Koh Pich Construction Company Cambodia-China Polytechnic University Daily Activities Report

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

KOH PICH CONSTRUCTION COMPANY

CAMBODIA-CHINA POLYTECHNIC UNIVERSITY


DAILY ACTIVITIES REPORT

Main Contractor: KPCC


Issued Date: Thursday, May 21, 2020 Issued No: CCPUI-023/2020
GROUP POSITION ATTENDANT DESCRIPTION
Project manager 1 Office and Site Management

Site supervisor 1 Site labor managerment

Arc. supervisor 1 Arc. drawing and technical management

QS engineer and Assistance 2 Prepare document such as payment claim, drawing, contract, other proposal and site inspection

Office MEP engineer and Assistance 2 Prepare document such as as-built,drawing, boq, other proposal and site inspection

Site engineer staff and Assistance 3 Follow up site progression, make report and site inspection

Surveyor engineer 1 Set up and checking coordinate for site installation,

Admins and Assistance 2 Prepare fix Asset, Prepare workers and Staff's OT, tick attendance, transfer request to central, prepare other proposal

Warehouse staff and Assistance 4 Stock Control, Material Purchasing.

Site Safety Safety 6 Strengthen discipline and safety in site

Site survey Survey 5 Follow up site progression, check level and coordination for site installation and do report.

Site MEP MEP 22 Standby for M&E, electrical work & AC system

Tower crane S.Workers 1 Standby for tower crane

Headman 1 Installing scaffolding and tube for roof tile arrangement

S56 S.Workers 16 Site cleaning area

Workers 6

Headman 1 Making handrail

S18 S.Workers 10 Site cleaning area

Workers 6

Headman 1 Tile arrangement at toilet

D27 S.Workers 12 Platering wall and prepare construction safety net

Workers 13 Site cleaning area

Headman 1 Concrete work

S16 S.Workers 15 Site cleaning area

Workers 5
KPCC

Headman 1 Platering work for frame window

S55 S.Workers 6 Rebar cutting at 6th floor

Workers 3 Site cleaning area

Headman 1 Brick arrangement at basement floor

S13 S.Workers 6 Site cleaning area

Workers 4

Headman 1 Platering work for frame window

S26 S.Workers 8 Brick arrangement for wall at 6th floor

Workers 2 Site cleaning area

Headman 1 Platering work for frame window

S16 Koh pich S.Workers 10 Installing scaffolding and tube for strengthen

Workers 0 Site cleaning area

Headman 0 Installing scaffolding and brick work at top roof

S19 S.Workers 9 Site cleaning area

Workers 5

Headman 0 Platering at roof main entrance

T67 S.Workers 9 Site cleaing area

Workers 4

Headman 1 Installation fence gate

S15 S.Workers 3 Site cleaing area

Workers 0

Headman 1 Moulding work for fence gate, main gate, main entrance

S87 S.Workers 16 Site cleaing area

Workers 4

Headman 0 Site cleaning and site material preparation

Team site cleaning S.Workers 0

Workers 6

Driver S.Workers 2 Standby for material and worker mobilization

Page1
Headman 0 Moulding decoration around
Moulding
S.Workers 10 Cleaning area
decoration
Workers 0

Headman 0 Installing ceiling board at main entrance

Ceiling S.Workers 5 Cleaning areas


Subcon.

Workers 0

Headman 0 Installing granite at main entrance

Marble work S.Workers 6 Cleaning areas

Workers 0

Headman 0 Painting work at 5th floor

Interior painting S.Workers 3 Cleaning areas

Workers 0

DESCRIPTION Number Labor

Brick work, plaster, installing and uninstalling scaffolding, KPCC Internal Subco. External Subco.
KPCC
Concrete work, tile roof, site arrangement and material preparation
Summary

Moulding decoration around 210 14 10


Internal Subco
Fence wall gate paining

Ceiling work Total Labor


External Sub
Marble work 234

Project Manager Reported By:

RITH RAVIN LAY SAMBO

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CCPU Project Work Report


Name: Daily Report
 ※Details of performance (specifical description) 21.05.2020 Weather (Hot) ○
【Yesterday's OT】
Description Work time Number worker

【Today's Work】
Description Work time Number worker
Marking plaster smoothing for exterior painting work 7:00 - 17:00 8
Brick work, plaster and painting for fence gate 7:00 - 17:00 14
Moulding work for main gate, fence gate and main entrance 7:00 - 17:00 19
Cutting and installing tube for exterior painting work 7:00 - 17:00 11
Tile arrangement at Toilet 7:00 - 17:00 10
Installing scaffolding and brick work at top roof 7:00 - 17:00 14
Brick work and plaster at main entrance 7:00 - 17:00 12
Brick work for fence gate and wall at basement floor 7:00 - 17:00 18
Concrete work 7:00 - 17:00 21
Making steel handrail 7:00 - 17:00 10
Platering wall and prepare construction safety net 7:00 - 17:00 15
Moulding decoration around 7:00 - 17:00 10
Roof tile installing 7:00 - 17:00 15
Painting ceiling board and installing C line for smartwood ceiling at main entrace 7:00 - 17:00 8
Painting interior at 5th floor 7:00 - 17:00 3
Installing granite at staircase at main entrance 7:00 - 17:00 6
Site cleaning all the floor 7:00 - 17:00 12
Prepare tube and scaffolding for exterior painting 7:00 - 17:00 6
Standby for MEP, electrical work & AC system 7:00 - 17:00 22
Total labour 234
【Message and Work Schedule for Tomorrow】
Description Work time Number worker

【Plant and Machinery Name】 Morning Shift Afternoon Shift Overtime


None

Morning Afternoon Rain Hours


【Rainy Report】
None None

【Percentage of progress for CCUPI 】

Task Description Unit Quantity Today's work (%) Completion's work (%)

Brick wall work Sq.m 8331.4 85%


Interior painting Sq.m 13955.00 46%
Exterior painting Sq.m 3779.10 0%
Ceilling work Sq.m 7068.00 75%
Tile work Sq.m 6577.87 70%
Glass work Sq.m 2069.25 70%
Door work Ls 149.00 15%
Moulding decoration work Sq.m 660.00 75%
Handrail work Sq.m 178.16 47%
Marble work Sq.m 1000.37 85%

Page 2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT

Photo Photo

Task's OT, Main entrance installation Installing formwork curb for ramp

Ceiling board installation for main entrance Ceiling board installation for main entrance

Moulding work for fence gate Fence gate installation

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION DAILY PHOTO FOR CCPU PROJECT


Photo Photo

Moulding work for column at main entrance Moulding work for column at main entrance

Tile roof arrangement Tile roof arrangement

Brick work at basement floor Moulding work for main gate

Page2
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT


13/05/2020

Photo

Front View

Back View

Page1
KPCC Project CAMBODIA-CHINA POLYTECHNIC UNIVERSITY
Daily Report

CONSTRUCTION FIX POINT FOR CCPU PROJECT

Photo

East View

West View

Page2