B-Civil Works BOQ Phase 1

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 28

D-0.

1 CIVIL WORK SUMMERY


Amoun Total
S.No Description of Item No
t Amount
Construction of Rectangular Water
C-1 1
Cooling Tank
Construction of 200m3 underground
C-2 1
at cooling basin
Artificail well at Boster Station
C-3 500m3 and at 200m3 Underground
RCC
Generator and Guard House at BH,
C-4 2
200M3 RCC Reservoir
Construction of Toilet at 1000M3,
C-5 500M3 Booster Station & at Borehole 3

C-6 Ground Reservior of 1000m3 1


C-7 Ground Reservior of 500m3 3
Construction of Guard House @
O-o 1
1000M3
Bill No. C- 06 Construction of Rectangular Cooling Structures
UNIT
UNI TOTAL
ITEM DESCRIPTION QNTY PRICE
T (BIRR)
(BIRR)
C-06.1.0 EARTH WORK
D-0.6.2 Site Clearing of Top Soil up to 20cm Depth m2 285
Bulk excavation in normal soil to a depth not
C-06.1.1 m3 115
exceeding 1.5m
D-0.6.3 Ditto but in soft rock formation m3 77
C-06.1.2 Ditto but in hard rock formation m3 38
Cart away all excavated material, deposit to
D-0.6.4 m3 230
appropriate distance not exceeding 1 km
Provide and fill with suitable selected granular
C-06.1.3 m3 100
material not exceeding 50cm
D-0.6.5 MASSONARY WORK
construct stone massonary trapezoidal foundation
C-06.1.4 wall of the chamber with 700mm at base and m2 125
600mm at the top
construct stone massonary trapezoidal wall of the
D-0.6.6 m2 230
birka with 600mm at base and 500mm at the top
50 cm thick basaltic or equivalent stone Hard core
C-06.1.5 well rolled, consolidated & blinded with crushed m3 126
stone
D-0.6.7 CONCRETE WORK
50mm thick lean concrete C-10 above the hard
C-06.1.6 m2 100
core
Reinforced concrete type C-30 of the base floor
D-0.6.8 filled into form work and vibrated around
reinforced bar
Provide, cut, bend and fix in position reinforced
C-06.1.7 steel bar. All according to structural drawing.
Price should include tying wires
D-0.6.9 Diameter 8 mm plain bar kg 100
C-06.1.8 Diameter 10 mm deformed bar kg 2,500
D-0.6.10 ACCESSORIES AND FINISHING
Provided and install access ladder internal and
external constructed out of 1 1/2" dia GS pipe and
C-06.1.9 LS 2
hooked to the wall as per the drawing; including
safety cages
three coats of plastering for the wall internal and
D-0.6.11 m2 720
external
C-
floor cement screeding m2 200
06.1.10
D-0.6.12 rendering external wall m2 360
C-
PIPES, VALVES AND FITTINGS
06.1.11
D-0.6.13 inlet fittings all PN16
C- Pipe and Fittings Supply for cooling basin at
06.1.12 borhole
D-0.6.14 DN 250 DCI double flanged bell mouth PN16 No 1
C-
DN 250 DCI 90 deg double flanged bend No 6
06.1.13
D-0.6.15 DN 250 DCI double flanged pipe, L = 6.0 meters No 6
C-
Tee DN 250 DCI double flanged PN16 No 1
06.1.14
D-0.6.16 DN 250 duoble flanged gate valve No 1
C-
DN 250 dismantling joint No 3
06.1.15
D-0.6.17 Water Meter DN 250 PN 16 No 1
C-
DN 250Non Swing Check Valve No 1
06.1.16
D-0.6.18 outlet fitting all PN16
C-
DN 250DCI flanged bell mouth No 1
06.1.17
D-0.6.19 DN 250 DCI 90 deg double flanged bend No 6
C-
DN 250 DCI double flanged pipe, L = 6.0 meters No 3
06.1.18
D-0.6.20 DN 250 DCI double flanged Tee No 1
C-
DN 250 flanged gate valve No 1
06.1.19
D-0.6.21 DN 250 dismantling joint No 1
Total of Bill . Construction of rectangular
cooling
Bill No. C- 03 Construction of Underground 200m3 RCC Reservoir @ Borehole

Item Unit Rate Total Contract


DESCRIPTION Unit Qty
(Birr) Amount(Birr)
C-03.1 EARTH WORK
C-03.1.1Site Clearing to remove top soil m2 105.62
C-03.1.2Bulk excavation in ordinary soil upto depth of 1.5m m3 161.28
C-03.1.3Ditto but in soft rock formation m3 129.50
C-03.1.4Ditto but in hard rock formation m3 104.32
Cart away all excavated material, deposit to
m3 233.82
C-03.1.5appropriate distance not exceeding 1 km
Provide and fill with suitable selected granular
m3 87.50
C-03.1.6material
Provide, fill and compact impermeable clay soil to a
m3 65.62
C-03.1.7finished thickness of 30 cm
Provide and fill hard core with hard basaltic or
equivalent stone, well compacted and blinded with
m2 98.52
crushed stone to a finished thickness of 25 cm under
C-03.1.8the reservoir and valve chamber
C-03.1.9CONCRETE WORK -
50mm thick lean concrete with mix ratio (1:3:6) under
m2 173.52
C-03.1.1the reservoir base slab and valve chamber
Reinforced concrete type C-30 filled into form
work and vibrated around reinforced bar mix ratio
C-03.1.1should be 1:2:3 in
C-03.1.1Base slab m3 44.46
C-03.1.1Concrete wall m3 45.64
C-03.1.1Concrete column m3 1.66
C-03.1.1Top slab m3 23.30
C-03.1.1Parapet m3 2.99
C-03.1.1Provide and fix formwork to -
C-03.1.1Base slab m2 47.39
C-03.1.1Wall m2 275.34
C-03.1.2Column m2 8.70
C-03.1.2Top slab m2 88.26
C-03.1.2Parapet m2 16.18
Provide, cut, bend and fix in position reinforced
steel bar. All according to structural drawing.
C-03.1.2Price should include tying wires
C-03.1.2Diameter 8 mm plain bar kg 31.20
C-03.1.2Diameter 10 mm deformed bar kg 3,436.60
C-03.1.2Diameter 12 mm deformed bar kg 3,630.00
C-03.1.2Diameter 14 mm deformed bar kg 2,811.00
C-03.1.2Diameter 16 mm deformed bar kg 772.71
Reinforced concrete type C-25 filled into form work
and vibrated around reinforced bar mix ratio should be m3 9.80
C-03.1.21:2:3 for valve chamber
C-03.1.3Block work
Provide and erect 20cm HCB wall for one side of the
valve chamber, having internal plastering and external m2 15.00
C-03.1.3rendering finish
C-03.1.3 Stone masonry foundation wall m3 20.00
C-03.1.3ACCESSORIES AND FINISHING -
Provide and apply 50mm cement screed to the
m2 157.10
C-03.1.3reservoir floor and roof slab
Provide and apply 3 coats of plaster to internal walls,
m2 281.06
columns and to embedded part of external wall surface
C-03.1.3
C-03.1.3Rendering external wall m2 153.18
Provided and install access internal and external
ladder constructed out of 25 mm dia GS pipe and
LS 1.00
hooked to the wall as per the drawing; including safety
C-03.1.3cages
Provide and install water stops made of natural or
synthetic rubber or elastometric plastic compound m 69.12
C-03.1.3with basic risen polyvinyl chloride (PVC)
C-03.1.3Plaster with water proof of internal wall surfaces m2 105.20
provide and insert plastic sheet for the base slab of the
m2 50.24
C-03.1.4embeded part
Provide and fix 6 mm sheet metal access cover with
No 2.00
C-03.1.4latch and lock for valve chamber and reservoir
C-03.1.4PIPES, VALVES AND FITTINGS
C-03.1.4Install inlet pipe
C-03.1.4DN 250, L=330cm double flanged pipe No 1
C-03.1.4DN 250, 90 degree Duck foot bend No 1
DN 250, double flanged L=1m with centrally welded
No 1
C-03.1.4puddle flange
C-03.1.4DN 250 dismantling piece No 1
C-03.1.4DN 250 flanged gate valve No 1
C-03.1.4DN 250 double flanged pipe L=1.25 m No 1
C-03.1.5DN 250, 90 degree double flanged elbow No 1
C-03.1.5DN 250, double flanged pipe L=4m No 1
C-03.1.5DN 250, double flanged pipe L=1.00m No 1
C-03.1.5DN 250 flanged spigot No 1
C-03.1.5DN 250 express collar No 1
C-03.1.5DN 250 flanged float valve No 1
C-03.1.5Install outlet pipe -
C-03.1.5DN 250 suction strainer No 1
DN 250 double flanged pipe L=1m with centrally
No 1
C-03.1.5welded puddle flange
C-03.1.5DN 250 dismantling piece No 1
C-03.1.6DN 250 flanged gate valve No 1
C-03.1.6DN 250, 900 double flanged bend No 1
C-03.1.6DN 250*150 double flanged reducer No 1
C-03.1.6DN 250 double flanged pipe L=1m No 1
C-03.1.6DN 250 flanged spigot No 1
C-03.1.6DN 250 express collar No 1
C-03.1.6DN 250 water meter No 1
C-03.1.6Install Overflow and Drain pipes
C-03.1.6DN 250 Flanged bell mouth No 1
DN 250 double flanged pipe L=180cm with puddle
No 1
C-03.1.7flange
C-03.1.7DN 250, 90 degree double flanged elbow No 2
DN 250, double flanged pipe L=1.0m with centrally
No 1
C-03.1.7welded puddle flange
C-03.1.7DN 250x250 all flanged Tee No 1
C-03.1.7DN 250 flanged gate valve No 1
C-03.1.7DN 250 flanged spigot No 2
C-03.1.7Install level indicator Ls
Provide and install DN 50 ventillation pipe with dome,
pcs 2
C-03.1.7L =1.0 meters
Total Carried for BILL NO. D-02 Summary -
11.15 319.825
315.29
4.535

442.810513
Bill No. C- 07 Construction of Artificial Well at 200m3 underground Booster, at Borehole
and at 500m3 RCC Ground Booster I TOT
UNIT
UN AL
ITEM DESCRIPTION QNTY PRICE
IT (BIR
(BIRR)
C-07.1 EARTH WORK R)
C-0.7.2 Site Clearing to remove Top Soil up to 20cm Depth m2 14.4
Bulk excavation in normal soil to a depth not
C-07.2 m3 20.0
exceeding 3m
C-0.7.3 Ditto but in soft rock formation not exceeding 2.5m m3 26.5
C-07.3 Ditto but in hard rock formation 2m m3 20.0
Cart away all excavated material, deposit to
C-0.7.4 m3 66.5
appropriate distance not exceeding 1 km
Provide and fill with suitable selected granular
C-07.4 m3 3.0
material not exceeding 50cm
Provide and fill hard core with hard basaltic or
equivalent stone, well compacted and blinded with
C-0.7.5 m2 7.9
crushed stone to a finished thickness of 25 cm under
the artificial and valve chamber
C-07.5 CONCRETE WORK
30cm thick lean concrete C-10 under the artificial
C-0.7.6 m2 3.6
base slab and valve chamber
Reinforced concrete type C-30 filled into form work
C-07.6
and vibrated around reinforced bar
C-0.7.7 Base slab m3 3.2
C-07.7 Concrete wall m3 9.9
C-0.7.8 Top slab m3 3.6
C-07.8 Valve Box m3 5.0
C-0.7.9 Provide and fix formwork to:
C-07.9 Base slab m2 6.6
C-0.7.10Wall m2 39.6
C-07.10 Top slab m2 5.6
Provide, cut, bend and fix in position reinforced
C-0.7.11steel bar. All according to structural drawing.
Price should include tying wires
C-07.11 Diameter 8 mm plain bar kg 80.0
C-0.7.12Diameter 12 mm deformed bar kg 515.0
C-07.12 ACCESSORIES AND FINISHING
Provided and install access ladder constructed out of
C-0.7.131 1/2" dia GS pipe and hooked to the casing as per LS 1.0
the drawing; including safety cages
C-0.7.14supply and install of steel casing DN600mm m 60.0
provide top acces consisting of GI pipe wellded and
C-0.7.15 m2 48.0
fixed in position as per the drwimg
PIPES, VALVES AND FITTINGS ALL ARE
C-0.7.16
PN16
inlet Pipe and Fittings Supply for artificial well @
C-0.7.17
BS 500M3 and at BH
C-0.7.18DN 250DCI double cross Tee No 1
C-0.7.19DN 250 DCI 90 deg double flanged bend No 5
C-0.7.20DN 250 DCI double flanged pipe, L = 6 meters No 1
C-0.7.21DN 250 DCI double flanged short pipe,L = 1.5 mm No 3
C-0.7.22DN 250 duoble flanged gate valve No 1
C-0.7.23DN 250 dismantling joint No 3
C-0.7.24250 OD HDPE PE100 stub flange with backing ring No 2
C-0.7.25DN 250Non Swing Check Valve No 1
C-0.7.26outlet Pipe and Fittings Supply for BS PN 16 DN 250
C-0.7.27DN 250 DCI 90 deg double flanged bend No 3
C-0.7.28DN 250 DCI double flanged pipe, L = 6.0 meters No 1
C-0.7.29DN 250 DCI double flanged pipe, L = 500 mm No 1
C-0.7.30DN 250 DCI duckfoot 90 deg double flanged bend No 1
C-0.7.31DN 250 dismantling joint No 1
C-0.7.32DN 250 Non Swing Check Valve No 3
Total of Bill . Construction of Artificial Wet Well
Bill No. C- 05 Generator and Guard House(9.32x7) At Borehole and At Booster I

S/n Description Unit Qty Unit cost Total cost


C-05.1 Earth Work
site clearing up to a depth of 20cm to remove top
C-05.2 m2 76.80
vegetative soil
Excavation of trench in foundation, minimum of
C-05.3 m3 8.16
0.5meter depth
C-05.4 Back filling of excavated trench m3 4.60
Excavation work up to a depth of 50 cm to reduce level
C-05.5 for placing hard core & carting away of exacted soil to m3 15.04
a distance not exceeding 500meter
C-05.6 Masonary
25 cm thick basaltic or equivalent stone Hard core well
C-05.7 m3 32.62
rolled, consolidated & blinded with crushed stone
Stone masonry work in cemement Sand mortar 1:3in
C-05.8 m3 15.50
ratio in foundation
250mm thick cemented stone pavement around the
C-05.9 building 1m wide, price includes excavation & all m2 16.32
materials, including selected material bedding
C-05.10 Concrete
C-05.11 10cm thick Lean concrete work above hard core m2 8.67
RCC work 1:2:4 vibrated in to form work around
C-05.12 m3 6.59
reinforcement in floor slab
C-05.13 Grade beam m3 12.00
C-05.14 Top tei beam m3 6.00
C-05.15 in Lintels m3 1.50
C-05.16 Generator seat m3 3.60
C-05.17 Block work
C-05.18 20cm thick hallow concrete block wall pcs 1,662.50
C-05.19 Roof work
Upper & lower truss member of 10cm dia eucalyptus
C-05.20 m2 480.00
wood with 50cm c/c,well seasoned & free of defects
Vertical & Diagonal truss member of 8cm dia
C-05.21 m2 350.00
eucalyptus wood ,well seasoned & free of defects
Zigba wood purling 5cm X 7cm fixed to the truss at
C-05.22 m 350.00
90cm C/C
C-05.23 Roofing with G-28 corrugated iron sheet m2 65.00
Galvanized sheet gutter G-30 ,150 X150mm, price
C-05.24 m 11.20
includes brackets and two coats of metal paint
C-05.25 Ditto but down pipes,120 X60mm m 10.20
C-05.26 supply & fix 25 X 200mm facial board m 11.20
C-05.27 Door and window
Supply & fix locally made metal window , with all
necessary iron monger locks ,mesh for protection & one
C-05.28 m2 2.50
coat of anti rust & two coats of metal paint as per the
drawing 1400mm X1200mm
Supply & fix locally made metal door , with all
necessary iron monger locks & one coat of anti rust &
C-05.29 no 3.00
two coats of metal paint as per the drawing 1500mm
X2000mm
C-05.30 Renforcement
Steel reinforcement work according to the structural
C-05.31 drawing price includes cutting, bending, tying, &
placing in a position
C-05.32 8mm kg 200.00
C-05.33 10mm kg 120.00
C-05.34 12mm kg 100.00
C-05.35 Finishing
C-05.36 Plastering in cement sand mortar for internal walls m2 166.00
C-05.37 plastering & tyrolyn render to the external surface m2 99.00
C-05.38 Cement screeding in floor m2 26.84
C-05.39 Electricity
Lights to fed through PVC sheated cable of 2 X 2.5
mm2 in thermoplastic conduit of 13.3mm in /under
C-05.40 m 4.00
surface including junction boxes ,screw type connectors
& flash mounted switches
Flush mounted socket outlet of 16Amp fed through PVC
sheathed cable of 3 X2.5mm2 in thermoplastic conduit
C-05.41 no 3.00
of 13.5mm in /under surface including junction boxes
,screw type insulating caps & cover
Flouresent lamp laminar type Philips or equivalent
C-05.42 no 3.00
,TMS02/240 with 1X40Watt
C-05.43 Supply and fix anchor bolt in the R.C. generator seat No 8.00
Total for BILL NO C-05 Generator and Guard
House(9.32x7.6) At Borehole and At Booster I
Bill No. C- 011.38Toilet At 1000m3, 500m^3 booster station and @ borehole
Bill No. D- 07.1: CONSTRUCTION OF SOAK AWAY PIT
Total
Item Un Unit
Item Description Qty Price
No it Price
(ETB)
C.11.39 Earth Work
C11.40 Clearing of site to remove top soil to a depth of 2 m2 12
C.11.40 Bulk excavation in ordinary soil to depth of 1.5m m3 15
C11.41 Bulk excavation in soft rock m3 15
C.11.41 Bulk excavation in hard rock m3 12
C11.42 Curt away excavated material m3 42
C.11.42 masonary work
C11.43 masonar wall with 50cm at the base and 40cm at tom3 35
C.11.43 concerete work
Reinforced concrete septic cover C30 (Cement
1440 kg/m3) filled into form work and vibrated
C11.44
around reinforced bars, mix ratio should be 1 :2:3
in
C.11.44 Soak pit top slab m3 2.25
C11.45 Reinforcement
Provide, cut, bend and fix in position reinforced
C.11.45 steel bar. All according to structural drawing.
Price shall include tying wires
C11.46 diameter 12 kg 650
C.11.46 diameter 10 kg 90
C11.47 diameter 8 kg 80
C.11.47 Miscellaneous
Supply and lay 100 mm dia. PVC pipe as shown
C11.48 on the drawing, price including excavation of m 100
earth and back filling drianage conection
C.11.48 Supply and fix 100x100 mm tee Pcs 4
Supply and fix 100 mm dia. PVC ventilation pipe
C11.49 Pcs 2
hood shaped covering (cowl)
Supply and fix 40*40cm manhole cover concrete
C.11.49 pcs 2
with handling frame
Sub total for SOAK AWAY PIT
Construction of toilet
C.11.52 Earth Work
Clearing of site to remove top soil to a depth of
C11.52 m2 9
200 mm
Excavation for stone masonry foundation; 0.5 m
C.11.53 m3 3
width and 0.5 m depth
Cart away and deposit excavated surplus material
C11.53 m3 6
to a distance not exceeding I km
C.11.54 fill for the selected material m2 3
C11.54 masonary work
Supply and place 250 mm thick hard core
C.11.55 m2 10
compacted to receive reinforced floor slab
Supply and place 500 mm thick hard core for
C11.55 m2 7
founation wall
C.11.56 Sub-Total
C11.56 Concrete and Block Work
Reinforced concrete grade C-25 with minimum
C11.57 cement content 1440 kg/m3 cast into formwork
and vibrated around reinforcement bars in
C.11.58 RC floor tie beam m3 3
C11.58 RC column m3 1.26
C.11.59 Mass concrete fill on floor slab (100 mm) m3 1.25
C.11.60 Lintel m3 0.05
C11.60 RC roof tie beams m3 2.5
Provide, fix in position, cut and bend reinforced
C.11.61 steel bar. All according to structural drawing.
Price should include tying wires
C11.61 Diameter 8 mm deformed bar kg 120
C.11.62 Diameter 10 mm deformed bar kg 98.79
C11.62 Provide, cut, and fix formwork beam column m2 19.2
C.11.63 Block work
C11.63 20cm HCB block for wall No 250
C.11.64 Sub-Total
C11.64 Carpentry and Roofing
Supply, assemble and fix in position roof truss
C.11.65 price shall include the application of three coats Pcs 25
and external anti-termite treatment
Supply and fix purl in in zigba wood size 50 x 70
C11.66 mm nailed into eucalyptus truss including three pcs 30
coats of anti - termite external treatment
Supply and fix roof cover in G-28 mm corrugated
galvanized iron sheet fixed into zigba wood purl
C.11.67 m2 24
in with dome headed galvanized nails (purlin and
ridge cover measured separately)
Supply and fix edge gutter formed in G- 28 flat
galvanized metal sheet including support brackets
1 mm thick shaped steel plate spaced at a
C11.67 m 5
maximum spacing of 1000 mm clc and fixed to
purl in - price includes metal primer and two coats
of synthetic enamel paint
Supply & fix diameter 100mm down pipe in G-28
including I mm thick metal support brackets fixed
C.11.68 m 15
at a maximum interval of 1000 mm fixed to walls
or columns
Supply and fix 25x 250 mm fascia board to purl
C11.68 m 9.8
in
Supply and fix metal windows size 1x1.8m price
C11.69 m2 1.8
includes lock hachs
Supply and fix metal doors size 2.1 Ox1 with
C.11.70 Pcs 2.1
figured glass in upper half portion
Finishing; finishing work shall include all surface
C11.70 pre-cleaning, polishing and cleaning at the end of
finishing
C.11.71 Floor screed in cement mortar 20 mm thick m2 1.8
Apply cement mortar pointing to all external
C11.71 m2 34
cement concrete block wall
Apply 3 coats of plastic paint to internal
C.11.72 ,externalwalls and synthetic paint to metal doors m2 36
and windows
C11.72 Sub-Total
C.11.73 Electrical Installation
C11.73 Supply and install the required electrical works LS 1
Sub-Total
Sub total for toilet
Total for 1 toilet including soak awey pit -
Bill No. D- 01 BOQ of 1000m3 Service
Unit Amou
Item NO Descriptions Unit Quantity rate nt
C-01.1 EARTHWORKS
Site Clearing to remove top soil to depth not
C-01.1.1 m2 314 314.16
exceeding 200mm
C-0.1.2 Excavation
Excavation shall includs from strutting ,
shuttering ,stabilising excavated surfaces and
C-01.1.2 keeping excavations free of water by bailing
out,pumping or other means. ( Excluding
disposal of excavated material )
C-0.1.1.3 Excavation for foundations
Bulk excavation in ordinary soil to depth not
C-01.1.3 M3 51.2 50.51
greater than 1m
Hard Rock : commencing surface 0.8m above
C-0.1.1.4 M3 10
final surface
Soft Rock : commencing surface 0.8m above
C-01.1.4 M3 10
final surface
C-0.1.1.5 Maximum
General Excavation
depth shall be depth of excavation
from thr orginal surface to 0.8m above the final
C-01.1.5
surface
C-0.1.1.6 Topsoil: maximum depth n.e. 0.25m M3 200
C-01.1.6 Common material; maximum depth 1.0m - 2.0m M3 400
C-0.1.1.7 Common material; maximum depth >2.0 <5m M3 440
C-01.1.7 Hard Rock ; maximum depth 2.0m - 5.0m M3 20
C-0.1.1.8 Ditto soft Rock M3 10
C-01.1.8 Disposal of Excavated Material
Approved material shall be retained for filling/
C-0.1.1.9 backfilling and unsuitabel material shall be
disposed to tip as directed by the Engineer.
C-01.1.9 Topsoil; maximum distance of haul n.e. 1 km M3 180
C-0.1.1.10Ditto but haulage exceeding 1 km M3 20
Common material ; maximum distace to haul
C-01.1.10 M3 640
n.e. 1 km
C-0.1.1.11Ditto but haulage
Hard Rock exceeding
; maximum 1 km
distance of haul n.e. 1 M3 200
C-01.1.11 km M3 20
C-0.1.1.12Soft Rock ; maximum distance of haul n.e 1 km M3 10
C-01.1.12 Back Filling
Include for compaction as specified and Filling
C-0.1.1.13
to Completed Structures
C-01.1.13 Filling of Excavated topsoil M3 200
C-0.1.1.14Non- selected excavated common material M3 300
Non-selected excavated common material
C-01.1.14 M3 375
( General )
C-0.1.1.15To stated depth or thickness
250mm approved hardcore below blinding
C-01.1.15 M2 100
concrete level
C-0.1.1.16Drain
Earth drain with slopes at 45 degrees , depth n.e.
C-01.1.16 M 310
1.5m
SUB-TOTAL For C-01.1.0
C-01.1.17 300mm
CONCRETE WORK
thick lean concrete with mix ratio
(1:3:6) under the reservoir base slab and valve
C-01.1.18 M2 393.65
chamber
Reinforced concrete type c-30 filled into from
C-01.1.19 work and vibrated around reniforced bar mix
ratio should 1:2:3
C-01.1.20 Base slab (C-30) M3 100.42
C-01.1.21 Concrete wall (C-30) M3 82.92
C-01.1.22 Concrete column (C-30) M3 6.63
C-01.1.23 Top slab(C-25) M3 45.93
C-01.1.24 Parapet (C-25) M3 22.00
C-01.1.25 Provide and fix formwork to
C-01.1.26 Base slab M2 16.49
C-01.1.27 Wall M2 547.80
C-01.1.28 Column M2 10.05
C-01.1.29 Top slab M2 240.40
C-01.1.30 Parapet M2 150.00
Provide cut,bend and fix in position renifoced
C-01.1.31 steel bar.All according to structural drawing .
Price should include tying wires.
C-01.1.32 Diameter 8mm plain bar kg 650.00
C-01.1.33 Diameter 12mm deformed bar kg 7,705.00
C-01.1.34 Diameter 14mm deformed bar kg 10,849.00
C-01.1.35 Diameter 16mm deformed bar kg 700.00
C-01.1.36 Diameter 20mm deformed bar kg 450.00
SUB-TOTAL FOR (C-01.1.17)
C-01.1.37 valve chambere
C-01.1.38 Concrete
Reniforced concrete type C-25 filled into from
C-01.1.39 work and vibrated around reniforced bar mix M3 16.20
ratio should be 1:2:3: for valve chambere
C-01.1.40 Provide and fix formwork for valve chamber to
C-01.1.41 Base slab M2 9.85
C-01.1.42 wall M2 112.20
C-01.1.43 Column M2 6.13
C-01.1.44 Top slab M2 13.79
Provide cut,bend and fix in position renifoced
C-01.1.45 steel bar.All according to structural drawing .
Price should include tying wires.
C-01.1.46 Diameter 8mm plain bar kg 797.00
C-01.1.47 Diameter 10mm deformed bar kg 190.00
C-01.1.48 Block
Providework
and construct 400mm thick pointed
stone masonary valve chamber for inlet
C-01.1.49 ,outlet,overflow and drain valves as per the Lps 1.00
drawing (top slab C-25)
C-01.1.50 ACCESSEORIES AND FINISHING
Provide and apply 50cm cement screed to the
C-01.1.51 M2 256.90
reservoir floor and roof slab
Provide and apply 3 coats of plaster to internal
C-01.1.52 walls columns and to embedded part of external M2 281.45
wall
C-01.1.53 Rendering external wall M2 276.40
Supply and fix external galvanised steel (6m)
C-01.1.54 and internal stainless steel (5.5m) ladder NO 1.00
complete with saftly cage as per design to
satisfaction of the Engineer
Supply and install external water level indicator
C-01.1.55 NO 1.00
complete
Provide andwith necessary
install water accessories
stops made of natural
or synthetic rubber or elastometric plastic
C-01.1.56 compound with basic risen polyvinyl chloride M 156.37
( PVC) and fix 6mm sheet metal access cover
provide
with latch and lock for valve chamber and
C-01.1.57 NO 3.00
reservoir
Provide and apply two coats of bituminous
C-01.1.58 asphalt over the plastered surface of the M2 52.15
embedded part of the reservoir
C-01.1.59 paint with
Provide andwater
placeproof forbrick
single the wall
layerand floorbase
cover to M2 302.00
protect the asphalt coat from the backfill
C-01.1.60 M2 52.15
material
SUB-TOTAL FOR (C-01.1.31)
PIPES, VALVES AND FITTINGS
C-01.1.61 Install inlet pipe
C-01.1.62 DN 250mm flanged bell mouth No 1
C-01.1.63 DN 250, L=330cm double flanged pipe No 1
C-01.1.64 DN 250, 900 Duck foot bend No 1
DN 250, double flanged L=1m with centrally welded
C-01.1.65 puddle flange No 1
C-01.1.66 DN 250 dismantling piece No 1
C-01.1.67 DN 250 flanged gate valve No 1
C-01.1.68 DN 250 double flanged pipe L=1.25 m No 1
C-01.1.69 DN250, 90 degree double flanged elbow No 1
C-01.1.70 DN 250, double flanged pipe L=4.5m No 3
C-01.1.71 DN 250, double flanged pipe L=1.00m No 1
C-01.1.72 DN 250 flanged spigot No 1
C-01.1.73 DN 250 express collar No 1
C-01.1.74 DN 250 flanged float valve No 1
Pipe support with pipe clamp, wall bracket, foot
C-01.1.75 plate and anchor bolts LS 1
C-01.1.76 Install outlet pipe 0
C-01.1.77 DN 250 suction strainer No 1
DN 250 double flanged pipe L=1m with centrally
C-01.1.78 welded puddle flange No 1
C-01.1.79 DN 250 dismantling piece No 1
C-01.1.80 DN 250 flanged gate valve No 1
C-01.1.81 DN 250, 90 degree double flanged bend No 1
C-01.1.82 DN 250 double flanged pipe L=1m No 1
C-01.1.83 DN 250 flanged spigot No 1
C-01.1.84 DN 250 express collar No 1
C-01.1.85 DN 250 water meter No 1
Pipe support with pipe clamp, wall bracket, foot
C-01.1.86 plate and anchor bolts LS 1
C-01.1.87 Install Overflow and Drain pipes
C-01.1.88 DN 250 Flanged bell mouth No 1
DN 250 double flanged pipe L=180cm with puddle
C-01.1.89 flange No 1
C-01.1.90 DN 250, 90 degree double flanged bend No 2
DN 250, double flanged pipe L=1.0m with centrally
C-01.1.91 welded puddle flange No 1
C-01.1.92 DN 250x250 all flanged Tee No 1
C-01.1.93 DN 250 flanged gate valve No 1
C-01.1.94 DN 250 flanged spigot No 2
C-01.1.95 Install level indicator pcs 1
Provide and install DN 100 ventillation pipe with
C-01.1.96 dome, L =6meters No 2
C-01.1.97 SUB-TOTAL FOR C-01.1.6
C-01.1.98 Compound Work
Filling and compacting of selected material
C-01.1.99 excavated from site in layers not exceeding M3 175
20cm thickness
Construction of 200mm*300m wide and 20cm
thick C-20 reinforced concrete drian around the
reservoir wall including the drinage ditch as
C-01.1.10 shown in the drawing. The work including M 68
excavation, cart away and selected backfill
material.
Mesh wires fencing consists of 2.5 mm wire
horizontal and diagonal member fixed to 2.5m
C-01.1.10 long concret post spaced C/C 2000mm, M 250
including all necessary material as per the
drawing.
Supply and construct gate type III as per the
C-01.1.10 NO 1
drawing
C-01.1.10 Compound Lighiting as per the drawing Ls 1
C-01.1.10 Testing, Disinfection and Commissioning Ls 1
C-01.1.10 Electrical Installation
Supply and install within guard house;
C-01.1.10 distribution board for flush mounting with lockl
abel door consisting of
C-01.1.10 1PC of ACD of 10A, 1-ph NO 1
C-01.1.11 2pc of ACB of 16A , 1-ph NO 1
Light points with switches, fed through Pvc
C-01.1.11 NO 2
insulated wire 2x2.5 mm 2 cable
Flush mounted socket outlets of 16a, 220V ,
C-01.1.11 50HZ , fed through PVC 3x2.5mm 2 cable , laid NO 2
on the roof and in 16mm conduit in the wall
Light fittings type philips TMS 012/136 or
C-01.1.11 NO 2
equvalent with 1x36 W lamps
Power line of PVC conductor of 2x 4mm2 from
C-01.1.11 NO 20
EEPCO&meter.
Supply install sign boards as specified by the
Engineer ( at gate entrance & main road)(1-
C-01.1.11 NO 1
3)m2
C-01.1.11 SUB-TOTAL FOR C-01.1.98
Total For BILL NO. C-01 (1000 m3)
Balancing Reservoir
BILL NO.C.11.0 Guard House (#1) at 1000m3 service Reservoir
Item Description
C11.1 Guard House (#1) at 1000m3 service Reservoir
C.11.2 Sub Structure
C11.2 Excavation & Earth Work
C.11.3 Clearing the top soil and unwanted material to depth of 200mm
C11.3 Bulk excavation in ordinary soil to depth not greater 50cm
C.11.4 Bulk excavation in rock to depth not greater 30cm
C.11.5 Cart away all excavated material, deposit to appropriate distance not exceeding 1km
C11.5 Masonary
Supply and fill hard core for founadation and hard basaltic or equivalent stone, well
C.11.6 compacted and blinded with crushed stone to a finished thickness of 25cm
C11.6 Concrete
5cm thick Work
class C-10 lean Concrete under masonry foundation walls
C.11.7
Reinforced concrete grade C-25 with minimum cement content 360 kg/m³ cast into
C11.7 formwork and vibrated around reinforcement bars in
C.11.8 Forcolumn
C11.8 Grade beams
C.11.9 Top tie beams
C11.9 Supply and fix sawn form work to
C.11.10 For column
C11.10 Grade beams
supply, cut, bend and fix in position steel reinforcement bars, strength S300. All
C.11.11 according to structural drawings. rate shall include tying wires and spacing bars
C11.11 Dia 8mm
C.11.12 Dia 10mm
Supply and raise class-B hollow concrete block (H.C.B) walls laid in cement mortar
C11.12 of mix ratio 1:3, according to drawing
C.11.13 a) 200mm thick
C11.13 Concrete Work
C.11.14 Mass concrete C-20 floor
C11.14 Roofing
Supply and fix roof cover in G-28 corrugated galvanized iron sheet fixed into zigba
wood purlin with dome headed galvanized nails including ridge cover and one coat
C.11.15 of anti rust paint
Supply and fix edge gutter made of G-28 flat galvanized metal sheet including
support brackets 1mm thick shaped steel plate spaced at a maximum spacing of
1000mm c/c and fixed to purlin, rate includes one coat of anti rust and two coats of
C11.15 synthetic
Supply andenamel paint.
fix down Development
drain length
pipe in sheet 500mm.
metal, size 80x60mm including strainer at
C.11.16 inlet
Supply and fix G-28 ribbed sheet to the external roof soffit & eve fixed to 50x40 mm
C11.16 zigba battens at 600x600mm spacing rate including one coat of anti rust paint.
C11.17 Carpentry and Joinery
Supply and fix in position well seasoned eucalyptus roof truss according to drawing,
C.11.18 rate shall include the application of two coats of external anti-termite treatment
C11.18 Lower chord dia 100mm
C.11.19 Upper chord dia 100mm
C11.19 Diagonal and vertical member dia 80mm
Supply and fix purlin in zigba wood size 50x70 mm nailed into eucalyptus truss
C.11.20 including two coats of anti - termite external treatment
Supply and fix 8mm thick chip wood ceiling fixed to 50x40mm zigba battens spacing
C11.20 600x600mm, rate includes battens and corner list
C.11.21 Supply and fix well seasoned Keraro facia board 200x30mm
C.11.22 Metal work
Supply and fix 38/1.5mm LTZ metal frame doors and windows covered with 1mm
thick sheet metal where specified or indicated; rate shall include one coat of anti-rust
C11.22 and three coats of synthetic paint; complete with all accessories
C.11.23 Door D1 0.9x2.1m
C11.23 Window W1 0.9x1.6m
C.11.24 Finishing
C11.24 Apply 32 coats of plastering to
andinternal
1 coat walls
of Tyrolean rendering to external walls
C.11.25
C11.25 Place 50mm thick cement screed to floor slab
C.11.26 Supply and place terrazzo window sills 250mm width
C11.26 Apply 3 coats of plastic paint to internal walls
C.11.27 ditto but to chip wood ceiling
C11.27 apply 3 coats of varnish painting to fascia board
C.11.28 Electrical installation
Rates include supply and installation of all items including the necessary civil works.
All materials shall be approved by the Supervisor.
C11.28 All distribution boards shall be wired and tested as per the relevant IEC standards
C.11.29 Distribution Board
C11.29 Flush mounted sub distribution board as shown on the drawings
C.11.30 Light points
Light points in medium duty rigid conduit of 16mm fed by PVC copper conductor of
C11.30 2x2.5mm²
C.11.31 Switches IP54
C11.31 10A/1ph flush mounted with appropriate cover plate, frame and box.
C.11.32 Single Switch
C11.32 Double Switch
C.11.33 Socket Outlet Power Points and Floor Box
Flush mounted with appropriate cover plate, frame and box
C11.33
Socket outlet 16A, 3pin or approved equivalent flush mounted 16A, 1ph fed by PVC
insulated copper cable of 3x2.5mm² in medium duty rigid thermoplastic conduit of
C.11.34 diameter 20mm.
C11.34 Light Fittings with Lamps
All light fittings should have appropriate electric gear, lamps, mounting and other
necessary accessories; types as per general electrical specifications; rate shall include
C.11.35 supply, installation and all works
C11.35 Type 5 - 23W - ceiling
C.11.36 Type 6 - 23W- wall
C11.36 Cabling
Supply, installation and all works related with cabling of the building for all electrical,
C.11.37 telephone and data lines in PVC conduits as specified
PVC sheathed cable for house connection rating of 0.6/1KV, 3x4mm², incl. PVC
C11.37 conduit
Total for Guard House at 1000m3 service Reservoir
Unit Quantity Rate Amount (Birr)

m² 25
m³ 3.6
m³ 4.5
m³ 8.1

m² 4.95

m² 3.2

m³ 2.5
m³ 5.5
m³ 2.5

m² 6.12
m² 6.5

kg 150
kg 250

no 525

m³ 2.24

m² 34

m 8.5
m 9.6

m² 5.2
m 120
m 120
m 100

m 18

m² 4.41
m 12.2

m2 1.89
m2 1.5

m² 19.6
m² 19.6
m² 9.28
m 1.6
m² 19.6
m² 9.6
m² 3.25

LS 1

nr 4

nr 2
nr 1

nr 2
nr 1
nr 3

LS 1

m 18
Bill No. C- 02 Construction of 500m3 @ BOOSTER I
Unit Contract
Item Description Contrac
Unit Price Amount
t Qty
C-02.1 EARTH WORK
Clearing the top soil and unwanted material to a depth
C-02.1.1 m2 254.3
of 200mm
Bulk excavation in ordinary soil to depth not greater
C-02.2 m3 120.0
than 0.6m
C-02.1.2 Ditto but to a depth not greater than 1m m3 86.5
C-02.3 Extra over for bulk excavation in hard rock m3 15.0
Back fill around reservoir walls with selected material
C-02.1.3 m3 56.4
from off site and well ram in layers every 25cm interval.
Cart away all excavated material, deposit to
C-02.1.4 m3 221.5
appropriate distance not exceeding 1 km
50cm thick basaltic or equivalent stone base for
C-02.5 m2 25.0
foundation
C-02.1.5 50cm thick hard trachyte stone hard core filling m2 133.2
C-02.6 CONCRETE AND MASONRY WORK
200mm thick lean concrete with mix ratio (1:3:6) under
C-02.1.6 m2 133.2
the reservoir base slab
Masonary pavment around the reservoir wih mass
C-02.7 m2 52.7
concrete
Reinforced concrete type C-30 filled into form work
C-02.1.7 and vibrated around reinforced bar.with mix ratio
(1:2:3)
C-02.8 In base slab( C-30) m3 50.0
C-02.1.8 In 25cm thick concrete wall(C-30) m3 57.3
C-02.9 in concrete column(C-30) m3 2.8
C-02.1.9 In top slab(C-25) m3 32.0
C-02.10 in ring and fillet(C-30) m3 21.5
C-02.1.10 Provide and fix formwork
C-02.11 In base slab m2 20.1
C-02.1.11 To wall m2 385.0
C-02.12 To column m2 26.2
C-02.1.12 To top slab m2 118.2
C-02.13 To ring and fillet m2 16.0
Provide, cut, bend and fix in position reinforced steel
C-02.1.13bar. All according to structural drawing. Price should
include tying wires.
C-02.1.14 Diameter 8 mm deformed bar kg 130.7
C-02.15 Diameter 10 mm deformed bar kg 4,650.2
C-02.1.15 Diameter 12 mm deformed bar kg 6,550.6
C-02.16 Diameter 14 mm deformed bar kg 1,650.0
C-02.1.16 Diameter 16 mm deformed bar kg 360.0
C-02.17 Diameter 20 mm deformed bar kg 300.1
Provide and construct 400 mm thick pointed stone
C-02.1.17masonry valve chamber for inlet, outlet, overflow and Lps 1.0
drain valves as per the drawing( top slab c-25)
C-02.18 ACCESSORIES & FINISHING
Provide and apply 50mm cement screed to the reservoir
C-02.1.18 m2 239.8
floor and roof slab and to valve chamber
Provide and apply 3 coats of plaster to internal walls,
C-02.19 m2 315.0
columns and to embeded part of external wall surface
C-02.1.19 Rendering external wall m2 157.0
Supply and install external water level indicator
C-02.20 No 1.0
complete with necessary accessories
Supply and fix external galvanised steel (6m) and
internal stainless steel (5.5m) ladder complete with
C-02.1.20 No 2.0
safety cage as per the design to the satisfaction of the
engineer.
Provide and install water stops made of natural or
C-02.21 synthetic rubber or elastometric plastic compound with m 120.0
basic risen polyvinyl chloride (PVC)
C-02.1.21 water proofing of internal walls m2 221.6
provide and insert plastic sheet for the base slab of the
C-02.22 embeded part m2 124.6

Provide and fix 6 mm sheet metal access cover with


C-02.1.22 No 4.0
latch and lock for valve chamber and reservoir
Installation of Pipes ,Valves & Fittings Supplied by the
C-02.24
client
C-02.1.24PIPES, VALVES AND FITTINGS
C-02.25 Install inlet pipe
C-02.1.25DN 250mm flanged bell mouth No 0
C-02.26 DN 250, L=330cm double flanged pipe No 1
C-02.1.26DN 250, 900 Duck foot bend No 1
DN 250, double flanged L=1m with centrally welded puddle
C-02.27 flange No 1
C-02.1.27DN 250 dismantling piece No 1
C-02.28 DN 250 flanged gate valve No 1
C-02.1.28DN 250 double flanged pipe L=1.25 m No 1
C-02.29 DN250, 900 double flanged bend No 1
C-02.1.29DN 250, double flanged pipe L=3.50m No 2
C-02.30 DN 250, double flanged pipe L=1.00m No 1
C-02.1.30DN 250 flanged spigot No 1
C-02.31 DN 250 express collar No 1
C-02.1.31DN 250 flanged float valve No 1
Pipe support with pipe clamp, wall bracket, foot plate and
C-02.32 anchor bolts LS 1
C-02.1.32Install outlet pipe
C-02.33 DN 250 suction strainer No 1
DN 250 double flanged pipe L=1m with centrally welded
C-02.1.33puddle flange No 1
C-02.34 DN 250 dismantling piece No 1
C-02.1.34DN 250 flanged gate valve No 1
C-02.35 DN 250, 900 double flanged bend No 1
C-02.1.35DN 250*150 double flanged reducer No 1
C-02.36 DN 250 double flanged pipe L=1m No 1
C-02.1.36DN 250 flanged spigot No 1
C-02.37 DN 250 express collar No 1
C-02.1.37DN 250 water meter No 1
Pipe support with pipe clamp, wall bracket, foot plate and
C-02.38 anchor bolts LS 0
C-02.1.38Install Overflow and Drain pipes
C-02.39 DN 250 Flanged bell mouth No 1
C-02.1.39DN 250 double flanged pipe L=180cm with puddle flange No 1
C-02.40 DN 250, 900 double flanged bend No 2
DN 250, double flanged pipe L=1.0m with centrally welded
C-02.1.40puddle flange No 1
C-02.41 DN 250x250 all flanged Tee No 1
C-02.1.41DN 250 flanged gate valve No 1
C-02.42 DN 250 flanged spigot No 2
C-02.1.42Install level indicator pcs 1
Provide and install DN100 ventillation pipe with dome, L
C-02.43 =1.0 meters pcs 2
C-02.1.43 Supply and istall hooper ( Staineless steel) No 1
Supply and Install level indicator with all its
C-02.44 ls 1
accessories
C-02.1.44 Compound Work
mesh wires fencing consists of 2.5 mm barbed wire
horizontal and diagonal member fixed to 2500 mm long
C-02.45 m 205
concrete post spaced every 2000mm, including all
necessary material as per the drawing
Stripping top soil from whole area surrounded by
C-02.1.45fence, including running to spoil and sterilization to m2 1,450
prevent vegetation growth
Gate, 6mm angle iron with metal sheet C/C 40 mm
fixed to 60*60*3 mm RHS frame, as shown in the
C-02.49 No 1
drawing; price includes lock & latches & earth work
(width 4.0m*height 2.60m)
Supply & install sign boards as specified by the
C-02.1.50 No 1
Engineer ( at gate entrance & main road)(1-3)m2
Total For C-02 Carried to Summary -