) in which machines are required for
completing the job.
22
4. In n jobs and 3 machines ABC problem, to convert the problem in 2 machines to solve further, the
minimum processing time on machine A and / or on machine C must be _____ than the maximum
processing time on machine B.
5. _____ is the process of determining which job to start first and in what order jobs should be processed
on the machine or in work centre.
[Ans. : (1 – Idle), (2 – Processing), (3 – Processing), (4 – greater), (5 – Job Sequencing)]
5. Five jobs (A, B, C, D and E) are waiting to be processed on Machine P first and then on Machine Q.
There processing times are given below. Using the Johnson’s Rule find the optimal job sequence.
Machines Jobs
A B C D E
P 1 5 5 9 1
Q 3 2 2 4 3
a) A – B – C – D – E b) A – E – D – B – C
c) A – C – B – D – E d) E – A – B – C – D
6. In sequencing if smallest time for a job belongs to machine- 1 then that job has to placed _____
of the sequence.
a) in the middle b) in the starting
c) at end d) none of them
7. In sequencing the time involved in moving jobs from one machine to another is ______ .
a) negligible b) positive number
c) significant d) none of them
8. _______ operation is carried out on a machine at a time.
a) Two b) at least one
c) only one d) non of them
9. Processing time Mij’s are _____ of order of processing the jobs.
a) dependent b) negligible
23
c) independent d) none of them
10. If there are n jobs to be performed, one at a time, on each of m machines, the possible
sequences would be
a) (n!)m b) (n)m
n
c) (m!) d) (m)n
11. Total elapsed time to process all jobs through two machine is given by
n n
a) ∑M1j b) ∑M1j+I1j
j=1 j=1
n
c) ∑M2j+∑M1j d) None of above
j=1
12. The minimum processing time on machine M1 and M2 are related as
a) Min t1j = Max t2j b) Min t1j ≥ Max t2j
c) Min t1j ≤ Max t2j d) Min t2j ≥ Max t1j
[Ans. : (1 – c); (2 – d); (3 – a); (4 – a); (5 -b); (6 – b); (7 – a); (8 – c); (9 – c); (10 – a); (11 – c); (12 – b)]
UNIT - IV
CHP. 9 - THEORY OF GAMES
I. Fill in the Blanks :
24
1. When a saddle point is present, a _______ strategy exists.
2. The ______ strategy minimizes the maximum loss.
3. Game models are classified by the number of ______ , the sum of all payoffs and the number of
strategies employed.
4. In a _____ strategy game, each player should optimize the expected gain.
5. The term ______ game implies that as much was won as was lost.
6. The lower value of the game is equal to the maximum maximum of the ______ values in the
rows of the payoff matrix.
7. In a Game, there are finite numbers of competitors called _____ .
8. Each player has a finite number of possible courses of action called ______ .
9. The figures shown as the outcomes of strategies in a matrix form are called ______ matrix.
10. The player playing the game always tries to choose the best course of action which results in optimal
pay off called ______ strategy.
11. The expected pay off when all the players of the game follow their optimal strategies is known
as _______ of the game
12. If a player knows exactly what the other player is going to do, a deterministic situation is obtained, then
it is ______ strategy.
13. Pure strategy games are normally solved by ______ method.
14. Mixed strategy games are normally solved by ______ method.
15. In a two-player ______ game, one player’s gain is the other player’s loss, so their interests are
diametrically opposed.
25
a) A firm chooses its dominant strategy, if one exists
b) Every competing firm in an industry chooses a strategy that is optimal given the choices of
every other firm.
c) Market price results in neither a surplus nor a shortage
d) All firms in an industry are earning zero economic profits
8. Game theory is concerned with
a) predicting the results of bets placed on games like roulette
b) the choice of an optimal strategy in conflict situations
c) utility maximization by firms in perfectly competitive markets
d) the migration patterns of caribou in Alaska
9. In game theory, the outcome or consequence of a strategy is referred to as the
a) payoff b) penalty
c) reward d) end-game strategy
10. A strategy that is best regardless of what rival players do is called
a) first-mover advantage. b) a Nash equilibrium strategy
c) tit-for-tat. d) a dominant strategy.
11. A common assumption about the players in a game is that
a) neither player knows the payoff matrix.
b) the players have different information about the payoff matrix.
c) only one of the players pursues a rational strategy.
d) the specific identity of the players is irrelevant to the play of the game.
26
20. Your opponent’s knowledge that you are using some specific non-optimal strategy does not benefit him
in the least.
[Ans. : True : 1, 6, 7, 8, 10, 11, 14, 15, 17, 19;
False : 2, 3, 4, 5, 9, 12, 13, 16, 18, 20]
[Ans. : (1 – f), (2 – a), (3 – e), (4 – b), (5 – c), (6 – h), (7 – d), (8 – i), (9 – g)]
27