Document Title:
SAFETY AUDITS
REV
ROVSHAN OGUZ CLIENT
Note:
This document is a controlled copy of the Rovshan Oguz Safety Management System. Any copies made
of this document are uncontrolled and are therefore not subject to review and further approval.
This document will be reviewed on an annual basis, at a minimum, to ensure its continued
appropriateness and effectiveness.
Document Title:
SAFETY AUDITS
PURPOSE
The purpose of this procedure is to determine a method of performing audits on elements of the
safety arrangements in operation to ensure their:
RESPONSIBILITY
AUDIT SCHEDULE
Audits shall be carried out on a monthly basis in a selected area / activity and shall
review all safety elements in the selected area.
Such audits are termed Workplace Safety Audits (WSA) and area / activity selected shall
be determined relevant to the project activities at the time. Check list Rovshan Oguz SF
005 is designed to facilitate in audit process. However, auditors shall rely on experience,
common sense and observation to assess safety in the workplace.
AUDIT PERSONNEL
The Audit Personnel should consist of Management / Supervision and shop floor workers.
CONDUCT OF AUDIT
On arranging an audit the Auditor shall inform the relevant supervisor(s) of the date, time and
subject of the audit.
The auditors shall, by observation and interview with relevant personnel, establish
implementation and effectiveness of safety arrangements, where appropriate, utilizing checklists,
and shall note their findings both positive and negative.
In conducting the audit, any unsafe acts observed / discovered, shall immediately be brought to
the attention of the operative and supervisor for immediate remedy.
Document Title:
SAFETY AUDITS
AUDIT REPORTING
All safety audits shall be reported by filling out the appropriate Report Form.
DISTRIBUTION
All audit reports shall be retained on file by the Safety Coordinator, with a standard distribution
to:
Company Director
General Deputy Director
HSE Manager
Supervisors
Project Engineers
Auditors.
Any actions agreed to close out findings shall have a time for completion agreed by the person
nominated to action the close out.
The auditor is responsible for conducting follow up surveillance to ensure that the action has
been closed out. Such close out shall be recorded on the appropriate audit report held by the
Safety Coordinator.