Ste1 1 Go into the beow website

https://cbom.atozmath.com/CBOM/Transportation.aspx?q=lcm

Step 2: Type number of rows and colums

Step 3 Insert Number from Question

Step 4 Selct method, Northwest or Least Cost (LCM)

Step 5 Click Find

Total required cost will be shown


Question

Solution

Location X Co-ordinate Y Co-ordinate Weekly Quantity


D1 5.8 9.4 300.0
D2 1.0 7.9 600.0
D3 6.2 7.4 200.0
D4 5.2 6.2 250.0
D5 6.4 3.9 450.0
D6 1.9 1.9 150.0
D7 2.4 0.8 200.0
D8 1.7 0.5 250.0
𝛴 30.6 38.0 2,400.0
𝑥̿ 3.7
𝑦̿ 5.4
CoG 3.7 5.4

Centre of Gravity Chart


10 9.4
9
8 7.9 7.4
7 6.2
6 5.38125
5
3.9
4
3
1.9
2
0.5 0.8
1
0
0 1 2 3 4 5 6 7
5
3.9
4
3
1.9
2
0.5 0.8
1
0
0 1 2 3 4 5 6 7

D1 D2 D3 D4 D5 D6 D7 D8 CoG
Month Export, A Naïve, F1 Simple average, F2 2 Period moving average
1 20
2 22 20 20.00
3 18 22 21.00 21.00
4 21 18 20.00 20.00
5 22 21 20.25 19.50
6 22 20.60 21.50
MAP

|A-F1|/N
3 Period moving average 4 Period moving average Weighted average A-F1 A-F2

2.0 2.0
4.0 3.0
20.00 17.4 3.0 1.0
20.33 20.25 18 1.0 1.8
20.33 20.75 19.5
6.6
10.0 7.8
4 4
2.5 1.9
MSE MAPE

(A-F1)^2/N-1 ((|A-F1|/Actual)*100%)/n Actual Value


(A-F1)^2 (A-F2)^2 ((|A-F1|/Actual)*100%)/n ((|A-F2|/Actual)*100%)/n
A1 20
4.0 0.09 0.09 A2 22
16.0 9.0 0.22 0.17 A3 18
9.0 1.0 0.14 0.05 A4 21
1.0 3.1 0.05 0.08 A5 22
A6 0

30.0 13.1 0.5 0.4


3.0 2.0 4 4
10.0 6.5 0.13 0.10

Smaller the more accurate, hence we will go for Expotential method


alpha, a 0.3
Expotential Forecast

Forecast Value Ft = Ft-1+a(At-1 - Ft-1) Expotential Forecast

F1
F2 20
F3 20.60 2.60
F4 19.82 1.18
F5 20.17 1.83
F6 20.72

5.6
3
1.87

for Expotential method