Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Saudi Aramco Test Report

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 11

SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.

00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. TEST PROCEDURE FOR CONTINUITY TEST

For jobsite acceptance, all windings shall be checked for continuity using
SAES-P-121
A1 a continuity tester.
Sec. 3.2
NETA, ATS- 2009

B. TEST RESULTS FOR CONTINUITY TEST

Continuity Test Pass Fail Test Date Remark

H1 - H2 H2 - H3 H3 -H1
Primary Windings

X1 - X2 X2 - X3 X3 - X1
Secondary Windings

C. TEST PROCEDURE AND CHECKLIST FOR INSULATION RESISTANCE (MEGGER) TEST

Connect all primary terminals together. SAES-P-121


C1
NETA, ATS- 2009 Sec. 3.2

Connect all secondary terminals together. SAES-P-121


C2
NETA, ATS- 2009 Sec. 3.2

Primary to secondary and ground test:


SAES-P-121
C3 Perform an insulation resistance test at 5000 Vdc test voltage.
Sec. 3.2
NETA, ATS- 2009

The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C4 index calculation.
Sec. 3.2
NETA, ATS- 2009

Correct for temperature. SAES-P-121


C5
NETA, ATS- 2009 Sec. 3.2

Record the results in the table. SAES-P-121


C6
NETA, ATS- 2009 Sec. 3.2

Compare test results to manufacturer's recommendations. SAES-P-121


C7
NETA, ATS- 2009 Sec. 3.2

Primary to secondary test:


SAES-P-121
C8 Perform an insulation resistance test at 5000 Vdc test voltage.
Sec. 3.2
NETA, ATS- 2009

The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C9 index calculation.
Sec. 3.2
NETA, ATS- 2009

Correct for temperature. SAES-P-121


C10
NETA, ATS- 2009 Sec. 3.2

Page 1 of 11
Record the results. SAES-P-121
C11
NETA, ATS- 2009 Sec. 3.2

Page 2 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Compare results to manufacturer's recommendations. SAES-P-121


C12
NETA, ATS- 2009 Sec. 3.2

Secondary to primary and ground test:


SAES-P-121
C13 Perform an insulation resistance test at 5000 Vdc test voltage.
Sec. 3.2
NETA, ATS- 2009

The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C14 index calculation.
Sec. 3.2
NETA, ATS- 2009

Correct for temperature. SAES-P-121


C15
NETA, ATS- 2009 Sec. 3.2

Record the results. SAES-P-121


C16
NETA, ATS- 2009 Sec. 3.2

Compare results to manufacturer's recommendations. SAES-P-121


C17
NETA, ATS- 2009 Sec. 3.2

D. TEST EQUIPMENT AND MATERIALS CRITERIA

Test shall be performed using a motor-driven or rectifier type insulation SAES-P-121


D1
resistance test set (Megohmeter) 5000 V dc. Sec. 3.2

Schedule Q
D2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

E. TEST RESULTS FOR INSULATION RESISTANCE TEST

TEST INSULATION RESISTANCE (MΩ)


Pass Fail Test Date Remark
JOBSITE PRI /SEC & SEC / PRI &
VOLTAGE TIME PRI / SEC
ACCEPTANCE - GRD GRD
INSULATION
RESISTANCE 5000 v 1 min

PRE-ENERGIZE -
INSULATION 5000 v 1 min
RESISTANCE

1 min
POLARIZATION
5000 v
INDEX
10 min

1 min

2 min
DIELECTRIC
3 min
ABSORPTION

Page 3 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
DIELECTRIC
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
ABSORPTION
4 min

5 min

F. CONCLUSIONS FOR INSULATION RESISTANCE TEST

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

For the insulation Resistance test, values of insulation resistance less


than manufacturer's minimum or the recommended minimum insulation
resistance values above should be investigated. Resistance values to be
SAES-P-121
F1 temperature corrected in accordance to attachment 1, NETA ATS, Table
Sec. 3.2
7.2.1 above. Overpotential test should not proceed until Insulation
resistance levels are raised to said minimum.
NETA, ATS- 2009

For the Polarization Index, the ratio of insulation resistance at 10 minutes


to insulation resistance at 1 minute value would be 2 or higher, values
SAES-P-121
F2 between 2 and 1 indicate marginal condition, and values below 1
Sec. 3.2
indicate poor condition.
NETA, ATS- 2009

For the dielectric-absorption test, the values recorded at each one minute
interval shall be plotted on log-log paper with coordinates for resistance
versus time. A good insulation system will have a slope that is a straight SAES-P-121
F3
line increasing in respect to time. The characteristic slope of a poor Sec. 3.2
insulation system will be a curve that flattens out with respect to time.
NETA, ATS- 2009

Test results are acceptable and in accordance with Saudi Aramco


F4 N/A
Engineering Standards and contractual requirements.

G. TEST PROCEDURE FOR TURNS RATIO VERIFICATION

Perform a turns ratio test on each phase from primary to secondary on all
SAES-P-121
G1 taps.
Sec. 3.2
NETA, ATS- 2009

Record the results below. SAES-P-121


G2
NETA, ATS- 2009 Sec. 3.2

Compare test results to manufacturer's recommendations or industrial


SAES-P-121
G3 standards.
Sec. 3.2
NETA, ATS- 2009

H. TEST EQUIPMENT CRITERIA FOR TURNS RATIO TEST

One of the following pieces of test equipment is required to perform the


transformer ratio verification testing requirements:
SAES-P-121
H1 1. Transformer Turns Ratio meter
Sec. 3.2
2. AC Voltage Supply and Voltmeter (+/- 0.5%)
3. Self-contained Transformer Test Set

Page 4 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Schedule Q
H2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

I. TEST RESULTS FOR TURNS RATIO TEST

Measured Ratio Factory Ratio


Tap Position Primary Volts Calculated Ratios
A B C A B C

J. CONCLUSIONS FOR TURNS RATIO TEST

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Turns ratio test results should not deviate more than one-half of one
SAES-P-121
J1 percent (0.5%) from calculated ratio.
Sec. 3.2
NETA, ATS- 2009

Test results are acceptable and in accordance with Saudi Aramco


J2 N/A
Engineering Standards and contractual requirements.

K. CORE MEGGER TEST

Before the core Megger test can be performed, inspect the transformer
and determine whether it has a core ground strap. The copper-foil ground
strap extends out of the core bottom between the bottom clamps. If the SAES-P-121
K1
strap is not present, the test is not necessary. If the strap is present, Sec. 3.2
perform the core Megger test.
NETA, ATS- 2009

Disconnect the core ground strap from the flexible jumper, which attaches
the strap to the bottom clamp. Make sure the ground strap is clear from SAES-P-121
K2
any contact with the transformer ground to isolate the clamp structure. Sec. 3.2
NETA, ATS- 2009

Take care not to pull the core ground strap out of the core, attach the hot
SAES-P-121
K3 lead of a 1000V dc Megohmeter to the core ground strap.
Sec. 3.2
NETA, ATS- 2009

Attach the ground lead of the Megohmeter to the core clamping bolt,
which is next to the core ground strap. Ensure the lead and core ground SAES-P-121
K4
strap are not in contact with the ground. Sec. 3.2
NETA, ATS- 2009

Page 5 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Energize the Megohmeter. A reading of 10 megohms or greater is


acceptable. Verify with the manufacturer for reading less than 10 SAES-P-121
K5
megohms. Record the results in the table below. Sec. 3.2
NETA, ATS- 2009

Reattach the core ground strap to the flexible jumper. SAES-P-121


K6
NETA, ATS- 2009 Sec. 3.2

INSULATION
Date
RESISTANCE READING Pass Fail Remark
Tested
(MΩ)

L. OVER POTENTIAL TEST

Connect all primary terminals together. SAES-P-121


L1
NETA, ATS- 2009 Sec. 3.2

Connect all secondary terminals together. SAES-P-121


L2
NETA, ATS- 2009 Sec. 3.2

Primary to secondary and ground test:


Perform a DC overpotential test not to exceed 75% of factory test values
SAES-P-121
L3 in accordance with IEEEC57.12.91, Sec 10.2. The test duration shall be
Sec. 3.2
for 1 minute once maximum test voltage is achieved.
NETA, ATS- 2009

Record results in the table. SAES-P-121


L4
NETA, ATS- 2009 Sec. 3.2

Primary to secondary test:


Perform a DC overpotential test not to exceed 75% of factory test values
SAES-P-121
L5 in accordance with IEEEC57.12.91, Sec 10.2. The test duration shall be
Sec. 3.2
for 1 minute once maximum test voltage is achieved.
NETA, ATS- 2009

SAES-P-121
L6 Record results in the table.
Sec. 3.2

Secondary to primary and ground test:


Perform a DC overpotential test not to exceed 75% of factory test values
SAES-P-121
L7 in accordance with IEEEC57.12.91, Sec 10.2. The test duration shall be
Sec. 3.2
for 1 minute once maximum test voltage is achieved.
NETA, ATS- 2009

SAES-P-121
L8 Record results in the table.
Sec. 3.2

M. TEST EQUIPMENT CRITERIA FOR OVERPOTENTIAL TEST

SAES-P-121
M1 Test shall be performed using a DC Overpotential Test Set.
Sec. 3.2

Schedule Q
M2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1

Test Equipment Manufacturer: Serial Number:

Page 6 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

N. TEST RESULTS FOR OVERPOTENTIAL TEST

Date
Test kV TIME (Min) PRI / SEC & GRD PRI / SEC SEC / PRI & GRD Pass Fail Remark
Tested

Step 1

Step 2

Step3

1 min

O. CONCLUSIONS FOR OVERPOTENTIAL TEST

A.C. high potential test voltage shall not exceed seventy-five percent
(75%) of factory test voltage or attachment 1, NETA ATS Table 7.3.1 for a SAES-P-121
O1
one (1) minute duration. Evaluation shall be on a go no-go basis. Sec. 3.2
NETA, ATS- 2009

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Pro Forma Contract), February 2008
2. SAES-P-121 -- Transformers and Reactors,28 January 2016
3. NETA ATS -- Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems, 2009
4. IEEE C57.12.91 -- IEEE Standard Test Code for Dry-Type Distribution and Power Transformers, 1/9/2001
5. ANSI / IEEE C57.94 -- IEEE Recommended Practice for Installation, Application, Operation, and Maintenance of Dry-Type General Purpose
Distribution and power Transformers, 3/8/1993

ATTACHMENTS:
1. NETA ATS -- Tables 10.14, 7.3.1, 7.1.2 and 7.2.1

NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose
listing states that the equipment, material, or services either meets appropriate designated standards or has been tested and found
suitable for a specified purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified
organization concerned with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by
manufacturer

Page 7 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
whose labeling the manufacturer indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Name, Title, Department,
Name, Initials and Date:
Company, Initials and Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Page 8 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
Attachment 1 -- NETA ATS
Table 100.14 NETA ATS

INSULATION RESISTANCE CONVERSION FACTORS FOR


CONVERSION OF TEST TEMPERATURE TO 20ºC

Table 7.3.1

APPLIED POTENTIAL TEST VOLTAGES

Nameplate Winding Voltage


Test Potential, in kV
Rating, in Volts

0 - 250 2.5

251 - 1200 4

1201 - 2500 10

2501 - 5000 12

5001 - 8660 19

8661 - 15000 31

1 INSULATION RESISTANCE TESTING

Table 100.5 NETA ATS

Page 9 of 11
Recommended minimum insulation resistance values at 40ºC (all
values in MΩ)

Minimum Insulation Resistance after 1


Test specimen
minute (MΩ)
kV + 1
For most windings made before about 1970,
all field windings, and others not described
(Example: 15kV machine is 15 + 1 = 16MΩ) below

For most dc armature and ac windings built


100
after about 1970 (form-wound coils)

For most machines with random-wound


5 stator coils and form-wound coils rated
below 1 kV

Insulation Resistance Test Record


Primary to Secondary Primary/Secondary to Ground Secondary/Primary to Ground
kV Time μ amp Meg Ω kV Time μ amp Meg Ω kV Time μ amp Meg Ω
1 min 1 min. 1 min.

10 min 10 min. 10 min.

15 min 15 min. 15 min.


POLARIZATION POLARIZATION POLARIZATION
INDEX INDEX INDEX
PI = R10/R1 PI = R10/R1 PI = R10/R1

ACCEPTABLE TEST VALUES

For Insulation Resistance.


Values
of insulation resistance less than manufacturer's minimum or the
recommended minimum insulation resistance values above should be
investigated. Resistance values to be temperature corrected in
accordance to Table 100.14 above. Overpotential test should not proceed
until Insulation resistance levels are raised to said minimum.

For Polarization Index.


An
absorption test polarization index ( ratio of insulation resistance at 10
minutes to insulation resistance at 1 minute) value would be 2 or higher,
values between 2 and 1 indicate marginal condition, and values below 1
indicate poor condition.

2 Turns Ratio Testing

Ratio Test Result


Measured Ratio Factory Ratio
Tap Position Primary Volts Calculated Ratios
A B C A B C

ACCEPTABLE TEST VALUES

Page 10 of 11
Turns ratio test results should not deviate more than one-half of one
percent (0.5%) from calculated ratio.

3 Excitation Current Test

4 Core Ground Test - 250V Megger Test

Yes No
Continuity
Result Acceptable

5 AC High Potential Test

Test kV
Time (minutes)

ACCEPTABLE TEST VALUES

A.C. high potential test voltage shall not exceed seventy-five percent
(75%) of factory test voltage or Table 7.3.1 below for a one (1) minute
duration. Evaluation shall be on a go no-go basis.

Page 11 of 11

You might also like