Scheduling 3
Scheduling 3
Scheduling 3
Detailed Estimate`
Baseline Budget
Preliminary
Cost Estimate Cost Control
Project Controls
Detailed Schedule
Baseline Schedule
1
2 1
3 2
4 3
5 4
6 5
7 6
8 7
9 8
10 9
10
11 11
12 12
13
2. Start/finish b. Baseline
Baseline:
Total cost of activities A and B =
$200 + 1 laborer * 2 hours * $40/hr = $ 280 each
Total cost of activity C =
$2,200 + 3 laborers * 3 hours * $40/hr = $2,560
Total cost for project = 2 * $280 + $2,560 = $3,120
Total man-hours for project = 2 + 2 + 3*3 = 13 man-
hours
Total duration for project = 2 + 3 = 5 hours
Summer 2020 Construction Management, CCE4031 - Dr. Saleh Mubarak 16
Percent Complete Example: Update
Activities A and B are now complete but the doors actually cost the
contractor $230 and took an extra hour for installation, i.e. 3 man-
hours (one laborer for 3 hours); each
Activity C has not yet started, no change is expected for cost or
duration.
What is the percent complete of this work package?
Data date
Actual
A
Baseline
Actual
B
Baseline
Updated
C
Baseline
1 2 3 4 5 6 hours
= 6+9 = 15
Percent Complete = 6 / 15 = 40%
B. Baseline:
Percent Complete = 4 / 13 = 30.8%
Actual:
Percent Complete = 3 / 6 = 50% A
Baseline: C
Actual:
A
Baseline: 1 2 3 4 5 6 Hours
Percent Complete = 5 / 7 = 71.4% Legend
Completed
Future
Baseline
CMU 40,000 28% 11,900 11,200 10,000 -700 1200 0.6 0.94 1.12 -2500 2.14
$ +
II I
- +
Time
III IV
Scheduling
compression. It further IV.
Materials management
classified them by V.
Construction work
project phase or VI.
management
function:
VII. Field labor management
VIII. Start-up phase
Path 2
Path 3
Path 4
Path 5
Path 6
Path 7
Path 8
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Path 2
Path 3
Path 4
Path 5
Path 6
Path 7
Path 8
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Path 2
Path 3
Path 4
Path 5
Path 6
Path 7
Path 8
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Path 2
Path 3
Path 4
Path 5
Path 6
Path 7
Path 8
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Path 2
Path 3
Path 4
Path 5
Path 6
Path 7
Path 8
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Schedule
compression
Schedule
compression
Schedule
compression
A C PF
5 8
0, 5 5, 13 13, 17 17, 24 25
F G
Path Length
4 7
14, 18 18, 25
ABEH 24
5, 16
ACEH 25
D
11 ACFH 23
7, 18 ACFG 24
ADG 23
Summer 2020 Construction Management, CCE4031 - Dr. Saleh Mubarak 72
Linear Project Crashing Overhead per day = $120
Days Cut 0
Project Duration 25
Increased cost $0
Direct Cost $4,950
Overhead Cost $3,000
Total Cost $7,950
Days Cut 0 1
Project Duration 25 24
Increased cost $0 $40
Direct Cost $4,950 $4,990
Overhead Cost $3,000 $2,880
Total Cost $7,950 $7,870
Days Cut 0 1 1
Project Duration 25 24 23
Increased cost $0 $40 $50
Direct Cost $4,950 $4,990 $5,040
Overhead Cost $3,000 $2,880 $2,760
Total Cost $7,950 $7,870 $7,800
Days Cut 0 1 1 1
Project Duration 25 24 23 22
Increased cost $0 $40 $50 $100
Direct Cost $4,950 $4,990 $5,040 $5,140
Overhead Cost $3,000 $2,880 $2,760 $2,640
Total Cost $7,950 $7,870 $7,800 $7,780
Days Cut 0 1 1 1 1
Project Duration 25 24 23 22 21
Increased cost $0 $40 $50 $100 $140
Direct Cost $4,950 $4,990 $5,040 $5,140 $5,280
Overhead Cost $3,000 $2,880 $2,760 $2,640 $2,520
Total Cost $7,950 $7,870 $7,800 $7,780 $7,800
Least Cost
Days Cut 0 1 1 1 1 1
Project Duration 25 24 23 22 21 20
Increased cost $0 $40 $50 $100 $140 $165
Direct Cost $4,950 $4,990 $5,040 $5,140 $5,280 $5,445
Overhead Cost $3,000 $2,880 $2,760 $2,640 $2,520 $2,400
Total Cost $7,950 $7,870 $7,800 $7,780 $7,800 $7,845
Least Cost
Path Duration
ABEH 24 24 23 22 21 20
ACEH 25 24 23 22 20 19
ACFH 23 22 22 21 20 19
ACFG 24 23 23 22 21 20
ADG 23 23 23 22 21 20
Days Cut 0 1 1 1 1 1 1
Project Duration 25 24 23 22 21 20 19
Increased cost $0 $40 $50 $100 $140 $165 $225
Direct Cost $4,950 $4,990 $5,040 $5,140 $5,280 $5,445 $5,670
Overhead Cost $3,000 $2,880 $2,760 $2,640 $2,520 $2,400 $2,280
Total Cost $7,950 $7,870 $7,800 $7,780 $7,800 $7,845 $7,950
Least Cost
Path Duration
ABEH 24 24 23 22 21 20 19
ACEH 25 24 23 22 20 19 19
ACFH 23 22 22 21 20 19 19
ACFG 24 23 23 22 21 20 19
ADG 23 23 23 22 21 20 19
Days Cut 0 1 1 1 1 1 1 1
Project Duration 25 24 23 22 21 20 19 18
Increased cost $0 $40 $50 $100 $140 $165 $225 $270
Direct Cost $4,950 $4,990 $5,040 $5,140 $5,280 $5,445 $5,670 $5,940
Overhead Cost $3,000 $2,880 $2,760 $2,640 $2,520 $2,400 $2,280 $2,160
Total Cost $7,950 $7,870 $7,800 $7,780 $7,800 $7,845 $7,950 $8,100
Least Cost Least Time
Summer 2020 Construction Management, CCE4031 - Dr. Saleh Mubarak 87
Example Solution: The Paths. Crashing
cycle #7: Act’s. G and H; by 1 day,
each
Path Duration
ABEH 24 24 23 22 21 20 19 18
ACEH 25 24 23 22 20 19 19 18
ACFH 23 22 22 21 20 19 19 18
ACFG 24 23 23 22 21 20 19 18
ADG 23 23 23 22 21 20 19 18
$8,100
$8,050
$8,000
Total Cost
$7,950
$7,900
$7,850
$7,800
$7,750
16 18 20 22 24 26 28
Project Duration
Days Cut 0 1 1 1 1 1 1 1
Project Duration 25 24 23 22 21 20 19 18
Increased cost $0 $40 $50 $100 $140 $165 $225 $270
Direct Cost $4,950 $4,990 $5,040 $5,140 $5,280 $5,445 $5,670 $5,940
Overhead Cost $5,000 $4,800 $4,600 $4,400 $4,200 $4,000 $3,800 $3,600
Total Cost $9,950 $9,790 $9,640 $9,540 $9,480 $9,445 $9,470 $9,540
Least Cost Least Time
Optimize
for best
results * Durations
Manipulate Durations* change due to
both user’s
manipulation
(crew
configuration,
work hours, etc.)
and impact of
new “productivity
zone”
0, 10 3, 11 4, 18 14, 19 15, 22
1 1 1 1
Excavating
Sub-base
Lay Concrete
Backfill
Compact
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Delays
Severe weather, failure to make timely decisions,
interference in the work
Delays by other parties (owner, A/E, lender,
government) such as materials delivery, testing
and inspections
Unexpected / differing site / underground
conditions
Changes resulting from cost-cutting
adjustmentsConstruction Management, CCE4031 - Dr. Saleh Mubarak 116
Summer 2020
What Situations Trigger Changes?
Change orders are generally issued if a change
is due to no fault of the contractor.
The contractor should keep careful records to
ensure full reimbursement for any changes.
Communication:
A verbal or written message
A process by which information is exchanged
between individuals through a common system of
symbols, signs, or behavior
Plural but singular or plural in construction:
a technique for expressing ideas effectively (as in
speech)
the technology of the transmission of information
(as by print or telecommunication)
Summer 2020 Construction Management, CCE4031 - Dr. Saleh Mubarak 176
Communication: Meaning
Communication is a social activity requiring the
coordinated effort of two or more individuals
Mere talk to produce sentences does not constitute
communication
Requires knowledge and ability (to communicate)
Both speaker and hearer must actively respond to
what transpires by signaling involvement, either
directly through words or indirectly through gestures
or similar nonverbal signals