B-Civil Works BOQ Phase 1
B-Civil Works BOQ Phase 1
B-Civil Works BOQ Phase 1
442.810513
Bill No. C- 07 Construction of Artificial Well at 200m3 underground Booster, at Borehole
and at 500m3 RCC Ground Booster I TOT
UNIT
UN AL
ITEM DESCRIPTION QNTY PRICE
IT (BIR
(BIRR)
C-07.1 EARTH WORK R)
C-0.7.2 Site Clearing to remove Top Soil up to 20cm Depth m2 14.4
Bulk excavation in normal soil to a depth not
C-07.2 m3 20.0
exceeding 3m
C-0.7.3 Ditto but in soft rock formation not exceeding 2.5m m3 26.5
C-07.3 Ditto but in hard rock formation 2m m3 20.0
Cart away all excavated material, deposit to
C-0.7.4 m3 66.5
appropriate distance not exceeding 1 km
Provide and fill with suitable selected granular
C-07.4 m3 3.0
material not exceeding 50cm
Provide and fill hard core with hard basaltic or
equivalent stone, well compacted and blinded with
C-0.7.5 m2 7.9
crushed stone to a finished thickness of 25 cm under
the artificial and valve chamber
C-07.5 CONCRETE WORK
30cm thick lean concrete C-10 under the artificial
C-0.7.6 m2 3.6
base slab and valve chamber
Reinforced concrete type C-30 filled into form work
C-07.6
and vibrated around reinforced bar
C-0.7.7 Base slab m3 3.2
C-07.7 Concrete wall m3 9.9
C-0.7.8 Top slab m3 3.6
C-07.8 Valve Box m3 5.0
C-0.7.9 Provide and fix formwork to:
C-07.9 Base slab m2 6.6
C-0.7.10Wall m2 39.6
C-07.10 Top slab m2 5.6
Provide, cut, bend and fix in position reinforced
C-0.7.11steel bar. All according to structural drawing.
Price should include tying wires
C-07.11 Diameter 8 mm plain bar kg 80.0
C-0.7.12Diameter 12 mm deformed bar kg 515.0
C-07.12 ACCESSORIES AND FINISHING
Provided and install access ladder constructed out of
C-0.7.131 1/2" dia GS pipe and hooked to the casing as per LS 1.0
the drawing; including safety cages
C-0.7.14supply and install of steel casing DN600mm m 60.0
provide top acces consisting of GI pipe wellded and
C-0.7.15 m2 48.0
fixed in position as per the drwimg
PIPES, VALVES AND FITTINGS ALL ARE
C-0.7.16
PN16
inlet Pipe and Fittings Supply for artificial well @
C-0.7.17
BS 500M3 and at BH
C-0.7.18DN 250DCI double cross Tee No 1
C-0.7.19DN 250 DCI 90 deg double flanged bend No 5
C-0.7.20DN 250 DCI double flanged pipe, L = 6 meters No 1
C-0.7.21DN 250 DCI double flanged short pipe,L = 1.5 mm No 3
C-0.7.22DN 250 duoble flanged gate valve No 1
C-0.7.23DN 250 dismantling joint No 3
C-0.7.24250 OD HDPE PE100 stub flange with backing ring No 2
C-0.7.25DN 250Non Swing Check Valve No 1
C-0.7.26outlet Pipe and Fittings Supply for BS PN 16 DN 250
C-0.7.27DN 250 DCI 90 deg double flanged bend No 3
C-0.7.28DN 250 DCI double flanged pipe, L = 6.0 meters No 1
C-0.7.29DN 250 DCI double flanged pipe, L = 500 mm No 1
C-0.7.30DN 250 DCI duckfoot 90 deg double flanged bend No 1
C-0.7.31DN 250 dismantling joint No 1
C-0.7.32DN 250 Non Swing Check Valve No 3
Total of Bill . Construction of Artificial Wet Well
Bill No. C- 05 Generator and Guard House(9.32x7) At Borehole and At Booster I
m² 25
m³ 3.6
m³ 4.5
m³ 8.1
m² 4.95
m² 3.2
m³ 2.5
m³ 5.5
m³ 2.5
m² 6.12
m² 6.5
kg 150
kg 250
no 525
m³ 2.24
m² 34
m 8.5
m 9.6
m² 5.2
m 120
m 120
m 100
m 18
m² 4.41
m 12.2
m2 1.89
m2 1.5
m² 19.6
m² 19.6
m² 9.28
m 1.6
m² 19.6
m² 9.6
m² 3.25
LS 1
nr 4
nr 2
nr 1
nr 2
nr 1
nr 3
LS 1
m 18
Bill No. C- 02 Construction of 500m3 @ BOOSTER I
Unit Contract
Item Description Contrac
Unit Price Amount
t Qty
C-02.1 EARTH WORK
Clearing the top soil and unwanted material to a depth
C-02.1.1 m2 254.3
of 200mm
Bulk excavation in ordinary soil to depth not greater
C-02.2 m3 120.0
than 0.6m
C-02.1.2 Ditto but to a depth not greater than 1m m3 86.5
C-02.3 Extra over for bulk excavation in hard rock m3 15.0
Back fill around reservoir walls with selected material
C-02.1.3 m3 56.4
from off site and well ram in layers every 25cm interval.
Cart away all excavated material, deposit to
C-02.1.4 m3 221.5
appropriate distance not exceeding 1 km
50cm thick basaltic or equivalent stone base for
C-02.5 m2 25.0
foundation
C-02.1.5 50cm thick hard trachyte stone hard core filling m2 133.2
C-02.6 CONCRETE AND MASONRY WORK
200mm thick lean concrete with mix ratio (1:3:6) under
C-02.1.6 m2 133.2
the reservoir base slab
Masonary pavment around the reservoir wih mass
C-02.7 m2 52.7
concrete
Reinforced concrete type C-30 filled into form work
C-02.1.7 and vibrated around reinforced bar.with mix ratio
(1:2:3)
C-02.8 In base slab( C-30) m3 50.0
C-02.1.8 In 25cm thick concrete wall(C-30) m3 57.3
C-02.9 in concrete column(C-30) m3 2.8
C-02.1.9 In top slab(C-25) m3 32.0
C-02.10 in ring and fillet(C-30) m3 21.5
C-02.1.10 Provide and fix formwork
C-02.11 In base slab m2 20.1
C-02.1.11 To wall m2 385.0
C-02.12 To column m2 26.2
C-02.1.12 To top slab m2 118.2
C-02.13 To ring and fillet m2 16.0
Provide, cut, bend and fix in position reinforced steel
C-02.1.13bar. All according to structural drawing. Price should
include tying wires.
C-02.1.14 Diameter 8 mm deformed bar kg 130.7
C-02.15 Diameter 10 mm deformed bar kg 4,650.2
C-02.1.15 Diameter 12 mm deformed bar kg 6,550.6
C-02.16 Diameter 14 mm deformed bar kg 1,650.0
C-02.1.16 Diameter 16 mm deformed bar kg 360.0
C-02.17 Diameter 20 mm deformed bar kg 300.1
Provide and construct 400 mm thick pointed stone
C-02.1.17masonry valve chamber for inlet, outlet, overflow and Lps 1.0
drain valves as per the drawing( top slab c-25)
C-02.18 ACCESSORIES & FINISHING
Provide and apply 50mm cement screed to the reservoir
C-02.1.18 m2 239.8
floor and roof slab and to valve chamber
Provide and apply 3 coats of plaster to internal walls,
C-02.19 m2 315.0
columns and to embeded part of external wall surface
C-02.1.19 Rendering external wall m2 157.0
Supply and install external water level indicator
C-02.20 No 1.0
complete with necessary accessories
Supply and fix external galvanised steel (6m) and
internal stainless steel (5.5m) ladder complete with
C-02.1.20 No 2.0
safety cage as per the design to the satisfaction of the
engineer.
Provide and install water stops made of natural or
C-02.21 synthetic rubber or elastometric plastic compound with m 120.0
basic risen polyvinyl chloride (PVC)
C-02.1.21 water proofing of internal walls m2 221.6
provide and insert plastic sheet for the base slab of the
C-02.22 embeded part m2 124.6