AE-CS-WF-200 Rev.a
AE-CS-WF-200 Rev.a
AE-CS-WF-200 Rev.a
4.7, 7.3,7.4
L.7,7.L,7.2, App. A
C Materials
NDE
Qc
Senior Materials Engineer
This document is the propety of Allseas and may contain confidential and proprietary ¡nformat¡on. It may not be used for any purpose
other than that for which it is supplied. This document may not be wholly or paftly disclosed, copied, duplicated or in any way made
use of without prior written approval of Allseas.
Page 2 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
1 INTRODUCTION 6
SCOPE 6
DEFINITIONS 6
DEVIATIONS 6
ABBREVIATIONS 7
INFORMATION TO BE PROVIDED BY COMPANY 8
QUALITY ASSURANCE, HEALTH, SAFETY AND ENVIRONMENT (QHSE) 8
1.6.1 Subcontractors 8
QUALITY CONTROL 8
1.7.1 Quality Plan 8
1.7.2 Equipment & Calibration 8
DOCUMENTATION 8
REFERENCES 9
1.9.1 Normative references 9
2 MATERIALS 9
GENERAL 9
MATERIAL GRADE 9
2.2.1 Lloyds certification or classification 9
MATERIAL ORIGIN 9
CERTIFICATION 10
“Z” GRADE MATERIAL 10
3 WELDING AND CUTTING 10
GENERAL 10
WELD MAP, WELD MATRIX, HEAT INPUT AND REPAIR PHILOSOPHY 10
PRE-QUALIFIED WELDING PROCEDURE 10
WELDING PROCESSES 11
WELDING CONSUMABLES 11
3.5.1 Consumable type and approval 11
3.5.2 Hydrogen content 11
3.5.3 Consumable storage, handling, etc. 11
3.5.4 Mechanical strength 11
3.5.5 Marking 11
3.5.6 Certification 11
3.5.7 Consumable test 11
3.5.8 SAW – flux recycling 12
3.5.9 SMAW 12
THERMAL CUTTING 12
3.6.2 After cutting 12
TACK WELDING 12
INTERRUPTION OF WELDING 12
DOUBLE SIDED WELDING 12
HEAT INPUT 13
ARC STRIKES 13
4 WELDING PROCEDURE QUALIFICATION 13
GENERAL 13
SCOPE 13
LOGGING OF PARAMETERS 13
RANGE OF APPROVAL 14
4.4.1 Manufacturer 14
4.4.2 Material 14
4.4.3 Mechanisation 14
4.4.4 Welding consumables 14
4.4.5 Joint types 14
4.4.6 Thickness range 14
4.4.7 Welding position 15
Page 3 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Page 5 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
1 INTRODUCTION
Scope
This specification covers the minimum requirements for the welding, fabrication, installation and inspection of
primary structural components.
This may include, but is not limited to temporary installation aids, winches, yoke footings, brackets sea
fastening, spreader bars, protection frames on permanent items, for the Allseas group of Companies,
hereinafter referred to as Company.
This specification shall be used by Company, and by Contractor and its Subcontractor(s) who supply services
to Company. Contractor including its employees, agents, and subcontractor(s) of any tier are hereinafter
referred to as Contractor.
It is the responsibility of the Contractor to ensure that all fabrication personnel adhere to the relevant sections
of this specification that are applicable to their scope of work.
Where reference is made to other codes than this specification, the revision shall apply which was current at
the date of contract award.
For materials, fabrication and inspection used for the construction, conversion, modification or repair of
ships, other marine structures and associated machinery which are classed, are intended for classification or
require certification by Lloyds Register (LR), the specification below shall prevail over
the AWS D.1.1;
Lloyd’s Register Rules for the Manufacture, Testing and Certification of Materials
If LR rules are applicable, all documents which are required to be approved by a LR surveyor shall be issued
for approval to both Company and LR surveyor.
When based on another design standard, third party and/or certifying authority is considered applicable
these shall apply, where the most stringent requirement shall prevail.
For any conflict of requirement not solved by the above stated order, precedence shall require resolution by
Company in writing. For deviations to this specification reference is made to section 1.3
Definitions
Agreement / Approval
Unless otherwise indicated, this means agreed in writing between Contractor and Company.
Shall
Indicates a mandatory requirement.
Should
Indicates that among several possibilities, one is recommended as particularly suitable, without mentioning or
excluding others, or that a certain course of action is preferred but not necessarily required.
Deviations
Deviations from this specification and pertaining documents are not allowed unless instructed by Company or
an approved Concession Request (CR). It remains the responsibility of the Contractor to raise a CR in writing
to Company.
In case of contradicting requirements or omissions are identified by Contractor, Contractor shall obtain written
clarification from Company via a Technical Query (TQ) before proceeding with the work involved.
Page 6 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
As a general rule, the requirements of relevant laws and governmental regulations and the regulations of the
appointed Authorities (e.g. Lloyds Register), shall be adhered to and cannot be waived by Company.
Note: Should Contractor consider their normal working practice preferable over a requirement as stated in this
specification, Contractor is encouraged to submit a CR about this requirement for Company’s consideration. A
CR shall be based on extensive technical justification for Company’s consideration.
CR’s from Subcontractors shall be endorsed by the main Contractor before issue to Company’s nominated
(site) representative.
Abbreviations
ALX Arc Logger X
AWS American Welding Society
Ceq Carbon Equivalent (IIW)
CJP Complete Joint Penetration
CR Concession Request
CTOD Crack Tip Opening Displacement
CVN Charpy V-notch impact testing
DNV Det Norske Veritas
ECA Engineering Critical Assessment
FCAW Flux Cored Arc Welding
GTAW Gas Tungsten Arc Welding
GMAW Gas Metal Arc Welding
HAZ Heat Affected Zone
HFI High Frequency Induction
IACS International Association of Classification Societies
IWE International Welding Engineer (in accordance with EN-ISO 14731)
IWT International Welding Technologist (in accordance with EN-ISO 14731)
IQI Image Quality Indicator
ITP Inspection and Test Plan
LR Lloyds Register
MPI Magnetic Particle Inspection
MRB Manufacturing Record Book
MUT Manual Ultrasonic Testing
N Normalised
NDE Non Destructive Examination
Pcm Carbon Equivalent - Critical metal parameter (Ito and Bessyo)
PIM Pre-Inspection Meeting
PJP Partial Joint Penetration
PO Purchase Order
PWHT Post Weld Heat Treatment
PQR Procedure Qualification Record
QC Quality Control
QHSE Quality Assurance, Health, Safety and Environment
QT Quenched & Tempered
SAW Submerged Arc Welding
SMAW Shielded Metal Arc Welding
SMYS Specified Minimum Yield Strength
SMTS Specified Minimum Tensile Strength
RT Radiographic Testing
t thickness
tbd to be determined
TMCP Thermo Mechanically Controlled Process
TQ Technical Query
(p)WPS (preliminary) Welding Procedure Specification
UTS Ultimate Tensile Strength
VT Visual Testing
WPQ Welding Procedure Qualification
WT Wall Thickness
(note; abbreviations may not be used in this document but in any other document or by way of communication)
Page 7 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
The Company nominated (site) representative shall have the right to undertake any audit as deemed necessary
to assess the effectiveness of the Contractor's quality system.
The Contractor shall also establish and maintain a Health, Safety Management and Environmental care system,
which meets both the governmental laws and statutory regulations.
1.6.1 Subcontractors
The Contractor must select competent Subcontractors and suppliers. It is the responsibility of the Contractor
to ensure that all subcontractor’s disciplines involved are familiarised with and shall adhere to the requirements
in this specification.
Quality Control
1.7.1 Quality Plan
Prior to commencement of the work the Contractor shall prepare for Company’ approval a Quality Plan,
including Inspection and Test Plan (ITP). Throughout this Quality Plan the Contractor will ensure that the
quality of the product is maintained during the execution of the work. The ITP details a systematic approach
on work activities, personnel responsibilities and all parties’ intervention points.
The Company nominated (site) representative shall have the right to undertake inspection or testing of raw
materials, purchased components, (partially) fabricated items or services, during any stage of manufacture at
which the quality of the finished goods may be affected.
Documentation
The Contractor, shall prepare all documentation that is required to ensure that the requirements of the work
are fully understood and communicated to the personnel performing the actual work.
In addition, the Contractor shall prepare all documentation required to show that the fabrication meets the
specified requirements.
The original documentation will be subject to approval by Company and shall finally be issued to Company in
the form of an as-built manufacturing record book (MRB) package (one hard-copy and one electronic copy).
In addition, Contractor shall safeguard a copy of all documentation, reference is made to purchase order terms
and conditions.
The contents of the Manufacturing Record Book shall as minimum fulfil the requirements as stated in Appendix
A. The chapters of the MRB shall be clearly separated, for example by cover pages. Chapters that are not
applicable for the scope of work shall be marked as such upon submittal of the draft MRB index.
Although it is required that Company approve documents prior to commencement of work, Contractor remains
responsible for the contents of these documents and the implementation thereof during fabrication (including
documents of Subcontractors and suppliers).
Page 8 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
References
The latest revision of the following references applies, unless stated otherwise in below section and/or the
Purchase Order/contract.
2 MATERIALS
General
All material shall comply with the requirements as laid down in table C-1 of Appendix C.
Material Grade
Material grades to be used shall be as indicated on the Company’ approved drawings. No changes to indicated
materials and material grades shall be made without the agreement of Company.
Mechanical properties shall satisfy the requirements as outlined in table C-1 of Appendix C.
Furthermore all materials will need to be manufactured by works that have been approved by Lloyd’s Register
for the type of product and grade of material to be supplied. Sometimes thickness is the driving factor (plates)
and sometimes weight (forgings & castings). The most recent list of approved works can be found via the
Lloyd’s Register’s internet sites.
Material Origin
Unless otherwise approved by Company, from all material with an origin not given below, test pieces shall
be extracted and tensile tested by Contractor. Furthermore one set of Charpy V-Notch impact test (CVN)
samples shall be extracted from the actual delivered, or to be delivered, material.
Page 9 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
One test per testing lot as per the applicable standard or specification shall apply.
Origins not subject to mandatory incoming material testing prior to use are: Australia, Austria, Belgium,
Brazil, Canada, Denmark, Finland, France, Germany, Ireland, Italy, Japan, Luxembourg, Netherlands,
Norway, Poland, Portugal, Slovenia, South Africa, South Korea, Spain, Sweden, Switzerland, Turkey, UAE,
United Kingdom, USA.
Regardless of the origin the actual manufacturer shall have a proven quality system complying to ISO 9001
or equivalent.
Certification
Unless otherwise indicated on the drawing, the Tender documents or Purchase order all materials used for
construction shall be ordered with an inspection certificate according to EN 10204 Type 3.1 or higher.
The certificate shall as a minimum detail the production method, delivery condition, chemical analyses, tensile
strength, yield strength, percentage of elongation and Charpy V-notch impact test values (including test
temperature).
A 3.1 type certificate is required for materials used in a welding procedure qualification.
General
Contractor shall assign a responsible employee for the coordination of welding activities. It is recommended
to arrange the responsibilities and tasks of personnel for welding coordination as per EN-ISO 14731.
Cutting and welding is only allowed in accordance with procedures approved by Company and strictly in
accordance with the approved ITP.
Page 10 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Welding processes
Unless otherwise approved by Company, acceptable welding processes are stated in Table 3-1.
Welding consumables
3.5.1 Consumable type and approval
All welding consumables shall be subject to Company’ approval. Lloyds approved consumables are mandatory
when Lloyds classification or certification is applicable. The list of approved consumables is published by LR.
Otherwise only AWS and/or EN designated welding consumables are acceptable.
3.5.5 Marking
Each type of welding consumable shall be uniquely and easily identifiable prior to and during use.
Unidentifiable consumables shall not be used.
3.5.6 Certification
Welding consumables shall have as minimum a type 3.1 inspection certificate in accordance with EN 10204.
Shielding gas shall have certification in accordance with ISO 14175.
a) WT < 50mm
1 All weld metal tensile test, only in case of non-LR approved welding consumables
1 Macro Section, including HV10 Hardness test for weld metal only
1 set of Charpy V-notch test weld metal.
b) WT ≥ 50mm
1 All weld metal tensile test, only in case of non-LR approved welding consumables
1 Macro Section, including HV10 Hardness test for weld metal only
1 set of Charpy V-notch test weld metal
1 set of Charpy V-notch test weld metal root.
Note: A consumable test shall be performed per consumable for a representative PQR, at the lowest required
CVN test temperature for all relevant PQRs, not for each individual PQR.
Page 11 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
3.5.9 SMAW
For Shielded Metal Arc Welding (SMAW), vacuum packed electrodes are highly recommended.
All vacuum packed consumable packages shall be clearly marked with the date and time of opening.
The package shall be discarded after the maximum opening duration, as specified by the consumable
manufacturer.
The use of re-baked electrodes for production purposes will require formal approval by Company, for which
an adequate control procedure will need to be issued for review and approval.
Thermal cutting
Prior to cutting, all materials, including free issued materials, shall be inspected for damages, correct
dimensions, flatness, markings, stamps and certification status.
The precautions, protection and location requirements as indicated in section 6.3 shall be taken into account.
The requirements as specified in section 6.4 shall be taken into account.
Tack welding
A separate qualified tack welding procedure is required. Alternatively, a qualified welding procedure may be
used as a basis for the tack weld procedure. It is recommended to increase the preheat by 50°C of the qualified
welding procedure. This alternative approach is only allowed after formal approval by Company.
If the production work requires welding over tack welds, a welding test shall be performed to qualify this
scenario. As part of this qualification, the tack welds shall be incorporated in the inspection length of the test
weld and their position recorded. A macro shall be taken from this position, and subjected to HV10 hardness
testing.
Interruption of welding
Welding should be performed as a continuous process and shall not be interrupted before the joint has
sufficient strength to avoid plastic yielding and cracking during handling. If welding is interrupted due to
production restraints, at least 3 passes, or half the thickness (whichever is less), shall be completed before
welding is interrupted. Before recommencing welding, the joint shall be reheated to at least the minimum
preheat temperature.
If welding on materials with Ceq ≥ 0.45 is interrupted, and minimum preheat temperature is not maintained
during the interruption, the weld shall be wrapped in dry insulating material and cool down in a slow uniform
manner.
Page 12 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Heat Input
For all welding processes, the final heat input should be within the range of 0.8 – 4.0 kJ/mm. If contractor
intents to qualify a final heat input range outside this range, this shall be subjected to separate approval by
Company.
The heat input shall be calculated with the following formula, i.e. in accordance with EN-1011-1:
𝑘(𝑈 ∗ 𝐼 ∗ 60)
𝐻𝐼 =
(𝑇𝑠 𝑥 1000)
HI = Heat Input [kJ/mm]
U = Voltage [V]
I = Amperage [A]
Ts = Travel speed [mm/minute]
k = thermal efficiency factor = 1 allowed for all welding processes.
In case k Factor is used, the thermal efficiency factor for the welding process are as followed:
SAW k = 1.0
SMAW k = 0.8
FCAW k = 0.8
GMAW (metal cored) k = 0.8
GTAW k = 0.6
When possible, parameters shall be measured close to the actual welding arc. The actual location of measuring
shall be recorded during the PQR welding trials. During production, the parameter verification tests shall be
performed at the same location used during PQR welding.
Contractor shall clarify heat input calculation for both procedure qualification and fabrication as part of the
issued weld matrix (ref. section 3.2) and issue to Company for approval.
Arc strikes
All arc strikes shall be removed by grinding and inspected by MPI to confirm complete removal of the arc
strike. If the material removal exceeds 0.5mm in depth, subjected area shall be checked by MUT for verification
on the minimum wall thickness. MUT shall be performed in accordance with a by Company approved
procedure.
General
In case of a new welding procedure qualification (WPQ), the preliminary Welding Procedure Specification
(pWPS) shall be issued for review and shall be qualified according to the non-destructive and destructive
testing requirements of this specification.
With reference to section 3.2 of this specification, Contractor shall submit a matrix detailing the extent of
procedure welding to be carried out, the extent of mechanical testing and NDE, application area of the
procedure(s) and testing schedule.
Specific procedures for repair welding (ref. section 6.11), buttering (ref. section 6.12) and tack welding (ref.
section 3.7) shall be included in this matrix and shall be representative for the actual production weld.
Scope
All welding procedures shall be qualified in accordance with this specification, AWS and/or LR Rules.
Logging of parameters
During procedure qualification welding, all parameters shall be checked and continuously recorded utilizing
“ALX” or similar arc monitoring and logging equipment, calibration of measurement equipment as per 1.7.2.
The welding records shall be subject to approval as part of welding procedure approval.
Page 13 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Range of approval
In addition to the requirements of the AWS and/or LR Rules, the following changes to the conditions qualified
shall lead to a new welding procedure qualification:
4.4.1 Manufacturer
A qualified WPS as per this specification obtained by a manufacturer is valid for welding in workshops or sites
under the same operational, technical and quality control management of that manufacturer.
4.4.2 Material
A change from QT to TMCP and vice versa
A change from N or as-rolled to QT or TMCP
In case of C ≤ 0.12% : an increase in Pcm (Ito and Bessyo) of more than +0.02
In case of C > 0.12% : an increase in Ceq (IIW) of more than +0.03
The inclusion of a weld primer.
Note: Both maximum Pcm and maximum Ceq shall be stated on the WPS. The validity of the WPS for a
production weld shall be judged based on either Pcm or Ceq, depending the C% of the to be welded materials
4.4.3 Mechanisation
A lower grade of mechanisation qualifies for a higher grade of mechanisation, but not vice versa. The grade
of mechanisation is defined as per AWS D.1.1 2010, with manual welding being the lowest grade, followed
by mechanized, semi-automatic and automatic, which is the highest grade of mechanisation.
The range of approval depending on the type of joint for CJP welds is given in Table 4-1.
4.4.9 PWHT
Omission or addition of PWHT
Branch welds
CJP groove welds in a T-, K- or Y connection with dihedral angle of less than 30° shall be in accordance with
AWS D1.1 section 9.15.4.2 and figure 9.24 in combination with an approved WPS in the weld positions 2G
and 5G or 6GR. In addition to this, welding of a mock-up piece shall be performed to demonstrate / establish
actual expected production parameters.
Fillet welds
A separate qualification is required for fillet welds.
Destructive testing
Destructive testing shall only be performed by a Company approved test laboratory.
Destructive testing shall be in accordance with AWS D1.1 latest edition and/or LR. In addition, the following
testing shall as a minimum be part of the test scope to meet Company’s requirements.
As the Charpy V-notch test locations requirements of AWS D1.1 and LR Rules are not fully aligned, Table 4-3
provides an overview of the test locations that are a minimum required for Company.
Page 15 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
In case materials with a different SMTS are joined, the requirements for the material with the lowest SMTS
shall apply.
For circumferential welds the test positions shall be at 12, 3 & 6 o’clock position, of which one shall include
the intersection between the longitudinal and the girth weld (with the exception of HFI and seamless pipe).
Each of these 3 macro specimens shall be subjected to HV10 hardness testing.
For CJP and fillet plate welds, one of the 3 macro specimens shall be subjected to HV10 hardness surveys,
taken at a (artificial) start/stop location of the weld test assembly. In addition, the macro specimen for fillet
welds shall be free from lack of penetration and the total area of any cavities or inclusions shall not exceed
5% of the fillet weld cross-sectional area.
Specimens shall be free from cracks and lack of fusion. Any other defects shall be within the limits specified
in section 7.2.
In the heat affected zone, the distance between two adjacent indentations shall be approximately 0.5mm. For
all other locations, the recommended distance between two adjacent indentations is maximum 1.0mm. Care
shall be taken that the distance between two adjacent indentations shall be at least three times the mean
diagonal of the actual largest indentation. Reference is made to Appendix B for guidance on testing locations.
Page 16 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
If required, CTOD testing is to be performed in accordance with BS7448 at minimum design temperature.
Scope and test locations are to be based on the input needed for the ‘no-PWHT’ ECA or as instructed by
Company.
4.8.6 Re-testing
Re-testing is allowed in accordance with the requirements in AWS D1.1 and or LR.
Re-testing is only allowed once per type of test and once per welding procedure.
Track records shall be available to prove that (tack) welders and welding operators are skilled, experienced
and qualified for using the applicable welding process.
Renewal of certification shall be verified and approved by a relevant Authority (IACS approved).
The direction of welding for vertical welding (uphill or downhill) is an essential variable for validity of the
qualification.
5.1.4 Identification
Qualified welders shall be easily physical identifiable during fabrication for the range of their qualifications.
6 FABRICATION
General
The following documents (if relevant) shall be approved by Company prior to the start of the fabrication:
Weld plan / matrix (ref. sections 3.2 and 4.1)
Welding procedures
Welder and welder operator qualifications (ref. section 5)
Post-weld treatment procedures (e.g. Soaking, PWHT)
NDE procedures and operators qualifications
Repair welding philosophy (ref. section 6.11.3)
Dimensional Control Procedures
Inspection and Test Plans
Fabrication Plans
Project specific instructions and procedures
Manufacturing Record Book index (see Appendix A)
Page 17 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Fabrication location
Fabrication shall take place in a suitable assembly location. Cooling down after flame cutting, gouging or
welding shall take place in a controlled manner to avoid unwanted material changes or distortions.
Rolling direction
Where indicated on drawings, the item shall be cut in the rolling direction of the material. For pad eyes, the
rolling direction shall always be in the predominant direction of the applied tensile forces.
Surface preparation/cleaning/finishing
6.6.1 Surface preparations and fusion faces
Prior to any welding, fusion faces shall be ground to bright metal. Fusion faces and surrounding areas over a
minimum distance of 50mm shall be clean, free from slag, scale, moisture, oil, paint or any other detrimental
elements.
6.6.2 Primers
Where primers are applied over areas that will subsequently be welded, they are to be of a quality with no
significant deleterious effect on the finished weld.
6.6.6 Finishing
Unless otherwise indicated on the drawing all sharp edges shall be broken. Burrs are not allowed.
Page 18 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
heated. If not feasible, the preheat temperature shall be confirmed on the heated face after an equalization
period after removal of the heat source. The time allowed for the temperature equalization shall be 2 minutes
per 25mm parent metal thickness of thickest member.
Interpass temperatures shall be measured on the same location as during welding procedure qualifications;
this shall be either on the deposited weld metal or the immediately adjacent parent metal near the bevels and
captured as such in the inspection protocols.
The Contractor shall prepare a PWHT procedure in using BSI-PD 5500 section 4.4.5 as a guideline for detailing:
Temperature of furnace
Heating and cooling rates/temperature gradients
Holding times
Holding temperature
Heating methods and facilities
Minimum amount of thermocouples
Location of thermocouples
Insulation
Control devices and recording equipment.
Each condition of supply of material requires a customised heat treatment. This procedure shall be submitted
to Company for approval.
For QT steel, the PWHT temperature shall not exceed the lowest actual tempering temperature of the products
minus 25°C.
All welds, including repair welds requiring PWHT shall be completed prior to that heat treatment being
performed, unless otherwise noted on the drawing.
In case unacceptable indications are found by final NDE, repair welding procedures shall take the heat treated
material condition into account, i.e. need to be specifically qualified for the PWHT condition (ref. section
6.11.6)
In the situation that it is not feasible to carry out the PWHT in a closed furnace, separate approval for an
alternative setup shall be obtained from Company.
Page 19 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
used, it has to be performed by qualified welders (ref. section 5.1.3) and in accordance with Company’
approved qualified procedures (ref. section 3.7). For preheat and cooling conditions special attention is
required.
Where possible, “Bullets” shall be used of mild steel (e.g. S355J2) or material equivalent to the base material.
Tack and temporary welds require to be removed with special care to ensure that the base material is not
unnecessarily damaged during and after removal. Removal by force (e.g. hammering) is not allowed.
Surface breaking defects such as scars are to be prevented, and if they occur they shall be removed in a
controlled manner. Subject area shall be ground smooth, whilst the original wall thickness of the subject
material shall be respected. After removal, the subject areas shall be MPI examined for surface defects. If the
material removal exceeds 0.5mm in depth, subjected area shall be checked by MUT for verification on the
minimum wall thickness. MUT shall be performed in accordance with a by Company approved procedure.
Tack welds shall not be incorporated into final CJP welds, unless specifically qualified (ref. section 3.7).
Straightening
6.10.1 General
Straightening is only allowed after approval of a detailed procedure and drawing by Company.
Only line straightening will be considered for approval by Company.
Contractor shall recognize the condition of supply of the to be straightened base material(s) and reflect this
in the specific procedures issued for approval.
After straightening, the mechanical properties shall meet the same requirements specified for the original
condition of the material.
Repair welding
6.11.1 General
The number of repairs at the same location on a specific weld shall be limited to two unless otherwise approved
by Company.
Repair welding shall always be carried with a minimum of two passes, using a Company approved repair
procedure.
If gouging is required, preheating shall be applied to the preheat temperature as required for the original
welding procedure, unless agreed otherwise.
In all cases at least 25mm of sound metal beyond each defect, as determined by visual inspection and/or
NDE, shall be removed.
All repairs shall be subject to 100% visual inspection and NDE as per section 7.3 upon completion.
The minimum excavation distance between separate weld repairs shall be 100mm. In the situation that the
distance between various excavations is less than 100mm, the excavation shall be made continuously.
After excavation of defect areas (ref. section 6.11.7 in case of cracks), visual inspection and MPI shall be
applied for confirmation of removal of the defect(s). Prior to any repair welding, the condition of the weld
preparation / excavation shall be absolutely free of any rust or debris grinded to bright metal finish.
Page 20 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Full qualification of repair welding procedure, in accordance with section 4, for which the repair welding
qualification is performed on a joint welded as per the original procedure
Repair welding in accordance with a previously approved procedure complimented with the following test
scope on a repair weld performed on a joint welded as per the original procedure:
o 1x Macro with HV10 hardness testing
o 1x CVN Fusion Line +2mm repair weld to original weld metal
o 1x CVN Fusion Line +2mm root repair weld to original weld metal (for qualification of repair thickness
> 50 mm).
Remedial action shall be proposed to Company and will be subject to approval. Depending on the magnitude
of the defects a detailed repair plan shall be provided to Company.
Removal of linear indications is only to be done by gouging and/or burring tool (rotary file) and not by grinding
as this might cause propagation of the defect.
Repair of cracks shall not be carried out prior to formal approval from Company.
Buttering
In case buttering is performed in accordance with a qualified and approved procedure, no separate
qualification is required.
In case a separate procedure is to be used, the buttering procedure shall be fully qualified in combination with
a CJP welding procedure (i.e. simulate the actual intended production weldment) in accordance with section
4.
In this case, additional Charpy V-notch testing shall be required in the buttering layer and at the heat affected
zones related to the buttering layer. Company’s instruction shall be acquired via a TQ in order to establish the
applicable CVN testing locations to cover this situation.
Dimensional control
In order to ensure tolerances will be met during and after construction, proper intermediate and final
dimensional control shall be performed on a regularly basis (frequency to the satisfaction of Company) by
Page 21 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
using suitable and calibrated equipment and measuring method. In case dimensional tolerances are not clear
to Contractor resolution in writing via a TQ shall be obtained.
Personnel responsible for dimensional inspection shall have a minimum of 12 months of documented
experience in the relevant industry sector with regards to dimensional inspection and shall be fully conversant
with the equipment used. The manufacturer shall ensure sufficient training and instruction of the personnel,
in order to provide a stable and repeatable inspection practice.
7 INSPECTION
General
7.1.1 Responsibility
Contractor shall carry out all inspection, testing, recording and documenting as required by this specification
and the applicable codes and standards. Items with deviations and/or defects shall be reworked, repaired or
replaced. The rework, repair or replacement and re-inspection shall be at no cost to Company.
7.1.5 Records
The required quality inspection records shall be promptly generated after each inspection. Manufacturing
records shall be compiled on a continuous basis, issued for approval and signed by the Company’ and
Contractor’s inspector(s). Tables and other cross-references shall be made such that information can be easily
retrieved. All reporting shall be in the English language.
Reference is made to Section 1.8 and Appendix A.
7.1.5.1 Traceability
Where plates, pipes, fittings or other components with unique identification numbers are used in
construction, these unique numbers shall be used in documentation when referring to these components.
required by Company. Cost related to verification and reinstatement shall be borne by Company but only when
results are in accordance with agreed specifications.
Personnel performing NDE and/or Visual Testing of finished welded joints shall as a minimum be qualified in
accordance with ISO 9712 level 2 for the applicable NDE methods. As well they shall have passed a visual
acuity test such as required by ISO 9712 or a Jaeger J-w test at 300 mm, within the previous 12 months.
Visual Examination
For Visual Examination, the applicable acceptance criteria is specified in AWS D1.1 for Cyclically Loaded Non-
Tubular Table 6.1 and Tubular Connections see Table 9.16.
As defined in Table 7-1 below, each weld shall undergo 100% visual testing. Visual testing of welds shall be
performed in accordance with a visual inspection procedure approved by Company. ISO 17637 can be used
as a guideline.
Final visual testing shall always be performed in the final (heat treated) condition of the product.
When the selected NDE method cannot lead to conclusive examination results, an alternative method shall be
applied in addition.
Time delay before the NDE is performed shall be a minimum of 24 hours after cooling down to ambient
temperature. For TMCP material no delay is required.
7.3.2 Repairs
When non-acceptable discontinuities are repaired, the repaired area shall be 100% examined in accordance
with the requirements as stated for the original NDE methods as defined in the ITP.
7.3.3 Reporting
Full detailed reporting of conditions and results will be required to ensure traceability (Reporting by exemption
will not be permitted). Reports shall be made available within 12 hours after examination.
NDE reports stating compliance or otherwise with the criteria established in the inspection procedure are to
be issued.
Component identification
Location and extent of testing
Heat treatment status
Weld type, procedure and configuration
Surface condition
Surface temperature
Inspection procedure reference
Equipment used
Results showing size, position and nature of any defects repaired
Statement of final acceptability to established criteria.
NDE Methods
Alternative NDE methods may be accepted by Company, prior to use an alternative NDE method approval
shall be obtained via a CR.
RT shall be carried out using X-ray. However, Gamma-ray may be used instead of X-ray, subject to Company
approval. Where Gamma-ray is used, the use of Co-60 is not allowed.
Only image quality indicators (IQI’s) of the wire type may be used in accordance with ISO 19232-1 or ASTM
and shall be placed on source side where possible. The required sensitivity is 1.8% or better on source side.
Where source side IQI’s cannot be applied, film side may be used, the required sensitivity for film side IQI’s
shall be 1.6% or better.
For excavated repair areas where surface temperatures exceed 55°C, dry powder may be applied.
The use of prods is not permitted at all.
Page 24 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Page 25 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Unless otherwise approved by Company, the hardness survey shall be as indicated below. For each traverse
of indentations there shall be a minimum of 3 individual indentations in each zone of the weldment, i.e. weld
metal, GCHAZ (both sides), HAZ (both sides), parent metal (both sides) and buttering weld metal if applicable.
Page 26 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Page 27 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Page 28 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
Page 29 of 30
Allseas Engineering BV
Corporate Specification for Welding & Fabrication of primary structural components
AE-CS-WF-200 REV. A
(General note 1) In the actual construction, material exceeding the qualified quality may be used. Ruling is the toughness requirement after welding. For example: If the
welding procedure qualification is based on welding material with a guaranteed and certified CVN @ -20 °C it is allowed to use material with a guaranteed CVN testing
temperate of -40 °C or lower. This providing all other essential variables are met.
(General note 2) For all plate material in QT condition as well as for all material grades, in any delivery condition, with a SMYS of 355 MPa or higher and a guaranteed
CVN testing temperature of -40 °C it shall be checked and proven that the actual plate delivered will be the plate or plates as tested from which the results are given on
the applicable certificate.
(Guidance note 3) To accommodate a reduction in impact toughness after welding, it is recommended to purchase material with a certified CVN energy value of at least
50% higher than required after welding. Certificates , type EN10204-3.1 or EN10204-3.2 as required, shall be checked for the proper CVN testing temperature and
achieved CVN energy values. For this base material the guaranteed CVN test temperature and energy requirements, either guaranteed by the standard or specification,
shall as a minimum comply and in a longitudinal direction with the values to be achieved after welding and the specified material grade.
(Guidance note 4) The materials as given as example are, where possible, based on the European Standard EN 10025-3, EN10025-4 or EN10025-6 respectively applicable
for normalized, material manufactured according a thermo mechanically controlled process or quenched and tempered material. The EN 10025-3 and EN10025-4 are
materials specified for use in more heavily loaded parts than as specified in the more generic standard EN 10025-2 (non-alloyed structural steel) .
Where available also material in accordance with EN10225 ( Weldable structural steel for fixed offshore structures) or any other recognised national or international
standard may be used if the per table C-1 required CVN test temperature and minimum specified impact energy is guaranteed and certified by the selected grade.
The appropriate LR , or similar DNV/ABS/GL grades, grades may be used as an alternative as well even if not required.
Page 30 of 30