BG Tunisia: Maintenance Department
BG Tunisia: Maintenance Department
BG Tunisia: Maintenance Department
Maintenance Department
2
Revision No: 0
3
Maintenance Department Scaff0lding Erection and Dismantling
CONTENTS
1.0 INTRODUCTION
1.0 INTRODUCTION
Where work cannot be safely done from the ground or from part of a building or other
permanent structure, there shall be provided either scaffolding or where appropriate
ladders or other means of support, all of which shall be sufficient to provide safe access
to and egress from the working place.
2. Inspection: The ability of a scaffold to carry its load is largely dependent on the
strength and condition of tubes used in construction. Consequently, tubes must
be checked to ensure they are:
Straight
Maintenance Department
Note: Tubes showing any evidence of damage from the aforementioned should be
destroyed.
All scaffold boards are manufactured from sawn and seasoned timber. Boards shall
comply with BS 2482 ‘ Specification for Timber Scaffold Boards’.
Timber boards come in three thickness – 38 mm, 50mm, 63 mm – and are normally 225
mm wide and 3.90 m long. Shorter boards are used when necessary. The most
common board is 225 mm x 38 mm.
1. Identification of boards:
Each board shall be identified by having the following information clearly marked on
it:
1. Foundation:
The foundations for a scaffold should be adequate to carry and dispose the load
imposed both locally at each standard and, in general, to carry the whole weight
of the scaffold.
The foundation for a scaffold should be maintained in an adequate condition
during the life of a scaffold.
On surfaces such as steel and concrete, which are of an adequate hardness and
thickness to prevent the scaffold tube penetrating into the surface, the uprights of
a scaffold may be placed directly on the surface, although it is generally
preferable to use a base plate.
On surfaces such as hard asphalt, timber flooring, and steel grating, where there
is a possibility of the standards deforming the surface, a base plate shall be used
at the bottom of each standard.
On soils, ash, hog gin, gravel soft asphalt and any type of flooring or paving
which would be penetrated by a standard with a base plate beneath it, or if there
is doubt about the surface, there shall be a further spreading of the load by a sole
plate of timber or other suitable material.
When a sole plate is used, the sole plate area beneath any one standard shall be
at least 1000 cm2, with minimum dimension of 219 mm, and if the sole plate is of
timber, it shall not be less than 35 mm thick. On sites where the ground is soft or
has been distributed, the sole plate area shall be not less than 1700 cm2 where
individual sole plates are used, e.g. under hoist towers, and not less than 3400
cm2 when two are combined under two standards. In this case, if the sole plate is
of timber, it may be necessary to use one with a total thickness in excess of 35
mm. Sole plates should wherever possible support at least two standards.
Maintenance Department
The soil or ground beneath the sole plate should be well compacted and free
from irregularities which would make the sole plate unstable or poorly bedded. It
is generally the responsibility of the main contractor to ensure that ground
conditions are adequately prepared to receive the scaffold.
On slopes exceeding 1 vertical to 10 horizontal, a check may have to be made on
the foundations to ensure the stability of the scaffold.
2. Base Plates:
The main function of a base plate is to distribute the load from the standard or raker
or other load bearing tube. Base plates shall measure at least 150 mm x 150 mm.
If the base plate is made of mild steel it shall be at least 5 mm thick. If made of other
materials then it must be thick enough to be capable of distributing the required load.
If fixing holes are incorporated in the design they must be diametrically opposed
(opposite each other), 6 mm in diameter, not less than 50 mm from the centre of the
plate, and not less than 19 mm from the edge.
The shank must be at least 50 mm high.
No base plate must ever bear directly on any fragile surface.
Where the surface slopes, suitably shaped packing pieces must be used to maintain
a level bearing.
3. Standards:
The standards carry the weight of the scaffold and should be very carefully spaced.
The vertical intervals at which standards are linked to one another, i.e. the lift height, is
one of the most important dimensions in scaffolding. This dimension should be
measured on site and maintained in accordance with the requirement of the design.
Standards should be plumb to within 20 mm in 2 m (subject to a maximum total
deviation of 50 mm).
Any joints in standards should be staggered. Joints in standards of access scaffolds
tied to a building may be made with either joint pins or sleeve couplers (sleeve couplers
are preferred). These types of coupler have limited load capacity in tension. In scaffolds
which are free standing or projecting above the level of a building or otherwise subject to
forces which would produce tension in the uprights, the standards should be joined in a
manner capable of resisting the applied tension.
No more than three out of four standards at the corner of any bay should have joints in
the same lift, except in the case of the bottom 6.5 m of a scaffold where an extended
base lift is necessary for pedestrian access or other reason. In these instances, when it
is permissible to have four joints in the same lift, one of these must be spliced with a
short length of tube.
Where any of the standards in a scaffold are founded in a light well or at a level lower
than the remainder of the standards, the extension downwards should be stiffened by
horizontal tubes, in two directions at right angles, and fixed at lift heights not greater
than that of the foot lift of the remaining scaffold. Where access for the personnel is
required under the first lift, a height of up to 2.7 m is permissible. This may necessitate a
special design.
Maintenance Department
3. Ledgers:
Ledgers join the standards together. They should be horizontal and fixed with right angle
couplers. A foot lift may follow the slope of the ground at the base of the scaffold, in
which case the ledgers will be fixed to transoms that are attached to standards with right
angle couplers. The area that the ledger spans between standards is called a bay.
Joints in ledgers may be made with sleeve couplers or expanding joint pins. Where
tension is likely to occur only sleeve couplers should be used. Joints in ledgers on the
same lift and in adjacent lifts should not normally occur in the same bay. However, when
guardrails are to remain permanently in place, the absence of a joint in the guardrail
may be accepted as giving sufficient continuity to the scaffold to permit joints in the
ledgers above and below it in the same bay. Where joints are necessary, they should be
positioned at a distance not greater than 1/3 of the span between adjacent standards.
4. Transoms:
Transoms may be fixed to the inside and outside ledgers with wrap over putlog couplers
or to the standards with right angle couplers.
The spacing of transoms and putlogs for boarded lifts should be in accordance with
Table 1. Board end transoms should be fixed so that the end overhang of a board does
not exceed that given in Table 1. In no case should the overhang be less than 50 mm.
Transoms and putlogs for non-boarded lifts should be fixed at one per pair of standards,
including the pair at each end of the scaffold, and should be fixed within 300 mm of the
standard.
On scaffolds of a height greater than 50 m, the transoms on non-boarded lifts, when
fixed at the frequency of one transom per pair of standards, should be fixed to the
ledgers or uprights with right angle or other suitable couplers provided they are capable
of sustaining a safe working slip load of 5 kN.
When a boarded platform is moved to a new level, the transoms on the lift from which
the boards have been taken may be re-arranged to comply with the requirements for a
non-boarded lift.
5. Ledger Bracing:
The ledger bracing may be fixed from ledger to ledger with right angle couplers or fixed
to the standards using swivel couplers.
To facilitate the inclusion of boarded lifts, bracing is sometimes placed between
standards, using swivel couplers, and ledgers, using double couplers.
The direction of ledger bracing is immaterial for the structural stability of the scaffold but
it should be pre-planned to take account of the intended use of the scaffold.
The bracing on boarded lifts should be from under the outside ledger of a boarded lift
down to the inside ledger of the lift below so as to avoid the toe-boards. This
arrangement may require an extra width on the scaffold to accommodate the brace.
In scaffolding over footpaths, it may not be possible to ledger brace the lowest lift.
Ledger bracing may be omitted from this lift provided the lengths of the standards in the
lift are not in excess of 2.7 m. In the latter case, account should be taken of the reduced
loading capacity of this lift which may necessitate a special design.
To improve access on one lift only, ledger bracing from the inside ledger to the guardrail
level of the lift below may be used, provided that every pair of standards is so braced
instead of every alternate pair.
Sway bracing should be provided to all scaffolds to prevent movement along the façade
of the building. One such brace assembly should be provided on every face at intervals
along the scaffold not exceeding 30 m. It need not be fixed where the scaffold is
securely butted between opposing outside or inside faces of returns or recesses,
provided that no length greater than 10 m is so fixed against movement in both
directions.
The two principle forms of brace arrangements are where the bracing takes the form of
either a zigzag from bottom to top or a continuous sloping tube from bottom to top. In
either case the bracing tube should be connected to:
Every standard with swivel couplers; or
Every lift on to extended transoms with right angle couplers.
The longitudinal brace should be fixed as near to the standard/ledger connection as
possible. When it is fixed to extended transoms, these should be fixed to the ledgers or
standards with right angle couplers.
The bracing should start from the base of the one of the outside standards. In the lower
lift, when the bracing is started, a guardrail should be placed through the braced bay to
prevent people passing.
When sway bracing is omitted, the lateral movement of both the inside and outside lines
of the standard at every lift should be prevented, either by both lines being adequately
butted or by adequate plan bracing on to firm points inserted at every level.
7. Scaffold Ties:
Ties should be provided to resist inward and outward movement of independent and
putlog scaffolds. They should have a minimum capacity of 6.25 kN.
When only two ties are required, it is preferable to place the ties toward the ends of a
straight run of scaffold
Maintenance Department
Ties should evenly be distributed over the scaffold with spacing not exceeding 8.5 m,
vertically or horizontally. Where the building surface permits a staggered arrangement of
ties, this should be adopted in preference to a rectangular pattern. They are normally
spaced at 6 m intervals horizontally and every 2nd lift vertically.
Scaffold platforms for persons only must be a minimum of 600 mm wide, i.e. when
erecting the scaffold. Increase to 4 boards wide when storing material, leaving a 2 board
clear passageway for persons to walk past. A 3 board minimum passageway should be
left clear when materials are being transported along the platform, which in this case
would normally be 5 boards wide.
Any group of boards across the width of the scaffold should be of the same length, with
all boards of the same thickness.
38 mm thick boards are the most common in use and are supplied in lengths of 3.90 m.
When these are used, there should be four transoms to each board. Boards, which are
38 mm thick and less than 3.3 m long, may be supported on three transoms. Boards,
which are nominally 38 mm thick and less than 2.10 m long, should not be used unless
they are securely fixed to prevent tipping.
Boards, which are less than 1.80 m long, may be supported on two transoms, but
should be fixed at both ends. Such boards occur adjacent to ladder openings and
provision should be made to prevent them from moving under impact and vibration.
Boards, which are used on small static and mobile access towers and on small
platforms, where the platform is surrounded by a guardrail and toe board, need to be
fixed down and should be prevented from moving laterally.
There are no permissible gaps in decking. Scaffolds should be erected as near to the
building as is reasonably practicable, except when it is required for workers to sit on the
edge of the boarded deck, in which case the gap should not exceed 300 mm.
Working platforms from which a person may fall more than 2 m should have a guardrail
and end guardrails fixed inside the standards at a height of at least 910 mm above the
level of the decking.
With the guardrails set at 910 mm, a second lower guardrail or higher toe board should
be provided to limit the gap to 470 mm. Suitably added brick guards or retaining boards
are an acceptable alternative to a second or intermediate guardrail.
Toe boards and end toe boards should be suitably fixed. They should be of such a
height that the gap between the top of the toe board and the guardrail does not exceed
470 mm and have minimum height of 150 mm. They should be placed inside the
standards.
Brick guards or other suitable vertical protection are desirable in cases where materials
may fall from the scaffold.
Maintenance Department
10. Ladders:
Ladders are frequently taken for granted and they are the cause of many serious
accidents.
New ladders should be protected by coating with wood preservative and clear varnish.
Painting is illegal; it can hide defects.
All ladders should be inspected frequently – the following points should be checked:
The stiles – for splits or cracks. Splintering, warping or bruising. A bruised stile
absorbs moisture which will encourage decay and lead to fracture.
The rungs – for signs of undue wear. No rungs should be missing.
The wedges of tie rods – for tightness.
The feet – splitting and fraying.
If a ladder cannot be properly repaired – scrap it.
Ladders should normally be placed on a firm, level base; on a sloping surface use an
adequate safety foot. They should be equally supported on each stile.
The correct angle for a ladder is about 75 degree to the horizontal, i.e. 1 meter out at the
base for every 4 meters of height.
Regulations state that a ladder over 3 meters in height must be tied or footed before
use. However, it is good practice to tie or foot ladders of any height.
Maintenance Department
Ladders should be lashed or secured to some convenient anchorage near the top on
both sides. This helps prevent the base slipping outwards and the top sliding sideways.
Only the stiles should be lashed. Where lashing at the top is not practicable, secure at
the base. If no other means of fixing a ladder to prevent slipping can be found, then
someone must hold it at the base when it is being used.
Where a long ladder is in use, an intermediate tie may be necessary to prevent undue
swaying or sagging.
Ladders should always be placed so that there is space behind each rung for a proper
foothold. Particular care should be taken at this point on the landing platform.
Ladders, when suspended, should be lashed so that they are equally supported on each
stile at top and bottom.
All ladders should extend 1 m above any landing place, or beyond the highest rung from
where a person may be working, to ensure an adequate handhold. If this is not possible
then a nearby handhold of equivalent height must be provided.
Wherever ladders pass through openings, in platforms etc., the opening must be no
larger than necessary for use and not more than 500 mm in width.
Erecting Ladders: Do not carry any ladder upright. Carry it horizontally on edge, holding
it under the lower stile to avoid pulling any of the joints.
Before setting up a ladder make sure the footing is secure and firm. Check that it will not
be in contact with any overhead danger such as live cables or lamps.
A ladder left out in the open will soon deteriorate. Store it under cover that is dry and
well ventilated. Lay the ladder flat on a rack supported along its length.
Most scaffolds require at least a simple lifting device to raise materials to the necessary
working height. Gin wheels are the most widely used.
The tube supporting the gin wheel should be fixed either to standards which have been
braced, e.g. a ledger braced pair of standards in an independent tied scaffold, or, in the
case of a putlog scaffold, to one standard and braced back to the ledger or putlog tube
at mature brickwork level.
Suspension point of the gin wheel on the supporting tube should not be more than 750
mm beyond its outer support point.
Ring type gin wheels are to be preferred, i.e. gin wheel with swivel eye fitments to slide
over the supporting tube and which can be held in position by couplers.
Ropes should comply with BS 2052. They should fit snugly into the rim of the wheel and
be regularly examined. They should be marked for identification. The most common
diameter for a fall rope is 18 mm.
Maintenance Department
Knots:
The recommended knots to be used when raising or lowering scaffold components are
as shown on this page, i.e. rolling hitch, timber hitch, and figure of eight knot.
Scaffold Towers:
Free standing structures which are self-supporting and not dependent totally on other
structures for their rigidity or stability. Three classes are generally recognised:
-Light duty access towers: stationary and mobile for use inside buildings (imposed load
not greater than 1.5 kN/m2).
-light duty access towers: stationary and mobile for use in the open (imposed load not
greater than 1.5 kN/m2).
-Heavy duty towers: these are always built to design details.
Dimensions will vary according to need, but standards should never be less than 1.2 m
or more than 2.7 m apart.
Foot ties should be fixed approximately 150 mm from the bottom of the standards.
Except for the working platform, ledgers and transoms should be fixed to standards with
right angle couplers.
Lifts should not exceed 2.7 m or be greater than the smallest base dimension.
Bracing is in two forms:
1. Plan bracing at the base, the working platform and at alternate
lifts.
2. Diagonal bracing to the full height of the scaffold on all four sides.
Plan bracing should be fixed to the standards with right angle couplers. Diagonal
bracing should be fixed to the ledgers and transoms by right angle or swivel couplers.
The recommended maximum freestanding height for static towers is 10.8 m, except that
this may be increased to 50 m if it is tied to s structure at 6 m intervals.
The working platform should be fully and closely boarded to an area of at least 1.2 m x
1.2 m.
Maintenance Department
Because of the changes which are made in a scaffold structure during its working life, it
is not safe to assume that dismantling can be carried out in the reverse order to the
erection. The scaffold, especially its tying and bracing, should be inspected prior to
dismantling.
The procedure of dismantling should be orderly and planned and should proceed
generally from the top in horizontal sections.
Scaffolds should not be dismantled in vertical sections from one end towards the other,
especially in cases where a hoist tower, which apparently gives support to the scaffold,
is to be left standing, unless special considerations is given to ties and bracings.
Scaffold belt
Level
Frogs
7/16” scaffold spanner
½” scaffold spanner
Podger
3ft tape
Full body harness
Fall arrester gear (when required)
These scaffold erectors, once on BGT Hannibal Gas Treatment Plant, will be required to
undertake a theoretical and practical test on erection and dismantling scaffold prior to
start work on the plant. The certified BG Tunisia Scaffold Supervisor, designated by the
Maintenance Manager, will decide of the design of the scaffold to be erected, and
decide about the competency of each scaffold erector. Training scaffold erectors is not
the responsibility of BG Tunisia.
The BG Tunisia designated Scaffold Supervisor responsible for the job must ensure that
the performing authority and the scaffolding erectors are made fully aware of the
scaffold requirements prior to execution. He should include details of the scaffold on the
PTW Request Form with any special requirements. Scaffold requirements shall be
discussed and agreed with the issuing authority when the PTW Request Form is
submitted.
When the scaffold is erected, the BG Tunisia designated Scaffolding Supervisor will
inspect and certify the scaffold for the job to start. A scaffold tag is used to indicate that
the scaffold is safe for use when green, and not safe for use or still under construction
when red.
If any change to the scaffold structure is required, then the Scaffold Supervisor should
be informed immediately to designate scaffold erecter(s) to do the necessary changes
on the structure.
The certified BG Scaffold Supervisor shall inspect the erected scaffold every 7
days.
The standing life of an erected scaffold is three months. If more than three
months, then all scaffold components shall be inspected for distortion and or
looseness, i.e. Scaffold Boards, Joints, Braces, Ties, Fittings etc.
During the erection of a scaffold a red scafftag shall be fixed indicating ‘ DO NOT
USE SCAFFOLD’.
Maintenance Department