Method Statement For Blockwork
Method Statement For Blockwork
Materials:
Solid Blocks, Cement, Sand, Water.
Preparatory Work:
Before start the work the roof slab of the upper floor need to be completely de-shuttered
and get the structural clearance.
Obtain the relevant approved GFC drawing and blockwork schedule from the
architectural.
Review the drawing and order the material as required.
Set out the locations for the blockwork with reference to the blockwork schedule.
All the blocks to be checked there is no any broken corners and blocks.
Determine the size of blocks as specified in the schedule of finishes.
Clean the work area and ensure it is accessible and passable.
Prepare the surface to blockwork: thoroughly clean the grime, grease, dirt, loose particles
and other substance that may interfere with the bond of cement mortar. Wet the surface.
Carry out the inspection checklist for the blockwork at site.
Provide and erect the scaffolding to the area as required.
Take the surveyor for the points of setting out as per approved GFC drawing.
Place the materials blocks, sand, cement and water to the location.
Prior to start the blockwork all the place where the blockwork will come in contact with
concrete structure need to be hacked. Cement mortar 1:3 should be splattered on the
hacked surface and cured for 3 days. This provide a good bond between the blockwork
and concrete structure.
The Marking should to transfer to the columns with which FFL, sill level and lintel level
are marked.
Make sure all the electrical conduits are raised from the floor slab or lowered from the
beam bottom to the required length.
Work Methodology