Central Business District CBD EAST - Phase 1 of The New Administrative Capital
Central Business District CBD EAST - Phase 1 of The New Administrative Capital
Central Business District CBD EAST - Phase 1 of The New Administrative Capital
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including Conditions of Contract and
Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes piping, special-duty valves, and hydronic specialties for hot-water
heating, chilled-water cooling, and condenser water systems; makeup water for these
systems; blowdown drain lines; and condensate drain piping.
B. Related Sections:
1.3 STANDARDS
A. The following standards are referred to in this section as alternative equivalent standards to
those specified in this section:
1.4 [DEFINITIONS
B. Painting inspector: BSC chemical, certified painting inspector (BGAS CSWIP) or (NACE)
level II and shall have minimum 10 years’ experience.
C. NDT inspector: NDT personal certified as level II minimum in the NDE methods utilized.
1.5 SUBMITTALS
A. Quality Manual and Quality plan for Contractor and its related Sub Contractors including:
B. Shop Drawings: Detail fabrication of piping Isometric & spools, pipe anchors, hangers,
special pipe support assemblies, alignment guides, expansion joints and loops, and their
attachment to the building structure. Detail location of anchors, alignment guides, welding
map and expansion joints and loops.
G. Release for shipment for ERW, Seam weld & spiral weld pipe and Equipment.
K. Field Test Reports: Written reports of tests specified in Part 3 of this Section. Include the
following:
A. Retain option below if section 1.4 is retained or if required for special projects Surface
preparation for all steel pipes: Shot blasting to SA 2.5 and then immediate application of 150
µm polyamide epoxy paint to be confirmed for proper bonding with pre-insulated pipes
B. Welding: Qualify processes and operators according to the ASME Boiler and Pressure
Vessel Code: Section IX, "Welding and Brazing Qualifications" and ASME B31.1 or
ASME B31.9 as applicable. Welders shall be certified for the type of pipe material specified,
welding process and position of welds required during fabrication of the piping. Welder’s
Qualification Test to be performed on site and attended by Contractor Welding Inspectors,
Third Party and Engineer prior to commencing piping fabrication.
C. Non destructive examination shall be performed to all pipe welds in accordance to ASME
B31.1 or ASTM B31.9 as applicable. A Non destructive test shall perform the tests and
submit the related reports after getting the approval and stamping of third party inspection
company, prior prequalification approval should be obtained from Engineer on NDT &
Third Party Inspection both companies.
D. All welds shall be identified by the welder’s mark and a sequence number. The Contractor
shall employ a Certified Welding Inspector (CWI) or CSWIP 3.1, NDT personal certified as
Level 2 minimum in the NDE methods utilized (independent of the contractor fabricating or
installing the piping) to visually examine all welds in accordance with inspection and
examination requirements of ASME B31.1 or ASME B31.9 as applicable. Any welds
failing the visual or NDE inspection shall be ground out or cutout, re-welded and radio
graphed at the expense of the Contractor. The CWI shall submit a written report signed and
stamped from the approved third party for each weld to the Engineer.
E. Additionally, 5% of all fitting, flange and Butt joint welds shop or field or as per ASME
requirements, minimum of 5% of Butt Joints welds, randomly selected by the Engineer,
shall be radio graphed at the expense of the contractor. The certified welding inspector shall
examine the films and provide a written report to the Engineer. All welds not meeting the
requirements of ASME B31.1 or ASME B31.9 latest edition as applicable will be ground
out, re-welded and re-radio graphed at the expense of the Contractor. If any 10% of the
randomly selected radio graphed welds fail, all welds in the piping will be radio graphed and
repaired at the expense of the contractor.
F. High rejection rate welders (with rejection rate of 25%or more) will be revoked from the
project
H. ASME Compliance: Comply with ASME B31.1 and ASME B31.9 as applicable for
materials, products, and installation. Safety valves and pressure vessels shall bear the
appropriate ASME label. Fabricate and stamp air separators and expansion tanks to comply
with the ASME Boiler and Pressure Vessel Code, Section VIII, Division 1.
I. All pre-insulated piping systems shall be completely sealed and waterproof, and they shall
be capable of allowing sufficient movement for thermal expansion and contraction. Each
assembly shall be factory-designed for the specific service medium, temperature, and
pressure. Expansion loops, expansion joints, anchors, and guides shall be furnished and
installed to provide a trouble-free system and avoid stress on any equipment.100% Welding
joints of Pre-insulated piping spools shall be tested by RT , RT films shall interpretation by
approved 3rd party
J. The pre-insulated pipe manufacturer shall comply with the inspection requirements of BS
EN 253 or approved equal.
4. Full Time Factory trained field technical assistance & supervision shall be provided
by pre-insulated manufacturer during installation.
5. Representative's daily written reports to the Resident Engineer: Present the original of
each report on the day it is prepared. The report shall be signed by the manufacturer's
representative. The report shall state whether or not the condition and quality of the
materials used and the installation of the system is in accordance with the plans,
specifications, and published standards of the manufacturer, and is satisfactory in all
respects. If anything connected with the installation is unsatisfactory, the report shall
state that corrective action has been taken or shall contain the manufacturer's
recommendations for corrective action. The report shall cover any condition that
could result in an unsatisfactory installation. The representative shall take prompt
action to return to the factory all damaged and defective material, and shall order
prompt replacement of such material.
6. On completion of the installation, the Contractor shall deliver to the Resident
Engineer a certificate from the manufacturer that the installation is in compliance
with all installation recommendations and warranty requirements of the manufacturer.
1.7 COORDINATION
A. Coordinate layout and installation of hydronic piping and suspension system components
with other construction, including light fixtures, HVAC equipment, fire-suppression-system
components, and partition assemblies.
C. Coordinate piping installation with roof curbs, equipment supports, and roof penetrations.
D. Coordinate pipe fitting pressure classes with products specified in related Sections.
E. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into base..
F. Coordinate installation of pipe sleeves for penetrations through exterior walls and floor
assemblies. Coordinate with requirements for firestopping specified in Section "Penetration
Firestopping" for fire and smoke wall and floor assemblies.
B. Products shall be carefully stored in a manner that will prevent damage and in an area that is
protected from the elements.
C. End caps weather supplied by the piping manufacturer or fabricated by the contractor are to
be placed at the ends of the piping sections to keep debris and reptiles from entering inside
the pipe while it is placed in storage.
D. Prefabricated sections of the pre-insulated pipe are to be handled per the manufacturer’s
recommendations or instructions.
E. All pre-insulated pipes shall be protected from direct sunlight while transported or stored.
A. Water Treatment Chemicals: Furnish sufficient chemicals for initial system startup and for
preventive maintenance for one year from date of Substantial Completion.
1.10 WARRANTY
PART 2 - PRODUCTS
A. General: Refer to Part 3 "Piping Applications" Article for applications of pipe and fitting
materials.
A. Minimum steel pipe size recommended for hydronic piping is NPS 3/4 (DN 20).
B. Chilled Water (above ground), Heating Water (above ground), Condenser Water (above
ground), and Vent Piping:
1. Steel pipes DN 50 and smaller: ASTM A53/A53M Grade B, ERW, Schedule 40 with
threaded ends.
2. Steel pipes DN 50 and up to DN 250: ASTM A53/A53M Grade B or ASTM
A106/A106M Grade B, ERW, Schedule 40 with beveled ends for butt welding
downstream the heat exchanger and could be accepted as roll Grooved ends for
Coupled Joints.
3. Steel pipes DN 300 to DN 600: ASTM A53/A53M Grade B, or ASTM A106/A106M
Grade B, ERW, and beveled ends for butt welding downstream the heat exchanger
and could be accepted as roll Grooved ends for Coupled Joints.
4. Pipes above DN 600: API 5L Grade B, SAW at both sides with helical seam and
beveled ends for butt welding downstream the heat exchanger and could be accepted
as roll Grooved ends for Coupled Joints.
5. Minimum wall thickness shall be in accordance with the calculation based on ASME
B31.1 to verify that wall thickness is adequate enough as per actual system pressure:
C. Extension of Domestic Water Make-up Piping: as specified for Domestic water piping.
Refer to section 221116 “Domestic Water Piping”.
A. Insulation for valves, fittings, field casing closures, as required, and other piping system
accessories shall be cellular glass conforming to ASTM C552, calcium silicate conforming
to ASTM C533 or polyurethane matching the pipe insulation. Insulation shall be pre-
molded, precut or job fabricated to fit and shall be removable and reusable. Thickness shall
match adjacent piping.
B. Metal jackets shall be provided for all pipe insulation in manholes. Insulation bands shall be
19 mm wide 0.13 mm stainless steel.
C. Buried fittings and accessories shall be factory fabricated and may have field foamed
polyurethane insulation to match adjacent piping and shall be protected with a covering
matching the pipe casing. Shrink sleeves shall be provided over casing connection joints.
A. General: Each pre-insulated section of piping shall have a complete sealing of the insulation
to provide permanent water and vapor seal at each end of the pre-insulated section of piping.
Pre-insulated sections of piping modified in the field shall be provided with an end seal
which is equivalent to the end seals furnished with the pre-insulated section of piping.
Provide complete sealing of the insulation at each end of each pre-insulated conduit section
by one of the following methods:
1. Carrying the outer casing over tapered pipe insulation ends and extending it to the
carrier pipe. Provide sufficient surface bonding area between the casing and the
carrier pipe to ensure a permanent water and vapor resistant seal.
2. Using specially designed prefabricated caps made of the same material and not less
than the same thickness as the casing. Provide sufficient surface bonding area
between the cap, and both the casing and carrier pipe, to ensure permanent water and
vapor resistant seal.
2.5 JOINTS:
A. Welded joints: Welded joints between sections of pipe and between pipe and fittings shall
be provided where specified or indicated. Branch connections shall be made with either
welding tees or forged branch outlet fittings attached to the main and reinforced against
external strains.
B. Flanged joints: Flanged joints shall be provided with gaskets and made perfectly square and
tight. Full-faced gaskets shall be used with cast-iron flanges and all gaskets shall be as thin
as the finish of the flange face permits. Gaskets shall be 5 mm (3/16-inch) thick for 25
through 300 mm (1 through 12 inch) flanges and 6 mm (1/4-inch) thick for flanges 350 mm
(14 inches) and larger.
C. Threaded joints: Joints shall be made tight with polytetrafluoroethylene tape applied to the
male threads only. Not more than three threads shall show after the joint is made up.
D. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according
to ASTM B 813.
E. Brazing Filler Metals: AWS A5.8/A5.8M, BCuP Series, copper-phosphorus alloys for
joining copper with copper; or BAg-1, silver alloy for joining copper with bronze or steel.
F. Mechanical joints: Sleeve and grooved pipe couplings shall be installed and protected
against corrosion as recommended by the coupling manufacturer. Joints between
nonmetallic and metallic carrier pipe shall be designed and furnished by the piping system
manufacturer. The transition pieces shall be factory fabricated and shall be designed so that
no field chemical welding of the carrier pipe will be required. Transitional joint connections
to manhole steel piping shall be made inside the manhole except for prefabricated, pre-piped
manholes where joints shall be outside the manhole wall.
H. Nonmetallic pipe joints: Nonmetallic pipe joints shall be installed in accordance with the
written instructions of the manufacturer.
A. General
B. 50 mm and Smaller: Screwed. Mechanical couplings are optional for water piping only.
4. Screwed: 150 pound malleable iron, ASME B16.3. 125 pound cast iron, ASME
B16.4, may be used in lieu of malleable iron. Bushing reduction of a single pipe size,
or use of close nipples, is not acceptable.
5. Unions: ASME B16.39.
6. Water hose connection adapter: Brass, pipe thread to 20 mm garden hose thread, with
hose cap nut.
C. 65 mm and Larger: Welded or flanged joints. Mechanical couplings and fittings are optional
for water piping only.
1. Pipe fitting material shall be to ASTM A 234/A 234M WPB, ASTM A105/A105M or
ASTM A53/A53M Grade B ERW.
2. Butt welding fittings: ASME B16.9 with same wall thickness as connecting piping.
Elbows shall be long radius type, unless otherwise noted.
3. Socket welded fittings shall be in accordance with ASME B16.11.
4. Welding flanges and bolting: ASME B16.5:
a. Water service: Weld neck or slip-on, plain face, with 6 mm (1/8 inch) thick full
face neoprene gasket suitable for 104 degrees C (220 degrees F).
b. Flange bolting: Carbon steel machine bolts or studs and nuts, ASTM A307,
Grade B.
D. Welded Branch and Tap Connections: Forged steel weldolets, or branchlets and threadolets
may be used for branch connections up to one pipe size smaller than the main. Forged steel
half-couplings, ASME B16.11 may be used for drain, vent and gage connections.
E. Mechanical Pipe Couplings and Fittings: If used and accepted by The Engineer shall be used
with roll grooved pipe, in water service up to 110 degrees C (230 degrees F).
A. Solder Joint:
B. Chemical feed piping for condenser water treatment: Chlorinated polyvinyl chloride
(CPVC), Schedule 80, ASTM F439.
A. Provide where copper tubing and ferrous metal pipe are joined.
C. 65 mm and Larger: Flange union with dielectric gasket and bolt sleeves, ASME B16.42.
B. Lubricant or Sealant: Oil and graphite or other compound approved for the intended service.
E. Welding Materials: Comply with Section II, Part C, of the ASME Boiler and Pressure
Vessel Code for welding materials appropriate for wall thickness and for chemical analysis
of pipe being welded.
F. Gasket Material: Thickness, material, and type suitable for fluid to be handled; and design
temperatures and pressures.
2.11 VALVES
A. Gate, globe, check, ball, butterfly valves and motorized valves are specified in Section
"General-Duty Valves for HVAC Piping."
C. All valves of the same type shall be products of a single manufacturer. Provide gate and
globe valves with packing that can be replaced with the valve under full working pressure.
D. Provide chain operators for valves 100 mm (4 inches) and larger when the centerline is
located 2400 mm (8 feet) or more above the floor or operating platform.
F. Dynamic Water Flow Balancing Valves, used for balancing, shut off and measuring of
pressure drop. Balancing valves shall be provided with two measuring nipples to have the
possibility to measure the differential pressure (water flow indirectly) through the balancing
valve and a tight shut off function with a hidden memory of the setting. Each valve shall be
provided with a label including at least the valve reference number, valve’s diameter, design
flow, setting after balancing and pressure drop in setting and design position. All valves
shall be supplied with Prefab insulation material sourced from the valve manufacturer, made
of Polyurethane, volume weight 50-60 Kg/cubic m.
G. Dynamic Water Flow Balancing Valves, DN 50 (NPS 2) and Smaller: bronze body, fitted
with a red nylon hand-wheel and a protection cap, 1035-kPa (150 psig) working pressure,
107 deg C (225 deg F) maximum operating temperature, and having threaded end
connections.
H. Dynamic Water Flow Balancing Valves, DN 65 (NPS 2-1/2) and Larger: Y-pattern globe
valve style, Cast-iron or steel body, fitted with seat seal cone, bonnet bolts chromed steel
and digital hand wheel, 1035-kPa (150 psig) working pressure, 107 deg C (225 deg F)
maximum operating temperature, and having flanged or grooved connections.
J. Safety Valves: Diaphragm-operated, bronze or brass body with brass and rubber, wetted,
internal working parts; shall suit system pressure and heat capacity and shall comply with
the ASME Boiler and Pressure Vessel Code, Section IV: Heating Boilers, Bear ASME
stamp
K. Pressure Relief Valve: Bronze or iron body and bronze or stainless steel trim, with testing
lever. Comply with ASME Code for Pressure Vessels, Section 8; bear ASME stamp.
L. Automatic Dynamic Flow-Control Valves: Gray-iron body, factory set to maintain constant
flow with plus or minus 5 percent over system pressure fluctuations, and equipped with a
readout kit including flow meter, probes, hoses, flow charts, and carrying case. Each valve
shall have an identification tag attached by chain, and be factory marked with the zone
identification, valve number, and flow rate. Valve shall be line size and one of the following
designs:
1. Gray-iron or brass body, designed for 1206 kPa (175 psig) at 93 deg C (200 deg F)
with stainless-steel piston and spring.
2. Brass or ferrous-metal body, designed for 2068 kPa (300 psig) at 121 deg C (250
deg F) with corrosion-resistant, tamperproof, self-cleaning, piston-spring assembly
easily removable for inspection or replacement.
3. Combination assemblies, including bronze ball valve and brass alloy control valve,
with stainless-steel piston and spring, fitted with pressure and temperature test valves,
and designed for 2067 kPa (300 psig) at 121 deg C (250 deg F).
M. Triple Duty Valve: Contractors option for use at pump discharge in lieu of check valve and
balancing/shut-off valve. Triple duty valve is a non-slam check valve with spring-loaded
weighted disc and a calibrated adjustment feature permitting regulation of pump discharge
flow and shut-off. Valves shall be designed to permit repacking under full line pressure.
Unit shall be installed on discharge side of pump in a horizontal or vertical position with the
stem up. Unit shall be cast iron body construction suitable for maximum working pressure
of 1205 kPa (175 PSI) and maximum operating temperature of 149 C (300 F), bronze disc
and seat, stainless steel stem and spring.
N. Drain Valves: Valves shall be the gate valve types which are in accordance with MSS SP-
80. Valve shall be manually operated, 20 mm pipe size and above with a threaded end
connection. Valve shall be provided with a water hose nipple adapter.
O. Drain Cocks: MSS SP-110, DN20 (3/4-inch NPS) ball valve, rated for 2760 kPa (400-psig)
minimum CWP. Include 2-piece, bronze body with standard port, chrome-plated brass ball,
replaceable seats and seals, blowout-proof stem, and vinyl-covered steel handle.
A. Air Vents
1. Manual Air Vent: Bronze body and nonferrous internal parts; 1035-kPa (150-psig)
working pressure; 107 deg C (225 deg F) operating temperature; manually operated
with screwdriver or thumbscrew; with DN 6 (NPS 1/8) discharge connection and
DN 15 (NPS 1/2) inlet connection.
2. Automatic Air Vent: Designed to vent automatically with float principle; bronze
body and nonferrous internal parts; 1035-kPa (150-psig) working pressure; 116 deg C
(240 deg F) operating temperature; with DN 8 (NPS 1/4) discharge connection and
DN 15 (NPS 1/2) inlet connection.
3. Air vents on water coils shall have not less than 3 mm threaded end connections.
4. Air vents on water mains shall have not less than 20 mm threaded end connections.
5. Air vents on all other applications shall have not less than 15 mm threaded end
connections
B. Closed Expansion Tanks: Welded carbon steel, rated for 1206-kPa (175-psig) working
pressure and 121 deg C (250 deg F) maximum operating temperature. Separate air charge
from system water to maintain design expansion capacity by a flexible bladder securely
sealed into tank. Provide sight glass and include drain fitting and taps for pressure gage and
air-charging fitting. Support vertical tanks with steel legs or base; support horizontal tanks
with steel saddles. Factory fabricate and test tank with taps and supports installed and
labeled according to the ASME Boiler & Pressure Vessel Code - Section VIII - Pressure
Vessels, Division 1.
C. Tangential-Type Air Separators: Welded black steel; ASME constructed and labeled for
1206-kPa (175-psig) minimum working pressure and 191 deg C (375 deg F) maximum
operating temperature; perforated stainless-steel air collector tube designed to direct released
air into expansion tank; tangential inlet and outlet connections; threaded connections for
DN 50 (NPS 2) and smaller; flanged connections for DN 65 (NPS 2-1/2) and larger;
threaded blowdown connection. Provide units in sizes for full-system flow capacity.
Applicable to central plants.
D. Y-Pattern Strainers: 1035-kPa (150-psig) working pressure; cast-iron body (ASTM A126-
04, Class B), flanged ends for DN 65 (NPS 2-1/2) and larger, threaded connections for
DN 50 (NPS 2) and smaller, bolted cover, perforated stainless-steel basket, and bottom drain
connection.
G. Spherical, Rubber, Flexible Connectors: Fiber-reinforced rubber body with steel flanges
drilled to align with Classes 150 and 300 steel flanges; operating temperatures up to 121
deg C (250 deg F) and pressures up to 1035 kPa (150 psig).
H. Packed, Slip, Expansion Joints: 1035-kPa (150-psig) minimum working pressure, steel pipe
fitting consisting of telescoping body and slip-pipe sections, packing ring, packing, limit
rods, flanged ends, and chrome-plated finish on slip-pipe telescoping section.
A. Minimum overall accuracy plus or minus three percent over a range of 70 to 110 percent of
design flow. Select devices for not less than 110 percent of design flow rate.
B. Venturi Type: Bronze, steel, or cast iron with bronze throat, with valved pressure sensing
taps upstream and at the throat.
C. Wafer Type Circuit Sensor: Cast iron wafer-type flow meter equipped with readout valves
to facilitate the connecting of a differential pressure meter. Each readout valve shall be fitted
with an integral check valve designed to minimize system fluid loss during the monitoring
process.
D. Self-Averaging Annular Sensor Type: Brass or stainless steel metering tube, shutoff valves
and quick-coupling pressure connections. Metering tube shall be rotatable so all sensing
ports may be pointed down-stream when unit is not in use.
F. Measurement and shut-off valve: An on/off ball valve with integral high regain venturi and
dual quick connect valves with integral check valves and color coded safety caps for
pressure/temperature readout.
G. A butterfly balancing valve as specified herein, with memory stop and quick connect valve
for pressure/temperature readout.
2. Include meter or equipment number, manufacturer's name, meter model, flow rate
factor and design flow rate in l/m (gpm).
I. Vent and drain hose and two 3000 mm (10 feet) lengths of hose with quick disconnect
connections.
J. Factory fabricated carrying case with hose compartment and a bound set of capacity curves
showing flow rate versus pressure differential.
K. Provide one portable meter for each range of differential pressure required for the installed
flow devices.
L. Permanently Mounted Water Flow Indicating Meters: Minimum 150 mm diameter, or 450
mm long scale, for 120 percent of design flow rate, direct reading in lps with three valve
manifold and two shut-off valves.
A. Factory built devices, inserted in the pipe lines, designed to absorb axial cyclical pipe
movement which results from thermal expansion and contraction. This includes factory-built
or field-fabricated guides located along the pipe lines to restrain lateral pipe motion and
direct the axial pipe movement into the expansion joints.
E. Expansion Compensators:
F. Expansion Joint Identification: Provide stamped brass or stainless steel nameplate on each
expansion joint listing the manufacturer, the allowable movement, flow direction, design
pressure and temperature, date of manufacture, and identifying the expansion joint by the
identification number on the contract drawings.
G. Guides: Provide factory-built guides along the pipe line to permit axial movement only and
to restrain lateral and angular movement. Guides must be designed to withstand a minimum
of 15 percent of the axial force which will be imposed on the expansion joints and anchors.
Field-built guides may be used if detailed on the contract drawings.
A. ASME B40.100, Accuracy Grade 1A, (pressure, vacuum, or compound for air, oil or water),
initial mid-scale accuracy 1 percent of scale (Qualify grade), metal or phenolic case, 115
mm (4-1/2 inches) in diameter, 6 mm (1/4 inch) NPT bottom connection, white dial with
black graduations and pointer, clear glass or acrylic plastic window, suitable for board
mounting. Provide red "set hand" to indicate normal working pressure.
B. Provide brass lever handle union cock. Provide brass/bronze pressure snubber for gages in
water service.
C. Range of Gages: Provide range equal to at least 130 percent of normal operating range.
1. For condenser water suction (compound): Minus 100 kPa (30 inches Hg) to plus 700
kPa (100 psig).
A. Pete's Plug: 6 mm (1/4 inch) MPT by 75 mm (3 inches) long, brass body and cap, with
retained safety cap, nordel self-closing valve cores, permanently installed in piping where
shown, or in lieu of pressure gage test connections shown on the drawings.
B. Provide one each of the following test items to the Resident Engineer:
1. 6 mm (1/4 inch) FPT by 3 mm (1/8 inch) diameter stainless steel pressure gage
adapter probe for extra long test plug. PETE'S 500 XL is an example.
2. 90 mm (3-1/2 inch) diameter, one percent accuracy, compound gage, , –—100 kPa
(30 inches) Hg to 700 kPa (100 psig) range.
3. 0 - 104 degrees C (220 degrees F) pocket thermometer one-half degree accuracy, 25
mm (one inch) dial, 125 mm (5 inch) long stainless steel stem, plastic case.
2.17 THERMOMETERS
A. Mercury or organic liquid filled type, red or blue column, clear plastic window, with 150
mm (6 inch) brass stem, straight, fixed or adjustable angle as required for each in reading.
C. Scale: Not less than 225 mm (9 inches), range as described below, two degree graduations.
D. Separable Socket (Well): Brass, extension neck type to clear pipe insulation.
E. Scale ranges may be slightly greater than shown to meet manufacturer's standard. Required
ranges in degrees C (F):
PART 3 - EXECUTION
A. External chilled water/ heating water pipes and chilled water/ heating water pipes inside
utility culverts or directly buried: Pre-insulated piping. Chilled water/ heating water pipes
inside building: Black steel pipes.
C. Chilled water/ heating water pipes above ground and exposed to outdoors: Black steel pipes.
A. General-Duty Valve Applications: Unless otherwise indicated, use the following valve
types:
B. Install shutoff duty valves at each branch connection to supply mains, at supply connection
to each piece of equipment, unless only one piece of equipment is connected in the branch
line. Install throttling duty valves at each branch connection to return mains, at return
connections to each piece of equipment, and elsewhere as indicated.
C. Install calibrated balancing valves in the return water line of each heating or cooling element
and elsewhere as required to facilitate system balancing.
D. Install silent type check valves at each pump discharge and elsewhere as required to control
flow direction.
E. Install safety valves as required by the ASME Boiler and Pressure Vessel Code. Install
safety-valve discharge piping, without valves, to floor. Comply with the ASME Boiler &
Pressure Vessel Code - Section VIII - Pressure Vessels, Division 1, for installation
requirements.
A. Install groups of pipes parallel to each other, spaced to permit applying insulation and
servicing of valves.
B. Install drains, consisting of a tee fitting, DN 20 (NPS 3/4) ball valve, and short DN 20
(NPS 3/4) threaded nipple with cap, at low points in piping system mains and risers, and
elsewhere as required for system drainage.
D. Reduce pipe sizes using eccentric reducer fitting installed with level side up.
E. Unless otherwise indicated, install branch connections to mains using tee fittings in main
pipe, with the takeoff coming out the bottom of the main pipe. For up-feed risers, install the
takeoff coming out the top of the main pipe.
F. Install strainers on supply side of each control valve, pressure-reducing valve, solenoid
valve, in-line pump, and elsewhere as indicated. Install DN 20 (NPS 3/4) nipple and ball
valve in blowdown connection of strainers DN 50 (NPS 2) and larger. Match size of strainer
blowoff connection for strainers smaller than DN 50 (NPS 2).
A. Hanger, support, and anchor devices are specified in Section "Hangers and Supports for
HVAC Piping and Equipment." Comply with requirements below for maximum spacing of
supports.
1. Adjustable steel clevis hangers for individual horizontal piping less than 6 m long.
2. Adjustable roller hangers and spring hangers for individual horizontal piping 6 m or
longer.
3. Pipe Roller: MSS SP-58 for multiple horizontal piping 6 m or longer, supported on a
trapeze.
4. Spring hangers to support vertical runs.
5. On plastic pipe, install rubber pads or cushions on bearing surfaces to prevent hanger
from scratching pipe.
C. Install hangers for steel piping with the following maximum spacing and minimum rod
sizes:
11. DN 300 (NPS 12): Maximum span, 7 m; minimum rod size, 22 mm.
12. DN 350 (NPS 14): Maximum span, 7.6 m; minimum rod size, 25 mm.
13. DN 400 (NPS 16): Maximum span, 8.2 m; minimum rod size, 25 mm.
14. DN 450 (NPS 18): Maximum span, 8.5 m; minimum rod size, 32 mm.
15. DN 500 (NPS 20): Maximum span, 9.1 m; minimum rod size, 32 mm.
D. Install hangers for drawn-temper copper piping with the following maximum spacing and
minimum rod sizes:
E. PVC Piping Hanger Spacing: Space hangers according to pipe manufacturer's written
instructions for service conditions. Avoid point loading. Space and install hangers with the
fewest practical rigid anchor points.
F. Support vertical runs at roof, at each floor, and at 3-m intervals between floors.
A. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.
B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before
assembly.
C. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to
tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook,"
using lead-free solder alloy complying with ASTM B 32.
D. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube"
Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8/A5.8M.
E. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut
threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore
full ID. Join pipe fittings and valves as follows:
1. Apply appropriate tape or thread compound to external pipe threads unless dry seal
threading is specified.
2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or
damaged. Do not use pipe sections that have cracked or open welds.
G. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service
application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.
H. Plastic Piping Solvent-Cemented Joints: Clean and dry joining surfaces. Join pipe and
fittings according to the following:
1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and
solvent cements.
2. CPVC Piping: Join according to ASTM D 2846/D 2846M Appendix.
3. PVC Pressure Piping: Join ASTM D 1785 schedule number, PVC pipe and PVC
socket fittings according to ASTM D 2672. Join other-than-schedule number PVC
pipe and socket fittings according to ASTM D 2855.
4. PVC Nonpressure Piping: Join according to ASTM D 2855.
I. Grooved Joints: Assemble joints with coupling and gasket, lubricant, and bolts. Cut or roll
grooves in ends of pipe based on pipe and coupling manufacturer's written instructions for
pipe wall thickness. Use grooved-end fittings and rigid, grooved-end-pipe couplings.
L. Mechanical and Heat Fusion Joints: Assemble joints according to fitting manufacturer’s
written instructions.
A. Install manual air vents at top of risers and high points in piping, at heat-transfer coils, and
elsewhere as required for system air venting.
B. Install automatic air vents in mechanical equipment rooms only at high points of system
piping, at heat-transfer coils, and elsewhere as required for system air venting.
C. Install combination air separator and strainer in pump suction lines. Install piping to
compression tank with a 2 percent upward slope toward tank. Install blowdown piping with
gate valve; extend to nearest drain.
D. Install expansion tanks on floor. Vent and purge air from hydronic system, and ensure tank
is properly charged with air to suit system design requirements.
A. Size for supply and return piping connections shall be same as for equipment connections.
C. Install bypass piping with globe valve around control valve. If multiple, parallel control
valves are installed, only one bypass is required.
D. Install ports for pressure and temperature gages at coil inlet connections.
1. Leave joints, including welds, uninsulated and exposed for examination during test.
2. Provide temporary restraints for expansion joints that cannot sustain reactions due to
test pressure. If temporary restraints are impractical, isolate expansion joints from
testing.
3. Flush system with clean water. Clean strainers.
4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure
shall be capable of sealing against test pressure without damage to valve. Install
blinds in flanged joints to isolate equipment.
5. Install safety valve, set at a pressure no more than one-third higher than test pressure,
to protect against damage by expanding liquid or other source of overpressure during
test.
1. Use ambient temperature water as a testing medium unless there is risk of damage
due to freezing. Another liquid that is safe for workers and compatible with piping
may be used.
2. While filling system, use vents installed at high points of system to release trapped
air. Use drains installed at low points for complete draining of liquid.
3. Check expansion tanks to determine that they are not air bound and that system is full
of water.
4. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the
design pressure. Test pressure shall not exceed maximum pressure for any vessel,
pump, valve, or other component in system under test. Verify that stress due to
pressure at bottom of vertical runs does not exceed either 90 percent of specified
minimum yield strength or 1.7 times "SE" value in Appendix A of ANSI/ASME
B31.9, "Building Services Piping."
5. After hydrostatic test pressure has been applied for at least 10 minutes, examine
piping, joints, and connections for leakage. Eliminate leaks by tightening, repairing,
or replacing components, and repeat hydrostatic test until there are no leaks.
6. Prepare written report of testing.
e. Heat input during welding is important value so the visual inspection for
welding activity “before, during and after” welding is required.
3.9 ADJUSTING
A. Mark calibrated nameplates of pump discharge valves after hydronic system balancing has
been completed, to permanently indicate final balanced position.
3.10 PAINTING
A. All exposed surfaces of ferrous and non-ferrous piping outdoors or indoors in equipment
rooms and exposed to view in occupied spaces shall be cleaned, primed and painted.
B. Refer to Sections "Interior Painting" and "Exterior Painting" for painting requirement.
3.11 CLEANING
A. Flush hydronic piping systems with clean water. Remove and clean or replace strainer
screens. After cleaning and flushing hydronic piping systems, but before balancing, remove
disposable fine-mesh strainers in pump suction diffusers.
B. Coordinate with HVAC water treatment Sub-Contractor for flushing requirement to ensure
adequacy of flushing prior to Chemical Treatment.