Ehs Risk Register / Assessment: Name of The Project Reference No Activities Covered
Ehs Risk Register / Assessment: Name of The Project Reference No Activities Covered
Ehs Risk Register / Assessment: Name of The Project Reference No Activities Covered
Assessment Re-assessment
Sl
Activity Hazard Risk Involved People at risk Existing Control Measures Risk Additional Control Measures Residu
No P S P S
Level al Risk
Sufficient no. of traffic marshal with 2 4 8 Workmen, alcohol test shall be ensure before 2 4 8
flags day time/ blinker night shall be deployed transportation.
deployed with escort & trailing vehicle. Prestart briefing and verification shall be carried
Trailer must be equipped with the Red out before carrying out job to mitigate
1 Transportation WORKING flags during day time and blinking lights miscommunication.
during night time.
WITH MULTI
Steel-Girder by All workmen shall be wear PPEs.
AXLE PUBLIC &
Transportation route shall be identified
TRAILER AND HIT BY TRAILER WORKMEN and well planned.
trailer to site
ROAD Multi axle trailer, trailing and escort
TRAFFIC vehicle shall be drove by experienced
location
and competent driver/operator.
Road diversion shall be done with
necessary precaution if required.
Working area shall be well isolated Installation of caution tape, reflectors, water
by installing barricading boards. barrier, jersey barriers, traffic cones shall be
Adequate no of traffic marshal shall ensured as per requirement.
Area lightening arrangement shall be done.
be deployed.
Well pre plan for traffic diversion shall be
WORKING Concrete blocks shall be placed at
prepared. 2 4 8
ON ROAD/ HIT BY OUTSIDER suitable places for protection from
3 4 12 Plan shall be briefed to all to carry out a good
WORKMEN / outsider vehicle.
LIVE VEHICLE / INTERFERENCE communication and team work during the job.
TRAFFIC/ OF PUBLIC
PUBLIC Live traffic shall be diverted with
ultimate precautions if necessary.
PUBLIC
Crane pulley/ hook/ web slings shall be
mechanically fit and shall be of
adequate/suitable capacity for lifting
the load.
3rd party inspection for all lifting tools
and tackles must be ensured before
starting the work.
Color coding of lifting tools & tackles
shall be ensured.
Well qualified and trained rigger shall be Lift evaluation plan, related checklists shall be
Erection of Steel- WORKMEN/
4 LIFTING AND FAILURE OF LIFTING deployed for signaling. prepared prior to the job.
Girder RIGGERS/ Lift evaluation shall be carried out Area shall be adequately lightened.
SHIFTING TOOLS AND TACKLES
STAFF /PUBLIC before each and every lift in a
prescribed form.
No person allowed roaming underneath
of lifted steel-Girder.
Unauthorized entry into lifting and
swing area shall be restricted.
Lifting and crane swing area shall be
isolated.