(Insert Project Name) (Insert Project Number)
(Insert Project Name) (Insert Project Number)
(Insert Project Name) (Insert Project Number)
1
Project Execution Plan
Contents
1 Project/Programme Details 5
2 Document Details 5
2.1 Document distribution 5
2.2 Related documents 5
3 Project Definition 6
3.1 Project Introduction, background and history 6
3.2 Project objectives 6
3.3 Project Scope 6
3.4 Project Interfaces 6
3.5 Project Assumptions 6
2
Project Execution Plan
6.6 Risk management procedures 13
6.7 Risk management roles and responsibilities 13
6.8 Risk management overview 13
6.8.1 Risk classification 13
6.8.2 Risk Register 13
6.9 Risk Reporting 14
8 Quality management 15
8.1 Quality management procedures 15
8.2 Quality management roles and responsibilities 15
8.3 Quality Management Requirements 16
8.3.1 General 16
8.3.2 Quality Standards 16
8.3.3 Lessons Learned 16
8.3.4 Scope Design Management 16
8.3.5 Tender Documentation 17
8.3.6 Quality Audit 17
8.3.7 Continuous Improvement 17
9 Project Administration 17
9.1 Project administration overview 17
9.2 Project administration roles and responsibilities 17
9.3 Document Control 18
9.3.1 Document numbering 18
9.3.2 Document storage and version control 18
9.4 Correspondence Control 18
9.4.1 Correspondence control system 18
9.4.2 Incoming correspondence 18
9.4.3 Outgoing correspondence 18
9.5 Meeting management 19
9.5.1 Meetings schedule 19
9.5.2 Meetings minutes 19
9.6 Staff Briefings 19
9.6.1 Staff induction 19
9.6.2 Staff training 20
3
Project Execution Plan
9.7 Software 20
10 Stakeholder Management 20
10.1 Stakeholder management overview 20
10.2 Stakeholder management roles and responsibilities 20
10.3 Identification and classification of Stakeholders 21
10.4 Stakeholder Management Phases 21
10.5 Stakeholder Management Process 21
10.6 Stakeholder Communications Plan 21
10.7 Stakeholder Commitments to date 21
4
Project Execution Plan
1 Project/Programme Details
Project/Programme Name
Project/Programme Sponsor
(SRO)
Project/Programme Manager
Group/Directorate
Start Date Completion Date
2 Document Details
Version Status Date Author/Editor Approved Details of changes
(Draft or (Sponsor)
Approved)
3 Project Definition
3.1 Project Introduction, background and history
5
Project Execution Plan
1.
2.
6
Project Execution Plan
Table 4.3 sets out the key approval authorities in relation to the project. The list is in no way exhaustive
and all necessary checks should be carried out in relation to third party approvals prior to any project
work commencing.
Planning manager
Reporting protocols are reviewed from time to time to reflect the changing needs of the project.
Project Controls
Manager
Planning Manager
Risk Owners
Action Owners
Contract strategy
The form of contract to be used for each Working group is set out in the Table 7.2.
8 Quality management
8.1 Quality management procedures
The primary goal of the quality management process for this project is to ensure business and
governance needs have been adequately satisfied. Ongoing quality management involves careful
evaluation and monitoring of objectives and deliverables, together the assessment of stakeholder
feedback and the implementation of changes to project methodology or management as appropriate.
Quality Control will therefore be an integral element of the Project Governance Process and will be
considered by the Project Governance Board at its monthly meetings. Specifically
The project will be managed in accordance with the governance structure outlined at 4.1 above.
Roles and responsibilities are also detailed.
This document provides an outline of the overall project objectives. The key milestones and
deliverables of the project are outlined in more detail in the accompanying Project Schedule and
will be subject to approval of the Governance Board.
In addition to the project/activity Quad Report that will form the basis for monthly reports a
consolidated Actions, Issues and Risk Log will be maintained which will provide oversight of all
such matters to the project Governance Board and team.
The full time project team will meet on a weekly basis to discuss progress and identify issues
which need to be progressed.
In relation to any system development, structured testing will take place including system test,
load & stress testing, user acceptance testing (UAT) and parallel run testing as appropriate.
A change control process will be utilised to support agreed project objectives and scope.
Project
Management
Office
Objective: Collect and communicate valuable lessons learned in different phases of the project from
previous projects both internal and external.
Continuously improve the quality of project management processes based on lessons learned and ensure
any strategy takes account of such lessons.
Related Procedure/Standard:
Lessons Learned Guidelines.
A Project Quality Audit Programme will be prepared by the Quality Manager and audit reports maintained
as quality records.
Quality Records: Quality Audit Programme and internal and external Quality Audit Reports.
9 Project Administration
9.1 Project administration overview
This section of the Project Execution Plan sets out the procedures for managing project administration
including: document control, correspondence control, meeting management, and staff briefings.
9.7 Software
Table 9.3 describes software packages which have been authorised and licensed for use on the Project,
including versioning.
Table 9.3 – Software Usage
Function Approved software package Version
10 Stakeholder Management
10.1 Stakeholder management overview
A stakeholder register will be kept that can be accessed by all relevant members of the Project Team,
and it is the responsibility of all team members to keep the register updated as consultation progresses by
forwarding any updated information to the appointed editor which requires inclusion in the Register. The
project will maintain a register of all commitments made to Stakeholders. The register shall track
progress in implementing the commitments.
Regular internal meetings will be convened between the persons responsible for stakeholder liaison to
discuss and agree the best course of action for each stakeholder where applicable. Stakeholder issues
will also feed into project development through the series of meetings.