Heavy Lifting
Heavy Lifting
Heavy Lifting
Each year, a number of mobile cranes overturn on construction sites causing serious
accidents involving personal injury, significant property damage and potential
business interruption claims. Most incidents are as a result of inadequate planning,
unclear responsibilities or unsafe use.
The hazards which increase the risk of an overturning event are many and include
unstable working platforms, subsurface voids, high winds, poor maintenance,
inexperienced crane operators and supervisors, excessive loads, underrated crane
capacity and poor use of outriggers and bearing plates, etc.
3. Appointed Person
The Appointed Person has overall
control of the lifting operation and their
duties should include:
assessment of the lifting operation
including planning, choice of crane and
equipment, and liaison with other
parties affected by the lift
ensuring inspection and maintenance
has been carried out
organisation and control of all lifting
operations
briefing the Crane Supervisor on the
contents of the method statement and
Lifting Plan
ensuring there is an effective
procedure for reporting defects and
incidents and taking any necessary
corrective action
Some of the duties, but not the
responsibilities, may be delegated for
simple lifts. The Appointed Person
should consult with other experts
including temporary works engineers
and crane suppliers.
4. Crane maintenance
The crane should be in a satisfactory
operating order at all times. Planned
maintenance should be undertaken and
thorough examinations performed, with
test certificates and documentation in
place. Detailed requirements are
included in BS7121 and the LOLER and
PUWER Regulations.
5. Contract lift vs crane hire
An organisation that requires a load to
be moved, and does not have its own
craneage, has two options: hiring a crane
(Hired Crane) or employing a contractor
to carry out the lifting operation
(Contract Lift). If an individual or
organisation does not have expertise in
lifting operations, they should not hire
cranes but should opt for the contract lift
option. Insurance arrangements should
be clarified. A summary of the options is
included in the following table.
6. Complexity of lift
The duties and extent of planning
involved for a lift will vary depending on
its complexity. Lifts are categorised into
basic, standard or complex. The
categorisation is a function of the level
of hazards present within the area of the
crane operation, which are established
through the risk assessment process.
Detailed guidance is provided in
BS 7121-1.
7. Risk assessment and
method statement
An essential element of any crane
operation is the production of a risk
assessment and method statement. The
risk assessment should be carried out by
the Appointed Person and identify the
hazards and risks associated with the
lifting operation. Reference should be
9. Siting
The siting of the crane should take into
account the crane standing and support
conditions, the effect of wind and the
adequacy of access to allow the placing
or erection of the crane in its working
position, as well as dismantling and
removal from site. Particular care needs
to be taken when siting mobile cranes in
or near the danger area at the edge of
open trenches and excavations as these
are likely to collapse without warning
(see C703). An engineering assessment
by a competent geotechnical engineer is
required before setting up in such a
location.
10. Checklists
The management, planning and
execution of a crane lift has to take into
account many aspects. Consequently, it
is recommended that the use of
checklists and pro formas are employed
to ensure no aspect is left unaddressed.
These may include (but not limited to)
key elements of the safe system of work,
the load and the lift, the location,
specifying and operating teams, the
crane, the lifting gear and any temporary
works. Sample checklists are included in
C703.
Ground conditions
The mechanism of overturning is often
as a result of a failure of the ground or
supporting structure beneath the crane
or its outriggers. The following aspects
are key to ensuring an adequate
foundation is provided.
11. Site categories and
underground hazards
Sites can be split into a number of
categories to highlight the most likely
hazards that need to be considered
and risk assessed. More attention is
required to establish the strength of
the ground where ground conditions
Undertake a suitable and sufficient site investigation to determine the nature of the
ground conditions. Ensure a suitably designed and compacted working platform is
installed and maintained.
Obtain existing services drawings and undertake trial pits, probing and cable
detection to identify all buried services and voids.
Ensure crane is set up a suitable distance from the edge of open excavations and slopes.
Undertake a suitable and sufficient site investigation to determine the nature of the
ground conditions. Monitor groundwater and soil saturation levels. Ensure a suitably
designed and compacted working platform is installed and maintained. Use suitable
bearing plates beneath outriggers.
Ensure only competent, trained persons are employed (see BS 7121-1). Consider a
Contract Lift if competence of supervisors is in doubt.
Ensure key positions are established and individuals appointed by letter detailing their
roles and responsibilities.
Provide a sketch illustrating the permissible set-up location(s) and allowable access
route(s). Prevent access to unsafe areas.
Ensure all lifting operations are subject to a Lifting Plan, including a risk assessment,
a method statement and a Permit to Lift.
Ensure a competent designer is employed and suitable Factor of Safety (FoS) used.
Clarify if the design criterion refers to ultimate bearing capacity (ground failure) or
allowable bearing pressure (including an FoS). See C703 for guidance.
Overloading
Load too heavy
Ensure the load to be lifted is not greater than allowed for in the planning. The rated
capacity limiter/indicator should be maintained in good order.
Stay within the agreed lifting location and radius. Avoid swinging loads or travelling
with high loads.
Mechanical failure
Poorly maintained crane
Ensure crane is regularly maintained in accordance with the LOLER and PUWER
Regulations and thorough examinations performed.
Case Study 1
Two construction companies were
prosecuted by the HSE following the
overturning of a 35-tonne truckmounted telescopic crane on site. The
collapse occurred after one of the
outriggers, which supported the crane,
sank into the ground.
The crane driver was forced to leap to
safety and the 5.7-tonne beam that was
being lifted into place narrowly missed
two employees as it fell. The principal
contractor and crane operator were both
fined and ordered to pay substantial
costs.
The incident could have been avoided
had the planning and supervision of the
lifting operation not been so deficient.
The crane overturned because it was
being operated, with the knowledge of
both companies, in a part of the site that
had not been prepared for such
activities. The roadway was not wide
enough to accommodate the outrigger
Case Study 2
The principal contractor and crane hire
company were ordered to pay a
substantial fine and costs after a serious
communications failure led to a mobile
crane toppling over on site. The
extended 50-metre jib fell across the
www.hsbeil.com
Leeds
t: 0113 388 4830
Ipswich
t: 0845 345 5513
Glasgow
t: 0845 345 5514
Birmingham
t: 0845 345 5512
Belfast
t: 0845 345 5516
Manchester
t: 0845 345 5511
Bristol
t: 0844 875 4260
Dublin
t: 01 234 2699
HSB Engineering Insurance Limited registered in England and Wales: 02396114, New London House, 6 London Street, London EC3R 7LP.
Registered as a branch in Ireland: 906020. Authorised by the Prudential Regulation Authority and regulated by the Financial Conduct Authority and
the Prudential Regulation Authority.
HSBEI-1307-0614