Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement For Railing Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

The Rise Residence & Resort Project

PROJECT TITLE

FASA 1A:

I) KONDOTEL B 43 TINGKAT = 629 UNIT

II) KONDOTEL C 41 TINGKAT = 529 UNIT

III) SHOP (RUANG PERIAGAAN) 1 1/2 TINGKAT

IV) PPU 2 TINGKAT = 1 UNIT

V) SSU 2 TINGKAT = 1 UNIT

UNTUK: TETUAN YEASHIN CONSTRUCTION SDN.BHD

METHOD STATEMENT FOR RAILING

Revised : 00 (30th Oct, 2020)

PREPARED BY: CHECKED & APPROVED BY:

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


The Rise Residence & Resort Project

METHOD STATEMENT FOR RAILING

1.0 PURPOSE

The main purpose of this method statement is to demonstrade the method and

procedure adopted in installing the factory pre-fabicated & pre-finished coat steel

balustrade and railing at Podium & Tower BC – The Rise residence & resort project with

all the required specifications, standards, quality assurance, proper construction

procedures and safety & health aspects.

2.0 MANPOWER & RESPONSIBILITIES

Item Manpower Descriptions

1 Construction Manager / Site Manager

2 Engineer / Supervisor / Surveyor / Safety

3 Skill Painters Workers

4 General Workers

The overall implementation & construction procedures of this method statement is under

the sole responsibility of the Construction Manager & Site Manager.

All safety procedures & safety measures relating to the nature of the works being carried

out are to be implemented under the supervision of the company Safety Officers, in

accordance with the project HSE plan.

QA/QC Engineer is responsible inspection for the quality assurance of the related

exterior wall finishing works as described in this method statement.

Technical staff shall monitor and make sure that documents like this method statement &

material requirement gain the necessary approval by client/architect.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd


The Rise Residence & Resort Project

3.0 MATERIAL

Item Material Descriptions

1 Railing Pre-Fabricated - Fluocarbon Coating

2 Bolt M10 Grade 4.6

3 Other Material Necessary

The other equal materials shall be approved by Main-Contractor/Client.

4.0 EQUIPMENT TO BE USED

Equipment Quantity

Electrical Driller

Electrical Screwdriver As Defined On

Laser Operated Leveler Actual Site

Welding Machine Condition.

Metal Cutter

Metal Works Hand Tools

5.0 SAFETY, HEALTH & ENVIROMENT

Greater efficiency in the finishing department can be obtained if each employees or

individual acquaints himself with the best shop habits. Instructors in shops should know

good shop practices and insist that employees follow appropriate rules and regulations.

Basic safety practices include the following:

- Use the appropriate PPE provided and keep it in excellent condition.

- Do the job right the safe way don’t take chances, report injuries & unsafe conditions.

- Clean floors, walls ceiling, and spray booth periodically. Comply all safety instruction.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd


The Rise Residence & Resort Project

6.0 CONSTRUCTION PREPARATION

• Obtain relevant approved construction drawings & material from Architect/Client .


• Make good completed structure in order to receive railing. All opening, holes, defect
honeycomb, unevenness jointing, cracks on floor must be properly filled by related
contractor before commencement of work.
• The steel balustrade & railing shall be pre-fabricated & pre-finished at
factory/manufactured in accordance with the approved shop drawing & material.
• Site dimensions, structural defect shall be verified, if any discrepancies are found and
request to follow up & rectify.
• Coordinate with other contractor to ensure works carried by others included MEP works
have been completed as per the agreed sequence.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd


The Rise Residence & Resort Project

7.0 SEQUENCES OF WORKS

1. Check setting out on layout plan for railing location as drawing.

2. Drill hole to concrete floor/kerb and install the pre-fabricated railing by expansion bolt as
detail drawing.

3. Insert timber/temporary support to adjust the railing level (vertical & horizontal). Then
fixed bu nut/welding to ensure railing no shaking.

4. Double check then protection railing by plastic/equal material & clean up area after works.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd


The Rise Residence & Resort Project

8.0 QUALITY CONTROL MEASURES

1. Check material & finishing correct as drawing.


2. Check height & curvature of railing as drawing section/elevation.
3. Check top rail level flatness & welding evenness.
4. Check connection detail of railing to floor & wall (if any).
5. Check distances of the posts are equal as drawing.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd

You might also like