Lesson Learned From Power System Design With Powerworld Simulator
Lesson Learned From Power System Design With Powerworld Simulator
net/publication/333922986
CITATIONS READS
0 125
2 authors, including:
Syafaruddin ..
Universitas Hasanuddin
86 PUBLICATIONS 1,461 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Modeling and simulation of wind power with permanent magnet synchronous generator (PMSG) View project
Real-time and continuous output power monitoring of photovoltaic (PV) systems View project
All content following this page was uploaded by Syafaruddin .. on 30 April 2020.
Abstract—Complexity design of power system is probably one of and other parameters in real time. With the animation, the users
the reluctances for undergraduate or graduate students to attend can imagine the real condition what is happening within the
power engineering courses. However, using simulation tools will complex power system. Moreover, the software is very
attract and encourage students to have their own design and model powerful and reliable in load flow analysis, faults study
as well as its analysis. This paper presents a protocol model of 10- includes selection of circuit breakers, bus condition and cabling
bus system with PowerWorld simulator includes load flow and within very complex system [13].
fault analysis as design verifications. To obtain a reliable model,
the basic knowledge of power system components following In this paper, a typical power system network as shown in
specific criteria must be fulfilled in the selection of initial data. In Fig.1 is arbitrarily designed by using PowerWorld Simulator
the verification stage, the proposed model has been tested with 8.0 OFP, ATC, PV-QV software package. The proposed model
load flow method in the normal and contingency operations, then is composed of 10 buses; bus-1 is considered as a slack
fault analysis is followed to simulate the proposed model responses (reference) bus whereas others are PQ buses. There are 4
in both three-phase and single-phase to ground faults. The generators which are connected by transformers to the 138kV
measured parameters in these stages are focused on the bus medium transmission line. Loads are attached in several buses,
voltage magnitude and its phase angle as one of the reference except for buses where generator connected. The measured
indicators for the state of power system operation. parameters as expected results are focused on the bus voltage
Keywords-10-Bus system, PowerWorld simulator, load flow, magnitude and its phase angle as one of the reference indicators
fault analysis, voltage magnitude, phase angle. for the stability state of power system operation.
I. INTRODUCTION
Power engineering subjects have been undergone less
attractive for undergraduate/graduate students in the last few
years. This trend will be serious problems behind the vast
growth of electricity industry worldwide. Negative perception
on the impacts of deregulation and restructuring in electricity
industry, high expectation of jobs requirements and perception
of power engineering as an old technology promote low interest
and motivation of students [1, 2]. Another reason is the
complexity of subjects which are taught in the power
engineering courses [3]. However, before reaching the ultimate
limit of this problem, several strategies have been offered to
make the power engineering fields become more attractive,
such as promoting technical challenges [4], collaborative
distance learning [2], [5] and through visualization and
simulation methods [6-9].
As one of the famous simulation software, the PowerWorld
simulator has been widely used in the power system application.
The combining with soft computing techniques, this simulator Fig.1. Proposed design of 10-bus power system
is applied for forecasting and mitigation of power system
blackout [10]. Other applications are the optimal power flow Accordingly, a good design of electrical power system is
simulation and animation of power system presented [11, 12]. required in order to maintain the continuity of supply-demand
The popularity of this software among other simulation tools power flow in any conditions. Therefore, verification in load
due to the ability to show the animation of power flows, voltage flow analysis, fault analysis and stability study are extremely
1A30-1 The 4th IEEE Conference on Power Engineering and Renewable Energy
ICPERE 2018
required. Load flow study is commonly used to assess the rated from 11.7 to 24.5%. The data of transformers is presented
performance of an existing system in the normal operation and in Table 2.
to design a new power system for future planning development,
while fault study is applied to obtain the appropriate setting and Table 2. Data leakage reactance of transformers
determine the interrupting and momentarily ratings of Capacity Leakage
Transformers Rating Voltage
protection system. Any changes of the power system in both (MVA) Reactance (p.u)
normal and fault conditions can be analyzed by stability study. T1 (FA) 22/138 kV 200 0.10
All these studies can be simultaneously performed in the T2 (FA) 13.8/138 kV 50 0.10
PowerWorld simulator, although the main objective in this T3 (FO) 20/138 kV 80 0.15
paper is only on the load flow and fault studies. By adding T4 (FO) 13.8/138 kV 50 0.15
specific data on the synchronous generators, such as inertia
constant and damping coefficient, then the proposed system Since the transformer is a static device, the leakage
will approach the configuration of IEEE 9 and 39 bus systems impedance is constant although the phase sequence is changed.
[14]. As a result, the positive sequence impedance is equal to the
negative sequence impedance. To allow zero sequence current
II. CRITERIA OF DATA SPECIFICATION flows, the neutral point should be connected to the ground. For
II.1 Selection of the Base Power, Voltage and Frequency transformers, the zero sequence impedance is also equal to
System. The base power, voltage and frequency system are leakage impedance [17].
intentionally determined following requirement of the system
II.4 Parameters of Transmission Lines. The
design. These values are 100 MVA, 22 kV on the side of
transmission lines are specified with nominal voltage and
generator at bus-1 (G1) and 50 Hz as the MVA base, voltage
frequency of 138 kV and 50Hz, respectively with operation
base and frequency system, respectively.
temperature at 50oC. The type of conductor is ACSR (Pheasant
II.2 Generators. A common voltage rating of generators 54/19) 1,272,000 CM with characteristic as outside diameter is
for practical purpose is in between 11 kV and 24 kV [15]. equal to 1.382 inches and the resistance is 0.084 Ω/mile per
Therefore, all generators will use the voltage rating within this conductor or 0.0522 Ω/km per conductor [18]. The reason of
range and the data about reactance and resistance are shown in choosing this conductor type is referred to the maximum current
Table 1. carrying capacity based on the total load of the proposed
system. Total load is about 237.12 MVA; comprises with 215
Table 1. Data reactance and resistance of generators
MW + j100 MVAR. Therefore, the magnitude of maximum
Parameters G1 G2 G3 G4 current carrying capacity can be calculated as follows:
Synchronous (Xd) 1.1 1.15 1.15 1.1 .
| |= = 992.0 (1)
Transient (Xd') 0.23 0.37 0.37 0.23 √
Reactances Substransient (Xd") 0.12 0.24 0.24 0.12 Basically, several types of conductors are also able to
(p.u) Negative sequence handle this maximum current, such as Grackle, Finch, Curlew
0.13 0.29 0.29 0.13
(X2) and Cardinal [19]. However, the ACSR (Pheasant 54/19) type
Zero sequence (X0) 0.05 0.11 0.11 0.05 is more properly safe for the expansion of the system in the
future with the approximated current carrying capacity of 1200
Resistances Positive sequence 0.005 0.012 0.012 0.005 A.
(p.u) Negative sequence 0.035 0.1 0.1 0.035 The other parameters, such as inductance and capacitance
should be determined from specific configuration of
• G1: Turbo Generator (solid rotor), 22 kV, 77 MVA, cos ϕ = transmission lines, which is designed as single 3 phase lines, as
0.972 lagging shown in Fig. 2.
• G2: Water wheel generator with damper, 13.8 kV, 42.7
MVA, cos ϕ = 0.94 lagging
• G3: Water wheel generator with damper, 20 kV, 67 MVA,
cos ϕ = 0.894 lagging
• G4: Turbo generator (solid rotor), 13.8 kV, 42.7 MVA, cos
ϕ = 0.94 lagging
Because G1 is connected to the slack bus, this generator
should be able to adjust its output anytime while system
parameters are changed.
II.3 Transformers. Power transformers with rating over Fig.2. Configuration of transmission lines
10 MVA and the highest voltage winding of 138 kV, the leakage The effective radius (r’) of each conductor is calculated by:
reactance can be specified according to its cooling system [16].
For the type of forced-air cooled (FA) is specified between 7 . "
= 0.7788 = 0.7788 = 0.0137 (2)
and 14% . Meawhile, for the type of forced-oil-cooled (FO) is
1A30-1 The 4th IEEE Conference on Power Engineering and Renewable Energy
ICPERE 2018
The geometric mean distance (GMD) is measured as: III. SIMULATION RESULTS AND DISCUSSION
= =13.44m (3) To assess the performance of load flow, it is required a
criteria of voltage in the bus. For the system 138kV, the
The inductance (L) and the inductive reactance (XL) are magnitude of voltage is limited between 0.90 p.u and 1.05 p.u
calculated as follows: in both normal and contingency operation [20]. For the system
between 1 kV and 132 kV, the permitted voltage regulation is
= 2 10 = 1.378 / (4) ±6% [21]. Meanwhile, the voltage phase angle in the normal
operation is limited within ±8 degrees.
=2 = 0.433 Ω/ (5)
III.1 Normal Operation. Table 5 shows the magnitude-
The capacitance (C) and the capacitive admittance (YC) are phase angle of voltage in all buses and the balance of output
calculated as follows: power that is generated and consumed in the normal operation.
= = 0.00838 (6) The magnitude and phase angle of voltage of buses are still in
the allowable range. The lowest magnitude voltage is 0.96 p.u
at bus-9, while the bus-4 has the highest magnitude voltage
= 2 = 2.632 / (7) about 1% higher than the voltage of slack bus generator. The
phase angles of voltage are still in the range of ±8 degrees.
The base Impedance (Zbase) is selected based on the equation
as follows: Table 5. Load flow results in the normal operating condition
( ) Voltage Angle Load Generation
= = = 190.44 (8) Buses
(p.u) (Deg) MW MVAR MW MVAR
1 1.00000 0.00 - - 75.44 18.25
The transmission lines parameters are shown in Table 3. 2 1.00185 -4.28 - - 40 15
3 1.00093 -3.66 - - 60 30
Table 3. Parameters of transmission lines
Distance 4 1.01153 -1.85 - - 40 15
Buses R (p.u) XL (p.u) BC (p.u) 5 0.98464 -4.39 40 20 - -
(km)
5-7 150 0.0411 0.341 0.0752 6 0.98769 -6.60 50 10 - -
5-8 110 0.0302 0.2501 0.0551 7 0.97281 -7.19 50 20 - -
5-9 120 0.0329 0.2728 0.0601 8 0.99749 -4.12 20 10 - -
6-8 110 0.0302 0.2501 0.0551 9 0.95777 -7.98 40 30 - -
6-10 100 0.0274 0.2273 0.0501 10 0.97004 -7.40 15 10 - -
7-10 140 0.0384 0.3182 0.0702
9-10 100 0.0274 0.2273 0.0501 In terms of power flows in the network, the system is
running in the high efficiency (99.8%) due to only 0.44 MW of
active power losses in the transmission line. Because of the
Since transmission line is also a static device, the phase transmission line is designed in the medium line configuration,
sequence has no effect on the impedance. As results, the the effect of line charging capacitor cannot be neglected. As a
positive sequence impedance (Z1) is equal to the negative result, the charging capacitor compensates for reactive power
sequence impedance (Z2). Due to possibility zero sequence and gives contribution to the whole network
current flows after neutral point connects to the ground, the zero
sequence impedance is commonly set by three times larger than III.2 Contingency Operation. In the contingency
Z1 or Z2 [18]. operation, there are two different scenarios where the generator
and transmission line are simultaneously failed. It will also be
II.5 Loads. The loads are located in the bus 5-10. The total
noticed later that the network has responded differently when
load recapitulation is shown in Table 4.
big generators go out, such as G3 and G4, where (G3 > G4). The
line failure is arbitrarily occurred in the line between bus 5 and
Table 4. Distribution of loads 6. The overall results of this condition are shown in Fig.3.
Loads
Buses Load (p.u)
(MW) (MVAR) In Fig.3, both magnitude and phase angle of voltage of some
5 40 20 0.40+j0.20 buses will be out of permitted range when G3 is off. For
6 50 10 0.50+j0.10 instance, the bus 3 and 7 have experienced a drop voltage to 0.8
7 50 20 0.50+j0.20 p.u and their voltage angles are falling to -20 degrees. By
8 20 10 0.20+j0.10 comparison, when G4 goes off, the magnitude voltage is
9 40 30 0.40+j0.30 basically in the range of allowable value, but the phase angle of
10 15 10 0.15+j0.10 some buses is remained lower than –8 degrees. As happened
Total 215 100 2.15 j1.00 when G4 is off, it will be almost similar result when the failure
1A30-1 The 4th IEEE Conference on Power Engineering and Renewable Energy
ICPERE 2018
magnitude and phase angle voltage at adjacent buses for each line, it is expected that the system parameters do not change too
phase become unbalanced. The bus voltage at fault location or drastically. However, if the system condition cannot be
the voltage at the phase fault will not be equal to zero if there is recovered naturally, the utility should be able to manipulate the
impedance being involved the fault to ground. In this case, it is system in order to bring back to the normal condition. The load
considered that bolted fault occurred in both types of fault. shedding method can provide remedies to the contingency
situation as the last option in maintaining the continuity of
Table 6. Three-phase fault simulation results in bus 8 utility services.
[16] W.D. Stevenson: Elements of Power System Analysis, 4th Ed., New [20] D. Holhbaugh, and D.Grimes: Final Report: “System Impact Study to
York:McGraw-Hill, 1982 Allegheny Energy Supply for 180MW Electric Generating Facility”,
[17] H. Saadat: Power System Analysis, Boston: WCB/McGraw-Hill, Boston, Lawrence County, PA, ATSI, 2001
1999 [21] C.L. Master: “Voltage rise: the big issue when connecting embedded
[18] Z.A.Yamayee, and J.L.Bala: Electromechanical Energy Devices and generation to long 11 kV overhead lines”, IEE Power Engineering
Power Systems, New York: J. Wiley, 1994 Journal, Vol.16(1), pp.5-12, (2002)
[19] J.D. Golver, and M. Sarma: Power System Analysis and Design: With
Personal Computer Applications, Boston: PWS Publisher, 1987