Saudi Aramco Test Report
Saudi Aramco Test Report
Saudi Aramco Test Report
00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
For jobsite acceptance, all windings shall be checked for continuity using
SAES-P-121
A1 a continuity tester.
Sec. 3.2
NETA, ATS- 2009
H1 - H2 H2 - H3 H3 -H1
Primary Windings
X1 - X2 X2 - X3 X3 - X1
Secondary Windings
The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C4 index calculation.
Sec. 3.2
NETA, ATS- 2009
The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C9 index calculation.
Sec. 3.2
NETA, ATS- 2009
Page 1 of 11
Record the results. SAES-P-121
C11
NETA, ATS- 2009 Sec. 3.2
Page 2 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
The test duration shall be for 1 minute and 10 minutes for polarization
SAES-P-121
C14 index calculation.
Sec. 3.2
NETA, ATS- 2009
Schedule Q
D2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1
PRE-ENERGIZE -
INSULATION 5000 v 1 min
RESISTANCE
1 min
POLARIZATION
5000 v
INDEX
10 min
1 min
2 min
DIELECTRIC
3 min
ABSORPTION
Page 3 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
DIELECTRIC
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
ABSORPTION
4 min
5 min
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
For the dielectric-absorption test, the values recorded at each one minute
interval shall be plotted on log-log paper with coordinates for resistance
versus time. A good insulation system will have a slope that is a straight SAES-P-121
F3
line increasing in respect to time. The characteristic slope of a poor Sec. 3.2
insulation system will be a curve that flattens out with respect to time.
NETA, ATS- 2009
Perform a turns ratio test on each phase from primary to secondary on all
SAES-P-121
G1 taps.
Sec. 3.2
NETA, ATS- 2009
Page 4 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Schedule Q
H2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Turns ratio test results should not deviate more than one-half of one
SAES-P-121
J1 percent (0.5%) from calculated ratio.
Sec. 3.2
NETA, ATS- 2009
Before the core Megger test can be performed, inspect the transformer
and determine whether it has a core ground strap. The copper-foil ground
strap extends out of the core bottom between the bottom clamps. If the SAES-P-121
K1
strap is not present, the test is not necessary. If the strap is present, Sec. 3.2
perform the core Megger test.
NETA, ATS- 2009
Disconnect the core ground strap from the flexible jumper, which attaches
the strap to the bottom clamp. Make sure the ground strap is clear from SAES-P-121
K2
any contact with the transformer ground to isolate the clamp structure. Sec. 3.2
NETA, ATS- 2009
Take care not to pull the core ground strap out of the core, attach the hot
SAES-P-121
K3 lead of a 1000V dc Megohmeter to the core ground strap.
Sec. 3.2
NETA, ATS- 2009
Attach the ground lead of the Megohmeter to the core clamping bolt,
which is next to the core ground strap. Ensure the lead and core ground SAES-P-121
K4
strap are not in contact with the ground. Sec. 3.2
NETA, ATS- 2009
Page 5 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
INSULATION
Date
RESISTANCE READING Pass Fail Remark
Tested
(MΩ)
SAES-P-121
L6 Record results in the table.
Sec. 3.2
SAES-P-121
L8 Record results in the table.
Sec. 3.2
SAES-P-121
M1 Test shall be performed using a DC Overpotential Test Set.
Sec. 3.2
Schedule Q
M2 The test equipment calibration cycle shall not exceed six months. Att. IV
Sec. 7.1
Page 6 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Date
Test kV TIME (Min) PRI / SEC & GRD PRI / SEC SEC / PRI & GRD Pass Fail Remark
Tested
Step 1
Step 2
Step3
1 min
A.C. high potential test voltage shall not exceed seventy-five percent
(75%) of factory test voltage or attachment 1, NETA ATS Table 7.3.1 for a SAES-P-121
O1
one (1) minute duration. Evaluation shall be on a go no-go basis. Sec. 3.2
NETA, ATS- 2009
REMARKS:
REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Pro Forma Contract), February 2008
2. SAES-P-121 -- Transformers and Reactors,28 January 2016
3. NETA ATS -- Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems, 2009
4. IEEE C57.12.91 -- IEEE Standard Test Code for Dry-Type Distribution and Power Transformers, 1/9/2001
5. ANSI / IEEE C57.94 -- IEEE Recommended Practice for Installation, Application, Operation, and Maintenance of Dry-Type General Purpose
Distribution and power Transformers, 3/8/1993
ATTACHMENTS:
1. NETA ATS -- Tables 10.14, 7.3.1, 7.1.2 and 7.2.1
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose
listing states that the equipment, material, or services either meets appropriate designated standards or has been tested and found
suitable for a specified purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified
organization concerned with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by
manufacturer
Page 7 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
whose labeling the manufacturer indicates compliance with appropriate standards or performance in a specified manner.
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED
Page 8 of 11
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Pre-
SATR-P-3908 3-Jul-18 ELECT
Commissioning and Functional Testing
Attachment 1 -- NETA ATS
Table 100.14 NETA ATS
Table 7.3.1
0 - 250 2.5
251 - 1200 4
1201 - 2500 10
2501 - 5000 12
5001 - 8660 19
8661 - 15000 31
Page 9 of 11
Recommended minimum insulation resistance values at 40ºC (all
values in MΩ)
Page 10 of 11
Turns ratio test results should not deviate more than one-half of one
percent (0.5%) from calculated ratio.
Yes No
Continuity
Result Acceptable
Test kV
Time (minutes)
A.C. high potential test voltage shall not exceed seventy-five percent
(75%) of factory test voltage or Table 7.3.1 below for a one (1) minute
duration. Evaluation shall be on a go no-go basis.
Page 11 of 11