Prelim Exam ALM
Prelim Exam ALM
Prelim Exam ALM
Prelim Exam
50/50
Scheduling Area
Refreshes the scorecard table, so that it displays the most up-to-date information.
Generate
The HP’s strategy and software approach for modern application delivery starts with a
what?
Unified platform
Creating requirements
Displays KPI calculations that enable you to determine the status of your release.
Scorecard tab
Allows you to capture a group of requirements, tests, or test assets at strategic points
in the project lifecycle to mark specific milestones.
Baselining
True
The Release Scope tab enables you to define and update release scope items.
True
This section enables you to open the ALM documentation library and other online
resources.
Help section
After the _____, the release goes through further testing cycles to test aspects, such as
functionality and performance of the application.
first cycle
A session/user authentication process that permits a user to enter one name and
password to access multiple applications.
Single Sign-on
Category views
True
Attachments
This cycle tests the new features with existing features that might have been impacted
by the changes.
Enables subject matter experts (SMEs) to work with Business Process Testing (BPT),
the HP test automation solution.
Release tree
Active/Inactive
Module addresses the need for a stronger connection between business process
modeling, quality assurance management, and requirements definition.
False
Changes the speed that it takes for ALM to calculate the KPI data.
Engines Throttle
Contains the Analysis tree in which you organize all of your analysis items.
If an application flaw is detected while running a test set, you can submit a defect.
True
This cycle ensures that the new features meet the expectations of the business.
Purge Area
Enables you to increase the number of parallel calculations performed on an entire site
Advanced Area
False
_______are checkpoints on a release timeline used to verify that the release and its
interim deliverables are progressing as planned.
Milestones
Enables you to manage resources used by your tests. You can organize your resources
by defining a hierarchical Test Resource tree containing resource folders and resources.
Test Resources
The Detailed tab enables you to select content to include in the release scope item
False
This is the two modules that have been completely redesigned as part of this release of
ALM 12.0.
A test set folder in the Test Lab module contains tests that are covered by your
requirements.
True
Tests the performance of the application for criteria such as number of concurrent users
that the application supports and the response time of the application.
Using the _____, you can report flaws in your application and track their repair during
all stages of the application management process.
A _______ is an independent business unit within an organization, with its own set of
rules, standards, resources, objectives, and applications.
Enable you to create and display a dynamic graphic representation of data related to
test plans and test sets.
Enables quality assurance managers to track application readiness by defining goals for
activities of an application release.
The testing process begins with defining defect in the Management module.
False
Release tree
False
Enabled for requirements, tests, and test assets to allow distributed teams to
collaborate and manage multiple versions of assets in parallel while maintaining data
integrity and providing an audit history of changes throughout the project lifecycle.
Version control
______ are the means for setting objectives on Project Planning and Tracking releases
and for planning and tracking release progress towards these objectives throughout its
duration.
Thresholds
After adding a cycle to a release, you specify the details for the cycle using the _____.
Details tab