Lesson-4-scheduling
Lesson-4-scheduling
Lesson 1:
Learning Outcomes:
On completion of this lesson a learner should:
1. Calculate the project completion date
2. Predict and calculate the cash flow
3. Improve work efficiency:
4. Draw both the arrow network and the node network for the
project:
5. Apply the PERT/CPM
Figure 4.0
Basic Networks
NETWORK ANALYSIS SYSTEMS
A network is a logical and chronological, graphic representation of
the activities (and events) composing a project.
Two types of network diagrams
Arrow networks were more popular in the 1960s and 1970s, and
then precedence diagrams (an advanced form of node diagrams)
became the choice for network scheduling.
Network scheduling has revolutionized the management of construction
projects.
ARROW NETWORK
Arrow networks are also called the arrow diagramming method (ADM),
activity on arrow (AOA) network, or the I-J method (because activities are
defined by the from node, I, and the to node, J
Example 1 A
Figure 4.1 B
D method because each
Notation: The arrow diagram is also called the I–J
activity is identified by the two nodes that define its start
and end. For example, activity A is also known as 10–20, B as 20–30, C as
20–40, and so on.
Example 2: Draw the arrow network for the project given next.
Activity IPA
A -
B A
C A
D B
E B,C
F C
Solution:
The solution requires two dummy activities (or simply dummies) (Figure 4.2)
B D
30
A D1
10 20 D2 50 E 60
A C 40 F
Figure 4.2
General Steps
Step 10. Find project completion time variance and conduct probability
analysis, such as the probability of meeting a customer target
completion time, under the condition of uncertainty in activity times.
Early Finish (EF) -The earliest time an activity can be finished and
is equal to the early start plus the duration. EF= ES+D
Late Finish (LF) -The latest time an activity can be finished.
Late Start (LS) -The latest time an activity can be started without
delaying the completion date of the project.
LS=LF-D
Total Float (TF) -The amount of time an activity may be delayed
without delaying the completion date of the project. TF=LF-EF=
LS-ES
This example is more complicated than the previous ones, requiring eight
dummies, as shown in Figure 4.3. However, real projects with hundreds
or thousands of activities, are far more complicate.
Example: Finish-to-Start Activity Relationships
Calculate the start, finish, and float for each activity in the
following CPM precedence network diagram.
Activity C and E have an F-S relationship with a 5-day negative lag.
The 5-day negative lag is equivalent to a 5-day lead, which means the
finish of Activity C must occur no later than 5 days after the start of
Activity E, given by the relationship: EFc, ≤ ES, + 5.
The use of negative lags is not recommended because they lead to
much confusion with respect to the meaning of the relationship and the
schedule as discussed in the following paragraphs.
The following diagram and accompanying table show the early and
late start, early and late finish, and the total and free float for each
activity.
Solution:
For activity C the calculations for total float and free float are:
.
1. What does a node mean in an arrow diagram?