Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

(Insert Project Name) (Insert Project Number)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 21
At a glance
Powered by AI
The key takeaways are that the document outlines the overall project management approach including organization, schedules, budgets, risks, quality, administration and stakeholder management.

The purpose of the Project Execution Plan is to ensure effective management of the project including coordination of activities, documentation of roles and responsibilities, and communication with stakeholders.

The main sections covered in the Project Execution Plan include project definition, organization, schedule management, budget/cost management, risk management, works activities, quality management, administration, and stakeholder management.

Project Execution Plan

[Insert Project Name]


[Insert Project Number]
Project Execution Plan

1
Project Execution Plan

Contents
1 Project/Programme Details 5

2 Document Details 5
2.1 Document distribution 5
2.2 Related documents 5

3 Project Definition 6
3.1 Project Introduction, background and history 6
3.2 Project objectives 6
3.3 Project Scope 6
3.4 Project Interfaces 6
3.5 Project Assumptions 6

4 Project organisation and authority 7


4.1 Project Governance 7
4.2 Key Roles and Responsibilities 7
4.3 Project responsibility matrix 8

5 Project schedule management 9


5.1 Programme Management Procedures 9
5.2 Programme Management Roles and Responsibilities 9
5.3 Programme Overview 9
5.3.1 Schedule hierarchy 9
5.3.2 Project milestones 9
5.3.3 Master Programme 9
5.4 Programme Update Procedure 9
5.5 Programme Baseline Review Procedure 10
5.6 Programme Progress Update and Review 10
5.7 Progress Reporting 10
5.8 Progress Meetings 10

6 Project Budget/Cost Management 11


6.1 Cost Management Procedures 11
6.2 Budget/Cost Management Roles and Responsibilities 11
6.2.1 Baseline budget 11
6.2.2 Cost management and control 11
6.2.3 Project cash flow 11
6.2.4 Management of commercially sensitive cost information 11
6.3 Budget update procedure 11
6.4 Budget/Cost Reporting 12
6.5 Budget/Cost Management Meetings 12

2
Project Execution Plan
6.6 Risk management procedures 13
6.7 Risk management roles and responsibilities 13
6.8 Risk management overview 13
6.8.1 Risk classification 13
6.8.2 Risk Register 13
6.9 Risk Reporting 14

7 Project Works Activities 14


7.1 Procurement procedures 14
7.2 Procurement roles and responsibilities 14
7.3 Procurement process overview 14
7.4 Procurement Reporting 15
7.5 Issues Management 15

8 Quality management 15
8.1 Quality management procedures 15
8.2 Quality management roles and responsibilities 15
8.3 Quality Management Requirements 16
8.3.1 General 16
8.3.2 Quality Standards 16
8.3.3 Lessons Learned 16
8.3.4 Scope Design Management 16
8.3.5 Tender Documentation 17
8.3.6 Quality Audit 17
8.3.7 Continuous Improvement 17

9 Project Administration 17
9.1 Project administration overview 17
9.2 Project administration roles and responsibilities 17
9.3 Document Control 18
9.3.1 Document numbering 18
9.3.2 Document storage and version control 18
9.4 Correspondence Control 18
9.4.1 Correspondence control system 18
9.4.2 Incoming correspondence 18
9.4.3 Outgoing correspondence 18
9.5 Meeting management 19
9.5.1 Meetings schedule 19
9.5.2 Meetings minutes 19
9.6 Staff Briefings 19
9.6.1 Staff induction 19
9.6.2 Staff training 20

3
Project Execution Plan
9.7 Software 20

10 Stakeholder Management 20
10.1 Stakeholder management overview 20
10.2 Stakeholder management roles and responsibilities 20
10.3 Identification and classification of Stakeholders 21
10.4 Stakeholder Management Phases 21
10.5 Stakeholder Management Process 21
10.6 Stakeholder Communications Plan 21
10.7 Stakeholder Commitments to date 21

4
Project Execution Plan

1 Project/Programme Details
Project/Programme Name
Project/Programme Sponsor
(SRO)
Project/Programme Manager
Group/Directorate
Start Date Completion Date

2 Document Details
Version Status Date Author/Editor Approved Details of changes
(Draft or (Sponsor)
Approved)

2.1 Document distribution


Name Location

2.2 Related documents


This Project Charter should be read in conjunction with the following documents:
 Stakeholder Communications Plan
 Work Breakdown Structure

3 Project Definition
3.1 Project Introduction, background and history

5
Project Execution Plan

3.2 Project objectives


Table 3.1 – Programme & Project Objectives
Objective Sub-objective Measures

3.3 Project Scope

3.4 Project Interfaces


The individual programme and project interfaces are as per those identified above.

3.5 Project Assumptions


Timely delivery of the project within budget is based upon the following key assumptions.
Assumptions

1.
2.

6
Project Execution Plan

4 Project organisation and authority


4.1 Project Governance
Figure 2.1 illustrates the overall governance structure for the project. Required approvals and approving
authorities are set out in table 4.1.
Figure 4.1: Overall governance structure
Table 4.1 - Required approvals and approving authorities
Approving authority Required approvals

4.2 Key Roles and Responsibilities


Tables 4.1 to 4.3 list the key personnel, advisors and third parties associated with the scheme and sets
out their roles and responsibilities.
Table 4.2 – Department of Finance Key project roles and responsibilities
Role Name Responsibilities

Table 4.3 - Project advisory team roles and responsibilities


Role Name Responsibilities

Table 4.3 sets out the key approval authorities in relation to the project. The list is in no way exhaustive
and all necessary checks should be carried out in relation to third party approvals prior to any project
work commencing.

Table 4.4 - Third party roles and responsibilities


Role Name Responsibilities
Project Execution Plan

Project organisation chart


Figure 4.1 illustrates the high level organisation structure of the DoF project management team.

4.3 Project responsibility matrix


Table 4.5 summarises the key high level project tasks and deliverables and the member of the project
management team responsible for each task or deliverable. It should be noted that existing line
management and staff in each of the Working Groups will be expected to take responsibility in each of
their functional areas with regard to the performance of these workgroup activities. The role of the project
team, with some exceptions, will not be to undertake the activities directly itself but to ensure that the
activities are planned, scheduled, resourced and implemented within the relevant line areas.
Project Management
Project Manager

Planning manager

Lead Press Office


Task
Office

Prepare, update and manage 


Project Programme at each
project phase
Prepare and update cost 
estimates at each project phase
Prepare, update and manage 
budget at each project phase and
annually
Record, report and manage 
project costs
Administer all contracts with 
suppliers, consultants and
service providers.
Prepare and manage Public 
Relations/Project Stakeholder
Communication Plan
Project Execution Plan

5 Project schedule management


5.1 Programme Management Procedures

5.2 Programme Management Roles and Responsibilities


The principal focus of the programme management process is vested in the roles and responsibilities
defined in Table 5.1 below:
Table 5.1 - Roles & Responsibilities
Role Name Responsibilities

5.3 Programme Overview

5.3.1 Schedule hierarchy


The project includes a hierarchy of sub-programmes, which can be rolled up into a master programme.
The programme hierarchy summarised in Figure 5.1.

5.3.2 Project milestones


The start and completion dates of key project tasks which constitute the baseline programme have been
defined in the Project Charter and these are summarised in Table 5.2 below:
Table 5.2 – Project Milestones
Key Task, Activity or Start Completio Key Dependencies Owner
Deliverable Date n Date

5.3.3 Master Programme


The Master Schedule is available at the following location:

5.4 Programme Update Procedure


Programme changes shall be adopted or rejected through the Project Change Management process
which is currently being finalised. Any programme change shall be analysed for wider impacts to the
project in terms of, risk, programme, cost and quality. All changes shall be ratified by the Steering
Committee.

5.5 Programme Baseline Review Procedure


Project Execution Plan
On a monthly basis, or where an event arises which has a significant impact on the project programme, a
baseline review by the Project Management Office will take place and, if appropriate to do so, the Master
Programme will be re-baselined. Proposals to re-baseline the Master Programme shall be submitted to
the Steering Committee for information.

5.6 Programme Progress Update and Review


The Master Programme will be reviewed on a regular basis (normally monthly) and actual progress will be
updated and reviewed against planned (baseline) progress. The results of this review will be reported in
the Project Monthly [Bi-monthly] Steering Committee Report.

5.7 Progress Reporting


A series of Progress Reports shall be produced throughout the project life-cycle to provide an up to date
and accurate report of actual progress against planned. Table 5.3 lists the progress reports that shall be
produced along with their frequency, circulation and owner:

Table 5.3 – Progress Reports


Report Title Frequency Circulation Owner

Reporting protocols are reviewed from time to time to reflect the changing needs of the project.

5.8 Progress Meetings


A series of Progress Meetings shall be held throughout the project life-cycle to provide a forum for
progress review, resolution of key progress issues and identification of key actions. Table 5.4 lists the
progress meetings that shall be held along with their frequency, key attendees and chairperson:
Table 5.4 – Progress Meetings
Meeting Title Frequency Attendance Chair Person
Project Execution Plan

6 Project Budget/Cost Management


6.1 Cost Management Procedures
The procedures for the development, management and update of the project budget are set out in the
following standards:

6.2 Budget/Cost Management Roles and Responsibilities


The principal focus of the cost management process is vested in the roles and responsibilities defined in
Table 6.1 below:
Table 6.1 – Cost Management Roles & Responsibilities
Role Name Responsibilities

6.2.1 Baseline budget

6.2.2 Cost management and control

6.2.3 Project cash flow

6.2.4 Management of commercially sensitive cost


information

Table 6.2 – Authority to view Commercially Sensitive Information


Information Authorised to view

6.3 Budget update procedure


The budget may be updated from time to time as the project develops. Budget updates may be required
as a result of:
 Increase / decrease of project overall scope;
 Transfer of scope from one part of the project to another;
 Change to the approved design;
 Realisation of an identified risk;
 Change in the contract condition;
 Realisation of an unforeseen event;
Project Execution Plan
 Modification in the project efficiency / inefficiency.
Budget changes shall be adopted or rejected through the Project Change Management process currently
being developed.
Budget changes which involve transfers between budget line items with no change to the overall total
budget and no reallocation of the risk or contingency line items must be approved by the Project
Manager. The Project Manager however cannot transfer budget from capital contributions approved by
the Sanctioning Authority).
Budget changes which involve reallocation of the risk line item must be approved by the [Insert Title].
Budget changes which involve reallocation of the contingency line item must be approved by [Insert Title].
Budget changes which result in an increase in the overall budget total as set out in the approved
Detailed / Final Business Case must be approved by the PPM Board.
On a quarterly basis, or where an event arises which has a significant impact on the project budget or
schedule, the Project Cash Flow Forecast will be updated and advised to the Project Manager.

6.4 Budget/Cost Reporting


The budget will be monitored on a monthly basis whereby actual, committed and forecast expenditure will
be reviewed against budget on a contract package by package basis. Project cost reports will be
generated from the DoF Management Information System. The results of this review will be reported in
the Project Monthly Report(s).
Table 6.3 – Budget / Cost Reports
Report Title Frequency Circulation Owner

6.5 Budget/Cost Management Meetings


A series of Contract Review Meetings shall be held throughout the project life-cycle to provide a forum for
cost, budget and claims review, resolution of key issues and identification of key actions. Table 6.4 lists
the meetings that shall be held along with their frequency, key attendees and chairperson:
Table 6.4 – Contract Review Meetings
Meeting Title Frequency Attendance Chair Person

6.6 Risk management procedures


Project Execution Plan
The procedures for the identification, assessment, and mitigation of project risks are set out in the
following standards:
 DoF Risk Management Standard

6.7 Risk management roles and responsibilities


The detailed project risk management structure, roles and responsibilities are defined in the Project Risk
Management Plan. The principal focus of the risk management process is vested in the roles and
responsibilities defined in Table 6.5 below:

Table 6.5 – Risk management Roles & Responsibilities


Role Name Responsibilities
Project Manager

Project Controls
Manager

Planning Manager
Risk Owners

Action Owners

Project Controls: Risk


6.8 Risk management overview

6.8.1 Risk classification


The project includes a hierarchy risk classifications, which can be rolled up into a single risk register as
summarised in Figure 6.1.

Figure 6.1: Risk classification

6.8.2 Risk Register


The Risk Register is key document which provides full details in relation to the description, classification,
assessment, and mitigation of all risks to the project. The development of the Risk Register is an iterative
process and requires sustained effort to fully capture, clear actions, action owners, completion dates and
modelling outputs. The register will remain as a live document, subject to regular amendment as new
risks are documented and current risks are managed out. Individual risks will be regularly reviewed with
the risk owners and the project team and updated as required. This process will provide an ongoing
assessment of the risks in the light of project development and the impact of control actions taken.

6.9 Risk Reporting


The Risk Register will be reviewed on a monthly basis and actual progress in implementing mitigation
actions will be reviewed against planned progress. The results of this review and a summary of the
status of the top 3 project risks will be reported in the Project Monthly Report.
Project Execution Plan

7 Project Works Activities


7.1 Procurement procedures
The procedures for the procurement of services, works and supplies for all projects are set out in the
following DoF Standards:
 DoF Procurement Policy and Procedures

7.2 Procurement roles and responsibilities


The principal focus of the procurement management process is vested in the roles and responsibilities
defined in table 7.1 below:

Table 7.1 – Enabling Works Roles & Responsibilities


Role Name Responsibilities

Project Controls: Risk

7.3 Procurement process overview

Contract strategy
The form of contract to be used for each Working group is set out in the Table 7.2.

Table 7.2 – Forms of Contract


Contract package Form of contract Comments

7.4 Procurement Reporting


Procurement activity each month will be reported in the Project Monthly Report.

7.5 Issues Management


In order to ensure the success of the project, all key issues will be identified and reported through the
reporting process. Where appropriate issues arise they will be assigned a priority according to the extent
Project Execution Plan
and severity of their impact. These issues to be assigned to the appropriate personnel to ensure their
resolution and take whatever actions are necessary. Issues will be proactively managed until resolved. An
Issues Register of the key issues, describing issue, possible impact, action and responsibility will be
maintained and reported at the monthly Project Governance meeting.

8 Quality management
8.1 Quality management procedures
The primary goal of the quality management process for this project is to ensure business and
governance needs have been adequately satisfied. Ongoing quality management involves careful
evaluation and monitoring of objectives and deliverables, together the assessment of stakeholder
feedback and the implementation of changes to project methodology or management as appropriate.
Quality Control will therefore be an integral element of the Project Governance Process and will be
considered by the Project Governance Board at its monthly meetings. Specifically
 The project will be managed in accordance with the governance structure outlined at 4.1 above.
Roles and responsibilities are also detailed.
 This document provides an outline of the overall project objectives. The key milestones and
deliverables of the project are outlined in more detail in the accompanying Project Schedule and
will be subject to approval of the Governance Board.
 In addition to the project/activity Quad Report that will form the basis for monthly reports a
consolidated Actions, Issues and Risk Log will be maintained which will provide oversight of all
such matters to the project Governance Board and team.
 The full time project team will meet on a weekly basis to discuss progress and identify issues
which need to be progressed.
 In relation to any system development, structured testing will take place including system test,
load & stress testing, user acceptance testing (UAT) and parallel run testing as appropriate.
 A change control process will be utilised to support agreed project objectives and scope.

8.2 Quality management roles and responsibilities


The principal focus of the quality management process is vested in the roles and responsibilities defined
in Table 8.1 below:

Table 8.1 – Quality Management Roles & Responsibilities


Role Name Responsibilities
Project Manager

Project
Management
Office

8.3 Quality Management Requirements


8.3.1 General
The quality requirements set out in this Project Execution Plan are applicable to the <name of project>
project in all phases. This section 8 describes essential aspects of quality on the project including:
Project Execution Plan
 Quality Standards
 Lessons learned
 Scope Design Management
 Tender Documentation
 Quality Audit
 Continuous Improvement

8.3.2 Quality Standards

8.3.3 Lessons Learned

Objective: Collect and communicate valuable lessons learned in different phases of the project from
previous projects both internal and external.
Continuously improve the quality of project management processes based on lessons learned and ensure
any strategy takes account of such lessons.

Responsibility: Project Manager

Quality Records: Lessons Learned database and reports

Related Procedure/Standard:
Lessons Learned Guidelines.

8.3.4 Scope Design Management


Objective: Manage the project design and design changes in a consistent and efficient manner. Provide
a Design Statement and fully document each stage of the design including production of Designer Risk
Assessments and all necessary categorised checks.
Responsibility: Project Engineer
Quality Records: Drawings; Specifications; Designer Risk Assessments; Minutes of design meetings;
Design Reports; Health & Safety File.
Related Procedure/Standard:

8.3.5 Tender Documentation

8.3.6 Quality Audit


The Quality Manager will perform internal and external quality audits at different stages of the Project.
Project Execution Plan
The scope of any quality audit may cover the overall quality management system, quality assurance
system and/or quality management system on the project or any individual process in relation to quality
management.

A Project Quality Audit Programme will be prepared by the Quality Manager and audit reports maintained
as quality records.

Objective: Ensure compliance with all project quality requirements

Responsibility: Quality Manager

Quality Records: Quality Audit Programme and internal and external Quality Audit Reports.

Related Procedure/Standard: [Insert]

8.3.7 Continuous Improvement


Continuous improvement is a principle of the project’s Quality Management criteria. The project quality
systems, plans and procedures will be reviewed regularly to ensure all lessons learned, suggestions and
discoveries from audits are taken into account to continuously improve the RPA and project quality
management processes and procedures.

9 Project Administration
9.1 Project administration overview
This section of the Project Execution Plan sets out the procedures for managing project administration
including: document control, correspondence control, meeting management, and staff briefings.

9.2 Project administration roles and responsibilities


The principal focus of project administration is vested in the roles and responsibilities defined in Table 9.1
below:

Table 9.1 – Project Administration Roles & Responsibilities


Role Name Responsibilities

9.3 Document Control


Project Execution Plan

9.3.1 Document numbering


The document numbering system on the project is generated automatically in the correspondence control
package, [Insert]. All documents issued externally are also accompanied by a transmittal generated
through [Insert].

9.3.2 Document storage and version control


Reports and other documents shall be stored on the RPA N: Drive. Reports are issued and received via
Expedition.

9.4 Correspondence Control

9.4.1 Correspondence control system


All Contract correspondence should be received and issued via Expedition. All scanned documentation
shall be attached to the electronic correspondence log by the Document Controller. It should be noted all
contractual correspondence should be received and issued in hard copy following the procedures within
the <insert name of this project> Document Control Procedure. Documents, drawings and sketches being
submitted by post must be submitted in hard and CD copy format.
All Project Team members should obtain access onto the Expedition system and go through the training
related to the software; this training is provided by RPA and should be requested via the Document
Controller. As a safeguard all incoming correspondence, once logged into Expedition, should also be e
mailed to team members on the distribution list.

9.4.2 Incoming correspondence


Received letters shall be recorded in Expedition by the document controller. All received letters are to be
reviewed and distributed or approved by the Project Manager.

9.4.3 Outgoing correspondence


Letters should be generated through Expedition, the letter printed on RPA headed paper, signed by the
Project Manager, scanned and sent to the Document Controller for issue.

9.5 Meeting management

9.5.1 Meetings schedule


Table 9.2 sets out the regular meetings held on the project.
Table 9.2 – Regular Project Meetings
Project Execution Plan
Meeting Chair Purpose Frequency / Output
Timing

9.5.2 Meetings minutes


Minutes should be recorded for all meetings. Minutes generated within Expedition record actions as new,
old or closed. All minutes, whether generated in expedition or not, should be printed on RPA headed
paper, signed, scanned and given to the Document Controller for issue.

9.6 Staff Briefings

9.6.1 Staff induction


Induction briefings to all new staff working on the project shall be conducted by the relevant line manager.
The content of this induction shall include:
 Overview of the suite of procedural and project documents
 An explanation on the contents within the Project Execution Plan
 Project scope
 Organisation, roles and responsibilities
 Document hierarchy
 Change control
 Document control

9.6.2 Staff training


Training courses that are required for the project:
 Insert
Project Execution Plan

9.7 Software
Table 9.3 describes software packages which have been authorised and licensed for use on the Project,
including versioning.
Table 9.3 – Software Usage
Function Approved software package Version

10 Stakeholder Management
10.1 Stakeholder management overview

10.2 Stakeholder management roles and responsibilities


The key stakeholders and their respective liaison manager are provided in Table 10.1 below:

Table 10.1 – Stakeholder Management Roles & Responsibilities


Stakeholder Lead Role

10.3 Identification and classification of Stakeholders


The stakeholder management process commences with identification of all stakeholders that can affect,
or be affected by the project, directly or indirectly. During the lifetime of the project stakeholders may
come and go depending on the activities at any one time.
In identifying the stakeholders on the project, the following questions were considered:
 Who is affected by the plan?
Project Execution Plan
 Who has an interest in the plan and its outcomes?
 Who can affect the plan’s adoption, implementation or execution?
 Who has expressed an opinion on the stakeholder issues involved?
 Who, because of demographic or other characteristics, ought to care or might care about the
plan?

10.4 Stakeholder Management Phases


All projects are split into distinct phases. This project is currently moving from the [insert] phase into the
[insert] phase.

10.5 Stakeholder Management Process


Any person looking to liaise with a stakeholder must firstly liaise with the person identified in the table
above to ensure that the particular stakeholder is being managed effectively. Issues raised during
stakeholder liaison must be fed back to the responsible person to ensure all issues are captured.
The responsible person co-ordinates all activities in relation to their stakeholder and must record all
stakeholder issues. Issues involving changes are dealt with using the Change Management Procedure.

A stakeholder register will be kept that can be accessed by all relevant members of the Project Team,
and it is the responsibility of all team members to keep the register updated as consultation progresses by
forwarding any updated information to the appointed editor which requires inclusion in the Register. The
project will maintain a register of all commitments made to Stakeholders. The register shall track
progress in implementing the commitments.
Regular internal meetings will be convened between the persons responsible for stakeholder liaison to
discuss and agree the best course of action for each stakeholder where applicable. Stakeholder issues
will also feed into project development through the series of meetings.

10.6 Stakeholder Communications Plan


The Project has developed a Stakeholder Communications Plan; the purpose of this plan is to ensure
effective communications with stakeholders in relation to the development and implementation of plans
for the delivery this project.
 The plan covers the period from

10.7 Stakeholder Commitments to date


 Insert

You might also like