River Training Works: 3.1 Objectives
River Training Works: 3.1 Objectives
River Training Works: 3.1 Objectives
1 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
2 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
3 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
4 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
river width, day, and the river the guide –banks is closed by
may be found to be flowing away ordinary embankments.
from it, necessitating the Sometimes, one of the guide banks
construction of another structure. may become unnecessary and may
This may lead to the extension of be dispensed with for economical
the structure for the entire river reasons. This may happen either
length between its khadirs. when the khadir bank is very near
the works – site thus serving the
But it is unwise and purpose of guide banks.
uneconomical to span the entire Plan section etc is shown below.
width of the river and to expose
the structure to vagaries of attack
and deep scour. Hence, a
structure such as a weir, or a
barrage, or a bridge, etc is
extended in a smaller width of
the river, and water is trained to
flow almost axially through this
without out-flanking the
structure. The river is normally
trained for this purpose with the
help of a pair of guide banks.
5 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
6 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
may not be adequate causing very after the construction of the weir and
high afflux. The amount of afflux above formula is not strictly
governs the top levels of the guide applicable. Most of the existing
banks as wells as that of the marginal weirs and bridges have been
buds. The distance to which the provided with a clear waterway from
afflux appreciable extends on the 10% to 50% more than that given by
upstream side governs the length and Lacey’s Regime perimeter.
sections of the marginal bunds.
(II) Shape of guide banks in plan:
The Waterway and the As stated earlier, the guide banks are
Discharge per meter run generally provided in pairs,
The waterway is the actual width symmetrical in plan and may either
from which the water has to flow be kept parallel or may diverge
after river is constricted. Since this slightly upstream of the works. The
width is reduced at the works –site, diverging guide banks may be
the depth of water and hence, the favored on the ground that they
HFL will go up. The rise in this HFL cover larger with of the khadirs and
is nothing but afflux. The limit exert an attracting influence on the
placed on afflux automatically flow. But they are not recommended
placed a limit on the constriction or mainly because for equal bank
on the waterway, since the two are lengths they provide relatively less
interdependent. In addition to high protection to the approach
afflux, the insufficient water away embankment under the worst
will cause excessive velocities, possible embayment as shown in the
causing dangerously deep scour figure below.
along the guide banks at the bridge
piers, etc on the other hand too long
a bridge or weir may cause slack
velocities, causing formation of
shoals with consequent non- uniform
flow distribution and an oblique
flow.
A likely figure to be adopted for
waterway may be given by Lacey’s
Regime perimeter (P) , given by p =
4.75 Q ; ( because in larger Figure: extent of protection provided by
rivers ,width is approximately equal the straight and divergent guide banks
to its perimeter ) In case of a Moreover, the divergent banks
bridge ,obstruction caused by piers induce oblique flow and tend to from
should be accounted for, and the shoals in the center. However, in a
above equation should be taken to particular case, where the
represent the clear effective approaching flow is oblique it may
waterway . It should be remembered become necessary to provide
that regime conditions are disturbed
7 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
8 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
discharges less than 7,000 cumecs) may very from 1.5. H.: 1V to 2.5 H
and a value of R = 580meters for V, (but generally kept as 2 H: 1 V),
discharges varying from 40,000 to depending on the construction
70,000 cumecs . For intermediate materials and the height of the bund
discharges i.e. between 20,000 A freeboard of 1.2 to 1.5 m is
40,000 cumecs, the value of R may generally provided.
be obtained by interpolation. (VI) Slope pitching: The sloping
The upstream curve is extended to water side of the entire guide bund
subtend an angle of 1200 to 140 at its as well as the sloping rear side of
center, as shown in figure below. the curved portions are pitched with
one man stone ( i.e. a stone which
can be lifted by one person-
weighing 40 to 50 kg) or concrete
blocks. The pitching should extend
up to 1 m, higher then HFL. The
rear side of the shank portion is not
pitched, but is generally coated with
0.3 to 0.6 earths for encouraging
vegetation growth, so as to make it
resistant against rain, wind etc.
Figure:
(b) Downstream curved portion. On The thickness of the
the downstream, the river fans out so pitching on the river side may be
as to attain its normal width. The calculated by the formula
downstream portion of the guide t = 0.006 Q1/3
bank ensures the safety of approach Where, t is the thickness of stone
embankments and prevents the river pitching in meters Q is the discharge
from attacking them. This purpose in cumecs.
can be well served by providing The thickness of pitching should be
short guide bund with sharp curved 25% more at the impregnable head
head. A radius equal to half the than for the rest of the bund.
radius at the upstream side may be (VII) Launching apron: Whenever a
provided, as shown in the above sloping face is protected by stone
figure. pitching against scour the pitching is
extended beyond the toe on the bed,
(V) The shank portion and section called Launching apron.
of bund: The straight portion of the If no such protection is provided
guide bund BC is called the shank scour will occur at the toe with
portion. The guide banks should consequent under –mining and
have a minimum top with of 4 collapse of the stone pitching. In
meters so as to provide sufficient order to obviate such a danger to the
carriage-way. Extra width may, slope, the pitching is extended on the
however be provided for storing horizontal river bed portion, which
pitching materials, etc side slope
9 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
1/ 3
Q
R = 0.47
f
where Q is the
discharge and f is silt factor and
values of x are tabulated for
different places in Table.
EXAMPLE
11 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
13 AWTI Abel T.
HYDARULIC STRUCTURES-II (G5-C) RIVER TRAINING WORKS
14 AWTI Abel T.