Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

EXERCISE #1 - PM Lab - 1Q2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Exercise 1

Getting Started with a Project: Project Activities and Network Representation

Discussion:
A Project is a temporary endeavor, having a defined beginning and end (usually constrained by date, but can be
by funding or deliverable), undertaken to meet particular goals and objective, usually to bring about beneficial
change or added value. The temporary nature of projects stands in contrast to business or operations, which are
repetitive, permanent or semi-permanent functional work to produce products or services.
Some examples of projects are; (a) writing, producing, deploying books; manuals; films, (b) software
development and distribution, (c) research and development, (d) construction work etc. For engineering students
project can be a construction and development of a study such as feasibility, marketing and practicum or thesis.
The goal of every project is success, and a successful project is a product of well-planned and properly
implemented activities. Therefore, in every project we have what we call Work Breakdown Structure (WBS). The
Work Breakdown Structure is a tree structure, which shows a subdivision of effort required to achieve an
objective; for example a program, project, and contract. The WBS may be hardware, product, service, or service
oriented. In a project of contract, the WBS is developed by starting with:
§   The End Objective and
§   Successively subdividing it into manageable components in terms of size, duration, and responsibility
(e.g., systems, subsystems, components, tasks, subtasks, and work packages) which include all steps
necessary to achieve the objective.
After the construction of WBS, network diagram can be formed to determine the flow of the project and to see if
all the activities are accurately orchestrated.
A network consists of a set of nodes linked by arcs (by branches). The figure below is a simple of network.

1   3   5   6  

7   8  

2   4  

Figure 1. Sample Network Diagram: Activity on Node


In network representation, each activity of a project is represented by an arc pointing in the direction of progress
in the project. The network nodes establish the precedence relationships among the different activities of the
project. In constructing a network we should consider the following rules;
1.   Each activity is represented by one, and only one, arc.
2.   Each activity must be identified by two distinct nodes and,
3.   To maintain the correct precedence relationships, the following questions must be answered as each
activity is added to the network; (a) what activities must immediately precede the current activity? And
(c) What activities must occur concurrently with the current activity?
Objectives: At the end of the activity students will be able to;
Ø   Familiarize with different project components and stages.
Ø   Construct work breakdown structure (WBS).
Ø   Transform work breakdown structure to network diagram.
Ø   Construct Network Diagram or Gantt chart in Microsoft Excel.

Example 1.
Maurice Publishing Inc. has a contract with Joan who authored the manual “Basics of Project Management for
Industrial Engineering and Engineering Management Students”. The simplified activities associated with the
production of the manual are given below. We are asked to develop the associated network for the project.
WBS Predecessor (s) Duration (Weeks)

A.   Manuscript proofreading by editor ---------- 3


B.   Sample pages prepared by ---------- 2
typesetter
C.   Manual cover design ---------- 4
D.   Preparation of network for book ---------- 3
figures
E.   Author’s approval of edited A,B 2
manuscript and sample pages
F.   Manual typesetting E 2

G.   Author checks typeset pages F 2

H.   Author checks artwork D 1

I.   Production of printing plates G,H 2

J.   Manual production and binding C,I 4


Steps in Constructing Network Diagram in Microsoft Excel

Step 1. Open a Microsoft Excel worksheet and copy the data in the figure below;

Figure 2. Microsoft Excel snapshot for the example’s WBS

Step 2. Create node and arc by clicking the clip art then select shapes click the circle icon for node and arrow for
branches.

1  

Figure 3. Snapshot of Circle figure to represent node.


Step 3. Continue doing the diagram until you finish the desired output as shown below;

Figure 4. Nodes and arcs for example 1.

Step 4. Do not forget to indicate the WBS letter code and duration by using text box (refer figure below)

Figure 5. Snapshot on how to indicate duration and letter code.


Figure 6. Final network represenatation for example 1.

Questions:
1.   What interpretation can we construct out of figure 5?
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________

2.   What are the advantages you have had while constructing the network representaion in Microsoft Excel?
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________

3.   Cite some recommendations.


____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________
Exercise 1a. Getting started with a Project: Project Activities and Network Representation

Name:__________________________________________ Date:_________________________
Course/Section:__________________________________ Rating:________________________

Below are the activities for constructing a new house. Develop the associated preoject network. Do not forget to
save your work in laboratory files.
Activity Predecessors (s) Duration (days)
A.   Clear Site ---------- 1
B.   Bring utilities to site ---------- 2
C.   Excavate A 1
D.   Pour foundation C 2
E.   Outside Plumbing B,C 6
F.   Frame House D 10
G.   Do electric wiring F 3
H.   Lay floor G 1
I.   Lay roof F 1
J.   Inside plumbing E,H 5
K.   Shingling I 2
L.   Outside sheating F,J 1
insulation
M.  Install windows and F 2
outside doors
N.   Do brick work L,M 4
O.   Insulate walls and G,J 2
ceiling
P.   Cover walls and O 2
ceiling
Q.   Insulate roof I,P 1
R.   Finish interior P 7
S.   Finish exterior I,N 7
T.   Landscape S 3
Draw  the  network  representation  (in  landscape  form)  for  exercise  1b.  
Exercise 1b. Getting started with a Project: Project Activities and Network Representation
Name:__________________________________________ Date:_________________________
Course/Section:__________________________________ Rating:________________________

Instruction: Think of a project you have done or you will do. Then do the following;
(a)   What is the project? ________________________________________________________
(b)  Complete the given table below, extend the table if the space provided is not enough.

Activity Predecessor (s) Duration

On a separate sheet construct the network diagram manually then create it in Microsoft Excel and do not forget
to save your work in your laboratory file.  

You might also like