METHOD STATEMENT
PLASTERING
P a g e 1 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE OF WORKS
4. METHOD
P a g e 2 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
1. PURPOSE
The purpose of this method statement is to ensure that wall plastering comply with specified
requirement.
This work procedure covers all activities required to produce acceptable wall mortar finish.
2. SCOPE OF WORKS
EQUIPMENT
MANPOWER
P a g e 3 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
4. METHOD
MATERIALS
1. Cement
2. Sand
Sand will be used for plastering is river sand (sand property test already submitted). Sand shall
be good quality and free from salt, mud, dust and hazardous level of organic matter.
3. Mortar mix
The volume of water will be visually adjusted so that the mixture mortar does not possess any
dry mixture.
P a g e 4 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
A. SURFACE PREPARATION
Plastering has 2 coats or 2 layer of plastering for 230mm wall and for 110mm wall only 1 coat of
plastering (See figure below):
P a g e 5 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
C. WORK PROCEDURE
FINISHING COAT:
Mortar with fine sand to be used and with 3mm thickness make the surface flat and
smooth. This coat is finished with wood floating or steel trowel finish. After a minimum of
2 weeks painting can be carried out.
P a g e 6 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
Wet the surface of masonry to receive plaster one hour before, so that while starting
plastering the surface is skin dry.
All embed MEP pipes, electrical boxes shall be completed before commencement of wall
plaster.
Throw the mortar for an area coverable by the straight edge, both vertically and
horizontally in one stretch.
Level the surface using the straight edge or aluminium square tube.
Float the surface and finish as per required thickness.
Repeat this operation for the entire area in stages (1st to final coat application)
Provide scaffolding when work height is more than 1.5 meter
Intermittently do check the surface for plumb, line and level and make up all deficiencies.
Provide 20mm coat plaster (two application) in internal and external surfaces of concrete
and masonry wall in as specified.
Trueness of plastered surface when checked with the straight edge of 3 meter length shall
not be greater than 4mm at any place.
Restrict the access to area where plastering is complete (To ensure better protection of
edges, corners, angles etc.).
Cure the plastering well for 3 days.
Note: Plastering work must be planned to complete each coat in a whole span for one day. In
case a large area or long span, a wooden stopper shall be provided at the edge of the area
where the plastering work for the day ends.
P a g e 7 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
P a g e 8 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
INSPECTION HOLDPOINT
PREPARATORY INSPECTION
S.N Items Conforms
1. Approved drawings Yes No
2. Material approved by client
FINAL INSPECTION
A. Before Plastering Application
1. All embed MEP completed (water pipe, drainage pipe,
etc)
2. Services within walls have been tested
3. Block wall surface shall be clean & dust,dirt,oil free
4. Free of bee holes, joint filled, crack repaired
3. Guide level
5. Control Joint/Expansion Joint (if needed)
6. Plaster Mesh installed
7. Surface should be watered one hour before plastering
8. Mix proportion of the mortar should checked as per
requirements
9. Protection (for other finishing material to avoid stain &
damages)
10. Scaffoldings
B. After Plastering Application
1. Surface Flatness
2. Surface smoothness
3. Wall alignment
4. Window/Door opening corner squareness
5. No crack surface
6. No bee holes
7. No hollow sound
8. Edging alignment
9. Curing
10. Housekeeping
P a g e 9 | 10
URBAN ARCHITECTURE Co. Ltd.
A5-A8, La Seine, Diamond Island, Tonle Basaac
Chamkarmon, Phnom Penh, Cambodia
Tel No. +855(0)-23-999-168
www.urban.com.kh
All works shall comply with safety procedure or instruction as set out in project safety plan
rules and regulations
Urban Safety Personnel will be on site during works
Qualified and skilled workers should be assign to the installation
All field personnel shall be required to wear their PPE
Preparatory meeting should be conducted before start the work
Provide lighting when work at night
Prepared by:
Urban Architecture
Q.C Department
19.11.18