Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report
QS engineer and Assistance 2 Prepare document such as payment claim, drawing, contract, other proposal and site inspection
Office MEP engineer and Assistance 2 Prepare document such as as-built,drawing, boq, other proposal and site inspection
Site engineer staff and Assistance 3 Follow up site progression, make report and site inspection
Admins and Assistance 2 Prepare fix Asset, Prepare workers and Staff's OT, tick attendance, transfer request to central, prepare other proposal
Site survey Survey 5 Follow up site progression, check level and coordination for site installation and do report.
Site MEP MEP 22 Standby for M&E, electrical work & AC system
Workers 6
Workers 6
Workers 5
KPCC
Workers 4
S16 Koh pich S.Workers 10 Installing scaffolding and tube for strengthen
Workers 5
Workers 4
Workers 0
Headman 1 Moulding work for fence gate, main gate, main entrance
Workers 4
Workers 6
Page1
Headman 0 Moulding decoration around
Moulding
S.Workers 10 Cleaning area
decoration
Workers 0
Workers 0
Workers 0
Workers 0
Brick work, plaster, installing and uninstalling scaffolding, KPCC Internal Subco. External Subco.
KPCC
Concrete work, tile roof, site arrangement and material preparation
Summary
Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
【Today's Work】
Description Work time Number worker
Marking plaster smoothing for exterior painting work 7:00 - 17:00 8
Brick work, plaster and painting for fence gate 7:00 - 17:00 14
Moulding work for main gate, fence gate and main entrance 7:00 - 17:00 19
Cutting and installing tube for exterior painting work 7:00 - 17:00 11
Tile arrangement at Toilet 7:00 - 17:00 10
Installing scaffolding and brick work at top roof 7:00 - 17:00 14
Brick work and plaster at main entrance 7:00 - 17:00 12
Brick work for fence gate and wall at basement floor 7:00 - 17:00 18
Concrete work 7:00 - 17:00 21
Making steel handrail 7:00 - 17:00 10
Platering wall and prepare construction safety net 7:00 - 17:00 15
Moulding decoration around 7:00 - 17:00 10
Roof tile installing 7:00 - 17:00 15
Painting ceiling board and installing C line for smartwood ceiling at main entrace 7:00 - 17:00 8
Painting interior at 5th floor 7:00 - 17:00 3
Installing granite at staircase at main entrance 7:00 - 17:00 6
Site cleaning all the floor 7:00 - 17:00 12
Prepare tube and scaffolding for exterior painting 7:00 - 17:00 6
Standby for MEP, electrical work & AC system 7:00 - 17:00 22
Total labour 234
【Message and Work Schedule for Tomorrow】
Description Work time Number worker
Task Description Unit Quantity Today's work (%) Completion's work (%)
Page 2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo Photo
Task's OT, Main entrance installation Installing formwork curb for ramp
Ceiling board installation for main entrance Ceiling board installation for main entrance
Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Moulding work for column at main entrance Moulding work for column at main entrance
Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo
Front View
Back View
Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report
Photo
East View
West View
Page2