Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Ehs Risk Register / Assessment: Name of The Project Reference No Activities Covered

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7
At a glance
Powered by AI
The key takeaways from the risk assessment are transportation of steel girders, girder assembly work, working at heights, and fall of materials. Various hazards are identified for each activity along with existing and additional control measures suggested.

Some of the main hazards identified in the risk assessment include failure of cranes/lifting tools and tackles, injury from road traffic during transportation, toppling of trailer, and fall from heights during erection work.

Precautions suggested for transporting steel girders include using trained and competent drivers, deploying traffic marshals, identifying transportation routes, and conducting route inspections.

EHS RISK REGISTER / ASSESSMENT

Name of the Project


Reference No
Activities Covered :
Transportation & Erection of Steel-Girder

Date of Risk Assessment Date of Next Risk Review

Name of the EHS Risk Assessment Leader:


EHS Risk Assessment Team members:

Risk Assessment Leader Reviewed by Approved by


Name:
Date:
Signature:
Distribution to:ALL CONCERNED

Severity Value Probability


Severity (S)
The event is almost certain
1 2 3 4
Very to occur and has occurred
1 1 2 3 4 Fatality 4
Likely repeatedly in the
2 2 4 6 8 construction industry
Probability(P)

Reportable Injury or illness


3 3 6 9 1
resulting in > 2 days off The event will probably
2 3 Likely
work / Permanent Total occur in most circumstances
4 4 8 12 1 Disability / Major Pollution
6 Non-Reportable Lost Time
Unlikel The event may occur only in
Injury/ Illness resulting < 2 2
y exceptional circumstances
days off work
Risk Matrix Injury or illness requiring Very
Very unlikely but remotely
First Aid treatment. Minor 1 Unlikel
possible
Pollution y
Risk Rating Risk level Recommended actions
1 to 3 Low Risk No additional risk control measures may be needed.
4 to 8 Medium Risk Work can be carried out with Risk controls in place
Don’t start work. Risk level must be reduced to Medium / low before
9 to 16 High Risk
commencing work.
EHS RISK REGISTER / ASSESSMENT

Assessment Re-assessment
Sl
Activity Hazard Risk Involved People at risk Existing Control Measures Risk Additional Control Measures Residu
No P S P S
Level al Risk
 Sufficient no. of traffic marshal with 2 4 8  Workmen, alcohol test shall be ensure before 2 4 8
flags day time/ blinker night shall be deployed transportation.
deployed with escort & trailing vehicle.  Prestart briefing and verification shall be carried
 Trailer must be equipped with the Red out before carrying out job to mitigate
1 Transportation WORKING flags during day time and blinking lights miscommunication.
during night time.
WITH MULTI
Steel-Girder by  All workmen shall be wear PPEs.
AXLE PUBLIC &
 Transportation route shall be identified
TRAILER AND HIT BY TRAILER WORKMEN and well planned.
trailer to site
ROAD  Multi axle trailer, trailing and escort
TRAFFIC vehicle shall be drove by experienced
location
and competent driver/operator.
 Road diversion shall be done with
necessary precaution if required.

 Experienced and competent operator 2 4 8 2 4 8


shall operate Crane only.  Lifting plan shall be briefed to all to avoid
 Crane helper shall be deployed. miscommunication.
 3rd party certificate of cranes, lifting  Lifting plan shall be prepared by erection team
tools 7 tackles shall be ensured before prior to start work.
starting the work.  Outrigger shall be checked during lifting.
 Lifting shall be carried out under the
FAILURE OF CRANE,
competent and experienced
LIFTING TOOL & supervision.
GIRDER
2. WORKING TACKLES, WORKMEN / STAFF  Competent riggers and signalman shall
WITH INJURY / FATAL INJURY. be deployed.
ASSEMBLY
CRANES  All checklist and paper work to be
signed for lifting & shifting before start
of the activity.
 All lifting tools & tackles must be
checked before starting the activity.
 Tag rope must be ensured.
 Compacted and levelled ground shall be
ensured for placing of cranes.
 Full extension of crane outriggers shall
be ensured.
 Provision of outrigger base plate shall
be done.
 Lifting area shall be isolated.
 No person shall be permitted to work or
go underneath the hoisted load.
 Lifting shall not be carried out during
adverse whether condition.
 Adequate lighting arrangement shall be
ensured in night shift.

 Suitable capacity of trailer shall be


arranged.
 Trained drivers shall be deployed  Trailer driver alcohol test shall be ensured
for trailer operation and easy before deployed transportation.
maneuverability shall be ensured
TRAILER PUBLIC & while radial turning. 2 4 8
TOPPLING OF TRAILER WORKMEN  Route inspection shall be carried out 2 4 8
by the competent person, site
engineer from staring point to
destination point.
 Transportation route shall be well
planned before executing the job.

 Before shifting the Girder a prior route 2 4 8 2 4 8


inspection shall be carried out by the
TRAILER engineer in charge from starting point
OVERHEAD ELECTRIC WORKMEN to destination point for any overhead
LINE . electric line/other obstruction.
 If such obstacle comes in the
transportation route, it shall be diverted
or precaution shall be taken.

 All critical inspection shall be ensure 3 1 3 3 1 3


before marching the trailer on to the
TRAILER TRAILER BREAK INCONVENIENCE TO
alignment.
DOWN /E NGINE PUBLIC
 3rd party certificate/ fitness
FAULT /TIRE BURST certificate and other documents
/SUSPENSION FAULT related to equipment shall be valid.
 Fitness tag shall be ensured for
trailer.
 Competent mechanic shall be
available.
 Compaction report of the area shall be
available.
 3rd party certificate of crane, all  Adequate light arrangement shall be done
lifting tools and tackles shall be during night.
ensured.  Pre-planning shall be done for crane placing and
 Color coding shall be available on lifting.
lifting tools and tackles.  Competent mechanic shall be available for
 Physical inspection of working area, emergency.
2 4 8
all tools & tackles shall be carried
out before starting the job.
 Fitness tag shall be ensured for
cranes.
 Ground shall be well compacted and
leveled.
 No person and vehicle shall be
TOPPLING OF CRANE / permitted to go underneath the
Crane marching WORKING HIT BY CRANE OR LIFTED
4. WORKMEN / hoisted load during loading of 2 4 8
and placing WITH HEAVY LOAD/ FAILURE OF
PUBLIC
counter weight.
EQUIPMENT LIFTING TOOLS AND  Well qualified and trained/
TACKLES/ CRANE experienced rigger shall be deployed
BREAKDOWN for rigging work.
 Barricading of crane swing area shall
be ensured before starting work (as
per drawing ).
 Suitable capacity crane shall be
used.
 Crane’s outriggers shall be fully
extended with suitable base plate..
 Double tag rope must be ensured
for handling any lifted load like
counter weight.

 Working area shall be well isolated  Installation of caution tape, reflectors, water
by installing barricading boards. barrier, jersey barriers, traffic cones shall be
 Adequate no of traffic marshal shall ensured as per requirement.
 Area lightening arrangement shall be done.
be deployed.
 Well pre plan for traffic diversion shall be
WORKING  Concrete blocks shall be placed at
prepared. 2 4 8
ON ROAD/ HIT BY OUTSIDER suitable places for protection from
3 4 12  Plan shall be briefed to all to carry out a good
WORKMEN / outsider vehicle.
LIVE VEHICLE / INTERFERENCE communication and team work during the job.
TRAFFIC/ OF PUBLIC
PUBLIC  Live traffic shall be diverted with
ultimate precautions if necessary.
PUBLIC
 Crane pulley/ hook/ web slings shall be
mechanically fit and shall be of
adequate/suitable capacity for lifting
the load.
 3rd party inspection for all lifting tools
and tackles must be ensured before
starting the work.
 Color coding of lifting tools & tackles
shall be ensured.
 Well qualified and trained rigger shall be  Lift evaluation plan, related checklists shall be
Erection of Steel- WORKMEN/
4 LIFTING AND FAILURE OF LIFTING deployed for signaling. prepared prior to the job.
Girder RIGGERS/  Lift evaluation shall be carried out  Area shall be adequately lightened.
SHIFTING TOOLS AND TACKLES
STAFF /PUBLIC before each and every lift in a
prescribed form.
 No person allowed roaming underneath
of lifted steel-Girder.
 Unauthorized entry into lifting and
swing area shall be restricted.
 Lifting and crane swing area shall be
isolated.

 Lift evaluation shall be carried out


before each and every lift in a
prescribed form.
 Ground compaction shall be ensured.
 Crane outriggers shall be fully extended.
 Base plate of suitable dimension shall
be installed under elephant foot of
WORKING  Miscommunication shall be avoided between
TOPPLING OF CRANE / outrigger.
WITH WORKMEN/ crane operators and signalmen.
BREAKDOWN OR FAILURE  Crane operation shall be done be 2 4 8 2 4 8
 Crane radius, boom length, and capacity shall
CRANE / RIGGERS/ experienced operator.
OF CRANES DURING be checked for safe lifting.
HEAVY STAFF /PUBLIC  Competent rigger, signalmen shall be
LIFTING deployed.
EQUIPMENT
 3rd party and other documents related
to crane shall be valid.
 Outrigger shall be checked during lifting
and swinging of load.

 Adequate area lighting shall be arranged prior


 Workmen must have good condition to lifting operation if planned during night.
WORKMEN double lanyard full body harness while
going for work at height.
WORKING  Proper access & handrail mid rail shall
be ensured on pier cap.
AT HEIGHT
 Provision for anchoring the lanyard full 2 4 8 2 4 8
FALL OF PERSON body harness shall be arranged like life
line.
 Sky lifter/ scissor lifter shall have valid
green tag and be operated by
competent operator.
 No lose material shall be allowed to go
up along with the U-Girder.
 For shifting the tools and tackles carry
bags shall be issued to working crew. 2 4 8 2 4 8
 No material shall be thrown from height
FALL OF MATERIALS WORKMEN
on ground.
 Steel-Girder shall be rested and aligned
on pier cap as per drawing.
P: Probability, S: Severity

You might also like