MDS - Wilmont Pharmacy Drone - Gantt Chart

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4
At a glance
Powered by AI
The key takeaways are that the project aims to develop drone prototypes to deliver pharmacy items and involves various phases from initiating to closeout including planning, execution, testing, management and control.

The overall project goal is to develop drone prototypes to deliver pharmacy items for Wilmont's Pharmacy.

The main project activities include initiating, planning, execution, testing, management and control. The sequence of activities is shown in the Gantt chart spanning weeks 1-42.

WILMONT'S PHARMACY DRONE CASE

PROJECT SCHEDULE
Project :Wilmont's Pharmacy
Revision Date: 6-Dec-2020 Crtical Path Items
Rev #: 00 WEEKS
WBS ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1.0 Develop Drone Prototypes
1.1 Initiating
1.1.1 Develop Scope and Plan
1.1.2 Engage Stakeholders
1.1.3 Raise Funds

1.2 Planning
1.2.1 System Design
1.2.2 Cost Estimate
1.2.3 Approvals
1.2.4 Create a Project Organization Chart

1.3 Execution
1.3.1 Purchase Materials
1.3.2 Rent equiptment and engage
1.3.3 Complete Assembly
1.3.4 Development of Mobile Application

1.4 Testing
1.4.1 Piloting and Delivering
1.4.2 Interface with flight operations
1.4.3 Interface Communications
1.4.4 Information Security Management
1.4.5 Drones Allocation
1.4.6 Drone Maintenance /Repair parts
1.4.7 First Delivery Through Drones

1.5 Management and Control


1.5.1 Regular Meetings
1.5.2 Quality Control and user Training
1.5.3 Monitoring Changes

1.6 Closeout
1.6.1 Audit Performance
1.6.2 Close out report
1.6.3 Documenting the files
Engineering Project Management_Mayfair Segumali-an_Gantt Chart Page 1 of 2
WEEKS
WBS ACTIVITY 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
1.0 Develop Drone Prototypes
1.1 Initiating
1.1.1 Develop Scope and Plan
1.1.2 Engage Stakeholders
1.1.3 Raise Funds

1.2 Planning
1.2.1 System Design
1.2.2 Cost Estimate
1.2.3 Approvals
1.2.4 Create a Project Organization Chart

1.3 Execution
1.3.1 Purchase Materials
1.3.2 Rent equiptment and engage
1.3.3 Complete Assembly
1.3.4 Development of Mobile Application

1.4 Testing
1.4.1 Piloting and Delivering
1.4.2 Interface with flight operations
1.4.3 Interface Communications
1.4.4 Information Security Management
1.4.5 Drones Allocation
1.4.6 Drone Maintenance /Repair parts
1.4.7 First Delivery Through Drones

1.5 Management and Control


1.5.1 Regular Meetings
1.5.2 Quality Control and user Training
1.5.3 Monitoring Changes

1.6 Closeout
1.6.1 Audit Performance
1.6.2 Close out report
1.6.3 Documenting the files
Engineering Project Management_Mayfair Segumali-an_Gantt Chart Page 2 of 2