Safe Use of Cranes
Safe Use of Cranes
Safe Use of Cranes
1. Introduction
6. Lifting equipment
7. Risk Assessment
8. Lifting Assessment
INTRODUCTION
In order to provide a safe system of work and to ensure compliance with
current legislation this site lifting plan has been developed and is to be
implemented by every member of the crane team involved with this project.
It is essential that all team members are fully competent and certified to carry
out their individual roles. (See section 13)
It is essential that all team members are confident that they can fulfil their
duties especially when works may need to be carried out at height.
Whether the lifting operations are repetitive or if they are a one off, a safe
system of work must be established and followed for the operation to be both
safe and successful.
The selection of suitable cranes and work equipment must be carried out.
A crane team is to be employed who are fully trained and competent and who
have had their roles and responsibilities clearly explained to them.
The areas for the cranes access and rigging etc must be properly planned and
properly prepared.
The crane team organisation chart is shown below and roles and duties are
continued beneath.
Appointed Person
Crane Supervisor
Crane Co-ordinator
Crane Operator
Slinger/Signaller
Appointed Person
The appointed person is able to delegate his duties to another person but the
responsibilities still remain the appointed persons.
Crane Supervisor
The crane supervisor role is to direct and supervise the lifting operation and
ensure that these are carried out in accordance with the relevant method
statement / lift plan.
The crane supervisor should be competent and suitably trained and must be
experienced to carry out all relevant duties.
The crane supervisor has authority to stop the lifting operation if he considers
it dangerous to proceed.
This role can be carried out by the appointed person or may be delegated to someone with appropriate
expertise in lifting operations.
Crane Co-ordinator
The crane co-ordinator’s role is to plan and direct the sequence of operations
of the cranes to ensure they do not collide with other cranes, loads and other
equipment and buildings.
This role can be carried out by a competent person with knowledge and experience in lifting operations.
Crane Operator
The crane operator is responsible for the correct operation of the crane in
accordance with the manufacturer’s instructions and within the safe system
of work.
Should any person near a lifting operation give the recognised stop signal the
operator must cease lifting operations immediately and confirm what actions
are required from the slinger / signaller.
The crane operator must report any defects to the appointed person
immediately. (The driver may report defects etc direct to the fitters etc but
the appointed person must still be made aware of this action)
Slinger / Signaller
The slinger / signaller is responsible for the attaching and detaching of loads
to and from the crane load lifting attachment and ensuring that the correct
accessories are used for that operation in accordance with the planning of the
operation.
The slinger / signaller is responsible for the safe movement of the crane and
clear direction must be given whether visual or hand signals.
Where more than one slinger / signaller is required, clear instruction must be
given when passing responsibility over to the next slinger / signaller.
The slinger / signaller must notify the appointed person of any damaged
equipment immediately.
The crane must only be operated under a safe system of work and within the
manufacturer’s instructions.
When the days operations are completed and the crane is “parked” the
operator must put the crane in out of service position and set the block at
minimum radius (mobile cranes), 25% radius (Luffing cranes), maximum
radius (Saddle jib cranes).(see manufacturers specifications)
The cabin must be secured at the end of the shift and where there is a risk of
intruders or protesters a lockable trap door will be required for tower cranes.
Regular inspections of the crane are to be carried out and this must be
recorded weekly in the site office.
Where there is a requirement for a person to climb the mast of a crane whilst
the crane is still operational the driver must be made aware of someone
climbing before they commence.
Any tools or equipment needed to be used must be secure and free from risk
of falling and if tools are to be lifted up using the crane they must be done so
using equipment designed for that task.
Where existing buildings are situated within the cranes radius specific control
measures must be put in place (these will be determined in the risk
assessments)
Signalling
Where available the recognised hand signals will be adopted and a copy of
those is attached.
Where hand signals are not suitable radio contact is to be established and
implemented, when using radio contact the slinger / signaller is to give clear,
concise directions and if unclear the driver is to stop all lifting operations (If
communication is lost during a lift the driver is also to stop)
The slinger / signallers are to be identifiable to the operators and this will be
achieved by the operatives wearing orange high visibility vests.
Additional allowances must be made if materials are wet or have been soaked
this can vary substantially.
Lifting loads
Once the slinger has secured a load it must be raised 150mm and the load is
to be re-checked for stability.
Once the slinger / signaler is assured of the stability of the load he will give
direction to the crane operator to proceed with the lift.
Where possible the direction of travel will be the shortest direction and will
be away from where operative are working beneath. If this is not possible the
slinger signaler is to warn operatives of loads above. On multi-crane sites,
this is to be addressed to all site workers during their site induction.
Loads must never be dragged as the cranes are only designed to lift in a
vertical plane and there a possibility of damage to the crane.
Lifting Equipment
Only slings and other lifting accessories for which a valid report of thorough
examination has been issued within the previous 6 months are to be used.
Lifting accessories should be clearly marked with the rated capacity and have
an identification number for record purposes.
Lifting equipment must be visually inspected before use with any defects
being reported immediately.
When lifting equipment is not being used it should be stored in secure dry
conditions, preferably by hanging on a rack where they cannot get tangled or
contaminated.
A maintenance and
service schedule is to be
established and
implemented.
A copy of certification
is to be retained on site
for record keeping and
reference.
Slinger / Signaller to
carry out visual
inspection prior to use
A lifting assessment is
to be carried out prior to
any unique or special
lifts being carried out.
Close proximity of Entanglement leading to A safe system of work
cranes/building/public loss of integrity of load is to be instigated
amenities ensuring the risk of
collision is eradicated.
ASSESSED BY………………………..DATE………………..
IDENTIFICATION AND ASSESSMENT OF LIFTING OPERATIONS
Operation * Items to be Max Crane Used Lifted From Lifted To Equipment Comments
Lifted Weight Used
Site Set-Up offices Welfare 2.5t Mobile Crane Delivery Vehicles Final position 4 leg 10t chains Survey required of site ground
facilities (Hired in) "On Site" as per site 4 no. 3t shackles conditions prior to crane set-up.
layout plan Crane Co-ordinator and
Slinger/Signaller to be in
attendance. Chains & shackles to
be hired with crane.
Piling Bundles of 2t All Cranes Delivery Vehicles 4 leg 6.7t chains Choke wrapped using 2 legs
Reinforcement
Reinforcement 1.5t Site position Final position 4- Leg 6t chains Lifting points to be clearly defined
cages in method statement .
Retaining Bundles of 2t Mobile / tower Delivery Vehicles Areas between 2 leg 6t chains Choke wrapped using 2 legs
Walls reinforcement Final position
R.M.D 2.5t Mobile / Tower Preparation area R.M.D lifting Approval required for R M D
Shutters devices and 2 system via Temp Work procedure
Wall Shutters leg 6t chains C Frame.
Concrete by Skip 3t / 6.5t Mobile / Tower Areas between 8t Drop Chain Ensure there are no loops or knots
in operating line. Keep tag lines as
short as practicable.
Main Frame Columns, Not yet To be advised Delivery vehicles Final position To be confirmed All offloading to be carried out
Steelwork beams, bracing known prior to within site boundaries.
commencement
Operation * Items to be Max Crane Used Lifted From Lifted To Equipment Comments
Lifted Weight Used
Plant and Compressors 3.0 t All Cranes Site location Final position 4 leg 6.7t chains Plant and machinery to be lifted by
machinery water bowsers their designated lifting points only.
Slinger Signaller to be in
attendance.
Tower Tower Crane 5t Mobile / Tower Delivery vehicle Final position 4 leg 6.7t chains Lifting points to be clearly defined
Crane Base Base Crane / Crawler in the method statement and
approved by Principal Contractor
Bundles of Shoring 2.5t All cranes Delivery vehicle Final position 4 leg 6.7t chains Slinger signaller to be in
Timber attendance.
Columns Reinforced 1.5t All Cranes Site Locations Final Position 4 leg 6.7t Chains Slinger Signaller to be in
cages 4 leg 6.7t chains attendance
Shuttering 1t
Concrete Skip 1t – 6.5t 8t drop chain
Operation * Items to be Max Crane Used Lifted From Lifted To Equipment Comments
Lifted Weight Used
Walls Reinforced 1.5t All cranes Site locations Final position 4 leg 6.7t chains Slinger signaller to be in
cages attendance.
Shuttering 1t
Concrete Skip 1t - 6.5t
Striking Shuttering 1t All cranes Site locations Final position 4 leg 6.7 t chains Slinger signaller to be in
walls and attendance.
columns
Ground Boat skip 4t All Cranes Site locations Final position 2 legs providing
Works they are of
sufficient
capacity or 8t
drop chain.
Load Method
Issue No.: 1
Date:
Record of lifting appliances and accessories
Lifting Appliances (e.g.
Cranes)
Description ID No. Supplier: Test Cert. 12 Monthly Used for lifting persons? Weekly
Expiry Date: Thorough Y/N. Inspections
Examination (If so, 6 Monthly carried out by:
Expiry Date: Thorough Exam’n?)
Issue No.:01
Date:
Crane team appointment and certification
Position Name Date Appointed
Appointed Person*
(Lifting Operations)
Deputy appointed
Person
Crane Co-ordinator
Crane Operators*
Signallers/Slingers*
Issue 01
* Must hold appropriate CPCS Cards No.:
Date: