Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

KOH PICH CONSTRUCTION COMPANY

CAMBODIA-CHINA POLYTECHNIC UNIVERSITY


DAILY ACTIVITIES REPORT

Main Contractor: KPCC


Issued Date: Monday, May 25, 2020 Issued No: CCPUI-025/2020
GROUP POSITION ATTENDANT DESCRIPTION
Project manager 1 Office and Site Management

Site supervisor 1 Site labor managerment

Arc. supervisor 1 Arc. drawing and technical management

QS engineer and Assistance 2 Prepare document such as payment claim, drawing, contract, other proposal and site inspection

Office MEP engineer and Assistance 2 Prepare document such as as-built,drawing, boq, other proposal and site inspection

Site engineer staff and Assistance 3 Follow up site progression, make report and site inspection

Surveyor engineer 1 Set up and checking coordinate for site installation,

Admins and Assistance 2 Prepare fix Asset, Prepare workers and Staff's OT, tick attendance, transfer request to central, prepare other proposal

Warehouse staff and Assistance 4 Stock Control, Material Purchasing.

Site Safety Safety 6 Strengthen discipline and safety in site

Site survey Survey 6 Follow up site progression, check level and coordination for site installation and do report.

Site MEP MEP 19 Standby for M&E, electrical work & AC system

Tower crane S.Workers 1 Standby for tower crane

Headman 1 Installing scaffolding and tube

S56 S.Workers 18 Tile and brick arrangement at top roof

Workers 6 Site cleaning area

Headman 1 Making steel fance gate and handrail

S18 S.Workers 14 Site cleaning area

Workers 7

Headman 1 Tile arrangement at toilet

D27 S.Workers 20 Brick work and plastering for frame window from 1F to 5F

Workers 18 Site cleaning area

Headman 1 Concrete work for ramp, curb for landscape in front the building

S16 S.Workers 13 Site cleaning area

Workers 4
KPCC

Headman 1 Installing scaffolding and tube for tile roof arrangement

S55 S.Workers 6 Site cleaning area

Workers 3

Headman 1 Brick work and plaster at main gate

S13 S.Workers 5 Site cleaning area

Workers 5

Headman 1 Smoothing plastering for frame window infront and behind the building

S26 S.Workers 10 Site cleaning area

Workers 1

Headman 1 Removing tube and scaffolding for installing glass window

S16 Koh pich S.Workers 6 Site cleaning area

Workers 0

Headman 0 Smoothing plaster at top roof

S19 S.Workers 10 Moving sand, cement for mixture

Workers 5 Site cleaning area

Headman 0 Brick arrangement and plaster at basement

T67 S.Workers 6 Site cleaing area

Workers 4

Headman 1 Concrete work for curb ramp

S15 S.Workers 6 Site cleaing area

Workers 1

Headman 1 Moulding work for fence gate, main gate, main entrance

S87 S.Workers 11 Site cleaing area

Workers 1

Headman 0 Site cleaning and site material preparation

Team site cleaning S.Workers 0

Workers 4

Driver S.Workers 2 Standby for material and worker mobilization

Page1
Headman 0 Moulding decoration around
Moulding
S.Workers 7 Cleaning area
decoration
Workers 0

Headman 0 Installing smartboard ceiling at main entrance

Ceiling S.Workers 5 Cleaning areas

Workers 0

Headman 0 Installing marb at staircase

Marble work S.Workers 6 Cleaning areas

Workers 0

Headman 0 Painting work at 5th floor


Subcon.

Interior painting S.Workers 3 Cleaning areas

Workers 0

Headman 0 Apply primer for exterior painting work

Exterior painting S.Workers 6 Cleaning areas

Workers 0

Headman 0 Installing frame and glass for window

Diamond glass S.Workers 13 Cleaning areas

Workers 0

Headman 0 Painting work for fence gate

Wall panel S.Workers 3 Cleaning areas

Workers 0

DESCRIPTION Number Labor

Brick work, plaster, installing and uninstalling scaffolding, KPCC Internal Subco. External Subco.
KPCC
Concrete work, tile roof, site arrangement and material preparation
Summary

Moulding decoration around, installing frame and glass window 213 23 20


Internal Subco
Fence wall gate paining

Ceiling work, apply primer for exterior painting Total Labor


External Sub
Marble work, interior painting work 256

Project Manager Reported By:

RITH RAVIN LAY SAMBO

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CCPU Project Work Report


Name: Daily Report
 ※Details of performance (specifical description) 25.05.2020 Weather (Hot) ○
【Today's Work】
Description Work time Number worker
Brick work and plastering wall for installing frame window side of the building 1F to 5F 7:00 - 17:00 20
Brick work and plastering wall for installing frame window infront and behind the building 7:00 - 17:00 15
Completed pour mortar at frame window 7:00 - 17:00 10
Tile roof arrangement 7:00 - 17:00 12
Brick work at top roof 7:00 - 17:00 14
Installing scaffolding and tube 7:00 - 17:00 12
Concrete work for curb ramp and garden 7:00 - 17:00 15
Concrete work for landscape in front the building 7:00 - 17:00 17
Removing tube at hole of frame window for installing glass 7:00 - 17:00 10
Moulding work for fance gate, main gate and main entrance 7:00 - 17:00 18
Installing frame and glass for window 7:00 - 17:00 13
Making steel fence gate and handrail 7:00 - 17:00 10
Smoothing plastering at fance gate and top roof 7:00 - 17:00 18
Apply primer for exterior painting work 7:00 - 17:00 6
Moulding decoration around 7:00 - 17:00 9
Brick work for basement floor 7:00 - 17:00 9
Painting interior at 5th floor 7:00 - 17:00 3
Painting fence gate 7:00 - 17:00 3
Ceiling smartwood installing at main entrance 7:00 - 17:00 5
Site cleaning all the floor 7:00 - 17:00 12
Marb staircase installation 7:00 - 17:00 6
Standby for MEP, electrical work & AC system 7:00 - 17:00 19
Total labour 256
【Plant and Machinery Name】 Description Work time
EX81 Soil preparation for pond 7:00-17:00
DT60 Soil preparation for pond 7:00-17:00
EX80 Fillback soil on head pile of 10th floor project 7:00-17:00
B61 Fillback soil on head pile of 10th floor project 7:00-17:00
Morning Afternoon Rain Hours
【Rainy Report】
None None

【Percentage of progress for CCUPI 】

Task Description Unit Quantity Today's work (%) Completion's work (%)

Brick wall work Sq.m 8331.4 85%


Interior painting Sq.m 13955.00 50%
Exterior painting Sq.m 3779.10 0%
Ceilling work Sq.m 7068.00 75%
Tile work Sq.m 6577.87 70%
Glass work Sq.m 2069.25 70%
Door work Ls 149.00 15%
Moulding decoration work Sq.m 660.00 80%
Handrail work Sq.m 178.16 50%
Marble work Sq.m 1000.37 85%

Page 2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT

Photo Photo

Site meeting to strengthen discipline and safety in site Moulduing work at roof main entrance

Moulding work for roof main gate Moulding work for top roof main building

Painting fance gate Making steel fence gate

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT


Photo Photo

Moulding work for main gate Ceiling board painting at main entrance

Installing light at ceiling Installing light at ceiling

Site installation for walkway Installing curb for ramp

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT


23/05/2020

Photo

Front View

Back View

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT

Photo

East View

West View

Page2

You might also like