Form 1 - General System Data: A) Basic System Information
Form 1 - General System Data: A) Basic System Information
C) Installer Information
Company name
Contact person
Mailing address
Telephone number
Email address
D) Commissioning Information
Commissioning party company
Commissioning party contact person
Commissioning party mailing address
Commissioning party telephone number
Commissioning party email address
E) Monitoring Information
Monitoring company
Monitoring company contact
Monitoring company mailing address
Monitoring company telephone number
Monitoring system contact email address
Type of Monitoring System
Web address to access monitoring data
Login details (username & password)
A) Module Information
Module model
Module manufacturer
Quantity of modules
B) Array Information
Array open circuit voltage (Voc)
Array short circuit current (Isc)
Array nominal voltage (Nom V)
Array power rating (kW DC)
C) Inverter Information
Inverter model
Inverter manufacturer
Inverter identification and serial number
Quantity of inverters
Total inverter power rating (kW AC)
Total number of strings
Number of modules per string
Array slope (degrees from horizontal)
Array azimuth (degrees east or west of due
south; due south = 0°)
D) Mounting Information
Mounting type Roof mount Ground mount BIPV
Other:
Method of fixing to roof (eg. ballasted,
fixed to structural roof member, etc.)
Conductor model
Raceway model
Junction box model
Grounding equipment model
Combiner box model (and fuse type
specified)
Quantity of combiner boxes
Disconnect model (and fuse type installed)
Quantity of disconnects
FORM 3 – SINGLE LINE WIRING DIAGRAM
A single line wiring diagram, including the following items must be provided (for large systems, this
information may be presented in table form):
PV string information
String cable specifications - size and type
String over-current protective device specifications (where fitted) - type and voltage/current ratings
Blocking diode type (if relevant)
AC system
AC isolator location, type and rating
AC overcurrent protective device location, type and rating
Residual current device location, type and rating (where fitted)
FORM 4 – OPERATION AND MAINTENANCE INFORMATION
Warranty documentation for PV modules and inverters - to include starting date and period of warranty.
Data sheet (if available) or relevant documentation for the array mounting system
Equipment manuals
IEC 61557 and IEC 61010 provide guidance on the measuring instruments and monitoring equipment
and methods that are appropriate for the inspection and testing of PV systems. If other measuring
equipment is used, it should have comparable performance and safety.
Ladder
Fall protection
Level
Camera
Pyranometer
Megohm-meter
Multi-meter
Compass
Inclinometer
Visual inspection should precede testing, and should normally be done prior to energizing the
installation.
IEC6034-6 provides the requirements for the inspection and commissioning of any electrical
installation. The following checklists are specific to the inspection and commissioning of PV
installations.
Electrical installation
All components are properly and
permanently connected (especially
junction boxes and leads).
Equipment complies with applicable
standards, including IEC 60364-6.
Equipment is easily accessible for
maintenance.
All wiring is connected.
Installed wire and conduit sizes match
the plans.
All electrical building penetrations are
permanently flashed or sealed as per
plan detail.
Wiring systems are protected against
wind, ice formation, extreme
temperatures, and solar radiation.
Fire stops are installed at all fire barrier
penetrations.
Permanent utility power is connected.
The internet is connected.
Mechanical installation
The array is ventilated as per the plan
detail.
The array frame is secured to the
building as per plan detail
All fasteners used on aluminum
structures or module frames are
stainless or as detailed in plan drawing.
Steel rack elements are hot-dipped
galvanized or better.
Dissimilar metals are isolated.
Electrical metallic tubing (EMT) or rigid
metal conduit (RMC) is used on the roof.
All system components are protected
against weather damage and corrosion.
All modules have been inspected for any
defects including delamination.
Mechanical and structural systems
conform to the plans.
String layout matches the as-built string
diagram.
Small systems: if no string diagram
exists, the string locations are marked
on the roof plan.
Large systems: if no string diagram
exists, the integrator has been notified.
DC system
DC components rated for continuous DC
operation.
All DC components rated to operate at
Voc STC x 1.25.
All DC components rated to operate at
Isc STC X 1.25
DC switch disconnect is properly fitted.
AC and DC cables are separated.
DC cables are adequately protected.
PV string cables, PV array cables and PV
DC main cables have been selected and
erected so as to minimize the risk of
earth faults and short-circuits
High voltage DC cabling ( > 120 V) is in
trunking / not accessible
PV rated cables
Systems with string over-current
protective devices:
String overcurrent protective
devices are correctly fitted and
specified to the requirements of
IEC 60364.
Rated for DC operation at the
fault energies present
Rated for operation at Voc STC x
# of modules in string x 1.15
Plug and socket connectors mated
together are of the same type and from
the same manufacturer.
Where a PV system has a direct
connection to earth on the DC side
(functional earth), a functional earth
fault interrupter is provided to the
requirements of IEC 60364.
AC system
Utility AC disconnect can be locked in
the ‘off’ position only.
Inverter protection settings comply with
local regulations.
Inverter type and power match the
system design documents.
Inverter power is appropriate for the
size of the array.
Low limit: 0.7 x array power rating
High limit: 1.2 x array power rating
Inverter can withstand maximum
voltage (Voc) and current (Isc) of the
array.
Means of isolating the inverter are
provided on the AC side.
Isolation and switching devices are
connected such that PV installation is
wired to the “load” side and the public
supply to the “source” side.
Safety
ESA Permit has been signed.
Electrical design is adapted properly.
All live parts are adequately
insulated/protected.
Working clearances are satisfactory.
The system has been properly grounded
at necessary locations.
Surge protection devices are installed as
per plan.
Area of all wiring loops kept as small as
possible.
Array frame equipotential bonding
installed to local codes.
Equipotential bonding conductors are
laid parallel to and bundled with the DC
cables.
Lockout/tagout procedures are in place
Labeling
Canadian Electric Code (CEC) required
labeling is present and made from
durable materials.
“DG SOURCE (DC) DISCONNECT”
“DG SYSTEM (AC) DISCONNECT”
“DG SYSTEM (UTILITY) DISCONNECT”
“WARNING TWO POWER SOURCES”
“WARNING MULTIPLE POWER SOURCES”
All circuits, protective devices, switches,
junctions, and terminals are properly
labeled.
Array combiner fuse type and rating is
labeled in each array combiner.
System diagram is displayed on-site in
an accessible location as per CEC
requirement.
Inverter protection settings and installer
details displayed on site.
Emergency shutdown protocol is
displayed on-site in an accessible
location.
AC and DC isolators are appropriately
labeled.
Any fused disconnect has the fuse type
and rating labeled.
Aesthetics
Module lines are straight and in line with
roof features.
Painting is satisfactorily completed.
Array skirts are installed acceptably.
Inverter fences/enclosures are built as
planned.
Required photographs
Arrays (from the front and rear if
possible, or at from least 2 angles)
One close up of module label
Racking system and connection point
flashing detail
Inverters (installation and name plate)
Conduit runs (all supports, roof, wall,
ceiling)
Combiner boxes (installation and name
plate)
Disconnects DC and AC (installation and
name plate)
Interconnection (meter and service
disconnect and metering cabinet)
Building penetrations
Fire stop penetrations
Noteworthy observations
FORM 8 – PV ARRAY TEST REPORT
The tests below must be performed for each inverter or string. Copy this page as needed.
ELECTRICAL MEASUREMENTS
String reference
String Module model
Number of modules
Array parameters Voc at STC
(as specified) Isc at STC
Type
String
Rating (A)
over-current
DC Rating (V)
protective device
Capacity (kA)
Type
String wiring Phase (mm²)
Earth (mm²)
Voc (V)
String test Isc (A)
Irradiance (W/m2)
Polarity check
Test voltage (V)
Array insulation
Pos – Earth (MΩ)
resistance
Neg – Earth (MΩ)
Earth continuity (where fitted)
Rating (A)
Rating (V)
Array isolator
Location
Functional check
Make & model
Inverter Serial number
Functioning OK
PERFORMANCE MEASUREMENTS
The values below will be used for performance verification below as per excel “PV Power Calculator”
DC operating voltage
DC operating current
AC operating voltage
AC operating current
Irradiance in the plane of the array
(W/m2)
Cell temp (°C)
PERFORMANCE VERIFICATION
DC output within 5% of expectations
AC output within 5% of expectations
Infrared imaging Yes No N/A Comments
NOTE: It is recommended that thermal images of the array be taken. Ensure images are taken when the
system is running near full power, with irradiance in the plane of the array greater than 400 W/m 2.
All modules from the front
All termination points of conductors in
array combiners, disconnects, and
inverters
Comments:
Source: IEC 62446 Ed.2, Grid connected PV systems – Minimum requirements for system documentation, commissioning tests
and inspection
FORM 9 – REQUIRED OWNER TRAINING
The owner of the PV system should be familiarized with the following aspects of system operations.
System layout
Important processes
Locations of disconnects
Inverter operation
Monitoring system operation (including relevant passwords and URLs for web-based systems)
Maintenance schedule
FORM 10 - PV SYSTEM VERIFICATION CERTIFICATE
This form is based on the model verification certificate in IEC 62446 Ed. 2
Description of installation
(list the key components installed)
Circuits tested
Required actions
Expected date of
Required action Assigned to
completion
Customer affirmation
I have been trained regarding the operation and maintenance of the PV system and have been
provided with relevant documentation.
The PV system has been commissioned to my satisfaction.
Name: Signature: Date:
*The extent of liability of the signatory(s) is limited to the work described above.
Next inspection recommended after not more than:
Comments: